Rural Development And Panchayat Raj Department Tender
... More
Search from a plethora of business opportunities for Tamil Nadu tenders posted on the eProcurement TamilNadu website and other online and offline sources. Here, on BidAssist, you can find the best tender opportunities to boost your enterprise by finding work in Tamil Nadu government tenders, PSUs, Municipal Corporations and more. Read on to learn about the bidder registration process, DSC and more.
Rural Development And Panchayat Raj Department - RDPR Tender
Civil And Construction
Road Construction
Eprocure
Opening Date26 Apr 2023
Closing Date3 May 2023
Tender Amount₹ 1,28,40,000
Costs
EMD
₹ 1,28,000Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2023_RDTN_306781_1Bid Award Id
ViewTender No
DIPR/2018/Tender/2023 Dated 05.04.2023Tender Authority
Rural Development And Panchayat Raj Department ViewPurchaser Address
-Website
http://https://www.tnrd.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Excavation in soil using Hydraulic Excavator and Tippers with disposal upto 1000m Excavation for road work in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers. Trimming bottom and side slopes , in accordance with requirements of lines grades and cross - section , and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m asb per Technical specification clause 302.3
69.3
-
-
... More
Construction of Embankment with Material Obtained from Road way Cutting Construction of embankment using tractor with grader with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of tables 300.1 and 300.2 as per technical specification clause 301.5 Filing with cut Earth
69.3
-
-
... More
collection and supply of carted earth from approved quarry an average lead 1km including cost and conveyance of all materials to site anf labour charges etc.
266.3
-
-
... More
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in Subbase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
796.87
-
-
... More
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.7 kg/sqm using mechanical means as per Technical Specification Clause 502
6375
-
-
... More
Applying TACK COAT over Primed WBM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
6375
-
-
... More
Providing and laying Bituminious concrete which shall consists of construction of a single course binder /wearing corse on a previosly prepared Bituminousbase to the requirements of the specification using 60/70 grade bitumen as per MorRTH specificaton CI.508.
Km 0/0 - 1/0
159.37
-
-
... More
Providing and laying including cost and conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction at Optimum moisture content and hire fuel charges for powerroller, watersprinkler and all other incidental charges such as traffic barricading and providing dangerlights etc. comp for base-course and side berms
Km 0/0-1/0
337.5
-
-
... More
Km 1/0 -1/155
232.88
-
-
... More
Road Marking by providing and laying of hot applied Thermoplastic Compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5mm exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes.
338
-
-
... More
Provision for Kilometre stones
1
-
-
... More
Provision for Hecta Metre stones
7
-
-
... More
Provision for Supplying and erection of Scheme Name board Cum Citizen Board
1
-
-
... More
Supply and fixing of Cautionary sign board
3
-
-
... More
STOP sign board
1
-
-
... More
Major road ahead
1
-
-
... More
Rubble strips ahead
1
-
-
... More
Polycarbonate molded body solar powered
6
-
-
... More
Rumble strips
2.81
-
-
... More
Thermoplastic Paint
0.5
-
-
... More
studds
60
-
-
... More
60cm equilateral triangle
8
-
-
... More
Towards the charges for routline
maintenance of the road work executed
under PMGSY including dressing of berms
by refilling the gully with the earth from
borrow pits, cleaning of wild seasonal
growth on berms, destilting of side drains
and CD works, white washing guard stones,
painting of KM, HM stones, parapets,
cutting of branches of trees, refixing
displaced guard stones, caution boards,
speed limit boards etc., with the periodicity
for the above activities as prescribed in IRCSP-
20:2002 and as directed by the
departmental officers except for the
constructional defects which has to be
rectified by the contractor at his own cost
-
-
-
... More
For the First Year from the date of
completion of work
1.69
-
-
... More
For the Second Year from the date of
completion of work
1.69
-
-
... More
For the Third Year from the date of
completion of work
1.69
-
-
... More
For the Fourth Year from the date of
completion of work
1.69
-
-
... More
For the Fifth Year from the date of
completion of work
1.69
-
-
... More
2.Renewal of the road from Avalappampatty to Gollapatti road KM 0/0 – 2/790
-
-
-
... More
Clearing the scrub jungle by uprooting including all cutting charges and disposing of the products and clearing as directed by departmental officers including all incidental charges etc. complete.
3348
-
-
... More
Excavation in soil using Hydraulic Excavator and Tippers with disposal upto 1000m Excavation for road work in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers. Trimming bottom and side slopes , in accordance with requirements of lines grades and cross - section , and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m asb per Technical specification clause 302.3
123.62
-
-
... More
Construction of Embankment with Material Obtained from Road way Cutting Construction of embankment using tractor with grader with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of tables 300.1 and 300.2 as per technical specification clause 301.5 Filing with cut Earth
123.62
-
-
... More
collection and supply of carted earth from approved quarry an average lead 1km including cost and conveyance of all materials to site anf labour charges etc.
441.7
-
-
... More
Advance patches of 50mm thick in KM 0/0 - 1/0
7.27
-
-
... More
in KM 1/0 - 2/0
6.14
-
-
... More
in KM 2/0 - 2/790
7.21
-
-
... More
Advance patches of 25mm thick in KM 0/0 - 1/0
4.99
-
-
... More
in KM 1/0 - 2/0
6.13
-
-
... More
in KM 2/0 - 2/790
4.09
-
-
... More
Applying TACK COAT over BT surface
10500
-
-
... More
Providing and laying Bituminious concrete which shall consists of construction of a single course binder /wearing corse on a previosly prepared Bituminousbase to the requirements of the specification using 60/70 grade bitumen as per MorRTH specificaton CI.508.
Km 0/0 - 1/0
262.51
-
-
... More
Providing and laying Gravel in KM 0/0 - 1/0
168.75
-
-
... More
Km 1/0 -2/0
168.75
-
-
... More
Km 2/0 -2/790
133.31
-
-
... More
Road marking
558
-
-
... More
Provision for Kilometre stones
2
-
-
... More
Provision for Hecta Metre stones
11
-
-
... More
Provision for Supplying and erection of Scheme Name board Cum Citizen Board
1
-
-
... More
Cautionary sign board
5
-
-
... More
STOP sign board
1
-
-
... More
Major road ahead
1
-
-
... More
Rubble strips ahead
1
-
-
... More
Polycarbonate molded body solar powered
6
-
-
... More
Rumble strips
2.81
-
-
... More
Thermoplastic Paint
0.5
-
-
... More
studds
40
-
-
... More
60cm equilateral triangle
5
-
-
... More
Towards the charges for routline
maintenance of the road work executed
under PMGSY including dressing of berms
by refilling the gully with the earth from
borrow pits, cleaning of wild seasonal
growth on berms, destilting of side drains
and CD works, white washing guard stones,
painting of KM, HM stones, parapets,
cutting of branches of trees, refixing
displaced guard stones, caution boards,
speed limit boards etc., with the periodicity
for the above activities as prescribed in IRCSP-
20:2002 and as directed by the
departmental officers except for the
constructional defects which has to be
rectified by the contractor at his own cost
-
-
-
... More
For the First Year from the date of
completion of work
2.79
-
-
... More
For the Second Year from the date of
completion of work
2.79
-
-
... More
For the Third Year from the date of
completion of work
2.79
-
-
... More
For the Fourth Year from the date of
completion of work
2.79
-
-
... More
For the Fifth Year from the date of
completion of work
2.79
-
-
... More
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
1
-
-