If you want to inquire about any e-tender the Punjab government has posted, Bidassist gives a one-stop solution i.e. being a registered bidder you will find every eprocurement Punjab tender on BidAssist.There is no need to enter all the details on the website of etender.up.nic.in as BidAssist helps you find the specific Punjab etender you're looking for. Read further to learn how to search and bid for etender Punjab.

Water Resources Department - WRD Tender

Works
Civil And Construction
Construction Material
Eprocure
Opening Date27 Jun 2024
Closing Date22 Jul 2024
Tender Amount₹ 1,26,47,072 
Notes
Download

Costs

  • EMD

    ₹ 2,52,941
  • Document Cost

    ₹ 5,000
  • Tender Fee

    ₹ 5,900

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Excavation of Soil using Hyraulic Excavator and hydraulic Tractor Trolly I/C cutting and loading in Trolly and transporting to the embankment locations with all lifts and leads. (a) Disposal/carraige from 0 upto 450m

7491.37

-

-

... More
Excavation of Soil using Hyraulic Excavator and hydraulic Tractor Trolly I/C cutting and loading in Trolly and transporting to the embankment locations with all lifts and leads. (b) Disposal/ carraige additional beyond 450m upto 1Km

7491.37

-

-

... More
Excavation of Soil using Hyraulic Excavator and hydraulic Tractor Trolly I/C cutting and loading in Trolly and transporting to the embankment locations with all lifts and leads. (c) Disposal/carraige for every additional Km upto 10Km

7491.37

-

-

... More
Extra for laying earth as per specification for compaction in 20 Cm. layers and dressing including the cost of rolling and watering as per P.W.D specifications.

7016.4

-

-

... More
Earth work for lip cutting for lining of irrigation channels inclusive of all allowance leads and dressing( as per earth work statement) (a) 0-1.5mt. depth

2763.47

-

-

... More
Dismantling of old lining and brick work in cement sand and mortar.

803.35

-

-

... More
Dressing of Earth work ( NEW )

32390.78

-

-

... More
Dressing and preparation of sub grade for side slopes.

13663.36

-

-

... More
Providing and laying Cement concrete (M-15) sleepers in bed and side slopes below the joints of concrete lining mixed in automatic computerized batching and mixing plant and transported to the site in transit mixers including supply carriage, loading & unloading of material complete in all respect as per design/drawing and PWD specifications IN SLEEPERS

51.16

-

-

... More
Laying 1:3 (cement: water) cement slurry with cement @ 2.25 kg per sqmt on prepared bed & side slope before laying concrete

16213.05

-

-

... More
Cement concrete lining 75mm. thick or less laid manually for irrigation channels, using cement concrete M-15 with cement content 325 kg/cum mixed in an automatic computerized Batching & Mixing Plant and transported to the site in transit mixers with an average lead of 1 Km(FOR TRAPEZOIDAL SECTION AND CUP SECTION OF ALL RADII)

873.91

-

-

... More
Providing and laying Cement concrete (M-15) for coping mixed in automatic computerized batching and mixing plant and transported to the site in transit mixers including supply ,carriage, loading & unloading of material complete in all respect as per design/drawing and PWD specifications IN COPING

164.67

-

-

... More
Filling of construction joints with sealing compound as per drawings and technical specifications with coarse sand and 6 per cent bitumen by weight-10 mm depth

4761.92

-

-

... More
Filling expansion joints with special impervious hot pour 12.5 mm wide

132.44

-

-

... More
Providing and laying LDPE 150 micron over sleeper on construction joints and expansion joints complete in all respect as per design/drawing and PWD specifications

94.22

-

-

... More
Shuttering for faces of concrete lining on side slopes and bed complete in all respect as per design/drawing and PWD specifications

1078.87

-

-

... More
Applying Bitumen Primer on side of Lining and top of sleeper for construction joint,etc. complete in all respects

671.43

-

-

... More
Earth work in excavation of foundation of structures as per drawing and technical specification,including setting out, construction of shoring and bracing, removal of stumps and other matter, dressing of sides and bottom and backfilling with excavated surplus soil in ordinary soil (B) Mechanical means Depth upto 3 mtr

171.63

-

-

... More
Dismantling brickwork tile, masonary or tile lining in cement

15.85

-

-

... More
Dismantling concrete in lime concrete, cement concrete of 1:6:12 or leaner mix

1.87

-

-

... More
Backfilling behind abutment, wing wall and return wall complete as per drawing and technical specifications (b) Sandy material

1.71

-

-

... More
Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications RCC Grade M20 Height upto 5m With Batching Plant, Transit Mixer and Concrete Pump

8.39

-

-

... More
Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications RCC Grade M25 Height upto 5m With Batching Plant, Transit Mixer and Concrete Pump

27.99

-

-

... More
Supplying, fitting and placing HYSD bar reinforcement in substructure complete as per drawing and Technical Specifications.

2.58

-

-

... More
Cement concrete 1:4:8 (b) with stone aggregate 40mm gauge (ii) mixing by mechanical means using concrete mixer volumetric type

5.97

-

-

... More
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanical mixed placed in foundation and compacted by vibration including curing for 14 days

10.71

-

-

... More
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entiresurface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and Technical Specification.

1.11

-

-

... More
Earth work involved in dismantling open flume A.P.M. or O.S.M. type outlets with 'H' more than 0.50 m but upto 0.90 m (including excavation, refilling, consolidation and dressing) .

3

-

-

... More
Dismantling O.F., A.P.M. or O.S.M. type outlets consisting of total dismantling with 'H' more than 0.50 m but upto 0.90 m.

3

-

-

... More
Extra labour for dressing bricks on O.F. and A.P.M. type outlets with 'H' more than 0.50 m but upto 0.90 m.

3

-

-

... More
Cement concrete 1:4:8 with Stone Ballast 40 mm gauge using concrete mixer volume metric type

2.27

-

-

... More
First class burnt brick work laid in cement sand mortar 1:3 in foundation and plinth.

21.48

-

-

... More
RCC M-20 mechanically batch mixed with batch type concrete mixer as per IS 1791 and vibrated by needle vibrator but excluding steel reinforcement centring and shuttering in foundation and plinth

1.53

-

-

... More
Shuttering for faces of concrete foundations and foundation beam & plinth beam (vertical or battering)

27.4

-

-

... More
Centering & Shuttering for flat surfaces such as roofs, landings, chajjas, shelves etc.

3.74

-

-

... More
Cold twisted detormed (Ribbed/ Tor steel) Bars (Fe 500 grade as per IS 1786-2008) , for R.C.C works, where not including in the complete rate of RCC including bending and binding placing in position complete

1.24

-

-

... More
Laying RCC 1:2:4 M-15 batch mixed stone ballast or shingle

0.75

-

-

... More
Bending binding and placing in position steel reinforcement 10 mm dia bars

0.44

-

-

... More
Any Other Items

1

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.