Tamil Nadu Generation And Distribution Corporation Limited Tender
View complete overview of Puducherry TANGEDCO Tender
Tamil Nadu Generation And Distribution Corporation Limited - TANGEDCO Tender
Eprocure
Opening Date12 Mar 2020
Closing Date21 May 2020
Tender AmountRefer Documents
Costs
EMD
₹ 30,500Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2020_EB_160997_1Bid Award Id
ViewTender No
GCC 145 GL 089 2019-2020Tender Authority
Tamil Nadu Generation And Distribution Corporation Limited ViewPurchaser Address
-Website
http://https://www.tangedco.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
RCC. 1:1 1/2:3 mix using 12 mm to 20mm HBS metal(machine crushed) for cable duct wall with formwork including cost of all labour, materials, water charges, lead, lift, etc, complete. But excluding cost fo steel reinforcement (by using mixer machine).
18
-
-
RCC. 1:1 1/2:3 mix using 12 mm to 20mm HBS metal(machine crushed) for cable duct cover slab with formwork including cost of all labour, materials, water charges, lead, lift, etc, complete. But excluding cost fo steel reinforcement (by using mixer machine).
4
-
-
Supplying and fabricating and placing in position of MS / RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift, labour, cost of binding wire, etc., complete.
5475
-
-
PCC 1:3:6, using 20mm HBG metal foundation without form work including cost of cement, all materials,water charges, labour, lead, lift, etc. complete.
94
-
-
PCC 1:2:4, using 20mm HBG metal foundation without form work including cost of cement, water charges, all materials, labour, lead, lift, etc. complete.
39
-
-
PCC 1:2:4, using 20mm HBG metal foundation with form work including cost of cement, all materials, labour, lead, lift, etc. complete.
98
-
-
Supply & Fabrication, Transport & fixing of GI angles for cable duct with anchorage and placing in position as directed by the engineer at site including cost of angles,cutting and all labour, lead, lift, etc. Complete
238
-
-
Plastering with CM. 1:3 mix 12mm thick for ceiling,fol, bath, RCC pillars, sunshade, loft, etc., including cost of materials, labour, water charges, lead, lift, watering, curing, etc., complete.
268
-
-
Supply and spreading of quarry dust inside the yard as per std. spec.including cost of materials ,labour lead,lift etc.complete.
161
-
-
Supply and apreading of 12-20mm of HB stone inside the yard as per std. spec.including cost of materials ,labour lead,lift etc
161
-
-
Colour washing two coats with approved qulity of colour pigments over one coat of white cement including cost of all materials , labour lead and lift etc complete.
242
-
-
Supplying and laying PVC pipe 110 mm outer dia 6kg/ cm2 ISI make for laying the sewer line including cost of pvc pipe coupling lbour for cutting laying fixing tighting etc including earth work excavation and refilling trench etc complete
18
-
-
Collection, supplying, stacking and spreading & filling of red gravel including compaction,cost of all materials lead lift labour etc complete as per the direction of site engineer.
723
-
-