Forest Department Tender

If you're looking for Rajasthan tenders online and are tired of typing tender ID over and again or going through the cumbersome government websites for it, you are in luck. We have collated every Eproc Rajasthan tender on BidAssist. And for any queries related to an e-tender Rajasthan, like bidding process, registration process, etc., are explained below. Read on.

Forest Department Tender

Works
Agriculture or Forestry Works
Eprocure
Opening Date26 Dec 2024
Closing Date2 Jan 2025
Tender Amount₹ 17,85,000 
Notes
Download

Costs

  • EMD

    ₹ 35,700
  • Document Cost

    ₹ 500
  • Tender Fee

    ₹ 500

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
2.3 Fencing by dry stone masonry: 2.3.3 Repairing of stone wall fencing in standard size by using the fallen stone 795 rmt.

667.8

194

129720.15

... More
2.2.1 New Ditch fencing:Digging of soil,taking out excavated soil and making the bund inside, Size of ditches 1.2m deep,1.5m wide at top and 0.9 wide at bottom,Dressing, alignment and layout(Vol.per runing meter m is equal to 1.44 cum. 2.2.1.1 Sandy Loam 63 rmt.

90.72

108

9862.17

... More
3.29 For the following works carried out by mechanical means (JCB) rates will be as: 3.29.1.1 Sandy loam soil 3.29.1 New ditch fencing excavation:-1.2 meter deep, 1.5 meter wide at top and 0.90 wide at bottom (1.44 cum) dug out of soil and making the 252 rmt.

362.88

60

21888.92

... More
2.2.1 New Ditch fencing:Digging of soil,taking out excavated soil and making the bund inside,Size of ditches 1.2m deep,1.5m wide at top and 0.9 wide at bottom,Dressing,alignment and layout(Vol.per runing meter m is equal to 1.44 cum. 2.2.1.2 Clayey Loam 120 rmt.

172.8

126

21923.14

... More
3.29 For the following works carried out by mechanical means (JCB) rates will be as: 3.29.1.2 Hard Clayey Loam Soil 3.29.1 New ditch fencing excavation:-1.2 meter deep, 1.5 meter wide at top and 0.90 wide at bottom (1.44 cum) dug out of soil and makin 480 rmt.

691.2

72

50125.82

... More
Providing and laying in position cement concrete including curing compaction etc. complete in specified grade excluding the cost of centring and shuttering All work up to plinth level. M15 grade Nominal Mix 1:2:4 (1 cement : 2 coarse sand : 4 graded stone)

2.23

3900

8697

... More
Providing and fabricating reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding (including cost of binding wire) all complete up to floor five level Cold twisted deformed bars 2.1x4+0.35x3=9.45 m x0.22 kg=2.079 kg per poll x 85 Post

176.72

66

11663.52

... More
Centring & Shuttering with plywood or steel sheets including strutting, propping bracing both ways with steel props and removal of formwork for upto floor five level for : beam 2.1x(0.1+0.15)+01x2.1x2=0.2x2.1+0.42=0.945 sqmx 85 poll

80.33

258

20725.14

... More
2.4.1 Barbed wire fencing 2.4.1.3 Transportation of Ready Blocks of Cement Concrete from 0 to 5 Kms.

85

17

1498.55

... More
2.4.1 Barbed wire fencing 2.4.1.4.1 Fixing of Cement/concrete Blocks on the spot by digging pit (khadda) including local transport

85

20

1764.6

... More
2.4.1 Barbed wire fencing 2.4.1.4.2 Tie the barbed wire and tighten it by thin wire 2.4.1.4 Fixing of Cement or Concrete blocks 405 rmt x 5 line

2025

2

4981.5

... More
2.4.1 Barbed wire fencing 2.4.1.4.3 Interlacing local bushes in barbed wire 2.4.1.4 Fixing of Cement or Concrete blocks 405 rmt

405

8

3316.95

... More
Supply/Purchase of Barbed wire for fencing

338

66

22308

... More
2.1 Advanced soil work 2.1.3 Layout for excavation of trenches 12000 rmt

12000

-

9960

... More
2.7.1 Digging of trenches (size 45cm x 45 cm)and separating stones from dugup soil and making mounds of the soil 2.7.1.1 Sandy loam soil 2500 rmt

506.25

106

53773.88

... More
2.7.1 Digging of trenches (size 45cm x 45 cm)and separating stones from dugup soil and making mounds of the soil 2.7.1.2 Clayey Loam Soil 3000 rmt

607.5

119

72353.25

... More
2.7.1 Digging of trenches (size 45cm x 45 cm)and separating stones from dugup soil and making mounds of the soil 2.7.1.3 Hard clayey Soil upto 20% boulders 6000 rmt

1215

158

191994.3

... More
2.7.1 Digging of trenches (size 45cm x 45 cm)and separating stones from dugup soil and making mounds of the soil 2.7.1.4 Hard clayey Soil more than 20% boulders 500 rmt

101.25

204

20712.71

... More
2.1 Advanced soil work 2.1.3 Layout for excavation of V-Ditches 800 rmt

800

-

664

... More
2.8 Digging of V-Ditches Size ( 0 + 0.3)/ 2x 1.2 M, ( 0.18 Cum per running meter) 2.8.1 Sandy loam soil 400 rmt

72

93

6711.84

... More
2.8 Digging of V-Ditches Size ( 0 + 0.3)/ 2x 1.2 M, ( 0.18 Cum per running meter) 2.8.2 Hard Clayey Loam Soil 400 rmt

72

108

7827.12

... More
2.1 Advanced soil work 2.1.2 Layout for excavation of pits 10000 nos

10000

-

9000

... More
2.6.1 Soil work:- Digging of pits (size 0.45 x 0.45 m x 0.45 m or (0.50+0.40)/2 X 0.45 cubic meter 2.6.1.1 Sandy loam soil 3000 pit

3000

10

30630

... More
2.6.1 Soil work:- Digging of pits (size 0.45 x 0.45 m x 0.45 m or (0.50+0.40)/2 X 0.45 cubic meter 2.6.1.2 Clayey Loam Soil 7000 pit

5000

12

60350

... More
2.6.1 Soil work:- Digging of pits (size 0.45 x 0.45 m x 0.45 m or (0.50+0.40)/2 X 0.45 cubic meter 2.6.1.3 Hard clayey Soil upto 20% boulders 1000 nos

1000

15

15140

... More
2.6.1 Soil work:- Digging of pits (size 0.45 x 0.45 m x 0.45 m or (0.50+0.40)/2 X 0.45 cubic meter 2.6.1.4 Hard clayey Soil more than 20% boulders 1000 nos

1000

18

18330

... More
3.28 Seed Collecting (rates of clean seeds) Note: If these are available in the market at lower rates. these should not be departmentally collected. 3.28.2 Babool

60

61

3700.8

... More
3.28 Seed Collecting (rates of clean seeds) Note: If these are available in the market at lower rates. these should not be departmentally collected. 3.28.3 Ber (kernels)

80

93

7471.2

... More
3.28 Seed Collecting (rates of clean seeds) Note: If these are available in the market at lower rates. these should not be departmentally collected. 3.28.6 Kumtha

150

116

17443.5

... More
3.28 Seed Collecting (rates of clean seeds) Note: If these are available in the market at lower rates. these should not be departmentally collected. 3.28.7 Acacia Tortalis

50

82

4140.5

... More
3.28 Seed Collecting (rates of clean seeds) Note: If these are available in the market at lower rates. these should not be departmentally collected. 3.28.11 Ronz

40

137

5497.2

... More
3.28 Seed Collecting (rates of clean seeds) Note: If these are available in the market at lower rates. these should not be departmentally collected. 3.28.22 Karanj

30

155

4651.2

... More
3.28 Seed Collecting (rates of clean seeds) Note: If these are available in the market at lower rates. these should not be departmentally collected. 3.28.23 Ratanjot

70

66

4685.8

... More
3.28 Seed Collecting (rates of clean seeds) Note: If these are available in the market at lower rates. these should not be departmentally collected. 3.28.27 Churel

30

280

8404.2

... More
3.28 Seed Collecting (rates of clean seeds) Note: If these are available in the market at lower rates. these should not be departmentally collected. 3.28.28 Khejadi

10

172

1726.7

... More
3.28 Seed Collecting (rates of clean seeds) Note: If these are available in the market at lower rates. these should not be departmentally collected. 3.28.29 Dhaman Grass

50

144

7223

... More
2.11 Soil Conservation work 2.11.1 To make check dams- Making check dams with dry stones (show the number of check dams and measurements in the measurement book) along with excavation and breaking of stones volume includes voids 100 cum

300

288

86481

... More
2.11.4 Making Earthen Check dam (volume including voids) 2.11.4.1 Sandy loam soil

2800

70

198268

... More
2.11.4 Making Earthen Check dam (volume including voids) 2.11.4.2 Clayey loam soil

800

99

79496

... More
Digging of Nadi No 01 6.2.1.2 In hard soil work through mechanical means

1150

100

115460

... More
Digging of Nadi No 02 6.2.1.2 In hard soil work through mechanical means

915

100

91866

... More
Digging of Nadi No 03 6.2.1.1 In soft/ordinary soil through mechanical means

1050

86

90300

... More
3.12 Fixing slab/ stone for marking blocks in tree plantation area:- Digging one foot deep pit and fixing stone and white washing including numbering.

2700

7

19089

... More
3.23 Construction of kutcha roads for vehicles movement.

2100

3

7392

... More
3.25 Miscellaneous 3.25.3 Watchman work in plantation area

78

259

20202

... More
Round Hodi Nirman - 41 B1.1.8 Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils

7.42

155

1150.1

... More
14 B4.4 Providing and laying in position specified grade of cement concrete for RCC structural elements upto floor five level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers( as required) excluding the cost of centering, shuttering and reinforcement for Arches, arch ribs, domes, vaults, shells, folded plate, chimneys, shafts , roofs having slope more than 15º ,vertical and horizontal fins individually or forming box louvers, facias and eaves boards M20 grade Nominal Mix / Design Mix

3.45

5154

17781.3

... More
62 B11.3.2 Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry, making of lines or groove etc complete but excluding the cost of nosing of steps etc. complete. 75mm thick with 20mm thick nominal size aggregate.

3.79

397

1504.63

... More
318 B6.1.7 Random Rubble stone masonary for foundation and plinth in Cement Sand Mortar above 30 Cm. thick wall in : Cement Mortar 1:6 (1Cement:6Sand).

1.62

2775

4495.5

... More
97 B6.2.7 Random Rubble stone masonary for superstructure above plinth level one storey height above 30 Cm. thick walls in : Cement Mortar 1:6 (1Cement:6Sand).

1.62

3220

5216.4

... More
99 B11.26 Random rubble dry stone Kharanja under floor.

0.45

1098

494.1

... More
4 BJ10.1.1 Stone slab roofing on ground for with fine grained stone slab from approved quarry with 150 mm top lime terracing with Hemp, Methi, Lime, Sandla with Gur & Gugal (as per JODHPUR PRACTICE) including ralthal, filling of joints of parapet and slab on both sides in cement sand mortar 1:4 lime batta (gola) 75mmx75mm Sandla and ceiling plaster in CM 1:4 with wire and nails etc. complete as per specification for span. Upto 2.00 metre.

3.79

2064

7822.56

... More
186 B12.1.1 Plaster on new surface on wall in cement sand mortar 1:3 including racking of joints etc. complete fine finish : 25 mm thick

35.44

228

8080.32

... More
Gate Pillar Nirman - 41 B1.1.8 Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils

2.33

155

361.15

... More
19 B3.1.6 Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering All work up to plinth level. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size).

0.35

2859

1000.65

... More
318 B6.1.7 Random Rubble stone masonary for foundation and plinth in Cement Sand Mortar above 30 Cm. thick wall in : Cement Mortar 1:6 (1Cement:6Sand).

1.98

2775

5494.5

... More
97 B6.2.7 Random Rubble stone masonary for superstructure above plinth level one storey height above 30 Cm. thick walls in : Cement Mortar 1:6 (1Cement:6Sand).

2.97

3220

9563.4

... More
186 B12.1.1 Plaster on new surface on wall in cement sand mortar 1:3 including racking of joints etc. complete fine finish : 25 mm thick

15.81

228

3604.68

... More
H-Shedule Item

-

-

-

... More
Constrution of Cattle guard Hut size 02 meter wide round shape with hight 03 meter (Jhopa) Prepare by Pal, Sarpani, Munjh Jewadi, etc

1

30000

30000

... More
Providing and fixing steel gate, grating and grills made of angles, tees, square bars, flats of black pipe with hold fast and fittings complete as per design and drawing including cutting welding and fabrication with priming coat of red oxide.

120

105

12600



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.