For getting the details of etenders, if you are looking for information about them from the cumbersome government websites but are tired of doing so, Bidassist comes up with a one stop solution. It collates every Eproc telangana tender on Bidassist. One can approach it for the bidding process, registration process, etc., are explained below.

Irrigation And CAD Department Tender

Works
Civil And Construction
Bridge Construction
Opening Date5 Nov 2024
Closing Date12 Nov 2024
Tender Amount₹ 24,19,194 
Notes
Download

Costs

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Box culvert Yedpally Mandal;Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for sub-structure / super- structure works including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) IRR-CCDW-2-9

49.1

6370

312801

... More
Box culvert Yedpally Mandal;Providing and laying insitu vibrated M-15(28days cube compressive strength not less than 15N / sqmm) grade cement concrete using 40mm down size approved , clean, hard,graded aggregate for foundation filling including cost of all materials,machinery,labour,formwork, cleaning, batching,mixing,placing, in position, levelling ,vibrating, finishing,curing etc.,complete with initial lead upto 5m and all lifts .IRR-CCDW2-3

26.16

5587

146151

... More
Box culvert Yedpally Mandal;Providing & constructing Sand filling below foudation including cost of all materials, machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts.IRR-CAW-5-1A

6.93

1404

9737

... More
Box culvert Yedpally Mandal;Excavation for Structures- Mechanical Means ( Data adopted from MORTH) Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. IRR-CCDW-1-2

32.67

124

4051

... More
Box culvert Yedpally Mandal;Dismantling of Stone masonry in cement mortar - TBSC-U.I-01

27.93

634

17708

... More
Box culvert Yedpally Mandal;Providing, Fabrication of Steel reinforcement cost and conveyance of steel ,binding wire and bar bending, placing of reinforcement at site including all other operations necessary to complete the finished item of work as per drawings or as directed by the Engineer-in-charge (IRR-CCDW-2-1)

7562.36

73

557800

... More
Box culvert Yedpally Mandal;Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for wearing coat including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. IRR-CCDW-2-26

6.6

6048

39917

... More
Box culvert Yedpally Mandal;Providing and laying insitu vibrated M-25 ( 28days cube compressive strength not less than 25 N / sq mm ) grade cement concrete using 20mm down size approved, clean, hard, graded aggregates including cost of all materials,machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC works of gallery,sluice, spillway crest, spillway d / s face,energy dissipating structures, training walls, piers, abutments and such other locations with initial lead upto 1 km and all lifts. ( Cement content : 380 kg / cum with use of super plasticiser,CA : 0.90 cum, blending ratio of CA--65:35, FA : 0.40 cum) IRR-DAW-2-8

47.03

5784

272052

... More
Box culvert Yedpally Mandal;Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for sub-structure / super- structure works including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) IRR-CCDW-2-9

56.2

6370

358025

... More
Box culvert Yedpally Mandal;Providing and laying insitu vibrated M-15(28days cube compressive strength not less than 15N / sqmm) grade cement concrete using 40mm down size approved , clean, hard,graded aggregate for foundation filling including cost of all materials,machinery,labour,formwork, cleaning, batching,mixing,placing, in position, levelling ,vibrating, finishing,curing etc.,complete with initial lead upto 5m and all lifts .IRR-CCDW2-3

37

5587

206763

... More
Box culvert Yedpally Mandal;Providing & constructing Sand filling below foudation including cost of all materials, machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts.IRR-CAW-5-1A

10.98

1404

15419

... More
Box culvert Yedpally Mandal;Excavation for Structures- Mechanical Means ( Data adopted from MORTH) Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. IRR-CCDW-1-2

36.72

124

4553

... More
Box culvert Yedpally Mandal;Dismantling of Stone masonry in cement mortar - TBSC-U.I-01

60.02

634

38052



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.