Search from a pool of business opportunities related to Odisha tenders on the online platform of BidAssist. Be it an Odisha PWD tender or a civil aviation tender, one can find every tender Odisha government, as well as PSUs and other organizations, post online. Every tender, active or achieved, is sourced from the eProcurement Odisha website and thus carries full credibility.
Odisha Construction Corporation Limited - OCCL Tender
Other Consultancy Services
Consultancy Services
Eprocure
Opening Date18 Jan 2024
Closing Date3 Feb 2024
Tender Amount₹ 4,01,36,173
Costs
EMD
₹ 4,02,000Document Cost
₹ 11,800Tender Fee
Refer Documents
Summary
Bid Identification No. Occl-fdp/01/2023-24
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_OCCL_99813_1Bid Award Id
ViewTender No
e-Procurement Notice No.56/OCCL/2023-24 (on-line)Tender Authority
Odisha Construction Corporation Limited ViewPurchaser Address
-Website
http://https://odishaconstruction.com/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Providing Effort and resource such as manpower, infrastructure, equipment, logistics and transport for DGPS Survey of forest land and ORSAC certification basing on No. of village cadastral maps involved, requirement of provisional geo-referencing. No. of PCPs involved, Demarcation of forest area as per divisional requirement. Computation of forest land area through digitization and comparison with area indicated in forest land schedule. etc. all complete.
48
-
3630
... More
DGPS Survey & Geo-referencing of Forest Land
-
-
-
... More
Identification of Primary Control Points (PCP) for DGPS observations for Geo-referencing of Reservoir Area. etc. all complete.
24
-
10780
... More
Identification of secondary Control Points (SCP) for DGPS observation for Geo-referencing of Reservoir Area . etc. all complete.
480
-
2420
... More
Identification of Secondary Control Points (SCP) in cadastral map for Geo-referencing of Reservoir Area etc. all complete.
480
-
3630
... More
Geo-referencing as per SCPS and identification of forest land patches for Geo-referencing of Reservoir Area etc. all complete.
80
-
440
... More
Providing Primary Control Points (PCP) Pillar (0.1x0.1x0.9) mtr including cost, carriage, colouring and fixing in position for Geo-referencing of Reservoir Area etc. all complete.
24
-
570
... More
Processing of DGPS observations, Geo-referencing of forest land Patches Generation of geo-referenced shape file of forest land patches Area computation and comparative statement etc. all complete.
1
-
181500
... More
Printing and delivery of 8 nos. of Hard copies/ soft copies of maps and reports to user agency after Geo-referencing of Forest land through DGPS survey
16
-
12100
... More
Coordination and Technical Compliance to Division and Tahsil Offices for their endorsement prior to ORSAC submission. Technical Support to ORSAC Verification and Certification and DFO's authentication etc. all complete.
2
-
192500
... More
Fixing of concrete pillar (0.1 x 0.1 x 0.9) mtr including cost, carriage, colouring of the selected forest boundary points etc. all complete.
480
-
570
... More
Providing all Effort and Resource manpower, logistics and transport for site selection for non-forest land for compensatory afforestation etc. complete.
1
-
2759526
... More
Preparatory Works for Computation of forest land area through digitisation and comparison with area indicated in forest land schedule for Demarcation, DGPS survey of CAF area and ORSAC Certification etc. all complete.
48
-
3630
... More
DGPS Survey & Geo-referencing of CAF Land
-
-
-
... More
Identification of Primary Control Points (PCP} Observation for Geo- referencing of CAF Area etc. all complete.
24
-
10780
... More
Identification of Secondary Control Point (SCP) for DGPS observation for Geo-referencing of CAF Area etc. all complete.
480
-
2420
... More
Identification of Secondary Control Points (SCP) in cadastral map for Geo-referencing of CAF Area etc. all complete.
480
-
3630
... More
Geo-referencing of the CAF Area as per SCPs and identification of CAF Area etc. all complete.
80
-
440
... More
Fixing Primary Control Points (PCP) Pillar (0.1 x 0.1x 0.9) mtr including cost, carriage, colouring etc. complete.
24
-
570
... More
Processing of DGPS observation & generation of geo-referenced shape file of CAF Area etc. all complete.
1
-
121000
... More
Printing and delivery of 8 Nos. of Hard copies/ soft copies of maps and reports to user agency etc. all complete.
64
-
8800
... More
Providing effort and resource such as manpower, logistics and transport for Preparation of Catchment Area Treatment Plan including its approval from MoEF&CC etc. All complete.
1
-
4044100
... More
Coordination and Technical Compliance to Division and Tehsil Offices for their endorsement prior to ORSAC submission. Technical Support during ORSAC Verification and Certification and DFOs authentication. etc. all complete.
2
-
192500
... More
Fixing of concrete Pillar (0.1 x 0.1 x 0.9) mtr including cost, carriage, colouring of the selected forest boundary points etc. all complete.
480
-
570
... More
Providing all Effort and Resource such as manpower, infrastructure & equipment for preparation of Maps basing on revenue cadastral maps, Integration of Satellite Image, Integration of Toposheets, map Integration of purpose wise break up etc. all complete.
1
-
121000
... More
Providing all Effort and Resource such as manpower, infrastructure & equipment for preparation of reports etc. all complete.
1
-
60500
... More
Providing all Effort and Resource such as manpower, infrastructure & equipment for Compilation of Enclosure etc. all complete.
1
-
60500
... More
Providing all Effort and Resource such as manpower, infrastructure & equipment for E-filing of the FDP document on MoEF & CC portal etc. all complete.
1
-
1379763
... More
Providing all Effort and Resource such as manpower, infrastructure & equipment for Authentication of Maps & land schedule by DFO basing on revenue cadastral maps, Integration of Satellite image, Integration of Toposheets, map Integration of purpose wise breakup etc. all complete.
1
-
242000
... More
Providing all Effort and Resource such as manpower, infrastructure & equipment for Formulation and recommendation of Site Specific Wildlife Management Plan from DFOs & RCCFs and presentation and approval from PCCF (WL)
1
-
1570800
... More
Providing all Effort and resources such as manpower, infrastructure, logistic, equipment for counting of no. of Trees, Extent of forest land involvment for computation of (fuelwood/fodder values, watershed services, bio -diversity and carbon value) to determine NPV Computation etc. all complete.
1
-
3449408
... More
Providing all Effort and Resources such as manpower, infrastructure & equipment for Formulation of CAF Scheme by DFO etc. all complete.
1
-
242000
... More
Providing all effort and Resources such as Manpower, logistics and transport for Formulation of Plan/ Schemes & transmission to CF etc. all complete .
1
-
363000
... More
Providing all Effort and Resources such as Manpower, Logistics and transport for conducting Gram Sabha among the affected villages under Forest Rights Act 2006, involving the concerned BDO, Sarpanchs, Gram Panchayats and obtaining necessary Clearance certificate from Collector & D.M. of concerned District under FRA etc. all complete.
1
-
1155000
... More
Providing all Effort and Resources such as Manpower, logistics and transport for Co-ordination and assistance for over all verification of FDP application with all necessary enclosures. CF's field inspection, inputs for CF's report, CF's recommendation etc. all complete.
1
-
363000
... More
Providing all Effort and Resources such as Manpower, logistics and transport for Assisting verification of field inspection reports, document checks, observation of Nodal Officer and recommendation to PCCF. Technical clarification to PCCF and their recommendation to Government etc. all complete .
1
-
3449408
... More
Providing all Effort and Resources such as Manpower, logistics and transport for Assisting/ Clarifying Govt. of Odisha for seeking prior approval from MoEF&CC, Govt. Of India etc. all complete.
1
-
3449408
... More
Providing all Effort and Resources such as Manpower, Logistics and transport for Assistance in presentations and incorporation of suggestions for Technical Compliance for Stage-I Clearance as required etc. all complete.
1
-
3449408
... More
Providing all Effort and Resources such as Manpower, Logistics and transport for Assistance in presentations and incorporation of final recommendation for Technical Compliance for Stage-II Clearance as required etc. all complete.
1
-
2759526