Dr BR Ambedkar Open University Tender

For getting the details of etenders, if you are looking for information about them from the cumbersome government websites but are tired of doing so, Bidassist comes up with a one stop solution. It collates every Eproc telangana tender on Bidassist. One can approach it for the bidding process, registration process, etc., are explained below.

Dr BR Ambedkar Open University - BRAOU Tender

Civil And Construction
Road Construction
Opening Date14 May 2022
Closing Date24 May 2022
Tender Amount₹ 17,10,971 
Notes
Download

Costs

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Formation of approach road with cement concrete pavement;Providing kerbing with PCC 1:2:4

5.21

-

40385.42

... More
Formation of approach road with cement concrete pavement;Plain Cement Concrete (1:2:4) (cement: fine aggregate: Coarse aggregate) for foundations and under flooring bed using coarse aggregate 40mm size hard , machine crushed granite from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials and including all charges for machine mixing, laying concrete in foundations and under flooring bed, ramming in 15 cm layers finishing top surface to the required level curing etc.,and overheads & contractors profit complete for finished item of work. (APSS No. 402)

62.35

-

483307.27

... More
Formation of approach road with cement concrete pavement;Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations and under flooring bed using coarse aggregate 40mm size hard , machine crushed granite from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials and including all charges for machine mixing, laying concrete in foundations and under flooring bed, ramming in 15 cm layers finishing top surface to the required level curing etc., and overheads & contractors profit complete for finished item of work. (APSS No. 402)

62.35

-

394092.53

... More
Formation of approach road with cement concrete pavement;Dry rolling over embankment with 8 to 10 tonns power roller including hire and conveyance of power roller etc., complete for finished item of work and as directed by the Engineer-in-Charge

8

-

13006.4

... More
Formation of approach road with cement concrete pavement;Filling with Carted Gravell in trenches, sides of foundations & basement from approved quarry consolidating deposited layer by watering and ramming, including all operational, incidental, labour charges, complete including cost and conveyance of sand / gravel for finished item of work. (APSS No 309 & 310).

322.5

-

175123.95

... More
Formation of approach road with cement concrete pavement;RR stone masonry in 2ns sort in CM(1:6) prop (cement : sand) using hard granite stones from approved quarry including cost and conveyance of all materials like cement, sand water, granite stones, etc., from approved quarry to site and including labour for cutting stones to required size and shape, mixing of cement, mortar, construction, scaffolding charges, curing etc., complete for finished item of work in foundation & basement. (APSS No. 615 & 601)

28.6

-

162493.76

... More
Formation of approach road with cement concrete pavement;Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse aggregate) for foundations and under flooring bed using coarse aggregate 40mm size hard , machine crushed granite from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials and including all charges for machine mixing, laying concrete in foundations and under flooring bed, ramming in 15 cm layers finishing top surface to the required level curing etc.,and overheads & contractors profit complete for finished item of work. (APSS No. 402) including PCC for rain water drain CRS wall

8.8

-

53807.69

... More
Formation of approach road with cement concrete pavement;Earth work excavation for foundations for buildings in hard rock (requiring Control blasting) and depositing on bank for all lifts and with an initial lead of 10m and up to 3m depth including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished item of work including seigniorage excluding de watering charges etc., as per SS 20 B(APSS 308)

93

-

141563.67

... More
Formation of approach road with cement concrete pavement;Earth work excavation for foundations (Manual Means) of buildings in ordinary rock ( not requiring blasting ) and depositing on bank with an initial lead of 10m and depth up to 3m including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished item of work including seigniorage excluding dewatering charges etc., as per SS 20 B(APSS 308)

165.24

-

46878.59



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.