For getting the details of etenders, if you are looking for information about them from the cumbersome government websites but are tired of doing so, Bidassist comes up with a one stop solution. It collates every Eproc telangana tender on Bidassist. One can approach it for the bidding process, registration process, etc., are explained below.
Municipal Administration Department Tender
Civil And Construction
Building Construction
Opening Date18 Nov 2024
Closing Date22 Nov 2024
Tender Amount₹ 3,78,575
Costs
EMD
₹ 3,786Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
557296Tender No
E1/Compound wall/Kuruva Community Hall/SDF/004/2024-25Tender Authority
Municipal Administration Department ViewPurchaser Address
-Website
http://tender.telangana.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
... More
Construction of Compound wall;BLD-CSTN-6-12-(67) : Construction of RR Masonary in Cement Mortor ( 1:6 ) Prop using hard granite stone including cost & Conveyance of all materials like Cement, Sand , Water, Granite Stones, including ,on all Materials, ,labour charges for cutting Stones to required size and shape, mixing of Cement Mortor ,Construction, Scaffolding Charges curing etc., complete for finished item of Work .
17.28
4637
80129.09
... More
Construction of Compound wall;BLD-CSTN-3-5 (22) -Using Concrete mixture all works up to Plinth Level: Plain Cement concrete nominal mix (1:4:8) prop (Cement : fine aggregate : coarse aggregate ) using 40mm size Hard Granite Machine Crushed Metal including cost and conveyance of all materials like cement, sand, coarse aggregate water etc., to site , seigniorage charges on all materials , labour charges , for mixing , laying, concrete , remming 15 cm layers, finishing top surface to the required level curing etc., complete for finished item of work for foundation and under flooring bed
2.88
4720
13594.87
... More
Construction of Compound wall;BLD-CSTN-2-1 (9): Earth work excavation in Ordinary soil by Manual Means-Upto 3 m depth for foundations and depositing on bank for all lifts and With an initial lead of 10m including all operational,incidenatl ,labour charges such as shoring , sheeting, planking, struting, etc. complete for finished item of work inculding seigniorage excluding dewatering charges etc as per SS - 20 B (APSS 308).
21.6
285
6163.95