Tamil Nadu Generation And Distribution Corporation Limited Tender
Search from a plethora of business opportunities for Tamil Nadu tenders posted on the eProcurement TamilNadu website and other online and offline sources. Here, on BidAssist, you can find the best tender opportunities to boost your enterprise by finding work in Tamil Nadu government tenders, PSUs, Municipal Corporations and more. Read on to learn about the bidder registration process, DSC and more.
Tamil Nadu Generation And Distribution Corporation Limited - TANGEDCO Tender
Civil And Construction
Civil Works Others
Eprocure
Opening Date3 Feb 2024
Closing Date14 Feb 2024
Tender Amount₹ 24,17,519 This is an estimated amount, exact amount may vary.
Costs
EMD
₹ 25,000Document Cost
Refer DocumentsTender Fee
Refer Documents
Summary
Works Contract In Respworks Contract In Respect Of East Division
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_EB_418113_1Bid Award Id
ViewTender No
SE/SEDC/WC.NO.046/2023-24 dt.30.01.2024Tender Authority
Tamil Nadu Generation And Distribution Corporation Limited ViewPurchaser Address
-Website
http://https://www.tangedco.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
Works Contract in respect of East Division Except Yercaud Sections
BOQ Items
Hard rock without Blasting.
20
-
-
RCC poles/Metal pole up to 8.00m (27’).
300
-
-
RCC poles/Metal pole up to 9.14.m(30’).
170
-
-
Erection of stay set complete.
120
-
-
HT V Cross arms / Channel Cross arms / Guarding Cross arm 4 1/2.
300
-
-
LT 3 Phase cross arm.
250
-
-
LT single Phase cross arm.
300
-
-
HT /LT TI Fitting.
150
-
-
Fixing of HT Pin Insulators (11/22/33KV).
300
-
-
Fixing of HT 11KV stain disc.
300
-
-
Fixing of HT 22KV stain disc.
120
-
-
Fixing of LT Pin Insulators.
300
-
-
Fixing of LT Shackle.
250
-
-
Fixing of knob.
150
-
-
Earthing of Pole with pit including burying looping and binding.
120
-
-
Paving of conductor ,Stringing, binding, Jumpering etc., 7/4.09 mm ACSR (per Km).
5
-
-
7/3.35mm ACSR 7/3.15mmAAAC (per Km).
5
-
-
7/2.59mm ACSR & 7/2.50mm AAAC (per Km).
10
-
-
Erection of Transformer structure complete in all respects with wiring Earthing ,fixing of open type fuse units ,HT/LT/LAS and jumpering 3 Nos.Earth pits with tubs including painting of metal parts, structure poles, fixing of top channel seating channel,belting angle Including Concreting ( Except erection of transformer).
10
-
-
Erection of Single Pole Structure.
8
-
-
Transporting Below 8 Kms.
50
-
-
Transporting above 8 Kms. For additional Km (Irrespective of weight in tonnage).
100
-
-
Transporting of poles from road side to pole pit including loading and unloading of poles by using JCB or manual up to 100 m.
50
-
-
Transporting of poles from road side to pole pit including loading and unloading of poles by using JCB or manual beyond 100 m.
200
-
-
Loading of poles upto 27".
300
-
-
Loading of poles upto 30".
150
-
-
Loading of metal poles (All sizes).
20
-
-
Un Loading of poles upto 27".
300
-
-
Un Loading of poles upto 30".
150
-
-
Unloading of metal poles (All sizes).
20
-
-
Unloading of materials.
50
-
-
Leading and Stacking of materials.
50
-
-
Flat Guarding including fixing of 2 Nos. Cross arms.
15
-
-
HT Guarding.
15
-
-
Releasing of Single Phase service wire and refixing.
300
-
-
Releasing of Three Phase service wire and refixing.
250
-
-
Erection of street light including Fixure fitting.
150
-
-
Mass concreting including materials (Cement+River sand / M. sand and blue metals and Watering).
25
-
-
Sleeve concreting including materials (Cement+River sand / M. sand and blue metals and Watering).
30
-
-
Dismantling of Transformer structure complete.
3
-
-
Dismantling of pole (9.0m and above).
75
-
-
Dismantling of pole (7.5mtr & 8mtr).
100
-
-
Dismantling of pole from pole pit (9.0m and above).
75
-
-
Dismantling of pole from pole pit (7.5mtr & 8mtr).
100
-
-
Dismantling of HT Pin Insulator.
120
-
-
Dismantling of HT TI Fitting.
60
-
-
Dismantling of11 KV disc.
150
-
-
Dismantling of 3 PH X arm.
75
-
-
Dismantling of Tapping X arm, V X arm & Guarding X arm.
90
-
-
Dismantling of 1 PH X arm.
120
-
-
Dismantling of Alu Knob.
100
-
-
Dismantling of LT pin Insulator.
200
-
-
Dismantling of LT Shackle Insulator.
150
-
-
Stay set complete Dismantling.
25
-
-
Dismantling of 7/4.09 mm ACSR conductor (km).
4
-
-
Dismantling of 7/3.35 mm ACSR conductor (Km).
5
-
-
Dismantling of 7/2.59 & 7/2.11 mmACSR conductor (Km).
7
-
-
Dismantling of street light.
25
-
-
Loading and unloading of Transformer upto 100 KVA.
5
-
-
Loading and unloading of Transformer above 100 KVA upto 200 KVA.
10
-
-
Loading and Unloading of HT Metering set.
2
-
-
Erection of New Transformer all Capacities (with Jumpering).
20
-
-
Erection of HT Metering set.
2
-
-
Replacement of failed Transformers all capacities.
2
-
-
Fencing of Distribution Transformer structure at road side fabrication and Erection.
6
-
-
Erection of New earth pipe by replacing the corroded earth pipe.
15
-
-
Releasing of grill from poles.
50
-
-
Re-stringing of HT/LT line ACSR 7/4.09 sqmm(for all sizes of conductors in Km).
2
-
-
Re-stringing of HT/LT line ACSR 7/3.35 sqmm & AAAC 7/3.15 sqmm (for all sizes of conductors in Km).
3
-
-
Re-stringing of HT/LT line ACSR 7/2.59 sqmm & AAAC 7/2.50 sqmm (for all sizes of conductors in Km).
5
-
-
Engaging of JCB / Crane For first 2 Hrs.
20
-
-
Engaging of JCB / Crane For every addition Hrs. `
25
-
-
Cutting of Coconut leaves (per tree).
150
-
-
Clearing of branches of trees.
120
-
-
Drilling of hole in channel only 3/4'' & 1''.
300
-
-
Cutting of Channel.
100
-
-
T.I Fitting welding with Clamps.
105
-
-
Labour charges for alteration of Back Clamps/Stay Clamps to suit for the works.
125
-
-
G.S.T. @18% should be Entered by the Bidder
1
-
-