Irrigation And CAD Department Tender

For getting the details of etenders, if you are looking for information about them from the cumbersome government websites but are tired of doing so, Bidassist comes up with a one stop solution. It collates every Eproc telangana tender on Bidassist. One can approach it for the bidding process, registration process, etc., are explained below.

Irrigation And CAD Department Tender

Works
Civil And Construction
Civil Works Others
Opening Date29 Sep 2023
Closing Date6 Oct 2023
Tender Amount₹ 21,94,46,407 
Notes
Download

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
construction of checkdam;Providing impervious hearting embankment with soil collected in embankment area inheaps as part of disposal of excavated soil from canal including cost of all materials,machinery,labour, all operations such as sortingout, spreading in layer of 25 cm before compaction,breaking clods,sectioning, watering and compacting each layer to density control of not lessthan 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Jafrapur (V))

2463.54

82

202257

... More
construction of checkdam;Providing homogeneous embankment using soil from approved borrow area in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transportation, spreading soil in layer of specified thickness, breaking clods, sectioning, watering, compacting to density control of not less than 95 percent or as stipulated using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Jafrapur (V))

576

205

118080

... More
construction of checkdam;Supplying & Fixing of High Performance Expansion Joint Filler board Confirming to IS:1838-20 MM THICK as directed by the Engineer-in-Charge (Jafrapur (V))

287.08

1078

309472

... More
construction of checkdam;Providing and constructing contraction joints by fixing 31 cm wide central bulb type PVC water stop in single line supported by 10 mm dia steel dowel rods on either side at 1 metre interval including cost of all materials, machinery, labour, valcunising joints etc., complete with all leads and lifts and all other operations necessary to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Jafrapur (V))

182.2

787

143501

... More
construction of checkdam;Providing and Constructing 30 cm thick dry rubble stone pitching including cost of all materials,labour,hand packing,finishing etc.to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Jafrapur (V))

1595.45

429

685884

... More
construction of checkdam;Providing and constructing 225 mm thick dry rubble stone pitching including cost of all materials, labour, hand packing, finishing etc. to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Jafrapur (V))

1636.36

288

472352

... More
construction of checkdam;Providing and constructing 15 cm thick Gravel backing below revetment including cost of all materials,labour,hand packing,finishing etc., complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Jafrapur (V))

3620

90

327972

... More
construction of checkdam;Providing, fabricating and placing in position reinforcement steel for RCC,below 36 dia rods overlaps and wastages wherever required, tying with 1.25 mm diameter soft annealed steel wire, including cost of all materials, machinery, labour etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Jafrapur (V))

34.15

74637

2548854

... More
construction of checkdam;Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Jafrapur (V))

2953.86

6992

20653389

... More
construction of checkdam;Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc. complete for plain concreter works to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Jafrapur (V))

4880

6503

31734640

... More
construction of checkdam;Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification,including setting out,construction of shoring and bracing,removal of stumps and other deleterious matter,dressing of sides and bottom and backfilling with approved material to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Jafrapur (V))

15232.98

123

1876703

... More
construction of checkdam;Cutting and burning or disposing off Apu / Jondu from marshy areas to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Jafrapur (V))

3000

8

24600

... More
construction of checkdam;Excavation in all kinds of soil including for boulders upto 0.30 m dia for Obstruction Removal etc., including dressing of bed and sides to required profile,cost of all materials, machinery, labour, placing the excavated stuff for formation of service road / embankment as directed etc., complete with lead up to 10m and lift up to 3m and all other operations necessary to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

2525

70

178012.5

... More
construction of checkdam;Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for wearing coat including cost of all materials, machinery, labour, formwork,cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,finishing, curing, packing joints with asphalt mortar etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

558.48

6931

3870825

... More
construction of checkdam;Providing impervious hearting embankment with soil collected in embankment area inheaps as part of disposal of excavated soil from canal including cost of all materials,machinery,labour, all operations such as sortingout, spreading in layer of 25 cm before compaction,breaking clods,sectioning, watering and compacting each layer to density control of not lessthan 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

1354

82

111163

... More
construction of checkdam;Providing homogeneous embankment using soil from approved borrow area in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transportation, spreading soil in layer of specified thickness, breaking clods, sectioning, watering, compacting to density control of not less than 95 percent or as stipulated using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

338

260

88015

... More
construction of checkdam;Supplying & Fixing of High Performance Expansion Joint Filler board Confirming to IS:1838-20 MM THICK as directed by the Engineer-in-Charge (Vengwapet (V))

327.77

1078

353336

... More
construction of checkdam;Providing and constructing contraction joints by fixing 31 cm wide central bulb type PVC water stop in single line supported by 10 mm dia steel dowel rods on either side at 1 metre interval including cost of all materials, machinery, labour, valcunising joints etc., complete with all leads and lifts and all other operations necessary to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

168.26

787

132522

... More
construction of checkdam;Providing and Constructing 30 cm thick dry rubble stone pitching including cost of all materials,labour,hand packing,finishing etc.to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

1528

430

657040

... More
construction of checkdam;Providing and constructing 225 mm thick dry rubble stone pitching including cost of all materials, labour, hand packing, finishing etc. to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

3466.58

288

1000802

... More
construction of checkdam;Providing and constructing 15 cm thick Gravel backing below revetment including cost of all materials,labour,hand packing,finishing etc., complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

1762.58

100

177139

... More
construction of checkdam;Providing, fabricating and placing in position reinforcement steel for RCC,below 36 dia rods overlaps and wastages wherever required, tying with 1.25 mm diameter soft annealed steel wire, including cost of all materials, machinery, labour etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

33.1

74637

2470485

... More
construction of checkdam;Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

2778.02

7117

19771168

... More
construction of checkdam;Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc. complete for plain concreter works to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

4119.7

6628

27305372

... More
construction of checkdam;Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification,including setting out,construction of shoring and bracing,removal of stumps and other deleterious matter,dressing of sides and bottom and backfilling with approved material to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Vengwapet (V))

20078.81

123

2473709

... More
construction of checkdam;Excavation in all kinds of soil including for boulders upto 0.30 m dia for Obstruction Removal etc., including dressing of bed and sides to required profile,cost of all materials, machinery, labour, placing the excavated stuff for formation of service road / embankment as directed etc., complete with lead up to 10m and lift up to 3m and all other operations necessary to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

8250

70

581625

... More
construction of checkdam;Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for wearing coat including cost of all materials, machinery, labour, formwork,cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,finishing, curing, packing joints with asphalt mortar etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

421.68

7097

2992705

... More
construction of checkdam;Providing impervious hearting embankment with soil collected in embankment area inheaps as part of disposal of excavated soil from canal including cost of all materials,machinery,labour, all operations such as sortingout, spreading in layer of 25 cm before compaction,breaking clods,sectioning, watering and compacting each layer to density control of not lessthan 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

1706.29

82

140086

... More
construction of checkdam;Providing homogeneous embankment using soil from approved borrow area in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transportation, spreading soil in layer of specified thickness, breaking clods, sectioning, watering, compacting to density control of not less than 95 percent or as stipulated using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

426.57

260

111079

... More
construction of checkdam;Supplying & Fixing of High Performance Expansion Joint Filler board Confirming to IS:1838-20 MM THICK as directed by the Engineer-in-Charge (Borigaon (V))

112.66

1078

121447

... More
construction of checkdam;Providing and constructing contraction joints by fixing 31 cm wide central bulb type PVC water stop in single line supported by 10 mm dia steel dowel rods on either side at 1 metre interval including cost of all materials, machinery, labour, valcunising joints etc., complete with all leads and lifts and all other operations necessary to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

175.88

787

138523

... More
construction of checkdam;Providing and Constructing 30 cm thick dry rubble stone pitching including cost of all materials,labour,hand packing,finishing etc.to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

2136

429

918266

... More
construction of checkdam;Providing and constructing 225 mm thick dry rubble stone pitching including cost of all materials, labour, hand packing, finishing etc. to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

5333.76

288

1539857

... More
construction of checkdam;Providing and constructing 15 cm thick Gravel backing below revetment including cost of all materials,labour,hand packing,finishing etc., complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

6333.76

100

636543

... More
construction of checkdam;Providing, fabricating and placing in position reinforcement steel for RCC,below 36 dia rods overlaps and wastages wherever required, tying with 1.25 mm diameter soft annealed steel wire, including cost of all materials, machinery, labour etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

33.49

74637

2499593

... More
construction of checkdam;Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

2350.11

7300

17157213

... More
construction of checkdam;Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc. complete for plain concreter works to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

4362.75

6812

29719053

... More
construction of checkdam;Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification,including setting out,construction of shoring and bracing,removal of stumps and other deleterious matter,dressing of sides and bottom and backfilling with approved material to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Borigaon (V))

21134.15

123

2603727

... More
construction of checkdam;Excavation in all kinds of soil including for boulders upto 0.30 m dia for Obstruction Removal etc., including dressing of bed and sides to required profile,cost of all materials, machinery, labour, placing the excavated stuff for formation of service road / embankment as directed etc., complete with lead up to 10m and lift up to 3m and all other operations necessary to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

5500

70

387750

... More
construction of checkdam;Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for wearing coat including cost of all materials, machinery, labour, formwork,cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,finishing, curing, packing joints with asphalt mortar etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

357

7177

2562189

... More
construction of checkdam;Providing impervious hearting embankment with soil collected in embankment area inheaps as part of disposal of excavated soil from canal including cost of all materials,machinery,labour, all operations such as sortingout, spreading in layer of 25 cm before compaction,breaking clods,sectioning, watering and compacting each layer to density control of not lessthan 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

1354

82

111163

... More
construction of checkdam;Providing homogeneous embankment using soil from approved borrow area in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transportation, spreading soil in layer of specified thickness, breaking clods, sectioning, watering, compacting to density control of not less than 95 percent or as stipulated using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

338

260

87981

... More
construction of checkdam;Supplying & Fixing of High Performance Expansion Joint Filler board Confirming to IS:1838-20 MM THICK as directed by the Engineer-in-Charge (Koutla - B (V))

236

1078

254408

... More
construction of checkdam;Providing and constructing contraction joints by fixing 31 cm wide central bulb type PVC water stop in single line supported by 10 mm dia steel dowel rods on either side at 1 metre interval including cost of all materials, machinery, labour, valcunising joints etc., complete with all leads and lifts and all other operations necessary to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

84

787

66158

... More
construction of checkdam;Providing and Constructing 30 cm thick dry rubble stone pitching including cost of all materials,labour,hand packing,finishing etc.to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

3234

430

1390620

... More
construction of checkdam;Providing and constructing 225 mm thick dry rubble stone pitching including cost of all materials, labour, hand packing, finishing etc. to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

4553

288

1314451

... More
construction of checkdam;Providing and constructing 15 cm thick Gravel backing below revetment including cost of all materials,labour,hand packing,finishing etc., complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

5543

100

557072

... More
construction of checkdam;Providing, fabricating and placing in position reinforcement steel for RCC,below 36 dia rods overlaps and wastages wherever required, tying with 1.25 mm diameter soft annealed steel wire, including cost of all materials, machinery, labour etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

17.18

74637

1282264

... More
construction of checkdam;Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing etc.,to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

1590

7378

11731020

... More
construction of checkdam;Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc. complete for plain concreter works to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

2565

6889

17670285

... More
construction of checkdam;Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification,including setting out,construction of shoring and bracing,removal of stumps and other deleterious matter,dressing of sides and bottom and backfilling with approved material to complete the finished item of work as per drawing or as directed by the Engineer-in-Charge (Koutla - B (V))

9346

123

1151427



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.