Search from a plethora of business opportunities for Tamil Nadu tenders posted on the eProcurement TamilNadu website and other online and offline sources. Here, on BidAssist, you can find the best tender opportunities to boost your enterprise by finding work in Tamil Nadu government tenders, PSUs, Municipal Corporations and more. Read on to learn about the bidder registration process, DSC and more.

Highways Department Tender

Works
Road Construction
Eprocure
+1Madurai, Tamil Nadu
Opening Date8 Nov 2024
Closing Date10 Dec 2024
Tender Amount₹ 26,71,70,000 
Notes
Download

Costs

Summary

Widening From Two Lane To Four Lane And Strengthening At Km 92 9 98 0 Of Ramanathapuram Nainarkoil Andakudi Elayankudi Sivagangai Melur Road Sh 34

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Excavation including removal and satisfactory disposal of all materials necessary for the construction of roadway and sidde drains in accordance with the specification and the line, grades and cross sections shown in the drawings or as indicated by the Engineer as per SS 20B for box cutting of widerning portion MORTH 111,112,301 to 305

-

-

-

... More
Road A

24869

146

3651763.96

... More
Road A (Junction Improvements)

610.16

146

89595.89

... More
Road A (Bus Lay Bay)

618.02

146

90750.06

... More
Providing compaction for embankment / making up of low berms using the available box cut earth including all hire and fuel charges for power roller for compaction, water sprinkler, including all labour charges for laying, spreading, watering etc., complete and as directed by the departmental engineers.

-

-

-

... More
Road A

24869

26

662510.16

... More
Granular Sub-base with Graded Material (Table:- 400-1) Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 ) - for grading- V Material as per MORTH Rev. V Clause No. 111, 112, 401 & 900.

-

-

-

... More
Road A

6007

2269

13630784.05

... More
Road A Box Culvert 93/6

24.38

2269

55321.88

... More
Road A (Junction Improvements)

174.99

2269

397078.56

... More
Road A (Bus Lay Bay)

146.25

2269

331863.19

... More
Granular Sub-base with Graded Material (Table:- 400-1) Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 ) - for grading- III Material as per MORTH Rev. V Clause No. 111, 112, 401 & 900.

-

-

-

... More
Road A

4621

2359

10904173.7

... More
Road A Box Culvert 93/6

18.75

2359

44244.38

... More
Road A (Junction Improvements)

85.25

2359

201164.43

... More
Road A (Bus Lay Bay)

120

2359

283164

... More
Wet Mix Macadam (Table 400-13) (Providing, laying, spreading and compacting graded stone aggregates for Wet Mix Macadam 250mm thick, including premixing the materials with water at OMC in mechnanical mix plant, conveyance of mixed materials by tipper to site, laying in uniform layers using pavers in Sub Base / Base course on well prepared surface and compacting with vibratory soil compactor to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5)

-

-

-

... More
Road A

14183

2366

33564494.99

... More
Road A Box Culvert 93/6

46.88

2366

110942.93

... More
Road A (Junction Improvements)

320.07

2366

757455.26

... More
Road A (Bus Lay Bay)

300

2366

709959

... More
Prime coat - Providing and laying PrimeCoat over WBM/ WMM surface using 7Kg of Emulsion Bitumen(SS1) per 10sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5..

-

-

-

... More
Road A

57561

81

4696401.99

... More
Road A (Junction Improvements)

1272.83

81

103850.2

... More
Road A (Bus Lay Bay)

1200

81

97908

... More
Tack Coat - Providing and applying tack coat with bitumen emulsion (RS-I type) using emulsion pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom as per clause 503 - over granular surfaces treated with primer as per MORTH Rev. V Clause No.111, 112,501, 503 & 900.

-

-

-

... More
Road A

57561

18

1082146.8

... More
Road A (Junction Improvements)

1272.83

18

23929.2

... More
Road A (Bus Lay Bay)

1200

18

22560

... More
Tack coat - Providing and layingTackCoat overWBM/ WMM surface (treated with primer) using 0.20Kg of Bitumen Emulsion(RS1) per 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5

-

-

-

... More
Road A

17935

27

484962.4

... More
Road A (Junction Improvements)

1269.13

27

34317.28

... More
Providing, laying 75mm consolidated thick Dense Bituminous Macadam using 0.24cum of 26.50 13.20mm, 0.25 cum of 13.20 -2.36 mm and 0.23cum of 2.36mm & below and with 53.20Kgs of VG40 Grade bitumen for premixing per 10 sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing the min there quired temperature in Central Hot Mix Plant 20-30 toncapacity, conveying the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm using paver to the specified grades and cross sections and compacted by Vibratory / Pneumatic Roller to the required density etc., including labour for attending topaver at site etc., including hire and fuel charges for 20-30 ton CMP with bitumen boiler, tipper trucks,Paver Finisher, Vibratory rollers andall other tools andplant required, includingall other incidental charges etc., complete as per specification using CMP as per clause 505 MORTH Rev-5

-

-

-

... More
Road A

4893

10144

49639142.49

... More
Road A (Junction Improvements)

42.3

10144

429130.54

... More
Road A (Bus Lay Bay)

60

10144

608695.8

... More
Bituminous Macadam -Providing, laying 50mm consolidated thick Bituminous Macadam using 0.20cum of 26.50 13.20mm, 0.43 cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRC metal with 37 Kgs of VG40 Grade bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing the min required temperature using Central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paversite, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10tonne Vibratory Roller to the required density etc., including labour for attending to paver to site etc., including hire and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks,Paver Finisher,Vibratory roller and all other tools and plant required, including all other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH Rev-5

-

-

-

... More
Road A

1126

9378

10559740.6

... More
Road A (Junction Improvements)

102.24

9378

958816.94

... More
Bituminous Concrete - rovidingandlaying Bituminous Concrete to 30/40 mm thick using 0.13 cum of 19.009.50mm, 0.17 cum of 9.50-2.36 mm and 0.26 cum of 2.36 and below with 50.30kgs of VG40 bitumen for premixing per 10s qm including cost and conveyance of all materials to CMPsite, heating the bitumen and aggregate to required temperature andmixing themin required temperature incentral hotmixplant20-30 toncapacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniformthickness of 40mm with mechanical paver to the specified grades and cross section and consolidated by 8-10 tonne Vibratory to th erequired densityetc., including labour for attending to paver to site etc., including hire charges and fuel charges for20-30tCMPwithbitumenboiler, tipper trucks, Paver Finisher,Vibratory roller and all other tools and plant required, including fuel andall other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5

-

-

-

... More
Road A

3020

11767

35538846.6

... More
Road A (Junction Improvements)

142.58

11767

1677857.2

... More
Road A (Bus Lay Bay)

48

11767

564855.84

... More
Construction of cement concrete centre median kerb with top and bottom width 150 and 165 mm respecively, 325 mm high in M 20 grade PCC on M 10 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone laid, foundation concrete laid manually, all complete as per clause 408.

-

-

-

... More
Road A (Centre Median)

9922.62

490

4863274.51

... More
Filling Carted Earth in between gap for median and island and above road level with approved materials deposited at site from roadway cutting and excavation for drain and foundation of otherstructures,spread,greaded and compacted as per CL:407 of MORTH

-

-

-

... More
Road A (Centre Median)

1932.71

42

82816.62

... More
Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of masonry, cement concrete, wood work, steel work, including T & P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres. (Existing Structure PCC)

-

-

-

... More
Road A Box Culvert 93/4

0.9

486

437.58

... More
Road A Box Culvert 93/6

18.32

486

8907.18

... More
Road A Box Culvert 93/8

2.51

486

1220.36

... More
Road A Box Culvert 93/10(ii)

1.17

486

568.85

... More
Road A Box Culvert 94/8

1.23

486

598.03

... More
Road A Box Culvert 95/2

0.4

486

194.48

... More
Road A Box Culvert 95/8

1.35

486

656.37

... More
Earth work excavation in all classes of soil except hard rock requiring blasting and depositing on bank as per SS20B with all leads and lifts and all other incidental charges such as baling out water shoring shrutting, walling & forming protective bunds wherever necessary etc complete as per relevant standard specification for FOUNDATION

-

-

-

... More
Road A Box Culvert 93/4

62.95

290

18255.5

... More
Road A Box Culvert 93/6

283.65

290

82258.5

... More
Road A Box Culvert 93/8

66.79

290

19369.1

... More
Road A Box Culvert 93/10(ii)

66.79

290

19369.1

... More
Road A Box Culvert 94/8

66.79

290

19369.1

... More
Road A Box Culvert 95/2

62.95

290

18255.5

... More
Road A Box Culvert 95/8

62.95

290

18255.5

... More
Plain Cement Concrete of Grade M-15, Nominal Mix 1:2:4 using 40mm ISS HBG metal including cost and conveyance of all materials to site and cement at site including cost of form work, soft water,labour charges for mixing, transporting, laying and curing concrete, working at depths tools and plants and incidental charges such as maintaining of protective bunds, cofferdams, shoring, strutting etc; complete as per relevant standard specification for BASE COURSE OF BOX CULVERT

-

-

-

... More
Road A Box Culvert 93/4

11.97

6132

73400.04

... More
Road A Box Culvert 93/6

18.05

6119

110447.95

... More
Road A Box Culvert 93/8

10.15

6119

62107.85

... More
Road A Box Culvert 93/10(ii)

10.15

6119

62107.85

... More
Road A Box Culvert 94/8

10.15

6105

61965.75

... More
Road A Box Culvert 95/2

11.97

6105

73076.85

... More
Road A Box Culvert 95/8

11.7

6105

71428.5

... More
Vibrated Reinforced Cement Concrete M-25 Grade Design Mix using ISS HBG metal including cost and conveyance of all materials to site and cement at site but excluding cost and fabrication of steel, including labour charges for mixing, transporting, laying, curing concrete, working at heights, hire charges for tools and plants, including all other incidental chargeas, etc., complete for BOX CULVERT BASE SLAB AND WALL

-

-

-

... More
Road A Box Culvert 93/4

18.92

12466

235856.72

... More
Road A Box Culvert 93/6

76.88

12347

949237.36

... More
Road A Box Culvert 93/8

22.5

12336

277560

... More
Road A Box Culvert 93/10(ii)

22.5

12336

277560

... More
Road A Box Culvert 94/8

22.5

12322

277245

... More
Road A Box Culvert 95/2

20.97

12939

271330.83

... More
Road A Box Culvert 95/8

20.97

12939

271330.83

... More
Supply and fabrication of Fe-500 steel required for all RCC items of works involved in the schedule, including cost of steel at site and cost of fabrication labour charges for cleaning the rods straightening,cutting,bending,tying grills, including over laping to the required length wherever necessary and providing to the reinforcement placing the reinforcement in position as specified in the drawings including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges , etc., complete. as per Section 2706 of MORT&H Specficaton (Fifth Revision-2013)

-

-

-

... More
Road A Box Culvert 93/4

1.88

95610

179938.02

... More
Road A Box Culvert 93/6

5.49

95610

524803.29

... More
Road A Box Culvert 93/8

1.66

95610

159095.04

... More
Road A Box Culvert 93/10(ii)

1.66

95610

159095.04

... More
Road A Box Culvert 94/8

1.66

95610

159095.04

... More
Road A Box Culvert 95/2

1.67

95610

159955.53

... More
Road A Box Culvert 95/8

1.69

95610

161198.46

... More
Vibrated Cement Concrete of Grade M-20, Nominal Mix 1:1.5:3 using 40mm ISS HBG metal including cost and conveyance of all materials to site and cement at site including cost of form work, soft water,labour charges for mixing, transporting, laying and curing concrete, working at depths tools and plants and incidental charges such as maintaining of protective bunds, cofferdams, shoring, strutting etc; complete as per relevant standard specification for WING WALLS

-

-

-

... More
Road A Box Culvert 93/4

46.79

8065

377361.35

... More
Road A Box Culvert 93/6

76.69

7855

602399.95

... More
Road A Box Culvert 93/8

76.69

7855

602399.95

... More
Road A Box Culvert 93/10(ii)

76.69

7855

602399.95

... More
Road A Box Culvert 94/8

76.69

7841

601326.29

... More
Road A Box Culvert 95/2

55.62

8011

445571.82

... More
Road A Box Culvert 95/8

55.62

8011

445571.82

... More
Vibrated cement Concrete M30 design mix using ISS size HBG graded metal including cost and conveyance of all materials to worksite and cement at site including all labour charges for fixing concrete, laying, vibrating, hire charges for tools and plants, compacting, curing with all leads for soft water, including all other incidental charges formwork cost of remolded expansion joints and fixing the same in position etc., complete for wearing coat of 75mm uniform thickness over deck slab and approach slab. as per Section 2702.2 of MORT&H Specficaton (Fifth Revision-2013)

-

-

-

... More
Road A Box Culvert 93/4

14.6

670

9795.14

... More
Road A Box Culvert 93/6

50.18

669

33615.58

... More
Road A Box Culvert 93/8

11.18

669

7489.48

... More
Road A Box Culvert 93/10(ii)

11.18

669

7489.48

... More
Road A Box Culvert 94/8

11.18

668

7477.18

... More
Road A Box Culvert 95/2

14.6

668

9764.48

... More
Road A Box Culvert 95/8

14.6

668

9764.48

... More
Providing FILTER MEDIA behind Abutment and Returns for 600mm thickness using filter material conforming to clause 309.3.2.B of MORT&H-Rev.5 well packed with smaller size towards the soil and bigger size towards the wall including cost and conveyance of all materials to worksite including labour charges and all other incidental charges, etc complete. as per CI.710.1.4 & Appendix 6 of IRC :78-2014

-

-

-

... More
Road A Box Culvert 93/4

6.66

1369

9117.54

... More
Road A Box Culvert 93/6

47.97

1359

65191.23

... More
Road A Box Culvert 93/8

14.59

1359

19827.81

... More
Road A Box Culvert 93/10(ii)

14.59

1359

19827.81

... More
Road A Box Culvert 94/8

14.59

1349

19681.91

... More
Road A Box Culvert 95/2

11.78

1349

15891.22

... More
Road A Box Culvert 95/8

11.78

1349

15891.22

... More
Filling behind Abutments and return wall with clean gritty gravel including cost and conveyance of gravel to worksite, laying, handling charges and filling in layers, tamping under optimum moisture content to get the maximum density including watering, with all leads for water and all other incidental charges etc., complete. as per CI.710.1.4 & Appendix 6 of IRC :78-2014

-

-

-

... More
Road A Box Culvert 93/4

26.64

343

9137.52

... More
Road A Box Culvert 93/6

11.99

329

3944.71

... More
Road A Box Culvert 93/8

21.87

343

7501.41

... More
Road A Box Culvert 93/10(ii)

21.87

329

7195.23

... More
Road A Box Culvert 94/8

21.87

329

7195.23

... More
Road A Box Culvert 95/2

17.67

315

5566.05

... More
Road A Box Culvert 95/8

17.67

315

5566.05

... More
Providing and fixing PVC seepage pipes of 110mm dia of required lengths for abutments and wings including costs and conveyance of all materials to work site and labour charges for fixing, etc. complete to drain the backfill in between abutment and wings

-

-

-

... More
Road A Box Culvert 93/4

8.69

192

1672.83

... More
Road A Box Culvert 93/6

18.67

192

3593.98

... More
Road A Box Culvert 93/8

10.27

192

1976.98

... More
Road A Box Culvert 93/10(ii)

10.27

192

1976.98

... More
Road A Box Culvert 94/8

10.28

192

1978.9

... More
Road A Box Culvert 95/2

9.21

192

1772.93

... More
Road A Box Culvert 95/8

8.96

192

1724.8

... More
Excavation including removal and satisfactory disposal of all materials necessary for the construction of roadway and sidde drains in accordance with the specification and the line, grades and cross sections shown in the drawings or as indicated by the Engineer as per SS 20B for box cutting of widerning portion MORTH 111,112,301 to 305

-

-

-

... More
Road A Box Culvert 93/6

165

196

32500.05

... More
Supply of NP3 Class RCC Pipe conforming to IS 458/2003 including cost of pipe as a finished work including all other incidental charges, testing charges including oading, unloading, transport and delivery in good condition at work site etc., complete, as directed by the Departmental Officers, as per standard specifications

-

-

-

... More
Road A Box Culvert 93/6

15

4276

64152

... More
Hoisting and fixing of NP3 Class RCC Pipe and Collars in proper gradient including all labour charges and all other incidental charges etc., complete, as directed by the Departmental Officers, as per standard specifications.

-

-

-

... More
Road A Box Culvert 93/6

15

266

3993

... More
Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of masonry, cement concrete, wood work, steel work, including T & P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres. (Existing Structure PCC M20 grade Hume Pipe Bed)

-

-

-

... More
Road A Slab Culvert 93/10

4

486

1944.8

... More
Road A Slab Culvert 95/2

5.89

486

2863.72

... More
Road A Slab Culvert 95/6

5.89

486

2863.72

... More
Road A Slab Culvert 96/6

11.94

486

5805.23

... More
Road A Slab Culvert 96/6(ii)

5.89

486

2863.72

... More
Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of masonry, cement concrete, wood work, steel work, including T & P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres. (Existing Structure RCC)

-

-

-

... More
Road A Slab Culvert 93/10

5.89

4308

25378.24

... More
Road A Slab Culvert 95/2

4

4308

17234.8

... More
Road A Slab Culvert 96/6(ii)

2

4308

8617.4

... More
Earthwork excavation in all classes of soil except soft disintegrated rock not requiring blasting and hardrock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidential charges such as baling our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for FOUNDATION OF ABUTMENTS, PIERS & RETURN WALL. as per section 300 of MORT&H Specifications (Fifth Revision -2013)

-

-

-

... More
Road A Slab Culvert 93/10

237.66

387

91974.42

... More
Road A Slab Culvert 95/2

140.24

387

54272.88

... More
Road A Slab Culvert 95/6

121.58

387

47051.46

... More
Road A Slab Culvert 96/6

141.78

387

54868.86

... More
Road A Slab Culvert 96/6(ii)

121.58

387

47051.46

... More
Plain Cement Concrete of grade M15 Nominal Mix using 40mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for LEVELLING COURSE.Under footing as per 2100 of MORT&H Specficaton (Fifth Revision-2013)

-

-

-

... More
Road A Slab Culvert 93/10

13.98

6196

86620.08

... More
Road A Slab Culvert 95/2

11.22

6196

69519.12

... More
Road A Slab Culvert 95/6

10.12

6182

62561.84

... More
Road A Slab Culvert 96/6

13.12

6196

81291.52

... More
Road A Slab Culvert 96/6(ii)

10.13

6196

62765.48

... More
Vibrated Cement Concrete of Grade M-20, Nomional Mix, using 40mm ISS HBG metal including cost and conveyance of all materials to site including cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, Tools and Plants and incidental charges such as maintaining of protective bunds, cofferdams, shoring, strutting etc; complete as per relevant standard specification, etc, complete as per relevant standard specification for FOOTINGS OF ABUTMENT AND RETURN WALLS. as per Section 1500,1700 & 2100 of MORT&H Specficaton (Fifth Revision-2013)

-

-

-

... More
Road A Slab Culvert 93/10

157.68

7122

1122996.96

... More
Road A Slab Culvert 95/2

92.86

7238

672120.68

... More
Road A Slab Culvert 95/6

83.8

7278

609896.4

... More
Road A Slab Culvert 96/6

95.5

7318

698869

... More
Road A Slab Culvert 96/6(ii)

83.8

7292

611069.6

... More
Vibrated Cement Concrete of grade M20 Nominal Mix using 40mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF ABUTMENTS, RETURN WALL AND PIERS ABOVE SILL LEVEL. as per Section 1500,1700 & 2200 of MORT&H Specficaton (Fifth Revision-2013)

-

-

-

... More
Road A Slab Culvert 93/10

63.47

9055

574720.85

... More
Road A Slab Culvert 95/2

44.07

9172

404210.04

... More
Road A Slab Culvert 95/6

38.76

9217

357250.92

... More
Road A Slab Culvert 96/6

57.62

9160

527799.2

... More
Road A Slab Culvert 96/6(ii)

38.77

9231

357885.87

... More
Vibrated Reinforced Cement Concrete of grade M30 design mix using ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants including all other incidental charges etc; complete as per relevant standard specifications, for DIRT WALL CUM BED BLOCK OVER ABUTMENTS AND BED BLOCK OVER PIERS.as per Section 1500,1700 & 2200 of MORT&H Specficaton (Fifth Revision-2013)

-

-

-

... More
Road A Slab Culvert 93/10

6.08

13040

79283.2

... More
Road A Slab Culvert 95/2

6.08

13040

79283.2

... More
Road A Slab Culvert 95/6

6.08

13026

79198.08

... More
Road A Slab Culvert 96/6

9.78

12619

123413.82

... More
Road A Slab Culvert 96/6(ii)

6.11

13016

79527.76

... More
Providing and fixing KRAFT PAPER for full width of seating of deck slab and including cost and conveyance to worksite, labour for fixing the same in correct position and all other incidental charges etc., complete.

-

-

-

... More
Road A Slab Culvert 93/10

9.08

110

998.8

... More
Road A Slab Culvert 95/2

9.08

110

998.8

... More
Road A Slab Culvert 95/6

9.08

110

998.8

... More
Road A Slab Culvert 96/6

17.96

110

1975.6

... More
Road A Slab Culvert 96/6(ii)

9.08

110

998.8

... More
Vibrated Reinforced Cement Concrete of grade M30 Design Mix using ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants including all other incidental charges etc; complete as per relevant standard specifications, for DECK SLAB and Safety Kerb. as per Section 1500,1700 & 2300 of MORT&H Specficaton (Fifth Revision-2013)

-

-

-

... More
Road A Slab Culvert 93/10

18.18

12151

220905.18

... More
Road A Slab Culvert 95/2

16.16

12151

196360.16

... More
Road A Slab Culvert 95/6

9.42

12074

113737.08

... More
Road A Slab Culvert 96/6

25.58

12236

312996.88

... More
Road A Slab Culvert 96/6(ii)

9.43

12088

113989.84

... More
Vibrated Reinforced Cement Concrete M-40, Grade, Design Mix, using ISS size hard granite broken graded metal including cost and conveyance of all materials to site including cement at site but excluding cost and fabrication of steel, including labour charges for mixing, transporting, laying, and curing concrete, working at heights, hire charges for tools and plants, including all other incidental charges etc.,, complete for RCC CRASH BARRIERS OVER DECK SLAB. as per Section 811,1700 & 2703.3 of MORT&H Specficaton (Fifth Revision-2013)

-

-

-

... More
Road A Slab Culvert 93/10

3.07

18200

55874

... More
Road A Slab Culvert 95/2

2.73

18048

49271.04

... More
Road A Slab Culvert 95/6

1.59

18067

28726.53

... More
Road A Slab Culvert 96/6

4.27

18328

78260.56

... More
Road A Slab Culvert 96/6(ii)

1.59

18620

29605.8

... More
Vibrated Cement Concrete M20 grade, Nominal Mix using 20mm ISS size hard granite broken metal including cost and conveyance of all materials to site and cement at site including labour charges for mixing, transporting, laying, and curing concrete, working at heights, hire charges for tools and plants, including all other incidental charges,etc.,complete as per standard specification for PCC PARAPETS OVER RETURN WALL. as per Section 1500 & 1700 of MORT&H Specficaton (Fifth Revision-2013)

-

-

-

... More
Road A Slab Culvert 93/10

5.46

13257

72383.22

... More
Road A Slab Culvert 95/2

5.46

13257

72383.22

... More
Road A Slab Culvert 95/6

5.46

13243

72306.78

... More
Road A Slab Culvert 96/6

5.46

13210

72126.6

... More
Road A Slab Culvert 96/6(ii)

5.46

13257

72383.22

... More
Plain Cement Concrete M15 (Nominal mix), using 40mm ISS HBG metal including cost and conveyance of all Materials to site and cement at site including form work , using soft water, labour charges for mixing, transporting and placing in position, compacting, finishing and curing, working at depths, hire charges for tools and plants and incidental charges, etc., complete, as per standard specifications complete as per relevant MORT&H specifications 1000&2100. for Approach Slab Levelling course

-

-

-

... More
Road A Slab Culvert 93/10

8.84

6705

59272.2

... More
Road A Slab Culvert 95/2

8.84

6705

59272.2

... More
Road A Slab Culvert 95/6

8.84

6692

59157.28

... More
Road A Slab Culvert 96/6

8.84

6705

59272.2

... More
Road A Slab Culvert 96/6(ii)

8.83

6705

59205.15

... More
Vibrated Reinforced Cement Concrete of grade M30 (Design mix) using 20mm ISS graded metal including cost and conveyance of all Materials to site excluding cost of steel including cost cement at site and including cost of formwork, labour charges for mixing, transporting, laying and curing concrete, working at heights, soft water, hire charges for Tools and Plants including all other incidental charges etc., complete as per MORT&H specifications 1000,1500,1600,1700 &2300 for Approach Slab.

-

-

-

... More
Road A Slab Culvert 93/10

19.32

9378

181182.96

... More
Road A Slab Culvert 95/2

19.32

9396

181530.72

... More
Road A Slab Culvert 95/6

19.32

9365

180931.8

... More
Road A Slab Culvert 96/6

19.32

9396

181530.72

... More
Road A Slab Culvert 96/6(ii)

19.32

9378

181182.96

... More
Supply and fabrication of Fe- 500 steel required for all RCC items of works involved In Flyover Super structure in the schedule and cost of TOR steel conforming to IS:1786 at site, including fabrication, labour charges for cleaning the rods, straightening, cutting, bending, tying grills with GI wires including overlapping to the required length wherever necessary and placing the reinforcement in position as specified in the drawings, including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc., complete, as per standard specifications Fe-500.

-

-

-

... More
Road A Slab Culvert 93/10

4.53

95610

433113.3

... More
Road A Slab Culvert 95/2

4.34

95610

414947.4

... More
Road A Slab Culvert 95/6

3.46

95610

331001.82

... More
Road A Slab Culvert 96/6

5.66

95610

541535.04

... More
Road A Slab Culvert 96/6(ii)

3.47

95610

331766.7

... More
Supply and fabrication of Fe-240 steel required in the schedule including cost of steel at site cost of providing and cost of fabrication, lablour charges for cleaning the rods, straightening, cutting, bending, tying grills including over lapping to the required rods, straightening, cutting, bending, tying grills including over lapping to the required length wherever necessary and providing to the reinforcement, placing the reinforcement in position as specified in the drawings including cost of PVC coated G.I binding wire of 18G,provision of spacer bars, cover blocks and all other incidental charges etc complete, Fe-240 grade for REINFORCEMENT FOR WEARING COAT

-

-

-

... More
Road A Slab Culvert 93/10

0.9

95610

86049

... More
Road A Slab Culvert 95/2

0.9

95610

86049

... More
Road A Slab Culvert 95/6

0.8

95610

76488

... More
Road A Slab Culvert 96/6

0.96

95610

91785.6

... More
Road A Slab Culvert 96/6(ii)

0.8

95610

76488

... More
Vibrated Cement concrete M30 Grade (Design mix) using 25mm,12mm,and 6mm IRC size hard broken granite metal including cost and conveyance of all materials to side cost of premoulded expansion joints and fixing the same in position including cost and labour charges for formwork, labour charges for laying , compacting , curing including all other incidental charges etc, complete for WEARING COAT 75mm uniform thickness over Deck Slab.

-

-

-

... More
Road A Slab Culvert 93/10

114.08

669

76422.19

... More
Road A Slab Culvert 95/2

108.56

669

72724.34

... More
Road A Slab Culvert 95/6

90.16

668

60299.01

... More
Road A Slab Culvert 96/6

102.12

669

68410.19

... More
Road A Slab Culvert 96/6(ii)

90.16

669

60398.18

... More
Supplying and fixing GI DRAINAGE SPOUTS 100mm dia as per GOI drawing SD/205 with grating arrangements at top as shown in the drawing and 100mm dia drainage spout projecting atleast 300mm beyond the bottom of deck slab as shown in the drawing, including cost and conveyance of Galvanised iron pipes and flats and fixing them in position, etc., complete as per cl 2705 of MORT&H specification. (V Revision)

-

-

-

... More
Road A Slab Culvert 93/10

2

2498

4996.2

... More
Road A Slab Culvert 95/2

2

2498

4996.2

... More
Road A Slab Culvert 95/6

2

2498

4996.2

... More
Road A Slab Culvert 96/6

4

2498

9992.4

... More
Road A Slab Culvert 96/6(ii)

2

2498

4996.2

... More
Providing FILTER MEDIA behind Abutment and Returns for 600mm thickness using filter material conforming to clause 309.3.2.B of MORT&H-Rev.5 well packed with smaller size towards the soil and bigger size towards the wall including cost and conveyance of all materials to worksite including labour charges and all other incidental charges, etc complete. as per CI.710.1.4 & Appendix 6 of IRC :78-2014

-

-

-

... More
Road A Slab Culvert 93/10

38.25

1359

51981.75

... More
Road A Slab Culvert 95/2

29.52

1359

40117.68

... More
Road A Slab Culvert 95/6

26.91

1349

36301.59

... More
Road A Slab Culvert 96/6

27.23

1359

37005.57

... More
Road A Slab Culvert 96/6(ii)

26.91

1359

36570.69

... More
Providing and fixing moulded Bitumen joint pad, for expansion joint including cost of sealing coumpound and priming cost clause 2100 of MORT & H Specification

-

-

-

... More
Road A Slab Culvert 93/10

6.74

719

4846.06

... More
Road A Slab Culvert 95/2

6.74

719

4846.06

... More
Road A Slab Culvert 95/6

6.74

719

4846.06

... More
Road A Slab Culvert 96/6(ii)

6.74

719

4846.06

... More
Supplying and fixing 300mm wide PVC EXPANSION JOINT in the 20mm expansion gap provided in between decks over piers and in between deck and dirt wall over abutment as shown in the drawing including cost and conveyance of expansion joints including shalimar pad and joint sealant etc., complete (In Deck slab)

-

-

-

... More
Road A Slab Culvert 96/6

3.37

653

2201.96

... More
Filling behind Abutments and return wall with clean gritty gravel including cost and conveyance of gravel to worksite, laying, handling charges and filling in layers, tamping under optimum moisture content to get the maximum density including watering, with all leads for water and all other incidental charges etc., complete. as per CI.710.1.4 & Appendix 6 of IRC :78-2014

-

-

-

... More
Road A Slab Culvert 93/10

104.39

329

34344.31

... More
Road A Slab Culvert 95/2

86.46

315

27234.9

... More
Road A Slab Culvert 95/6

81.37

315

25631.55

... More
Road A Slab Culvert 96/6

18.05

315

5685.75

... More
Road A Slab Culvert 96/6(ii)

80.95

315

25499.25

... More
Providing weep holes in brick masonry/plain/reinforced concrte abutment,wing wall/return wall with 150 mm dia P.V.C Pipe extending through the full width of the structure with slope of 1V: 20H towards drawing foce. Complete as per Drawing and Technical Specifications., (Weep hole)

-

-

-

... More
Road A Slab Culvert 93/10

57.76

192

11118.8

... More
Road A Slab Culvert 95/2

52.96

192

10194.8

... More
Road A Slab Culvert 95/6

51.36

192

9886.8

... More
Road A Slab Culvert 96/6

47.44

192

9132.2

... More
Road A Slab Culvert 96/6(ii)

47.82

192

9205.35

... More
Painting two coats with Ready mix plastic enamel paint and approved colour including priming coat over the cement surface complete including scrapping clean removal of dirt of parts over cement surface

-

-

-

... More
Road A Slab Culvert 93/10

56.38

250

14100.64

... More
Road A Slab Culvert 95/2

53.58

250

13400.36

... More
Road A Slab Culvert 95/6

44.26

250

11069.43

... More
Road A Slab Culvert 96/6(ii)

44.26

250

11069.43

... More
Earthwork excavation in all classes of soils except hard rock requring blasting depositing on bank with all leads and lifts as per SS 20B including cost of all labour,materials, tools, equipments and all incidential charges such as bailing out water providing and maintaining necessary conferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and cleaning the site and disposal of all surplus materials etc complete as per relevant standard specifiation for FOUNDATION OF RETAINING WALL

-

-

-

... More
Road A (Retaining wall)

139.2

123

17157.79

... More
Vibrated Cement Concrete of Grade M-15, Nominal Mix 1:2:4 using 40mm ISS HBG metal including cost and conveyance of all materials to site and cement at site including cost of form work, soft water,labour charges for mixing, transporting, laying and curing concrete, working at depths tools and plants and incidental charges such as maintaining of protective bunds, cofferdams, shoring, strutting etc; complete as per relevant standard specification for BELOW SILL LEVEL

-

-

-

... More
Road A (Retaining wall)

103.66

7214

747844.7

... More
Vibrated Cement Concrete of Grade M-15, Nominal Mix 1:2:4 using 40mm ISS HBG metal including cost and conveyance of all materials to site and cement at site including cost of form work, soft water,labour charges for mixing, transporting, laying and curing concrete, working at depths tools and plants and incidental charges such as maintaining of protective bunds, cofferdams, shoring, strutting etc; complete as per relevant standard specification for ABOVE SILL LEVEL

-

-

-

... More
Road A (Retaining wall)

68.85

9339

643041.79

... More
Providing and fixing SEEPAGE PIPES of 110mm dia PVC pipes of required length for Retaining Walls including cost and conveyance of all materials to worksite, cost and labour for 900mm dia. Semi-spherical back fill arrangements with 100mm size broken granite chips at the periphery and labour charges for fixing etc., to drain of the Backfill in the Retaining Wall

-

-

-

... More
Road A (Retaining wall)

25.68

192

4943.4

... More
Filling behind Abutments and return wall with clean gritty gravel including cost and conveyance of gravel to worksite, laying, handling charges and filling in layers, tamping under optimum moisture content to get the maximum density including watering, with all leads for water and all other incidental charges etc., complete. as per CI.710.1.4 & Appendix 6 of IRC :78-2014 (Refilling labour charge only)

-

-

-

... More
Road A (Retaining wall)

169.85

289

49108.73

... More
Providing and laying of hot applied Thermoplastic compound 2.5 mm thick including reflectorising Unit RM Basic Rate approved for the year 2024-2025 (w.e.f. 15.07.2024) 6500.00 glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes etc., complete as per MoRT&H specification No.803

-

-

-

... More
Road A (Road Furniture)

4041

890

3596490

... More
Providing and fixing reflective road studs of ‘category A’ Raised pavement markers made out of poly carbonate / methyl methercrylate/ABS moulded body confirming to ASTM D 788 and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face with retro reflectance and chromaticity values conforming to ASTM D4280. The reflective raised pavement markers shall also confirm to the MORTH circular No RW / NH. 33023/10/ 97-DO. III dt 11.06.97. The height, width and length shall not be less than 15 mm, 90 mm and 100 mm and with minimum reflective area of 13 Sq.cm on each side and the slope to the base shall be 35 +/- 5 degree. Each reflector shall have a CIL not less than values specified in Table 2 of said MORTH circular. The strength of detachment of the integrated cylindrical shanks, (of diameter not less than 19 +/- 2mm and height not less than 30+/- 2 mm) from the body is to be a minimum value of 500 Kgf. Fixing will beby drilling holes on the road for the shanks to go inside, without nails and using epoxy resin based adhesive as permanufacturer’s recommendation and complete as directed by the engineer. The marker shall support a load of 13635 Kg tested in accordance with ASTM D4280 and confirming to IRC 35 - 2015 guidelines and MoRT&H specification 804 etc., complete

-

-

-

... More
Road A (Road Furniture)

26558

480

12747840

... More
Supplying of Solar Raised Pavement Markers made of polycarbonate molded body, solar powered, LED self- illumination in active mode, 360 degree illumination and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face in passive mode. The product shall support a load of 13635 kg tested in accordance to MORTH and ASTM D 4280 Type H. The product should be resistant to water ingress according to IP 65 standards with IS 12063: 1987 Category 2 and should withstand temperatures in the range of -7 C to 70 C. Flashing rate and color of lighting is to be provided as per requirement. There should be minimum current losses of less than 20 micro-amperes in sleep-charging mode to enhance product life and single charge should provide for a minimum autonomy of 50 hours. The height, width and length shall not be less than 10 mm x 100 mm x 100 mm. Fixing will be by drilling holes on the road for the shanks to go inside, without nails and using epoxy resin based adhesive as per manufacturer's recommendation and complete as directed by the engineer. Warranty Certificate and test reports confirming to compressive strength as per MORTH circular shall be obtained from the manufacturer and submitted to the engineer-in-charge. Two Years Warranty Certificate for Solar RPM for the quantity installed and a certified copy of test reports from an independent test laboratory conforming to water ingress shall be obtained from the Manufacturer by the contractor and submitted to the engineer-in-charge.

-

-

-

... More
Road A (Road Furniture)

140

3300

462000

... More
Providing and erecting of Retro - Reflectorised Cautionary, Mandatory and Informatory signs (without definition board) made out of High Intensity Prismatic Grade Sheeting confirming to Type-IV standards of IRC-67: 2012 and ASTM D 4956 –09, specification and fixed over 2mm thick Aluminium sheet fixed over a back supporting frame of 25mm x 25mmx3mm Mild Steel angle and supported on amild steel angle post 75X75X6mm with a clear height of not less than 2.10m from the ground level to the bottom of the sign board and 0.60m below ground level. The sign post should be painted as per IRC 67-2012 and firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45cmX45cmX60cm size including cost and conveyance of all materials, equipment, Machinery and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer-in-charge. High intensity Retro - Reflectro shee shall consist of minimum coefficient of Retro-reflection as per Table 6.6 of IRC 67-2012. The retro - reflective sheeting shall be covered under 7 year warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC 67:2012 . ( as per MoRT&H SpecificationNo.801)

-

-

-

... More
90cm Equilateral triangle

-

-

-

... More
Road A (Road Furniture)

10

5126

51260

... More
60cm circular

-

-

-

... More
Road A (Road Furniture)

16

4513

72208

... More
80x60CM Rectangular

-

-

-

... More
Road A (Road Furniture)

10

6349

63490

... More
60x60CM Square

-

-

-

... More
Road A (Road Furniture)

35

5184

181440

... More
90CM High Octagon

-

-

-

... More
Road A (Road Furniture)

10

8205

82050

... More
Hazard Marker Traffic Signs - Type-IV - Providing and Erecting of Retro - Reflectorised Hazard Marker Traffic Sign made out of High Intensity Prismatic Grade Sheeting confirming to Type-IV standards of IRe-67: 2012 and ASTM D 4956 -09, specification and fixed over 2mm thick Aluminium sheet fixed over a back supporting frame of 25mmx25mmx3mm Mild Steel angle and supported on a mild steel angle post 75X75X6mm and 0.60m below ground level. The sign post should be painted as per IRe 67-2012 and firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45cmX45cmX60cm size including cost and conveyance of all materials, equipment, Machinery and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge. High intensity Retro - Reflectro sheet shall consist of minimum coefficient of Retro-reflection as per Table 6.6 of IRe 67-2012. The retro- reflective sheeting shall be covered under 7 year warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRe 67:2012. (as per MORT&HSpecification No.801)

-

-

-

... More
Road A (Road Furniture)

30

4000

120000

... More
Providing and erecting Direction and Place Identification Retro-reflectorised Sign made out of High Intensity Prismatic Grade Sheeting confirming to Type-IV standards of IRC-67 : 2012 and ASTM D 4956-09, specification and fixed over 2mm thick Aluminium sheet fixed over a back supporting frame of 25mm x 25mm x 3mm Mild Steel angle and supported on a mild steel angle post 75x75x6mm with a clear height of not less than 2.10m from the ground level to the bottom of the sign board and 0.60m below ground level. The sign post should be painted as per IRC 67-2012 and firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45cm x 45cm x 60cm size including cost and conveyance of all materials, eqipment, machinery and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge, High intensity Retro - Relectro sheet shall consist of minimum coefficient of Retro-reflection as per Table 6.6 of IRC 67-2012. The retro - reflective sheeting shall be covered under 7 year warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC 67:2012 (as per MORT&H Specification No.801)

-

-

-

... More
or sign having area more than 0.6

-

-

-

... More
Road A (Road Furniture)

29.16

11491

335077.56

... More
Rigid Median Marker Providing fixing of Median marker double sided made of polycarbonate for impact resistance and good weather ability. Polycarbonate used for molding the median marker shall have a minimum Izod impact strength value of 600 J!m at room temperature. The impact strength of the poly carbonate should not decrease to less than 70% of its initial value on being subjected to UV weathering as per ASTM G 155 for 1000 hours or exposure to 2 years of natural weathering. The body of the median marker shall be in the form of an isosceles trapezoidal structure of length 15 ern height and width of 10 x 10 cm. The median marker shall have fluorescent yellow retro - reflective sheeting confirming to Tpe XI specifications as per ASTM D 4956.Area of reflective sheeting should not be less than 70 cm2 .Edge of retro reflective shall be concealed using a grill! mesh! similar mechanism to prevent vandalism and sheeting pilferage. The logo of the manufacturer shall be embossed and painted in contrasting colour on both side of median marker for distinct identification.

-

-

-

... More
Road A (Road Furniture)

2080

470

977600

... More
Solar Blinker Proving and fixing Solar powered Traffic Blinkers of 30cm dia with Polycarbonate Dome 5mm Red of Led 150 Nos. iri each Red Blinkers Light - 1 No. with Red / White / Blue Led Blinkers Delineator Solar Panel : 12v 50w Solar Panel — 1 No. 12v 18 AH Battery - 1 No. with Box, Solar Circuit Controller Board Box. Straight Pole : MS Pole 3” dia 2.5mm thick 18 Feet height pole (1 No.) with 2 Feet under ground pole foundation, pole painting including transportation charges, installation charges etc., complete as per standard specification

-

-

-

... More
Road A (Road Furniture)

20

25000

500000

... More
Metal Beam Crash Barrier Type - A, "w" single Guard Providing and erecting Single sided Double Guard Metal Beam Crash Barrier System 1.70m high, comprising of 3mm thick wall “W” beams posts and spacer channels shall be made by cold roll forming using HR conform to IS 5986 Fe 410/360 and dip galvanized having Zinc Mass of 550gms/ sqm, minimum 950mm above road/ ground level fixed on ISMC series channel vertical post 150x75x5mm spaced 2m center to center 312mm x 83mm flange width x 3mm thick, 4318mm long post directly embedded in the concrete (M15) pit size 350x350x800mm for a depth of 750mm below ground. All fixing bolts and nuts hot dip galvanized conforming to IS:1367 clause 4.60 all complete as per Technical Specification and as directed by the Engineer-in-charge

-

-

-

... More
Road A (Road Furniture)

1000

6500

6500000

... More
Road Delineators Supplying and installation of delineators (road way indicators, hazard markers and object markers), 80-100 ern high above ground level, painted at alternatively black and white in 15 em wide strips, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels at the top, buried or pressed into the ground and conforming to IRC-79 etc., complete (as per MORT&Hspecification No. 806)

-

-

-

... More
Road A (Road Furniture)

60

2400

144000

... More
Supply and fixing of Kilometre stone of standard design and drawing as per IRC:8-1980 (second revision),including painting and numbering etc., and all other incidental charges etc., complete.

-

-

-

... More
Road A (Road Furniture)

7

2197

15379

... More
Supply and fixing of HM stone of standard design and drawing as per IRC:26-1967, including painting and numbering etc., and all other incidental charges etc., complete.

-

-

-

... More
Road A (Road Furniture)

20

574

11493

... More
Basic cost of value put to tender as per estimate

1

226412449

-

... More
Add GST at 18%

1

40754241

-

... More
Total Value put to Tender

1

267166690

-

... More
Negotiated Percentage

1

-

-

... More
Final Negotiated Value

1

-

-

... More
Add GST at 18% of Final Negotiated Value

1

-

-

... More
Total Value of Contract Including 18% of GST

1

-

-

... More
Basic cost of value put to tender as per Estimate

-

-

226412449

... More
Quoted Rate in Figures (Total Value of Contract Including 18% of GST )

-

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements

Past Bidders
This list is curated from the bidders of the similar tenders in the past

Unlock the Tender details for free
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.