Water Resources Department Tender
Search from a plethora of business opportunities for Tamil Nadu tenders posted on the eProcurement TamilNadu website and other online and offline sources. Here, on BidAssist, you can find the best tender opportunities to boost your enterprise by finding work in Tamil Nadu government tenders, PSUs, Municipal Corporations and more. Read on to learn about the bidder registration process, DSC and more.
Water Resources Department - WRD Tender
Civil And Construction
Excavation
Eprocure
Opening Date16 Feb 2024
Closing DateCancelled
Tender Amount₹ 55,44,000
Costs
EMD
₹ 38,000Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_WRD_420247_2Tender No
5SE/TBC/TNY/2023-2024(9)Tender Authority
Water Resources Department ViewPurchaser Address
-Website
http://tntenders.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Earthwork excavating and depositing on bank with initial lead of 10m & initial lift of 2m in Hard stiff clay, stiff black cotton, hard red earth, shales, marruam, gravel, stoney earth and earth mixed with small size boulders etc., complete as per relevant standard specification and as directed by the departmental officers.
355
-
-
Earthwork for foundation in hard stiff clay excavating and deposition on bank with initial lead of 10m & initial lift of 2m in Hard stiff clay, stiff black cotton, hard red earth, shales, maurram, gravel, stoney erath and earth mixed with small size boulders etc., complete complying with standard specification and as directed by the departmental officers.
188.5
-
-
Providing and placing in position Plain Cement concrete of M-10 using broken hard granite coarse aggregate (well graded) of nominal maximum size of 40mm to IS specified grading and using crushed stone sand(m-sand) ( to achieve the specified characteristic strength of 10 N / mm² in 28 days ) and mixing the incredients in approved mixer including dewatering of the placement site by baling/pumping and diverting wherever necessary placing in layers and watering, curing, finishing the surface with all leads and lifts etc., complete in all respects so as to attain the profile and strength as specified in the approved drawings and specification etc., complete complying with standard specification and as directed by the departmental officers. (Without Vibration Charges)
51
-
-
Providing and placing in Position of Plain cement concrete of grade M15 using hard broken stone aggregate of maximum nominal size of 60% of 40mm and 40 % of 20mm IS specified grading and using crushed stone sand(m-sand) ( to achieve the specified characteristic strength of 15 N / mm² in 28 days ) and mixing the incredients in approved mixer including dewatering of the placement site by baling/pumping and diverting wherever necessary placing in layers and watering, curing, finishing the surface with all leads and lifts etc., complete in all respects so as to attain the profile and strength as specified in the approved drawings and specification etc., complete complying with standard specification and as directed by the departmental officers.
123
-
-
Supplying and erecting water tight steel centering for sides and sofits including supports and strutting upto 3.29M height for plain surface such as RCC slab, vertical slabs, side slabs of RCC works wioth all cross bracings using mild steel B.G.10gauge sheets of size 90cm x60cmx10 gauge stiffend with welded mils dteel angels of size 25mm x25mmx3mm for boarding laid over silver oak(country wood) joists of size 10cmx6.5 spaced at about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre etc., complete complying with standard specification and as directed by the Engineer incharge of work (The retrieved materials should be taken back by the contractor). The payment should be made after the concrete is laid.
-
-
-
With out Strutting
317.5
-
-
With Strutting
92.6
-
-
Gravel backing for revetment and apron in layers not exceeding 15cm thick, including watering, consolidation and trimming the top surface so as to receive the Rough Stones and including stacking for pre measurement etc., complete complying with standard specification and as directed by the departmental officers.
151
-
-
Manufacturing and fixing of M15 grade cement concrete block of size 300X250X200mm using hard broken stone aggregate of maximum nominal size of 20mm including moulding charges casting of blocks, finishing, curing and conveyance of all materials to work site and fixing the same in postion and handling charges for the same in position including all other incidental charges etc., complete complying with standard specification and as directed by the departmental officers.
196
-
-
Refilling with excavated earth in layers not exceeding 23cm thickness and watering to OMC (Optimum Moisture content) and compaction of each layer to 95% of proctor Density through deployment of appropriate compaction equipment (8-10T power roller) vibrator power roller of short width (0.90m width drum) power roller or vibratory power roller / fuel operated of electrically operated, vibratory plate compactors, ensuring compaction of designed bund section including side slops etc., complete as directed by the Engineer in charge of works and as per the technical specifications.
526
-
-
GST at 18%
1
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements