Search from a pool of business opportunities related to Odisha tenders on the online platform of BidAssist. Be it an Odisha PWD tender or a civil aviation tender, one can find every tender Odisha government, as well as PSUs and other organizations, post online. Every tender, active or achieved, is sourced from the eProcurement Odisha website and thus carries full credibility.

Odisha Construction Corporation Limited - OCCL Tender

Civil And Construction
Irrigation Work
Eprocure
Opening Date19 Jan 2022
Closing Date8 Feb 2022
Tender Amount₹ 48,54,37,951 
Notes
Download

Costs

Summary

Construction Of Under Ground Pipe Line Irrigation System (gravity Flow) Bisamgiri

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Backfilling the excavated trenches, after laying of D.I./H.D.P.E. Pipes, with suitable excavated materials(Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required ,including disposal of the surplus excavated earth away from work site with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

-

-

-

... More
a) In zones where depth of cutting is less than equal to 2.5m

14558.48

-

41

... More
Procurement and supply of centrifugally cast (spun) Ductile Iron pressure pipes with Spigot and Socket ended class K7 Pipes suitable for (push on type) Rubber Gasket jointing conforming to IS:8329-2000 (latest Revision) with inside Factory- centrifugally-applied cement mortar lining ( Slag Cement) and external Zinc coating followed by a finishing layer of Bitumen coating duly ISI marked including cost of EPDM Gasket complete including cost of pipe, cost of testing, inspection charges etc. transportation to work site, stacking at site, loading, un-loading, handling, rehandling, labour cess, including all taxes , duties, insurance, etc. (excluding GST) complete as per the specification and directions of the Engineer-in -charge; for the following nominal diameters.

-

-

-

... More
i) DN 250

1576.62

-

2783.21

... More
ii) DN 300

124.85

-

3508.53

... More
iii) DN 350

29.94

-

4289.36

... More
iv) DN 400

582.08

-

5137.46

... More
v) DN 450

624.87

-

6168.47

... More
Procurement and supply of High Density Polyethylene ( HDPE) pipes of material grade PE 100 with pressure rating PN 6 conforming to IS:4984-2016 ( latest Revision) duly ISI marked, of standard length, including cost of pipes , cost of testing, inspection charges, transportation to work site, stacking at site with local handling and rehandling, including loading and un- loading, labour cess, including all taxes, duties, insurance, etc. (excluding GST) complete in all respect as per the specification and directions of the Engineer-in-charge; for the following nominal diameters.

-

-

-

... More
i) 125mm

3712.08

-

390.52

... More
ii) 140mm

1540.87

-

489.43

... More
iii) 160mm

721.41

-

641.27

... More
iv) 200mm

4400.19

-

999.43

... More
v) 225mm

1245.59

-

1261.82

... More
Labour for laying D.I. pipes in the excavated trenches to required level and grade, with proper jointing, including cost of all materials, labour, machineries, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc. (excluding GST) complete including all lifts and delifts, as per the specifications and directions of the Engineer- in-charge. For the following nominal Diameters;

-

-

-

... More
i) DN 250

1576.62

-

114.3

... More
ii) DN 300

124.85

-

134.4

... More
iii) DN 350

29.94

-

184

... More
iv) DN 400

582.08

-

208.1

... More
v) DN 450

624.87

-

245.3

... More
Labour for fixing & laying H.D.P.E. pipes with its fittings & Specials including Ball valves in the excavated trenches, proper to required level and grade with proper jointing of pipes having electro fusion jointing systems, including cost of all materials, labour, machinaries, equipment, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc.(excluding GST) complete including all lifts and delifts, as per the specifications and directions of Engineer- in-charge. for the following nominal Diameters;

-

-

-

... More
i) 125mm

3712.08

-

155.2

... More
ii) 140mm

1540.87

-

171.7

... More
iii) 160mm

721.41

-

199.3

... More
iv) 200mm

4400.19

-

274.3

... More
v) 225mm

4400.19

-

305.3

... More
Supply of D.I. Pipe Fittings required for proper alignment of pipe lines as per approved drawing such as bends, Tees, reducers, Cross etc of required specification , at work site, including cost of materials, carriage, labour, all taxes ,labour cess & duties, loading, un- loading, handling, rehandling, etc.(excluding GST) complete as per the specification and directions of the Engineer-in charge.

13.07

-

14118.36

... More
Supply of H.D.P.E. Pipe Fittings required for proper alignment of pipe line as per approved drawing ,such as bends, Tees, Reducers, Cross etc of required specifications, at work site, including cost of materials, carriage, labour, all taxes , labour cess & duties, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge.

292

-

836.77

... More
Labour for fitting & fixing of all D.I. pipe fittings such as Bends, Tees, Reducers, cross etc at required location of D.I. pipe line Network in the trenches as per the Approved specifications and Drawing including all machineries, sundries, T&P, carriage of fittings, loading, unloading, handling, rehandling, etc. at work site including all lifts and delifts, with all taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of the Engineer-in-charge.

13.07

-

516.5

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Butter Fly Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

7

-

32834

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Air Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

6

-

33893

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Sluice Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

3

-

32625

... More
Construction of Precast RCC (M-25 Grade) Lift Well chambers , as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

4

-

31100

... More
Construction of Precast RCC (M-25 Grade) Outlet chambers, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

-

-

-

... More
a) 2 Ha Outlets

25

-

10582

... More
b) 1 Ha Outlet

48

-

7644

... More
Supply of D.I. Double Flanged (short body) Butter Fly Valve with EPDM liner conforming to IS:13095-2020 (latest version) with Stainless Steel shaft and pin with manual operation & required specifications at work site including testing and inspection charges, including cost of materials & all fittings, Specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge For the following sizes.

-

-

-

... More
i) 450mm

1

-

94637.63

... More
ii) 200mm

2

-

19023.05

... More
iii) 150mm

4

-

17238.98

... More
Supply of D.I. Tamper Proof Combination Air Valve PN 1.0 conforming to IS:14845-2000( latest revision) as per mfg.std with isolating Sluice valve as per Sluice Valve specifications, at work site, including cost of materials, all fittings, specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
i) 100mm

1

-

75605.52

... More
ii) 80mm

5

-

28184.96

... More
Supply of D.I. Double Flanged gland-less Sluice Valve of PN-1.0 (IS:14846- 2000 Latest version) with non rising Stainless Steel spindle and EPDM Liner stem seal of required specifications as Scour Valve at work site, including testing and inspection charges, including cost of materials, all fittings and specials, all insurance, taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge. For the following sizes

-

-

-

... More
i) 100mm

1

-

14216.76

... More
ii) 150mm

2

-

21557.44

... More
Supply of HDPE Ball Valves of material PE100 pressure rating PN 6.0 of required specifications to site of work, including testing and inspection charges, including cost of materials, all fittings and specials, all taxes, insurances & duties, stacking at site transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
i) 125mm

98

-

2854.68

... More
Labour for fittings & fixing of different sizes of D.I. Butterfly valves, D.I. Air valves, D.I. Sluice valve, HDPE Ball valve as per the Approved specifications and Drawing at required designated location of the underground pipe line laid in the trenches including all materials, sundries, T&P,including all lifts and delifts, loading, unloading, handling, rehandling with all Taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of Engineer-in-charge for the following sizes.

-

-

-

... More
Butterfly valves

-

-

-

... More
i) 450mm

1

-

6186.7

... More
ii) 200mm

2

-

1638

... More
iii) 150mm

4

-

1234.9

... More
Air Valves

-

-

-

... More
i) 100mm

1

-

622

... More
ii) 80mm

5

-

315.9

... More
Sluice Valves

-

-

-

... More
i) 100mm

1

-

814.5

... More
ii) 150mm

2

-

1234.9

... More
Construction of Road Crossing such as SH/MDR/ODR/VR etc. for the under ground pipe line with the pipe line laid inside RCC NP- 3 Hume Pipe of Diameter minimum 300mm larger than the outer Diameter of distribution pipe line, below the road as per the Approved Drawing with minimum 1.50m.earth cover above the top of RCC Hume Pipe up to the road surface, including cost of diversion of traffic, including cost of restoration of dismantled road work, with cost & carriage of RCC NP-3 Hume Pipe, all leads, lifts and delifts, including cost of excavation, all materials, carriage, handling, rehandling, laying and aligning of the RCC Hume Pipe including all taxes, labour cess, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in-charge.

13

-

33845

... More
Construction of River/Nallah Crossing of the under ground pipe line with RCC lining of pipe &Thrust Block as per the Approved Drawing including cost of Earthwork, RCC, PCC, Reinforcement & Shuttering, including cost of diversion work, including restoration of the Nallah/stream, including dewatering of foundation pit, including cost of all materials, labour, T&P, carriage, including all leads, lifts and delifts, all taxes, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

1

-

103137

... More
Construction of Horizontal Thrust Blocks at different location of the distribution network, as per approved Drawings and specifications including Excavation of foundation, dressing and levelling the bed, depositing the surplus excavated material after backfilling away from work site, including all PCC, RCC, reinforcements, shuttering and centring, , including cost of all materials, Carriage, Handling and rehandling, fixing the pipe line in proper position, including all leads, lifts and delifts, including all labour,T&P, machineries etc, including royalty, all taxes (excluding GST), including labour cess, . complete as per the specification and direction in Engineer-in-charge.

7

-

5851.19

... More
Construction of Intake Well Chamber near the existing Diversion Weir to facilitate off taking of the Distribution network Main Pipe including cost of excavation of foundation by mechanical means, including all RCC work, PCC work, as per the Approved Drawing including cost of fixing the off taking pipe and silt excluder pipe, including cost of RCC Cover Slab of the intake Well Chamber with man-holes, including fixing of the Galvanised rungs all complete as per the Approved Drawings, including all materials, labour, T&P,HYSD Reinforcement, Shoring, Centring and Shuttering, including all leads, lifts and delifts, including disposal of surplus earth away from work site, levelling and finishing the work site, including all taxes, royalties, labour cess(excluding GST), with transportation, handling and rehandling of all materials, complete as per the specifications and direction of Engineer-in-charge (Payment to be made through following items of work)

-

-

-

... More
Excavation of Foundation of Intake well by mechanical means in all kinds of Soil, including Stoney earth, gravel,moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) as per the approved drawing, including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per approved drawing, specification and the directions of the Engineer - in- charge.

117.78

-

72.32

... More
Providing PCC M15 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area , as per approved drawing, to proper level and thickness, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per the specification and direction of Engineer-in-charge.

4.12

-

3920.9

... More
Providing RCC M25 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area to proper level and thickness, as per approved drawing, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per approved drawing, the specification and direction of Engineer-in-charge.

42.78

-

4385.9

... More
Providing rigid and smooth centring and shuttering to all concrete works , PCC and RCC, as per approved drawings, for F1 finish of the concrete surfaces, for all heights, including cost of all shuttering and centring materials, including dismantling of the centring and shuttering after specified period, including carriage, handling and rehandling, all leads, lifts and delifts, all taxes, labour cess etc (excluding GST) complete as per approved drawing, specification and direction of Engineer-in-Charge.

233

-

675.2

... More
Providing HYSD bars for Reinforcement, cutting, bending and binding the reinforcement bars to proper grill as per the approved drawing, including cost and carriage of HYSD bars to work site, including cost of binding wire, all labour ,T&P etc, complete to receive the concrete, including all taxes, labour cess etc (excluding GST), including all leads, lifts and delifts, handling and rehandling as per the approved drawing, specification and Engineer-in- Charge.

22.85

-

8616.04

... More
Backfilling the excavated foundation, after completion of the intake structure, with suitable excavated materials (Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required , including disposal of the surplus excavated earth away from work site, finishing the site clean, with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

75.1

-

31.3

... More
Operation & Maintenance for UGPL Irrigation Network for 98.74 Ha of CCA including CAD network for Five kharif/five Rabi crop season which ever is later after commissioning UGPL Irrigation system including cost of all material, labour cess, all taxes etc. complete to provide successful irrigation to ayacut 98.74 Ha. as directed by the Engineer-in-Charge.(excluding GST)

98.74

-

1955

... More
Execution of under ground pipe line (UGPL) system for a total CCA of 111.95 Ha in Karanja Minor Irrigation Projects on percentage rate basis including pre construction survey, execution as per planning & design, testing of pipe materials, providing & laying with DI pipes (DI or = 250mm dia) Ductile Iron class- K7 and K9 as per relevant IS code as per approved Drawing , with suitable jointing materials for stiffness class 2500 N/M2 as per IS-12709 & IS-14402 and High Density Polyethylene (HDPE) pipes of class PE-100, PN 6,PN8,PN10 and PN12.5 as per Approved Drawing , as per relevant IS code (HDPE pipe internal dia 250mm) having test pressure of approved standard for Pipe network as specified in technical specification, including D.I Air valves, , Butterfly valves, Sluice Valves, Reducers, Tee, Cross and Bend of matching materials, nuts & bolts of required sizes & specification and of approved make and quality and other construction materials including cost of all materials labour charges, all taxes, labour cess, Excluding GST, loading & unloading charges, transportation charges, cost of lowering, laying and jointing to proper alignment and position including earth work in excavation of trenches in all kinds of soils, D.I, Rock strata and with sand cushion of approved thickness for pipes and proper compaction of back filled earth and borrow earth in layers and including cost of Cement Concreting / R.C .C of approved grades, NP3 Hume Pipes of required diameter, Flush Structures and Turnout structures at required locations as per Approved Drawing etc. complete with all other ancillary works to complete the pipe network for providing irrigation at each ha. of CCA as per specification and direction of the Engineer-in-charge.

-

-

-

... More
Earthwork in excavation in Trenches by mechanical means for laying Ductile Iron (D.I )/ HDPE Pipes of different sizes in the UGPL Distribution Network in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) for depth of excavation up to 2.50m.including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per specification and the directions of the Engineer - in- charge.

17994.83

-

72.96

... More
Filling the excavated trench with 150 mm thick sand free from silt and organic materials suitably spread to uniform thickness in rock & D.I. zone of the excavated trench for laying D.I./ H.D.P.E. Pipes over it with cost of all materials including royalties, labour cess, including cost of transportation, with all leads and lifts/delifts, including loading, un-loading , handling, rehandling and T&P etc.(excluding GST) complete as per specification and the directions of the Engineer- in-Charge.

17994.83

-

27.2

... More
Backfilling the excavated trenches, after laying of D.I./H.D.P.E. Pipes, with suitable excavated materials(Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required ,including disposal of the surplus excavated earth away from work site with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

-

-

-

... More
a) In zones where depth of cutting is less than equal to 2.5m

17994.83

-

40.62

... More
Procurement and supply of centrifugally cast (spun) Ductile Iron pressure pipes with Spigot and Socket ended class K7 Pipes suitable for (push on type) Rubber Gasket jointing conforming to IS:8329-2000 (latest Revision) with inside Factory- centrifugally-applied cement mortar lining ( Slag Cement) and external Zinc coating followed by a finishing layer of Bitumen coating duly ISI marked including cost of EPDM Gasket complete including cost of pipe, cost of testing, inspection charges etc. transportation to work site, stacking at site, loading, un-loading, handling, rehandling, labour cess, including all taxes , duties, insurance, etc. (excluding GST) complete as per the specification and directions of the Engineer-in -charge; for the following nominal diameters

-

-

-

... More
i) DN 250

1378.68

-

2778.03

... More
ii) DN 300

385.11

-

3502.06

... More
iii) DN 350

39.95

-

4280.74

... More
iv) DN 500

854.69

-

7160.58

... More
Procurement and supply of High Density Polyethylene ( HDPE) pipes of material grade PE 100 with pressure rating PN 6 conforming to IS:4984-2016 ( latest Revision) duly ISI marked, of standard length, including cost of pipes , cost of testing, inspection charges, transportation to work site, stacking at site with local handling and rehandling, including loading and un- loading, labour cess, including all taxes, duties, insurance, etc. (excluding GST) complete in all respect as per the specification and directions of the Engineer-in-charge; for the following nominal diameters.

-

-

-

... More
i) 110mm

212.3

-

305.03

... More
ii) 125mm

2296.55

-

390.03

... More
iii) 140mm

3818.32

-

488.81

... More
iv) 160mm

1542.87

-

640.48

... More
v) 180mm

1832.41

-

794.35

... More
vi) 200mm

2967.53

-

998.16

... More
vii) 225mm

2666.43

-

1260.25

... More
Labour for laying D.I. pipes in the excavated trenches to required level and grade, with proper jointing, including cost of all materials, labour, machineries, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc. (excluding GST) complete including all lifts and delifts, as per the specifications and directions of the Engineer- in-charge. For the following nominal Diameters;

-

-

-

... More
i) DN 250

1378.68

-

114.3

... More
ii) DN 300

385.11

-

134.4

... More
iii) DN 350

39.95

-

184

... More
iv) DN 500

854.69

-

264.1

... More
Labour for fixing & laying H.D.P.E. pipes with its fittings & Specials including Ball valves in the excavated trenches, proper to required level and grade with proper jointing of pipes having electro fusion jointing systems, including cost of all materials, , equipment, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc.(excluding GST) complete including all lifts and delifts, as per the specifications and directions of Engineer- in-charge. for the following nominal Diameters;

-

-

-

... More
i) 110mm

212.3

-

137.7

... More
ii) 125mm

2296.55

-

155.2

... More
iii) 140mm

3818.32

-

171.7

... More
iv) 160mm

1542.87

-

199.3

... More
v) 180mm

1832.41

-

199.3

... More
vi) 200mm

2967.53

-

274.3

... More
vii) 225mm

2666.43

-

305.3

... More
Supply of D.I. Pipe Fittings required for proper alignment of pipe lines as per approved drawing such as bends, Tees, reducers, Cross etc of required specification , at work site, including cost of materials, carriage, labour, all taxes ,labour cess & duties, loading, un- loading, handling, rehandling, etc.(excluding GST) complete as per the specification and directions of the Engineer-in charge.

12.25

-

14118.36

... More
Supply of H.D.P.E. Pipe Fittings required for proper alignment of pipe line as per approved drawing ,such as bends, Tees, Reducers, Cross etc of required specifications, at work site, including cost of materials, carriage, labour, all taxes , labour cess & duties, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge.

366

-

1159.03

... More
Labour for fitting & fixing of all D.I. pipe fittings such as Bends, Tees, Reducers, cross etc at required location of D.I. pipe line Network in the trenches as per the Approved specifications and Drawing including all machineries, sundries, T&P, carriage of fittings, loading, unloading, handling, rehandling, etc. at work site including all lifts and delifts, with all taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of the Engineer-in-charge.

12.25

-

516.5

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Butter Fly Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

11

-

32992

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Air Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

7

-

34045

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Sluice Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

3

-

32783

... More
Construction of Precast RCC (M-25 Grade) Lift Well chambers , as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

12

-

31251

... More
Construction of Precast RCC (M-25 Grade) Outlet chambers, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

-

-

-

... More
a) 2 Ha Outlets

37

-

10749

... More
b) 1 Ha Outlet

35

-

7809

... More
Supply of D.I. Double Flanged (short body) Butter Fly Valve with EPDM liner conforming to IS:13095-2020 (latest version) with Stainless Steel shaft and pin with manual operation & required specifications at work site including testing and inspection charges, including cost of materials & all fittings, Specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge For the following sizes.

-

-

-

... More
i) 500mm

1

-

106662.17

... More
ii) 350mm

1

-

65556.8

... More
iii) 300mm

1

-

50338.25

... More
iv) 200mm

2

-

19023.05

... More
v) 150mm

6

-

17238.98

... More
Supply of D.I. Tamper Proof Combination Air Valve PN 1.0 conforming to IS:14845-2000( latest revision) as per mfg.std with isolating Sluice valve as per Sluice Valve specifications, at work site, including cost of materials, all fittings, specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
i) 100mm

1

-

36493.17

... More
ii) 80mm

5

-

28184.96

... More
iii) 50mm

1

-

17942.85

... More
Supply of D.I. Double Flanged gland-less Sluice Valve of PN-1.0 (IS:14846- 2000 Latest version) with non rising Stainless Steel spindle and EPDM Liner stem seal of required specifications as Scour Valve at work site, including testing and inspection charges, including cost of materials, all fittings and specials, all insurance, taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
i) 80mm

3

-

10569.65

... More
Supply of HDPE Ball Valves of material PE100 pressure rating PN 6.0 of required specifications to site of work, including testing and inspection charges, including cost of materials, all fittings and specials, all taxes, insurances & duties, stacking at site transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as directions of the Engineer-in charge. For the following sizes

-

-

-

... More
i) 125mm

109

-

2854.68

... More
Labour for fittings & fixing of different sizes of D.I. Butterfly valves, D.I. Air valves, D.I. Sluice valve, HDPE Ball valve as per the Approved specifications and Drawing at required designated location of the underground pipe line laid in the trenches including all materials, sundries, T&P,including all lifts and delifts, loading, unloading, handling, rehandling with all Taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of Engineer-in-charge for the following sizes.

-

-

-

... More
Butterfly valves

-

-

-

... More
i) 500mm

1

-

7251.7

... More
ii) 350mm

1

-

3790.3

... More
iii) 300mm

1

-

2873.53

... More
iv) 200mm

2

-

1637.94

... More
v) 150mm

6

-

1234.85

... More
Air Valves

-

-

-

... More
i) 100mm

1

-

622

... More
ii) 80mm

5

-

315.9

... More
iii) 50mm

1

-

315.9

... More
Sluice Valves

-

-

-

... More
i) 80mm

3

-

506.3

... More
Construction of Road Crossing such as SH/MDR/ODR/VR etc. for the under ground pipe line with the pipe line laid inside RCC NP- 3 Hume Pipe of Diameter minimum 300mm larger than the outer Diameter of distribution pipe line, below the road as per the Approved Drawing with minimum 1.50m.earth cover above the top of RCC Hume Pipe up to the road surface, including cost of diversion of traffic, including cost of restoration of dismantled road work, with cost & carriage of RCC NP-3 Hume Pipe, all leads, lifts and delifts, including cost of excavation, all materials, carriage, handling, rehandling, laying and aligning of the RCC Hume Pipe including all taxes, labour cess, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in-charge.

6

-

37610

... More
Construction of River/Nallah Crossing of the under ground pipe line with RCC lining of pipe &Thrust Block as per the Approved Drawing including cost of Earthwork, RCC, PCC, Reinforcement & Shuttering, including cost of diversion work, including restoration of the Nallah/stream, including dewatering of foundation pit, including cost of all materials, labour, T&P, carriage, including all leads, lifts and delifts, all taxes, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

4

-

54803

... More
Construction of Intake Well Chamber near the existing Diversion Weir to facilitate off taking of the Distribution network Main Pipe including cost of excavation of foundation by mechanical means, including all RCC work, PCC work, as per the Approved Drawing including cost of fixing the off taking pipe and silt excluder pipe, including cost of RCC Cover Slab of the intake Well Chamber with man-holes, including fixing of the Galvanised rungs all complete as per the Approved Drawings, including all materials, labour, T&P,HYSD Reinforcement, Shoring, Centring and Shuttering, including all leads, lifts and delifts, including disposal of surplus earth away from work site, levelling and finishing the work site, including all taxes, royalties, labour cess(excluding GST), with transportation, handling and rehandling of all materials, complete as per the specifications and direction of Engineer-in-charge (Payment to be made through following items of work)

-

-

-

... More
Excavation of Foundation of Intake well by mechanical means in all kinds of Soil, including Stoney earth, gravel,moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) as per the approved drawing, including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per approved drawing, specification and the directions of the Engineer - in- charge.

120.81

-

72.72

... More
Providing PCC M15 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area , as per approved drawing, to proper level and thickness, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per the specification and direction of Engineer-in-charge.

4.12

-

3920.9

... More
Providing RCC M25 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area to proper level and thickness, as per approved drawing, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per approved drawing, the specification and direction of Engineer-in-charge.

42.25

-

4542

... More
Providing rigid and smooth centering and shuttering to all concrete works , PCC and RCC, as per approved drawings, for F1 finish of the concrete surfaces, for all heights, including cost of all shuttering and centering materials, including dismantling of the centering and shuttering after specified period, including carriage, handling and rehandling, all leads, lifts and delifts, all taxes, labour cess etc (excluding GST) complete as per approved drawing, specification and direction of Engineer-in-Charge.

230.65

-

675.2

... More
Providing HYSD bars for Reinforcement, cutting, bending and binding the reinforcement bars to proper grill as per the approved drawing, including cost and carriage of HYSD bars to work site, including cost of binding wire, all labour ,T&P etc, complete to receive the concrete, including all taxes, labour cess etc (excluding GST), including all leads, lifts and delifts, handling and rehandling as per the approved drawing, specification and Engineer-in- Charge.

22.61

-

8609.4

... More
Backfilling the excavated foundation, after completion of the intake structure, with suitable excavated materials (Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required , including disposal of the surplus excavated earth away from work site, finishing the site clean, with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

76.9

-

31.3

... More
Operation & Maintenance for UGPL Irrigation Network for 111.95 Ha of CCA including CAD network for Five kharif/five Rabi crop season which ever is later after commissioning UGPL Irrigation system including cost of all material, labour cess, all taxes etc. complete to provide successful irrigation to ayacut 111.95 Ha. as directed by the Engineer-in-Charge.(excluding GST)

111.95

-

1955

... More
Execution of under ground pipe line (UGPL) system for a total CCA of 353.63 Ha in Pujariguda Minor Irrigation Projects on percentage rate basis including pre construction survey, execution as per planning & design, testing of pipe materials, providing & laying with DI pipes (DI or = 250mm dia) Ductile Iron class- K7 and K9 as per relevant IS code as per approved Drawing , with suitable jointing materials for stiffness class 2500 N/M2 as per IS-12709 & IS-14402 and High Density Polyethylene (HDPE) pipes of class PE-100, PN 6,PN8,PN10 and PN12.5 as per Approved Drawing , as per relevant IS code (HDPE pipe internal dia 250mm) having test pressure of approved standard for Pipe network as specified in technical specification, including D.I Air valves, , Butterfly valves, Sluice Valves, Reducers, Tee, Cross and Bend of matching materials, nuts & bolts of required sizes & specification and of approved make and quality and other construction materials including cost of all materials labour charges, all taxes, labour cess, Excluding GST, loading & unloading charges, transportation charges, cost of lowering, laying and jointing to proper alignment and position including earth work in excavation of trenches in all kinds of soils, D.I, Rock strata and with sand cushion of approved thickness for pipes and proper compaction of back filled earth and borrow earth in layers and including cost of Cement Concreting / R.C .C of approved grades, NP3 Hume Pipes of required diameter, Flush Structures and Turnout structures at required locations as per Approved Drawing etc. complete with all other ancillary works to complete the pipe network for providing irrigation at each ha. of CCA as per specification and direction of the Engineer-in-charge.

-

-

-

... More
Earthwork in excavation in Trenches by mechanical means for laying Ductile Iron (D.I )/ HDPE Pipes of different sizes in the UGPL Distribution Network in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) for depth of excavation up to 2.50m.including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per specification and the directions of the Engineer - in- charge.

41986.36

-

71.32

... More
Filling the excavated trench with 150 mm thick sand free from silt and organic materials suitably spread to uniform thickness in rock & D.I. zone of the excavated trench for laying D.I./ H.D.P.E. Pipes over it with cost of all materials including royalties, labour cess, including cost of transportation, with all leads and lifts/delifts, including loading, un-loading , handling, rehandling and T&P etc.(excluding GST) complete as per specification and the directions of the Engineer- in - charge.

41986.36

-

25.21

... More
Backfilling the excavated trenches, after laying of D.I./H.D.P.E. Pipes, with suitable excavated materials(Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required ,including disposal of the surplus excavated earth away from work site with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

-

-

-

... More
a) In zones where depth of cutting is less than equal to 2.5m

41986.36

-

40.08

... More
Procurement and supply of centrifugally cast (spun) Ductile Iron pressure pipes with Spigot and Socket ended class K7 Pipes suitable for (pushon type) Rubber Gasket jointing conforming to IS:8329-2000 (latest Revision) with inside Factory- centrifugally-applied cement mortar lining ( Slag Cement) and external Zinc coating followed by a finishing layer of Bitumen coating duly ISI marked including cost of EPDM Gasket complete including cost of pipe, cost of testing, inspection charges etc. transportation to work site, stacking at site, loading, un-loading, handling, rehandling, labour cess, including all taxes , duties, insurance, etc. (excluding GST) complete as per the specification and directions of the Engineer-in -charge; for the following nominal diameters

-

-

-

... More
i) DN 250

449.78

-

2801.2

... More
ii) DN 300

907.41

-

3531.03

... More
iii) DN 350

257.45

-

4319.36

... More
iv) DN 400

1862

-

5173.46

... More
v) DN 500

165.24

-

7218.51

... More
vi) DN 600

275.69

-

9401.25

... More
vii) DN 700

181.41

-

13207.7

... More
viii) DN 750

133.81

-

14836.24

... More
ix) DN 800

222.07

-

16650.96

... More
x) DN 900

341.43

-

21332.21

... More
Procurement and supply of High Density Polyethylene ( HDPE) pipes of material grade PE 100 with pressure rating PN 6 conforming to IS:4984-2016 ( latest Revision) duly ISI marked, of standard length, including cost of pipes , cost of testing, inspection charges, transportation to work site, stacking at site with local handling and rehandling, including loading and un- loading, labour cess, including all taxes, duties, insurance, etc. (excluding GST) complete in all respect as per the specification and directions of the Engineer-in-charge; for the following nominal diameters.

-

-

-

... More
i) 125mm

26279.55

-

392.2

... More
ii) 140mm

1048.13

-

491.52

... More
iii) 160mm

2444.04

-

644.05

... More
iv) 180mm

1168.09

-

800.1

... More
v) 200mm

3548.63

-

1003.82

... More
vi) 225mm

1129.43

-

1267.26

... More
vii) 250mm

1572.2

-

1561.48

... More
Labour for laying D.I. pipes in the excavated trenches to required level and grade, with proper jointing, including cost of all materials, labour, machineries, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc. (excluding GST) complete including all lifts and delifts, as per the specifications and directions of the Engineer- in-charge. For the following nominal Diameters;

-

-

-

... More
i) DN 250

449.78

-

114.3

... More
ii) DN 300

907.41

-

134.4

... More
iii) DN 350

257.45

-

184

... More
iv) DN 400

1862

-

208.1

... More
v) DN 500

165.24

-

264.1

... More
vi) DN 600

275.69

-

354.4

... More
vii) DN 700

181.41

-

594.6

... More
viii) DN 750

133.81

-

623.8

... More
ix) DN 800

222.07

-

679.5

... More
x) DN 900

341.43

-

910.4

... More
Labour for fixing & laying H.D.P.E. pipes with its fittings & Specials including Ball valves in the excavated trenches, proper to required level and grade with proper jointing of pipes having electro fusion jointing systems, including cost of all materials, , equipment, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc.(excluding GST) complete including all lifts and delifts, as per the specifications and directions of Engineer- in-charge. for the following nominal Diameters;

-

-

-

... More
i) 125mm

26279.55

-

155.2

... More
ii) 140mm

1048.13

-

171.7

... More
iii) 160mm

2444.04

-

199.3

... More
iv) 180mm

1168.09

-

274.3

... More
v) 200mm

3548.63

-

274.3

... More
vi) 225mm

1129.43

-

305.3

... More
vii) 250mm

1572.2

-

360.2

... More
Supply of D.I. Pipe Fittings required for proper alignment of pipe lines as per approved drawing such as bends, Tees, reducers, Cross etc of required specification , at work site, including cost of materials, carriage, labour, all taxes ,labour cess & duties, loading, un- loading, handling, rehandling, etc.(excluding GST) complete as per the specification and directions of the Engineer-in charge.

41.48

-

14118.36

... More
Supply of H.D.P.E. Pipe Fittings required for proper alignment of pipe line as per approved drawing ,such as bends, Tees, Reducers, Cross etc of required specifications, at work site, including cost of materials, carriage, labour, all taxes , labour cess & duties, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge.

1019

-

727.93

... More
Labour for fitting & fixing of all D.I. pipe fittings such as Bends, Tees, Reducers, cross etc at required location of D.I. pipe line Network in the trenches as per the Approved specifications and Drawing including all machineries, sundries, T&P, carriage of fittings, loading, unloading, handling, rehandling, etc. at work site including all lifts and delifts, with all taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of the Engineer-in-charge.

41.48

-

516.5

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Butter Fly Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P,including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

27

-

33159

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Air Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

11

-

34179

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Sluice Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

2

-

32948

... More
Construction of Precast RCC (M-25 Grade) Outlet chambers, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

-

-

-

... More
a) 2 Ha Outlets

152

-

10804

... More
b) 1 Ha Outlet

72

-

7697

... More
Supply of D.I. Double Flanged (short body) Butter Fly Valve with EPDM liner conforming to IS:13095-2020 (latest version) with Stainless Steel shaft and pin with manual operation & required specifications at work site including testing and inspection charges, including cost of materials & all fittings, Specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge For the following sizes.

-

-

-

... More
i) 900mm

1

-

432473.72

... More
ii) 700mm

1

-

253458

... More
iii) 350mm

1

-

65556.8

... More
iv) 300mm

1

-

50338.25

... More
v) 250mm

1

-

41150.55

... More
vi) 200mm

2

-

19023.05

... More
vii) 150mm

10

-

17239.45

... More
viii) 125mm

3

-

15522.29

... More
ix) 100mm

7

-

13805.12

... More
Supply of D.I. Tamper Proof Combination Air Valve PN 1.0 conforming to IS:14845-2000( latest revision) as per mfg.std with isolating Sluice valve as per Sluice Valve specifications, at work site, including cost of materials, all fittings, specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
i) 150mm

2

-

64765.24

... More
ii) 80mm

3

-

28184.96

... More
iii) 50mm

6

-

17942.85

... More
Supply of D.I. Double Flanged gland-less Sluice Valve of PN-1.0 (IS:14846- 2000 Latest version) with non rising Stainless Steel spindle and EPDM Liner stem seal of required specifications as Scour Valve at work site, including testing and inspection charges, including cost of materials, all fittings and specials, all insurance, taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
i) 200mm

1

-

36656.94

... More
ii) 150mm

1

-

21557.44

... More
Supply of HDPE Ball Valves of material PE100 pressure rating PN 6.0 of required specifications to site of work, including testing and inspection charges, including cost of materials, all fittings and specials, all taxes, insurances & duties, stacking at site transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
i) 125mm

376

-

2854.68

... More
Labour for fittings & fixing of different sizes of D.I. Butterfly valves, D.I. Air valves, D.I. Sluice valve, HDPE Ball valve as per the Approved specifications and Drawing at required designated location of the underground pipe line laid in the trenches including all materials, sundries, T&P,including all lifts and delifts, loading, unloading, handling, rehandling with all Taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of Engineer-in-charge for the following sizes.

-

-

-

... More
Butterfly valves

-

-

-

... More
i) 900mm

1

-

15474

... More
ii) 700mm

1

-

8512.7

... More
iii) 350mm

1

-

2495.2

... More
iv) 300mm

1

-

1879.2

... More
v) 250mm

1

-

1658.8

... More
vi) 200mm

2

-

1139.2

... More
vii) 150mm

10

-

954.1

... More
viii) 125mm

3

-

679.3

... More
ix) 100mm

7

-

626.6

... More
Sluice Valves

-

-

-

... More
i) 200mm

1

-

1139.2

... More
ii) 150mm

1

-

954.1

... More
Air Valves

-

-

-

... More
i) 150mm

2

-

553.9

... More
ii) 80mm

3

-

227

... More
iii) 50mm

6

-

227

... More
Construction of Road Crossing such as SH/MDR/ODR/VR etc. for the under ground pipe line with the pipe line laid inside RCC NP- 3 Hume Pipe of Diameter minimum 300mm larger than the outer Diameter of distribution pipe line, below the road as per the Approved Drawing with minimum 1.50m.earth cover above the top of RCC Hume Pipe up to the road surface, including cost of diversion of traffic, including cost of restoration of dismantled road work, with cost & carriage of RCC NP-3 Hume Pipe, all leads, lifts and delifts, including cost of excavation, all materials, carriage, handling, rehandling, laying and aligning of the RCC Hume Pipe including all taxes, labour cess, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in-charge.

35

-

26327

... More
Construction of River/Nallah Crossing of the under ground pipe line with RCC lining of pipe &Thrust Block as per the Approved Drawing including cost of Earthwork, RCC, PCC, Reinforcement & Shuttering, including cost of diversion work, including restoration of the Nallah/stream, including dewatering of foundation pit, including cost of all materials, labour, T&P, carriage, including all leads, lifts and delifts, all taxes, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

2

-

76168

... More
Construction of Horizontal Thrust Blocks at different location of the distribution network, as per approved Drawings and specifications including Excavation of foundation, dressing and levelling the bed, depositing the surplus excavated material after backfilling away from work site, including all PCC, RCC, reinforcements, shuttering and centering, , including cost of all materials, Carriage, Handling and rehandling, fixing the pipe line in proper position, including all leads, lifts and delifts, including all labour,T&P, machineries etc, including royalty, all taxes (excluding GST), including labour cess, . complete as per the specification and direction in Engineer-in-charge.

1

-

5569.96

... More
Construction of Intake Well Chamber near the existing Diversion Weir to facilitate off taking of the Distribution network Main Pipe including cost of excavation of foundation by mechanical means, including all RCC work, PCC work, as per the Approved Drawing including cost of fixing the off taking pipe and silt excluder pipe, including cost of RCC Cover Slab of the intake Well Chamber with man-holes, including fixing of the Galvanised rungs all complete as per the Approved Drawings, including all materials, labour, T&P,HYSD Reinforcement, Shoring, Centring and Shuttering, including all leads, lifts and delifts, including disposal of surplus earth away from work site, levelling and finishing the work site, including all taxes, royalties, labour cess(excluding GST), with transportation, handling and rehandling of all materials, complete as per the specifications and direction of Engineer-in-charge (Payment to be made through following items of work)

-

-

-

... More
Excavation of Foundation of Intake well by mechanical means in all kinds of Soil, including Stoney earth, gravel,moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment (blasting is not allowed) as per the approved drawing, including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per approved drawing, specification and the directions of the Engineer - in- charge.

146.19

-

75.39

... More
Providing PCC M15 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area , as per approved drawing, to proper level and thickness, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per the specification and direction of Engineer-in-charge.

4.12

-

4063.83

... More
Providing RCC M25 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area to proper level and thickness, as per approved drawing, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per approved drawing, the specification and direction of Engineer-in-charge.

52.33

-

4700.33

... More
Providing rigid and smooth centring and shuttering to all concrete works , PCC and RCC, as per approved drawings, for F1 finish of the concrete surfaces, for all heights, including cost of all shuttering and centring materials, including dismantling of the centring and shuttering after specified period, including carriage, handling and rehandling, all leads, lifts and delifts, all taxes, labour cess etc (excluding GST) complete as per approved drawing, specification and direction of Engineer-in-Charge.

319.05

-

675.2

... More
Providing HYSD bars for Reinforcement, cutting, bending and binding the reinforcement bars to proper grill as per the approved drawing, including cost and carriage of HYSD bars to work site, including cost of binding wire, all labour ,T&P etc, complete to receive the concrete, including all taxes, labour cess etc (excluding GST), including all leads, lifts and delifts, handling and rehandling as per the approved drawing, specification and Engineer-in- Charge.

27.98

-

8610.05

... More
Backfilling the excavated foundation, after completion of the intake structure, with suitable excavated materials (Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required , including disposal of the surplus excavated earth away from work site, finishing the site clean, with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

91.8

-

31.3

... More
Operation & Maintenance for UGPL Irrigation Network for 353.63 Ha of CCA including CAD network for Five kharif/five Rabi crop season which ever is later after commissioning UGPL Irrigation system including cost of all material, labour cess, all taxes etc. complete to provide successful irrigation to ayacut 353.63 Ha. as directed by the Engineer-in-Charge.(excluding GST)

353.63

-

1955

... More
Execution of under ground pipe line (UGPL) system for a total CCA of 559.755 Ha in Jariguma Minor Irrigation Projects on percentage rate basis including pre construction survey, execution as per planning & design, testing of pipe materials, providing & laying with DI pipes (DI or = 250mm dia) Ductile Iron class- K7 and K9 as per relevant IS code as per approved Drawing , with suitable jointing materials for stiffness class 2500 N/M2 as per IS-12709 & IS-14402 and High Density Polyethylene (HDPE) pipes of class PE-100, PN 6,PN8,PN10 and PN12.5 as per Approved Drawing , as per relevant IS code (HDPE pipe internal dia 250mm) having test pressure of approved standard for Pipe network as specified in technical specification, including D.I Air valves, , Butterfly valves, Sluice Valves, Reducers, Tee, Cross and Bend of matching materials, nuts & bolts of required sizes & specification and of approved make and quality and other construction materials including cost of all materials labour charges, all taxes, labour cess, Excluding GST, loading & unloading charges, transportation charges, cost of lowering, laying and jointing to proper alignment and position including earth work in excavation of trenches in all kinds of soils, D.I, Rock strata and with sand cushion of approved thickness for pipes and proper compaction of back filled earth and borrow earth in layers and including cost of Cement Concreting / R.C .C of approved grades, NP3 Hume Pipes of required diameter, Flush Structures and Turnout structures at required locations as per Approved Drawing etc. complete with all other ancillary works to complete the pipe network for providing irrigation at each ha. of CCA as per specification and direction of the Engineer-in-charge.

-

-

-

... More
Earthwork in excavation in Trenches by mechanical means for laying Ductile Iron (D.I )/ HDPE Pipes of different sizes in the UGPL Distribution Network in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) for depth of excavation up to 2.50m.including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per specification and the directions of the Engineer - in- charge.

71426.46

-

71.69

... More
Filling the excavated trench with 150 mm thick sand free from silt and organic materials suitably spread to uniform thickness in rock & D.I. zone of the excavated trench for laying D.I./ H.D.P.E. Pipes over it with cost of all materials including royalties, labour cess, including cost of transportation, with all leads and lifts/delifts, including loading, un-loading , handling, rehandling and T&P etc.(excluding GST) complete as per specification and the directions of the Engineer- in - charge.

71426.46

-

27.75

... More
Backfilling the excavated trenches, after laying of D.I./H.D.P.E. Pipes, with suitable excavated materials(Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required ,including disposal of the surplus excavated earth away from work site with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

-

-

-

... More
a) In zones where depth of cutting is less than equal to 2.5m

71426.46

-

40.3

... More
Procurement and supply of centrifugally cast (spun) Ductile Iron pressure pipes with Spigot and Socket ended class K7 Pipes suitable for (pushon type) Rubber Gasket jointing conforming to IS:8329-2000 (latest Revision) with inside Factory- centrifugally-applied cement mortar lining ( Slag Cement) and external Zinc coating followed by a finishing layer of Bitumen coating duly ISI marked including cost of EPDM Gasket complete including cost of pipe, cost of testing, inspection charges etc. transportation to work site, stacking at site, loading, un-loading, handling, rehandling, labour cess, including all taxes , duties, insurance, etc. (excluding GST) complete as per the specification and directions of the Engineer-in -charge; for the following nominal diameters

-

-

-

... More
DI K7 900 mm DIA

110.1

-

21872.91

... More
DI K7 800 mm DIA

31.25

-

16921.31

... More
DI K7 700 mm DIA

1657.56

-

13478.05

... More
DI K7 600 mm DIA

948.6

-

9581.48

... More
DI K7 500 mm DIA

1190.29

-

7353.69

... More
DI K7 450 mm DIA

1465.86

-

6348.64

... More
DI K7 400 mm DIA

965.16

-

5281.6

... More
DI K7 350 mm DIA

292.1

-

4409.48

... More
DI K7 300 mm DIA

796.8

-

3598.62

... More
DI K7 250 mm DIA

1139.38

-

2855.27

... More
Procurement and supply of High Density Polyethylene ( HDPE) pipes of material grade PE 100 with pressure rating PN 6 conforming to IS:4984-2016 ( latest Revision) duly ISI marked, of standard length, including cost of pipes , cost of testing, inspection charges, transportation to work site, stacking at site with local handling and rehandling, including loading and un- loading, labour cess, including all taxes, duties, insurance, etc. (excluding GST) complete in all respect as per the specification and directions of the Engineer-in-charge; for the following nominal diameters.

-

-

-

... More
HDPE PN6 225 mm DIA

1734.54

-

1283.66

... More
HDPE PN6 200 mm DIA

5115.07

-

1017.01

... More
HDPE PN6 180 mm DIA

3755.08

-

808.78

... More
HDPE PN6 160 mm DIA

4015.13

-

652.36

... More
HDPE PN6 140 mm DIA

7867.58

-

498

... More
HDPE PN6 125 mm DIA

40341.96

-

397.32

... More
Labour for laying D.I. pipes in the excavated trenches to required level and grade, with proper jointing, including cost of all materials, labour, machineries, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc. (excluding GST) complete including all lifts and delifts, as per the specifications and directions of the Engineer- in-charge. For the following nominal Diameters;

-

-

-

... More
DI K7 900 mm DIA

110.1

-

910.4

... More
DI K7 800 mm DIA

31.25

-

679.5

... More
DI K7 700 mm DIA

1657.56

-

594.6

... More
DI K7 600 mm DIA

948.6

-

354.4

... More
DI K7 500 mm DIA

1190.29

-

264.1

... More
DI K7 450 mm DIA

1465.86

-

245.3

... More
DI K7 400 mm DIA

965.16

-

208.1

... More
DI K7 350 mm DIA

292.1

-

184

... More
DI K7 300 mm DIA

796.8

-

134.4

... More
DI K7 250 mm DIA

1139.38

-

114.3

... More
Labour for fixing & laying H.D.P.E. pipes with its fittings & Specials including Ball valves in the excavated trenches, proper to required level and grade with proper jointing of pipes having electro fusion jointing systems, including cost of all materials, , equipment, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc.(excluding GST) complete including all lifts and delifts, as per the specifications and directions of Engineer- in-charge. for the following nominal Diameters;

-

-

-

... More
HDPE PN6 225 mm DIA

1734.54

-

305.3

... More
HDPE PN6 200 mm DIA

5115.07

-

274.3

... More
HDPE PN6 180 mm DIA

3755.08

-

274.3

... More
HDPE PN6 160 mm DIA

4015.13

-

199.3

... More
HDPE PN6 140 mm DIA

7867.58

-

171.7

... More
HDPE PN6 125 mm DIA

40341.96

-

155.2

... More
Supply of D.I. Pipe Fittings required for proper alignment of pipe lines as per approved drawing such as bends, Tees, reducers, Cross etc of required specification , at work site, including cost of materials, carriage, labour, all taxes ,labour cess & duties, loading, un- loading, handling, rehandling, etc.(excluding GST) complete as per the specification and directions of the Engineer-in charge.

69.18

-

14118.36

... More
Supply of H.D.P.E. Pipe Fittings required for proper alignment of pipe line as per approved drawing ,such as bends, Tees, Reducers, Cross etc of required specifications, at work site, including cost of materials, carriage, labour, all taxes , labour cess & duties, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge.

1594

-

534.64

... More
Labour for fitting & fixing of all D.I. pipe fittings such as Bends, Tees, Reducers, cross etc at required location of D.I. pipe line Network in the trenches as per the Approved specifications and Drawing including all machineries, sundries, T&P, carriage of fittings, loading, unloading, handling, rehandling, etc. at work site including all lifts and delifts, with all taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of the Engineer-in-charge.

69.18

-

516.5

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Butter Fly Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P,including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

72

-

32354

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Air Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

33

-

33366

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Sluice Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

5

-

32143

... More
Construction of Precast RCC (M-25 Grade) Outlet chambers, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

-

-

-

... More
a) 2 Ha Outlets

75

-

10478

... More
b) 1 Ha Outlet

312

-

7438

... More
Supply of D.I. Double Flanged (short body) Butter Fly Valve with EPDM liner conforming to IS:13095-2020 (latest version) with Stainless Steel shaft and pin with manual operation & required specifications at work site including testing and inspection charges, including cost of materials & all fittings, Specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge For the following sizes.

-

-

-

... More
125 mm

50

-

15522.29

... More
150 mm

13

-

17239.45

... More
200 mm

4

-

19023.05

... More
300 mm

3

-

50338.25

... More
350 mm

1

-

65556.8

... More
400 mm

1

-

81096.28

... More
Supply of D.I. Tamper Proof Combination Air Valve PN 1.0 conforming to IS:14845-2000( latest revision) as per mfg.std with isolating Sluice valve as per Sluice Valve specifications, at work site, including cost of materials, all fittings, specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in charge. For the following sizes.

-

-

-

15

-

17942.85

4

-

22563.3

... More
100 mm

6

-

28923.67

... More
150 mm

8

-

46105.74

... More
Supply of D.I. Double Flanged gland-less Sluice Valve of PN-1.0 (IS:14846- 2000 Latest version) with non rising Stainless Steel spindle and EPDM Liner stem seal of required specifications as Scour Valve at work site, including testing and inspection charges, including cost of materials, all fittings and specials, all insurance, taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
150 mm

2

-

56402.44

... More
300 mm

2

-

68180.05

... More
350 mm

1

-

79543

... More
Supply of HDPE Ball Valves of material PE100 pressure rating PN 6.0 of required specifications to site of work, including testing and inspection charges, including cost of materials, all fittings and specials, all taxes, insurances & duties, stacking at site transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
i) 125mm

10

-

2854.68

... More
ii) 110mm

452

-

2854.68

... More
Labour for fittings & fixing of different sizes of D.I. Butterfly valves, D.I. Air valves, D.I. Sluice valve, HDPE Ball valve as per the Approved specifications and Drawing at required designated location of the underground pipe line laid in the trenches including all materials, sundries, T&P,including all lifts and delifts, loading, unloading, handling, rehandling with all Taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of Engineer-in-charge for the following sizes.

-

-

-

... More
Butterfly valves

-

-

-

... More
125 mm

50

-

840.8

... More
150 mm

13

-

1159

... More
200 mm

4

-

1487

... More
300 mm

3

-

2572

... More
350 mm

1

-

3426.3

... More
400 mm

1

-

4548.8

... More
Air Valves

-

-

-

15

-

506.1

4

-

506.1

... More
100 mm

6

-

814

... More
150 mm

8

-

1234.1

... More
Sluice Valves

-

-

-

... More
150 mm

2

-

1234.1

... More
300 mm

2

-

2872.3

... More
350 mm

1

-

3788.6

... More
Construction of Road Crossing such as SH/MDR/ODR/VR etc. for the under ground pipe line with the pipe line laid inside RCC NP- 3 Hume Pipe of Diameter minimum 300mm larger than the outer Diameter of distribution pipe line, below the road as per the Approved Drawing with minimum 1.50m.earth cover above the top of RCC Hume Pipe up to the road surface, including cost of diversion of traffic, including cost of restoration of dismantled road work, with cost & carriage of RCC NP-3 Hume Pipe, all leads, lifts and delifts, including cost of excavation, all materials, carriage, handling, rehandling, laying and aligning of the RCC Hume Pipe including all taxes, labour cess, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in-charge.

36

-

38345

... More
Construction of River/Nallah Crossing of the under ground pipe line with RCC lining of pipe &Thrust Block as per the Approved Drawing including cost of Earthwork, RCC, PCC, Reinforcement & Shuttering, including cost of diversion work, including restoration of the Nallah/stream, including dewatering of foundation pit, including cost of all materials, labour, T&P, carriage, including all leads, lifts and delifts, all taxes, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

4

-

85320

... More
Construction of Horizontal Thrust Blocks at different location of the distribution network, as per approved Drawings and specifications including Excavation of foundation, dressing and levelling the bed, depositing the surplus excavated material after backfilling away from work site, including all PCC, RCC, reinforcements, shuttering and centring, , including cost of all materials, Carriage, Handling and rehandling, fixing the pipe line in proper position, including all leads, lifts and delifts, including all labour,T&P, machineries etc, including royalty, all taxes (excluding GST), including labour cess, . complete as per the specification and direction in Engineer-in-charge.

40

-

5471

... More
Construction of Intake Well Chamber near the existing Diversion Weir to facilitate off taking of the Distribution network Main Pipe including cost of excavation of foundation by mechanical means, including all RCC work, PCC work, as per the Approved Drawing including cost of fixing the off taking pipe and silt excluder pipe, including cost of RCC Cover Slab of the intake Well Chamber with man-holes, including fixing of the Galvanised rungs all complete as per the Approved Drawings, including all materials, labour, T&P,HYSD Reinforcement, Shoring, Centring and Shuttering, including all leads, lifts and delifts, including disposal of surplus earth away from work site, levelling and finishing the work site, including all taxes, royalties, labour cess(excluding GST), with transportation, handling and rehandling of all materials, complete as per the specifications and direction of Engineer-in-charge (Payment to be made through following items of work)

-

-

-

... More
Excavation of Foundation of Intake well by mechanical means in all kinds of Soil, including Stoney earth, gravel,moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) as per the approved drawing, including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per approved drawing, specification and the directions of the Engineer - in- charge.

891.53

-

71.02

... More
Providing PCC M15 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area , as per approved drawing, to proper level and thickness, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per the specification and direction of Engineer-in-charge.

4.43

-

4047.04

... More
Providing RCC M25 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area to proper level and thickness, as per approved drawing, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per approved drawing, the specification and direction of Engineer-in-charge.

142.63

-

4698.2

... More
Providing rigid and smooth centring and shuttering to all concrete works , PCC and RCC, as per approved drawings, for F1 finish of the concrete surfaces, for all heights, including cost of all shuttering and centring materials, including dismantling of the centring and shuttering after specified period, including carriage, handling and rehandling, all leads, lifts and delifts, all taxes, labour cess etc (excluding GST) complete as per approved drawing, specification and direction of Engineer-in-Charge.

420.36

-

675.2

... More
Providing HYSD bars for Reinforcement, cutting, bending and binding the reinforcement bars to proper grill as per the approved drawing, including cost and carriage of HYSD bars to work site, including cost of binding wire, all labour ,T&P etc, complete to receive the concrete, including all taxes, labour cess etc (excluding GST), including all leads, lifts and delifts, handling and rehandling as per the approved drawing, specification and Engineer-in- Charge.

35.29

-

7739.15

... More
Backfilling the excavated foundation, after completion of the intake structure, with suitable excavated materials (Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required , including disposal of the surplus excavated earth away from work site, finishing the site clean, with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

205.01

-

31.3

... More
Operation & Maintenance for UGPL Irrigation Network for 559.755Ha of CCA including CAD network for Five kharif/five Rabi crop season which ever is later after commissioning UGPL Irrigation system including cost of all material, labour cess, all taxes etc. complete to provide successful irrigation to ayacut 559.755 Ha. as directed by the Engineer-in-Charge.(excluding GST)

559.76

-

1955

... More
Execution of under ground pipe line (UGPL) system for a total CCA of 210.352 Ha in Bisamgiri Minor Irrigation Projects on percentage rate basis including pre construction survey, execution as per planning & design, testing of pipe materials, providing & laying with DI pipes (DI or = 250mm dia) Ductile Iron class- K7 and K9 as per relevant IS code as per approved Drawing , with suitable jointing materials for stiffness class 2500 N/M2 as per IS-12709 & IS-14402 and High Density Polyethylene (HDPE) pipes of class PE-100, PN 6,PN8,PN10 and PN12.5 as per Approved Drawing , as per relevant IS code (HDPE pipe internal dia 250mm) having test pressure of approved standard for Pipe network as specified in technical specification, including D.I Air valves, , Butterfly valves, Sluice Valves, Reducers, Tee, Cross and Bend of matching materials, nuts & bolts of required sizes & specification and of approved make and quality and other construction materials including cost of all materials labour charges, all taxes, labour cess, Excluding GST, loading & unloading charges, transportation charges, cost of lowering, laying and jointing to proper alignment and position including earth work in excavation of trenches in all kinds of soils, D.I, Rock strata and with sand cushion of approved thickness for pipes and proper compaction of back filled earth and borrow earth in layers and including cost of Cement Concreting / R.C .C of approved grades, NP3 Hume Pipes of required diameter, Flush Structures and Turnout structures at required locations as per Approved Drawing etc. complete with all other ancillary works to complete the pipe network for providing irrigation at each ha. of CCA as per specification and direction of the Engineer-in-charge.

-

-

-

... More
Earthwork in excavation in Trenches by mechanical means for laying Ductile Iron (D.I )/ HDPE Pipes of different sizes in the UGPL Distribution Network in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) for depth of excavation up to 2.50m.including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per specification and the directions of the Engineer - in- charge.

23853.85

-

77.44

... More
Earthwork in excavation in Trenches by mechanical means for laying Ductile Iron (D.I )/ HDPE Pipes of different sizes in the UGPL Distribution Network in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) for depth of excavation more than 2.50m. including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per specification and the directions of the Engineer - in- charge.

925

-

5022.61

... More
Filling the excavated trench with 150 mm thick sand free from silt and organic materials suitably spread to uniform thickness in rock & D.I. zone of the excavated trench for laying D.I./ H.D.P.E. Pipes over it with cost of all materials including royalties, labour cess, including cost of transportation, with all leads and lifts/delifts, including loading, un-loading , handling, rehandling and T&P etc.(excluding GST) complete as per specification and the directions of the Engineer- in - charge.

24778.85

-

49.62

... More
Backfilling the excavated trenches, after laying of D.I./H.D.P.E. Pipes, with suitable excavated materials(Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required ,including disposal of the surplus excavated earth away from work site with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

-

-

-

... More
a) In zones where depth of cutting is less than equal to 2.5m

23853.85

-

42.81

... More
b) In zones where depth of cutting is more than 2.5m

925

-

2772.35

... More
Procurement and supply of centrifugally cast (spun) Ductile Iron pressure pipes with Spigot and Socket ended class K7 Pipes suitable for (pushon type) Rubber Gasket jointing conforming to IS:8329-2000 (latest Revision) with inside Factory- centrifugally-applied cement mortar lining ( Slag Cement) and external Zinc coating followed by a finishing layer of Bitumen coating duly ISI marked including cost of EPDM Gasket complete including cost of pipe, cost of testing, inspection charges etc. transportation to work site, stacking at site, loading, un-loading, handling, rehandling, labour cess, including all taxes , duties, insurance, etc. (excluding GST) complete as per the specification and directions of the Engineer-in -charge; for the following nominal diameters

-

-

-

... More
DI K7 600 mm DIA

2503.97

-

9517.11

... More
DI K7 500 mm DIA

1306.86

-

7305.42

... More
DI K7 450 mm DIA

251.81

-

6300.37

... More
DI K7 400 mm DIA

507.8

-

5242.98

... More
DI K7 300 mm DIA

668.08

-

3574.48

... More
DI K7 250 mm DIA

227.1

-

2835.96

... More
Procurement and supply of High Density Polyethylene ( HDPE) pipes of material grade PE 100 with pressure rating PN 6 conforming to IS:4984-2016 ( latest Revision) duly ISI marked, of standard length, including cost of pipes , cost of testing, inspection charges, transportation to work site, stacking at site with local handling and rehandling, including loading and un- loading, labour cess, including all taxes, duties, insurance, etc. (excluding GST) complete in all respect as per the specification and directions of the Engineer-in-charge; for the following nominal diameters.

-

-

-

... More
HDPE PN6 225 mm DIA

419.46

-

1277.81

... More
HDPE PN6 200 mm DIA

4229.27

-

1012.29

... More
HDPE PN6 180 mm DIA

1030.55

-

805.67

... More
HDPE PN6 160 mm DIA

861.81

-

649.39

... More
HDPE PN6 140 mm DIA

2266.35

-

432.99

... More
HDPE PN6 125 mm DIA

10505.79

-

395.49

... More
Labour for laying D.I. pipes in the excavated trenches to required level and grade, with proper jointing, including cost of all materials, labour, machineries, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc. (excluding GST) complete including all lifts and delifts, as per the specifications and directions of the Engineer- in-charge. For the following nominal Diameters;

-

-

-

... More
DI K7 600 mm DIA

2503.97

-

354.4

... More
DI K7 500 mm DIA

1306.86

-

264.1

... More
DI K7 450 mm DIA

251.81

-

245.3

... More
DI K7 400 mm DIA

507.8

-

208.1

... More
DI K7 300 mm DIA

668.08

-

134.4

... More
DI K7 250 mm DIA

227.1

-

114.3

... More
Labour for fixing & laying H.D.P.E. pipes with its fittings & Specials including Ball valves in the excavated trenches, proper to required level and grade with proper jointing of pipes having electro fusion jointing systems, including cost of all materials, , equipment, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc.(excluding GST) complete including all lifts and delifts, as per the specifications and directions of Engineer- in-charge. for the following nominal Diameters;

-

-

-

... More
HDPE PN6 225 mm DIA

419.46

-

305.3

... More
HDPE PN6 200 mm DIA

4229.27

-

274.3

... More
HDPE PN6 180 mm DIA

1030.55

-

274.3

... More
HDPE PN6 160 mm DIA

861.81

-

199.3

... More
HDPE PN6 140 mm DIA

2266.35

-

171.7

... More
HDPE PN6 125 mm DIA

10505.79

-

155.2

... More
Supply of D.I. Pipe Fittings required for proper alignment of pipe lines as per approved drawing such as bends, Tees, reducers, Cross etc of required specification , at work site, including cost of materials, carriage, labour, all taxes ,labour cess & duties, loading, un- loading, handling, rehandling, etc.(excluding GST) complete as per the specification and directions of the Engineer-in charge.

25.72

-

14118.36

... More
Supply of H.D.P.E. Pipe Fittings required for proper alignment of pipe line as per approved drawing ,such as bends, Tees, Reducers, Cross etc of required specifications, at work site, including cost of materials, carriage, labour, all taxes , labour cess & duties, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge.

653

-

458.57

... More
Labour for fitting & fixing of all D.I. pipe fittings such as Bends, Tees, Reducers, cross etc at required location of D.I. pipe line Network in the trenches as per the Approved specifications and Drawing including all machineries, sundries, T&P, carriage of fittings, loading, unloading, handling, rehandling, etc. at work site including all lifts and delifts, with all taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of the Engineer-in-charge.

25.72

-

516.5

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Butter Fly Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P,including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

24

-

33842

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Air Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

16

-

35176

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Sluice Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

3

-

33627

... More
Construction of Precast RCC (M-25 Grade) Outlet chambers, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

-

-

-

... More
a) 2 Ha Outlets

37

-

11123

... More
b) 1 Ha Outlet

99

-

7869

... More
Supply of D.I. Double Flanged (short body) Butter Fly Valve with EPDM liner conforming to IS:13095-2020 (latest version) with Stainless Steel shaft and pin with manual operation & required specifications at work site including testing and inspection charges, including cost of materials & all fittings, Specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge For the following sizes.

-

-

-

... More
125 mm

11

-

15522.29

... More
150 mm

6

-

17239.45

... More
200 mm

7

-

19023.05

... More
Supply of D.I. Tamper Proof Combination Air Valve PN 1.0 conforming to IS:14845-2000( latest revision) as per mfg.std with isolating Sluice valve as per Sluice Valve specifications, at work site, including cost of materials, all fittings, specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in charge. For the following sizes.

-

-

-

4

-

17942.85

2

-

22563.3

... More
100 mm

2

-

28923.67

... More
150 mm

8

-

46105.74

... More
Supply of D.I. Double Flanged gland-less Sluice Valve of PN-1.0 (IS:14846- 2000 Latest version) with non rising Stainless Steel spindle and EPDM Liner stem seal of required specifications as Scour Valve at work site, including testing and inspection charges, including cost of materials, all fittings and specials, all insurance, taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
250 mm

1

-

51768.06

1

-

10569.65

... More
200 mm

1

-

36656.94

... More
Supply of HDPE Ball Valves of material PE100 pressure rating PN 6.0 of required specifications to site of work, including testing and inspection charges, including cost of materials, all fittings and specials, all taxes, insurances & duties, stacking at site transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
i) 125mm

21

-

2854.68

... More
ii) 110mm

152

-

2854.68

... More
Labour for fittings & fixing of different sizes of D.I. Butterfly valves, D.I. Air valves, D.I. Sluice valve, HDPE Ball valve as per the Approved specifications and Drawing at required designated location of the underground pipe line laid in the trenches including all materials, sundries, T&P,including all lifts and delifts, loading, unloading, handling, rehandling with all Taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of Engineer-in-charge for the following sizes.

-

-

-

... More
Butterfly valves

-

-

-

... More
125 mm

11

-

844.1

... More
150 mm

6

-

1164

... More
200 mm

7

-

1492.5

... More
Air Valves

-

-

-

4

-

507.7

2

-

507.7

... More
100 mm

2

-

817.2

... More
150 mm

8

-

1239.2

... More
Sluice Valves

-

-

-

... More
250 mm

1

-

2424.2

1

-

477.7

... More
200 mm

1

-

1642.8

... More
Construction of Road Crossing such as SH/MDR/ODR/VR etc. for the under ground pipe line with the pipe line laid inside RCC NP- 3 Hume Pipe of Diameter minimum 300mm larger than the outer Diameter of distribution pipe line, below the road as per the Approved Drawing with minimum 1.50m.earth cover above the top of RCC Hume Pipe up to the road surface, including cost of diversion of traffic, including cost of restoration of dismantled road work, with cost & carriage of RCC NP-3 Hume Pipe, all leads, lifts and delifts, including cost of excavation, all materials, carriage, handling, rehandling, laying and aligning of the RCC Hume Pipe including all taxes, labour cess, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in-charge.

10

-

35208

... More
Construction of Horizontal Thrust Blocks at different location of the distribution network, as per approved Drawings and specifications including Excavation of foundation, dressing and levelling the bed, depositing the surplus excavated material after backfilling away from work site, including all PCC, RCC, reinforcements, shuttering and centering, , including cost of all materials, Carriage, Handling and rehandling, fixing the pipe line in proper position, including all leads, lifts and delifts, including all labour,T&P, machineries etc, including royalty, all taxes (excluding GST), including labour cess, . complete as per the specification and direction in Engineer-in-charge.

31

-

5523.34

... More
Construction of Intake Well Chamber near the existing Diversion Weir to facilitate off taking of the Distribution network Main Pipe including cost of excavation of foundation by mechanical means, including all RCC work, PCC work, as per the Approved Drawing including cost of fixing the off taking pipe and silt excluder pipe, including cost of RCC Cover Slab of the intake Well Chamber with man-holes, including fixing of the Galvanised rungs all complete as per the Approved Drawings, including all materials, labour, T&P,HYSD Reinforcement, Shoring, Centring and Shuttering, including all leads, lifts and delifts, including disposal of surplus earth away from work site, levelling and finishing the work site, including all taxes, royalties, labour cess(excluding GST), with transportation, handling and rehandling of all materials, complete as per the specifications and direction of Engineer-in-charge (Payment to be made through following items of work)

-

-

-

... More
Excavation of Foundation of Intake well by mechanical means in all kinds of Soil, including Stoney earth, gravel,moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) as per the approved drawing, including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per approved drawing, specification and the directions of the Engineer - in- charge.

120.81

-

72.72

... More
Providing PCC M15 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area , as per approved drawing, to proper level and thickness, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per the specification and direction of Engineer-in-charge.

4.12

-

4533.84

... More
Providing RCC M25 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area to proper level and thickness, as per approved drawing, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per approved drawing, the specification and direction of Engineer-in-charge.

42.25

-

5177.67

... More
Providing rigid and smooth centring and shuttering to all concrete works , PCC and RCC, as per approved drawings, for F1 finish of the concrete surfaces, for all heights, including cost of all shuttering and centring materials, including dismantling of the centring and shuttering after specified period, including carriage, handling and rehandling, all leads, lifts and delifts, all taxes, labour cess etc (excluding GST) complete as per approved drawing, specification and direction of Engineer-in-Charge.

230.65

-

675.2

... More
Providing HYSD bars for Reinforcement, cutting, bending and binding the reinforcement bars to proper grill as per the approved drawing, including cost and carriage of HYSD bars to work site, including cost of binding wire, all labour ,T&P etc, complete to receive the concrete, including all taxes, labour cess etc (excluding GST), including all leads, lifts and delifts, handling and rehandling as per the approved drawing, specification and Engineer-in- Charge.

22.61

-

8648.15

... More
Backfilling the excavated foundation, after completion of the intake structure, with suitable excavated materials (Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required , including disposal of the surplus excavated earth away from work site, finishing the site clean, with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

76.9

-

31.3

... More
Operation & Maintenance for UGPL Irrigation Network for 210.352 Ha of CCA including CAD network for Five kharif/five Rabi crop season which ever is later after commissioning UGPL Irrigation system including cost of all material, labour cess, all taxes etc. complete to provide successful irrigation to ayacut 210.352 Ha. as directed by the Engineer-in-Charge.(excluding GST)

210.35

-

1955

... More
Execution of under ground pipe line (UGPL) system for a total CCA of 166.484 Ha in Karangabhata Minor Irrigation Projects on percentage rate basis including pre construction survey, execution as per planning & design, testing of pipe materials, providing & laying with DI pipes (DI or = 250mm dia) Ductile Iron class- K7 and K9 as per relevant IS code as per approved Drawing , with suitable jointing materials for stiffness class 2500 N/M2 as per IS-12709 & IS-14402 and High Density Polyethylene (HDPE) pipes of class PE-100, PN 6,PN8,PN10 and PN12.5 as per Approved Drawing , as per relevant IS code (HDPE pipe internal dia 250mm) having test pressure of approved standard for Pipe network as specified in technical specification, including D.I Air valves, , Butterfly valves, Sluice Valves, Reducers, Tee, Cross and Bend of matching materials, nuts & bolts of required sizes & specification and of approved make and quality and other construction materials including cost of all materials labour charges, all taxes, labour cess, Excluding GST, loading & unloading charges, transportation charges, cost of lowering, laying and jointing to proper alignment and position including earth work in excavation of trenches in all kinds of soils, D.I, Rock strata and with sand cushion of approved thickness for pipes and proper compaction of back filled earth and borrow earth in layers and including cost of Cement Concreting / R.C .C of approved grades, NP3 Hume Pipes of required diameter, Flush Structures and Turnout structures at required locations as per Approved Drawing etc. complete with all other ancillary works to complete the pipe network for providing irrigation at each ha. of CCA as per specification and direction of the Engineer-in-charge.

-

-

-

... More
Earthwork in excavation in Trenches by mechanical means for laying Ductile Iron (D.I )/ HDPE Pipes of different sizes in the UGPL Distribution Network in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) for depth of excavation up to 2.50m.including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per specification and the directions of the Engineer - in- charge.

18519.55

-

74.51

... More
Earthwork in excavation in Trenches by mechanical means for laying Ductile Iron (D.I )/ HDPE Pipes of different sizes in the UGPL Distribution Network in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) for depth of excavation more than 2.50m. including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per specification and the directions of the Engineer - in- charge.

300

-

1489.88

... More
Filling the excavated trench with 150 mm thick sand free from silt and organic materials suitably spread to uniform thickness in rock & D.I. zone of the excavated trench for laying D.I./ H.D.P.E. Pipes over it with cost of all materials including royalties, labour cess, including cost of transportation, with all leads and lifts/delifts, including loading, un-loading , handling, rehandling and T&P etc.(excluding GST) complete as per specification and the directions of the Engineer- in - charge.

18819.55

-

21.94

... More
Backfilling the excavated trenches, after laying of D.I./H.D.P.E. Pipes, with suitable excavated materials(Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required ,including disposal of the surplus excavated earth away from work site with all leads, lifts and delofts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

-

-

-

... More
a) In zones where depth of cutting is less than equal to 2.5m

18519.55

-

41.47

... More
b) In zones where depth of cutting is more than 2.5m

300

-

705.95

... More
Procurement and supply of centrifugally cast (spun) Ductile Iron pressure pipes with Spigot and Socket ended class K7 Pipes suitable for (push on type) Rubber Gasket jointing conforming to IS:8329-2000 (latest Revision) with inside Factory- centrifugally-applied cement mortar lining ( Slag Cement) and external Zinc coating followed by a finishing layer of Bitumen coating duly ISI marked including cost of EPDM Gasket complete including cost of pipe, cost of testing, inspection charges etc. transportation to work site, stacking at site, loading, un-loading, handling, rehandling, labour cess, including all taxes , duties, insurance, etc. (excluding GST) complete as per the specification and directions of the Engineer-in -charge; for the following nominal diameters

-

-

-

... More
DI K7 600 mm DIA

515.74

-

9482.78

... More
DI K7 500 mm DIA

804

-

7279.66

... More
DI K7 450 mm DIA

27.84

-

6274.61

... More
DI K7 400 mm DIA

431

-

5222.38

... More
DI K7 350 mm DIA

102.4

-

4360.13

... More
DI K7 300 mm DIA

212.89

-

3561.6

... More
DI K7 250 mm DIA

592.09

-

2825.66

... More
Procurement and supply of High Density Polyethylene ( HDPE) pipes of material grade PE 100 with pressure rating PN 6 conforming to IS:4984-2016 ( latest Revision) duly ISI marked, of standard length, including cost of pipes , cost of testing, inspection charges, transportation to work site, stacking at site with local handling and rehandling, including loading and un- loading, labour cess, including all taxes, duties, insurance, etc. (excluding GST) complete in all respect as per the specification and directions of the Engineer-in-charge; for the following nominal diameters.

-

-

-

... More
HDPE PN6 225 mm DIA

812.53

-

1274.68

... More
HDPE PN6 200 mm DIA

7119.44

-

1009.78

... More
HDPE PN6 180 mm DIA

1290.59

-

804

... More
HDPE PN6 160 mm DIA

2050.16

-

647.81

... More
HDPE PN6 140 mm DIA

1228.49

-

494.48

... More
HDPE PN6 125 mm DIA

3632.38

-

394.53

... More
Labour for laying D.I. pipes in the excavated trenches to required level and grade, with proper jointing, including cost of all materials, labour, machineries, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc. (excluding GST) complete including all lifts and delofts, as per the specifications and directions of the Engineer- in-charge. For the following nominal Diameters;

-

-

-

... More
DI K7 600 mm DIA

515.74

-

354.4

... More
DI K7 500 mm DIA

804

-

264.1

... More
DI K7 450 mm DIA

27.84

-

245.3

... More
DI K7 400 mm DIA

431

-

208.1

... More
DI K7 350 mm DIA

102.4

-

184

... More
DI K7 300 mm DIA

212.89

-

134.4

... More
DI K7 250 mm DIA

592.09

-

114.3

... More
Labour for fixing & laying H.D.P.E. pipes with its fittings & Specials including Ball valves in the excavated trenches, proper to required level and grade with proper jointing of pipes having electro fusion jointing systems, including cost of all materials, labour, machineries, equipment, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc.(excluding GST) complete including all lifts and delofts, as per the specifications and directions of Engineer- in-charge. for the following nominal Diameters;

-

-

-

... More
HDPE PN6 225 mm DIA

812.53

-

305.3

... More
HDPE PN6 200 mm DIA

7119.44

-

274.3

... More
HDPE PN6 180 mm DIA

1290.59

-

274.3

... More
HDPE PN6 160 mm DIA

2050.16

-

199.3

... More
HDPE PN6 140 mm DIA

1228.49

-

171.7

... More
HDPE PN6 125 mm DIA

3632.38

-

155.2

... More
Supply of D.I. Pipe Fittings required for proper alignment of pipe lines as per approved drawing such as bends, Tees, reducers, Cross etc of required specification , at work site, including cost of materials, carriage, labour, all taxes ,labour cess & duties, loading, un- loading, handling, rehandling, etc.(excluding GST) complete as per the specification and directions of the Engineer-in charge.

15.03

-

14118.36

... More
Supply of H.D.P.E. Pipe Fittings required for proper alignment of pipe line as per approved drawing ,such as bends, Tees, Reducers, Cross etc of required specifications, at work site, including cost of materials, carriage, labour, all taxes , labour cess & duties, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge.

521

-

721.98

... More
Labour for fitting & fixing of all D.I. pipe fittings such as Bends, Tees, Reducers, cross etc at required location of D.I. pipe line Network in the trenches as per the Approved specifications and Drawing including all machineries, sundries, T&P, carriage of fittings, loading, unloading, handling, rehandling, etc. at work site including all lifts and delofts, with all taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of the Engineer-in-charge.

15.03

-

516.5

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Butter Fly Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delofts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

18

-

32681

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Air Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delofts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

7

-

33563

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Sluice Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delofts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

1

-

32471

... More
Construction of Precast RCC (M-25 Grade) Outlet chambers, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delofts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

-

-

-

... More
a) 2 Ha Outlets

35

-

10820

... More
b) 1 Ha Outlet

90

-

7589

... More
Supply of D.I. Double Flanged (short body) Butter Fly Valve with EPDM liner conforming to IS:13095-2020 (latest version) with Stainless Steel shaft and pin with manual operation & required specifications at work site including testing and inspection charges, including cost of materials & all fittings, Specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge For the following sizes.

-

-

-

... More
125 mm

2

-

15522.29

... More
150 mm

5

-

17239.45

... More
200 mm

11

-

19023.05

... More
Supply of D.I. Tamper Proof Combination Air Valve PN 1.0 conforming to IS:14845-2000( latest revision) as per mfg.std with isolating Sluice valve as per Sluice Valve specifications, at work site, including cost of materials, all fittings, specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in charge. For the following sizes.

-

-

-

2

-

17942.85

1

-

22563.3

... More
100 mm

2

-

28923.67

... More
150 mm

2

-

46105.74

... More
Supply of D.I. Double Flanged gland-less Sluice Valve of PN-1.0 (IS:14846- 2000 Latest version) with non rising Stainless Steel spindle and EPDM Liner stem seal of required specifications as Scour Valve at work site, including testing and inspection charges, including cost of materials, all fittings and specials, all insurance, taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
200 mm

1

-

36656.94

... More
Supply of HDPE Ball Valves of material PE100 pressure rating PN 6.0 of required specifications to site of work, including testing and inspection charges, including cost of materials, all fittings and specials, all taxes, insurances & duties, stacking at site transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
125 mm

72

-

2854.68

... More
110 mm

88

-

2854.68

... More
Labour for fittings & fixing of different sizes of D.I. Butterfly valves, D.I. Air valves, D.I. Sluice valve, HDPE Ball valve as per the Approved specifications and Drawing at required designated location of the underground pipe line laid in the trenches including all materials, sundries, T&P, including all lifts and delofts, loading, unloading, handling, rehandling with all Taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of Engineer-in-charge for the following sizes.

-

-

-

... More
Butterfly valves

-

-

-

... More
125 mm

2

-

864.5

... More
150 mm

5

-

1189.2

... More
200 mm

11

-

1537.8

... More
Air Valves

-

-

-

2

-

315.9

1

-

315.9

... More
100 mm

2

-

622

... More
150 mm

2

-

756.3

... More
Sluice Valves

-

-

-

... More
200 mm

1

-

1537.8

... More
Construction of Road Crossing such as SH/MDR/ODR/VR etc. for the under ground pipe line with the pipe line laid inside RCC NP- 3 Hume Pipe of Diameter minimum 300mm larger than the outer Diameter of distribution pipe line, below the road as per the Approved Drawing with minimum 1.50m.earth cover above the top of RCC Hume Pipe up to the road surface, including cost of diversion of traffic, including cost of restoration of dismantled road work, with cost & carriage of RCC NP-3 Hume Pipe, all leads, lifts and delofts, including cost of excavation, all materials, carriage, handling, rehandling, laying and aligning of the RCC Hume Pipe including all taxes, labour cess, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in-charge.

13

-

48425

... More
Construction of Horizontal Thrust Blocks at different location of the distribution network, as per approved Drawings and specifications including Excavation of foundation, dressing and levelling the bed, depositing the surplus excavated material after backfilling away from work site, including all PCC, RCC, reinforcements, shuttering and centring, , including cost of all materials, Carriage, Handling and rehandling, fixing the pipe line in proper position, including all leads, lifts and delifts, including all labour, T&P, machineries etc, including royalty, all taxes (excluding GST), including labour cess, . complete as per the specification and direction in Engineer-in-charge.

8

-

5535.17

... More
Construction of River/Nallah Crossing of the under ground pipe line with RCC lining of pipe &Thrust Block as per the Approved Drawing including cost of Earthwork, RCC, PCC, Reinforcement & Shuttering, including cost of diversion work, including restoration of the Nallah/stream, including dewatering of foundation pit, including cost of all materials, labour, T&P, carriage, including all leads, lifts and delofts, all taxes, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

3

-

55930

... More
Construction of Intake Well Chamber near the existing Diversion Weir to facilitate off taking of the Distribution network Main Pipe including cost of excavation of foundation by mechanical means, including all RCC work, PCC work, as per the Approved Drawing including cost of fixing the off taking pipe and silt excluder pipe, including cost of RCC Cover Slab of the intake Well Chamber with man-holes, including fixing of the Galvanised rungs all complete as per the Approved Drawings, including all materials, labour, T&P,HYSD Reinforcement, Shoring, Centring and Shuttering, including all leads, lifts and delofts, including disposal of surplus earth away from work site, levelling and finishing the work site, including all taxes, royalties, labour cess(excluding GST), with transportation, handling and rehandling of all materials, complete as per the specifications and direction of Engineer-in-charge (Payment to be made through following items of work)

-

-

-

... More
Excavation of Foundation of Intake well by mechanical means in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment (blasting is not allowed) as per the approved drawing, including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per approved drawing, specification and the directions of the Engineer - in- charge.

120.81

-

72.72

... More
Providing PCC M15 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area , as per approved drawing, to proper level and thickness, with proper compaction, including cost of all materials, carriage of all materials and royalty, centering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delofts, labours, including all taxes, labour cess (Excluding GST) etc complete as per the specification and direction of Engineer-in-charge.

4.12

-

3923.49

... More
Providing RCC M25 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area to proper level and thickness, as per approved drawing, with proper compaction, including cost of all materials, carriage of all materials and royalty, centering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delofts, labours, including all taxes, labour cess (Excluding GST) etc complete as per approved drawing, the specification and direction of Engineer-in-charge.

42.25

-

4634.8

... More
Providing rigid and smooth centring and shuttering to all concrete works , PCC and RCC, as per approved drawings, for F1 finish of the concrete surfaces, for all heights, including cost of all shuttering and centring materials, including dismantling of the centring and shuttering after specified period, including carriage, handling and rehandling, all leads, lifts and delofts, all taxes, labour cess etc (excluding GST) complete as per approved drawing, specification and direction of Engineer-in-Charge.

230.65

-

675.2

... More
Providing HYSD bars for Reinforcement, cutting, bending and binding the reinforcement bars to proper grill as per the approved drawing, including cost and carriage of HYSD bars to work site, including cost of binding wire, all labour ,T&P etc, complete to receive the concrete, including all taxes, labour cess etc (excluding GST), including all leads, lifts and delofts, handling and rehandling as per the approved drawing, specification and Engineer-in- Charge.

22.61

-

8174.65

... More
Backfilling the excavated foundation, after completion of the intake structure, with suitable excavated materials (Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required , including disposal of the surplus excavated earth away from work site, finishing the site clean, with all leads, lifts and delofts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

76.9

-

31.3

... More
Operation & Maintenance for UGPL Irrigation Network for 166.484 Ha of CCA including CAD network for Five kharif/five Rabi crop season which ever is later after commissioning UGPL Irrigation system including cost of all material, labour cess, all taxes etc. complete to provide successful irrigation to ayacut 166.484 Ha. as directed by the Engineer-in-Charge.(excluding GST)

166.48

-

1955

... More
Execution of under ground pipe line (UGPL) system for a total CCA of 165.754 Ha in Ghataguda Minor Irrigation Projects on percentage rate basis including pre construction survey, execution as per planning & design, testing of pipe materials, providing & laying with DI pipes (DI or = 250mm dia) Ductile Iron class- K7 and K9 as per relevant IS code as per approved Drawing , with suitable jointing materials for stiffness class 2500 N/M2 as per IS-12709 & IS-14402 and High Density Polyethylene (HDPE) pipes of class PE-100, PN 6,PN8,PN10 and PN12.5 as per Approved Drawing , as per relevant IS code (HDPE pipe internal dia 250mm) having test pressure of approved standard for Pipe network as specified in technical specification, including D.I Air valves, , Butterfly valves, Sluice Valves, Reducers, Tee, Cross and Bend of matching materials, nuts & bolts of required sizes & specification and of approved make and quality and other construction materials including cost of all materials labour charges, all taxes, labour cess, Excluding GST, loading & unloading charges, transportation charges, cost of lowering, laying and jointing to proper alignment and position including earth work in excavation of trenches in all kinds of soils, D.I, Rock strata and with sand cushion of approved thickness for pipes and proper compaction of back filled earth and borrow earth in layers and including cost of Cement Concreting / R.C .C of approved grades, NP3 Hume Pipes of required diameter, Flush Structures and Turnout structures at required locations as per Approved Drawing etc. complete with all other ancillary works to complete the pipe network for providing irrigation at each ha. of CCA as per specification and direction of the Engineer-in-charge.

-

-

-

... More
Earthwork in excavation in Trenches by mechanical means for laying Ductile Iron (D.I )/ HDPE Pipes of different sizes in the UGPL Distribution Network in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) for depth of excavation up to 2.50m.including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per specification and the directions of the Engineer - in- charge.

15448.41

-

71.35

... More
Earthwork in excavation in Trenches by mechanical means for laying Ductile Iron (D.I )/ HDPE Pipes of different sizes in the UGPL Distribution Network in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) for depth of excavation more than 2.50m. including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per specification and the directions of the Engineer - in- charge.

775

-

2831.72

... More
Filling the excavated trench with 150 mm thick sand free from silt and organic materials suitably spread to uniform thickness in rock & D.I. zone of the excavated trench for laying D.I./ H.D.P.E. Pipes over it with cost of all materials including royalties, labour cess, including cost of transportation, with all leads and lifts/ loading, un-loading , handling, rehandling and T&P etc.(excluding GST) complete as per specification and the directions of the Engineer- in - charge.

16223.41

-

25.61

... More
Backfilling the excavated trenches, after laying of D.I./H.D.P.E. Pipes, with suitable excavated materials(Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required ,including disposal of the surplus excavated earth away from work site with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

-

-

-

... More
a) In zones where depth of cutting is less than equal to 2.5m

15448.41

-

40.05

... More
b) In zones where depth of cutting is more than 2.5m

775

-

1309.75

... More
Procurement and supply of centrifugally cast (spun) Ductile Iron pressure pipes with Spigot and Socket ended class K7 Pipes suitable for (push on type) Rubber Gasket jointing conforming to IS:8329-2000 (latest Revision) with inside Factory- centrifugally-applied cement mortar lining ( Slag Cement) and external Zinc coating followed by a finishing layer of Bitumen coating duly ISI marked including cost of EPDM Gasket complete including cost of pipe, cost of testing, inspection charges etc. transportation to work site, stacking at site, loading, un-loading, handling, rehandling, labour cess, including all taxes , duties, insurance, etc. (excluding GST) complete as per the specification and directions of the Engineer-in -charge; for the following nominal diameters

-

-

-

... More
DI K7 600 mm DIA

699.89

-

9581.48

... More
DI K7 500 mm DIA

624.44

-

7353.69

... More
DI K7 450 mm DIA

286.01

-

6348.64

... More
DI K7 400 mm DIA

128.8

-

5281.6

... More
DI K7 300 mm DIA

1146.09

-

3598.62

... More
DI K7 250 mm DIA

413.67

-

2855.27

... More
Procurement and supply of High Density Polyethylene ( HDPE) pipes of material grade PE 100 with pressure rating PN 6 conforming to IS:4984-2016 ( latest Revision) duly ISI marked, of standard length, including cost of pipes , cost of testing, inspection charges, transportation to work site, stacking at site with local handling and rehandling, including loading and un- loading, labour cess, including all taxes, duties, insurance, etc. (excluding GST) complete in all respect as per the specification and directions of the Engineer-in-charge; for the following nominal diameters.

-

-

-

... More
HDPE PN6 225 mm DIA

316.26

-

1283.66

... More
HDPE PN6 200 mm DIA

1834.71

-

1017.01

... More
HDPE PN6 180 mm DIA

388.48

-

808.78

... More
HDPE PN6 160 mm DIA

1449.64

-

652.36

... More
HDPE PN6 140 mm DIA

2083.55

-

498

... More
HDPE PN6 125 mm DIA

6851.87

-

397.32

... More
Labour for laying D.I. pipes in the excavated trenches to required level and grade, with proper jointing, including cost of all materials, labour, machineries, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc. (excluding GST) complete including all lifts and delifts, as per the specifications and directions of the Engineer- in-charge. For the following nominal Diameters;

-

-

-

... More
DI K7 600 mm DIA

699.89

-

354.4

... More
DI K7 500 mm DIA

624.44

-

264.1

... More
DI K7 450 mm DIA

286.01

-

245.3

... More
DI K7 400 mm DIA

128.8

-

208.1

... More
DI K7 300 mm DIA

1146.09

-

134.4

... More
DI K7 250 mm DIA

413.67

-

114.3

... More
Labour for fixing & laying H.D.P.E. pipes with its fittings & Specials including Ball valves in the excavated trenches, proper to required level and grade with proper jointing of pipes having electro fusion jointing systems, including cost of all materials, labour, machineries, equipment, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc.(excluding GST) complete including all lifts and delofts, as per the specifications and directions of Engineer- in-charge. for the following nominal Diameters;

-

-

-

... More
HDPE PN6 225 mm DIA

316.26

-

305.3

... More
HDPE PN6 200 mm DIA

1834.71

-

274.3

... More
HDPE PN6 180 mm DIA

388.48

-

274.3

... More
HDPE PN6 160 mm DIA

1449.64

-

199.3

... More
HDPE PN6 140 mm DIA

2083.55

-

171.7

... More
HDPE PN6 125 mm DIA

6851.87

-

155.2

... More
Supply of D.I. Pipe Fittings required for proper alignment of pipe lines as per approved drawing such as bends, Tees, reducers, Cross etc of required specification , at work site, including cost of materials, carriage, labour, all taxes ,labour cess & duties, loading, un- loading, handling, rehandling, etc.(excluding GST) complete as per the specification and directions of the Engineer-in charge.

19.11

-

14118.36

... More
Supply of H.D.P.E. Pipe Fittings required for proper alignment of pipe line as per approved drawing ,such as bends, Tees, Reducers, Cross etc of required specifications, at work site, including cost of materials, carriage, labour, all taxes , labour cess & duties, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge.

454

-

576.41

... More
Labour for fitting & fixing of all D.I. pipe fittings such as Bends, Tees, Reducers, cross etc at required location of D.I. pipe line Network in the trenches as per the Approved specifications and Drawing including all machineries, sundries, T&P, carriage of fittings, loading, unloading, handling, rehandling, etc. at work site including all lifts and delifts, with all taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of the Engineer-in-charge.

19.11

-

516.5

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Butter Fly Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P,including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

19

-

32252

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Air Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

8

-

32546

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Sluice Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

2

-

32042

... More
Construction of Precast RCC (M-25 Grade) Outlet chambers, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

-

-

-

... More
a) 2 Ha Outlets

55

-

10487

... More
b) 1 Ha Outlet

43

-

7540

... More
Supply of D.I. Double Flanged (short body) Butter Fly Valve with EPDM liner conforming to IS:13095-2020 (latest version) with Stainless Steel shaft and pin with manual operation & required specifications at work site including testing and inspection charges, including cost of materials & all fittings, Specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge For the following sizes.

-

-

-

... More
125 mm

8

-

15522.29

... More
150 mm

8

-

17239.45

... More
200 mm

3

-

19023.05

... More
Supply of D.I. Tamper Proof Combination Air Valve PN 1.0 conforming to IS:14845-2000( latest revision) as per mfg.std with isolating Sluice valve as per Sluice Valve specifications, at work site, including cost of materials, all fittings, specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in charge. For the following sizes.

-

-

-

2

-

17942.85

3

-

22563.3

... More
100 mm

1

-

28923.67

... More
150 mm

2

-

46105.74

... More
Supply of D.I. Double Flanged gland-less Sluice Valve of PN-1.0 (IS:14846- 2000 Latest version) with non rising Stainless Steel spindle and EPDM Liner stem seal of required specifications as Scour Valve at work site, including testing and inspection charges, including cost of materials, all fittings and specials, all insurance, taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
150 mm

1

-

21557.44

... More
125 mm

1

-

17887.1

... More
Supply of HDPE Ball Valves of material PE100 pressure rating PN 6.0 of required specifications to site of work, including testing and inspection charges, including cost of materials, all fittings and specials, all taxes, insurances & duties, stacking at site transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
i) 125mm

13

-

2854.68

... More
ii) 110mm

140

-

2854.68

... More
Labour for fittings & fixing of different sizes of D.I. Butterfly valves, D.I. Air valves, D.I. Sluice valve, HDPE Ball valve as per the Approved specifications and Drawing at required designated location of the underground pipe line laid in the trenches including all materials, sundries, T&P,including all lifts and delifts, loading, unloading, handling, rehandling with all Taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of Engineer-in-charge for the following sizes.

-

-

-

... More
Butterfly valves

-

-

-

... More
125 mm

8

-

859.4

... More
150 mm

8

-

1182.6

... More
200 mm

3

-

1527

... More
Air Valves

-

-

-

2

-

315.9

3

-

315.9

... More
100 mm

1

-

622

... More
150 mm

2

-

756.3

... More
Sluice Valves

-

-

-

... More
150 mm

1

-

1182.6

... More
125 mm

1

-

859.4

... More
Construction of Road Crossing such as SH/MDR/ODR/VR etc. for the under ground pipe line with the pipe line laid inside RCC NP- 3 Hume Pipe of Diameter minimum 300mm larger than the outer Diameter of distribution pipe line, below the road as per the Approved Drawing with minimum 1.50m.earth cover above the top of RCC Hume Pipe up to the road surface, including cost of diversion of traffic, including cost of restoration of dismantled road work, with cost & carriage of RCC NP-3 Hume Pipe, all leads, lifts and delofts, including cost of excavation, all materials, carriage, handling, rehandling, laying and aligning of the RCC Hume Pipe including all taxes, labour cess, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in-charge.

3

-

60303

... More
Construction of River/Nallah Crossing of the under ground pipe line with RCC lining of pipe &Thrust Block as per the Approved Drawing including cost of Earthwork, RCC, PCC, Reinforcement & Shuttering, including cost of diversion work, including restoration of the Nallah/stream, including dewatering of foundation pit, including cost of all materials, labour, T&P, carriage, including all leads, lifts and delifts, all taxes, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

2

-

68077

... More
Construction of Horizontal Thrust Blocks at different location of the distribution network, as per approved Drawings and specifications including Excavation of foundation, dressing and levelling the bed, depositing the surplus excavated material after backfilling away from work site, including all PCC, RCC, reinforcements, shuttering and centering, , including cost of all materials, Carriage, Handling and rehandling, fixing the pipe line in proper position, including all leads, lifts and delifts, including all labour,T&P, machineries etc, including royalty, all taxes (excluding GST), including labour cess, . complete as per the specification and direction in Engineer-in-charge.

4

-

5296.9

... More
Construction of Intake Well Chamber near the existing Diversion Weir to facilitate off taking of the Distribution network Main Pipe including cost of excavation of foundation by mechanical means, including all RCC work, PCC work, as per the Approved Drawing including cost of fixing the off taking pipe and silt excluder pipe, including cost of RCC Cover Slab of the intake Well Chamber with man-holes, including fixing of the Galvanised rungs all complete as per the Approved Drawings, including all materials, labour, T&P,HYSD Reinforcement, Shoring, Centring and Shuttering, including all leads, lifts and delifts, including disposal of surplus earth away from work site, levelling and finishing the work site, including all taxes, royalties, labour cess(excluding GST), with transportation, handling and rehandling of all materials, complete as per the specifications and direction of Engineer-in-charge (Payment to be made through following items of work)

-

-

-

... More
Excavation of Foundation of Intake well by mechanical means in all kinds of Soil, including Stoney earth, gravel,moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) as per the approved drawing, including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per approved drawing, specification and the directions of the Engineer - in- charge.

120.81

-

72.72

... More
Providing PCC M15 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area , as per approved drawing, to proper level and thickness, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per the specification and direction of Engineer-in-charge.

4.12

-

3890.65

... More
Providing RCC M25 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area to proper level and thickness, as per approved drawing, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per approved drawing, the specification and direction of Engineer-in-charge.

42.25

-

4517.85

... More
Providing rigid and smooth centring and shuttering to all concrete works , PCC and RCC, as per approved drawings, for F1 finish of the concrete surfaces, for all heights, including cost of all shuttering and centring materials, including dismantling of the centring and shuttering after specified period, including carriage, handling and rehandling, all leads, lifts and delifts, all taxes, labour cess etc (excluding GST) complete as per approved drawing, specification and direction of Engineer-in-Charge.

230.65

-

675.2

... More
Providing HYSD bars for Reinforcement, cutting, bending and binding the reinforcement bars to proper grill as per the approved drawing, including cost and carriage of HYSD bars to work site, including cost of binding wire, all labour ,T&P etc, complete to receive the concrete, including all taxes, labour cess etc (excluding GST), including all leads, lifts and delifts, handling and rehandling as per the approved drawing, specification and Engineer-in- Charge.

22.61

-

7869.88

... More
Backfilling the excavated foundation, after completion of the intake structure, with suitable excavated materials (Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required , including disposal of the surplus excavated earth away from work site, finishing the site clean, with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

76.9

-

31.3

... More
Operation & Maintenance for UGPL Irrigation Network for 165.754 Ha of CCA including CAD network for Five kharif/five Rabi crop season which ever is later after commissioning UGPL Irrigation system including cost of all material, labour cess, all taxes etc. complete to provide successful irrigation to ayacut 165.754 Ha. as directed by the Engineer-in-Charge.(excluding GST)

165.75

-

1955

... More
Execution of under ground pipe line (UGPL) system for a total CCA of 198.149 Ha in Chitughat Minor Irrigation Projects on percentage rate basis including pre construction survey, execution as per planning & design, testing of pipe materials, providing & laying with DI pipes (DI or = 250mm dia) Ductile Iron class- K7 and K9 as per relevant IS code as per approved Drawing , with suitable jointing materials for stiffness class 2500 N/M2 as per IS-12709 & IS-14402 and High Density Polyethylene (HDPE) pipes of class PE-100, PN 6,PN8,PN10 and PN12.5 as per Approved Drawing , as per relevant IS code (HDPE pipe internal dia 250mm) having test pressure of approved standard for Pipe network as specified in technical specification, including D.I Air valves, , Butterfly valves, Sluice Valves, Reducers, Tee, Cross and Bend of matching materials, nuts & bolts of required sizes & specification and of approved make and quality and other construction materials including cost of all materials labour charges, all taxes, labour cess, Excluding GST, loading & unloading charges, transportation charges, cost of lowering, laying and jointing to proper alignment and position including earth work in excavation of trenches in all kinds of soils, D.I, Rock strata and with sand cushion of approved thickness for pipes and proper compaction of back filled earth and borrow earth in layers and including cost of Cement Concreting / R.C .C of approved grades, NP3 Hume Pipes of required diameter, Flush Structures and Turnout structures at required locations as per Approved Drawing etc. complete with all other ancillary works to complete the pipe network for providing irrigation at each ha. of CCA as per specification and direction of the Engineer-in-charge.

-

-

-

... More
Earthwork in excavation in Trenches by mechanical means for laying Ductile Iron (D.I )/ HDPE Pipes of different sizes in the UGPL Distribution Network in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) for depth of excavation up to 2.50m.including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per specification and the directions of the Engineer - in- charge.

21122.55

-

70.39

... More
Earthwork in excavation in Trenches by mechanical means for laying Ductile Iron (D.I )/ HDPE Pipes of different sizes in the UGPL Distribution Network in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) for depth of excavation more than 2.50m. including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per specification and the directions of the Engineer - in- charge.

875

-

863.81

... More
Filling the excavated trench with 150 mm thick sand free from silt and organic materials suitably spread to uniform thickness in rock & D.I. zone of the excavated trench for laying D.I./ H.D.P.E. Pipes over it with cost of all materials including royalties, labour cess, including cost of transportation, with all leads and lifts/ loading, un-loading , handling, rehandling and T&P etc.(excluding GST) complete as per specification and the directions of the Engineer- in - charge.

21997.55

-

24.69

... More
Backfilling the excavated trenches, after laying of D.I./H.D.P.E. Pipes, with suitable excavated materials(Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required ,including disposal of the surplus excavated earth away from work site with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

-

-

-

... More
a) In zones where depth of cutting is less than equal to 2.5m

21122.55

-

39.95

... More
b) In zones where depth of cutting is more than 2.5m

875

-

471.15

... More
Procurement and supply of centrifugally cast (spun) Ductile Iron pressure pipes with Spigot and Socket ended class K7 Pipes suitable for (push on type) Rubber Gasket jointing conforming to IS:8329-2000 (latest Revision) with inside Factory- centrifugally-applied cement mortar lining ( Slag Cement) and external Zinc coating followed by a finishing layer of Bitumen coating duly ISI marked including cost of EPDM Gasket complete including cost of pipe, cost of testing, inspection charges etc. transportation to work site, stacking at site, loading, un-loading, handling, rehandling, labour cess, including all taxes , duties, insurance, etc. (excluding GST) complete as per the specification and directions of the Engineer-in -charge; for the following nominal diameters

-

-

-

... More
DI K7 600 mm DIA

1403.24

-

9568.06

... More
DI K7 500 mm DIA

327.3

-

7343.62

... More
DI K7 400 mm DIA

305.2

-

5273.54

... More
DI K7 350 mm DIA

214.6

-

4402.77

... More
DI K7 300 mm DIA

579

-

3593.58

... More
DI K7 250 mm DIA

68.89

-

2851.24

... More
Procurement and supply of High Density Polyethylene ( HDPE) pipes of material grade PE 100 with pressure rating PN 6 conforming to IS:4984-2016 ( latest Revision) duly ISI marked, of standard length, including cost of pipes , cost of testing, inspection charges, transportation to work site, stacking at site with local handling and rehandling, including loading and un- loading, labour cess, including all taxes, duties, insurance, etc. (excluding GST) complete in all respect as per the specification and directions of the Engineer-in-charge; for the following nominal diameters.

-

-

-

... More
HDPE PN6 225 mm DIA

723.25

-

1282.43

... More
HDPE PN6 200 mm DIA

3437.53

-

1016.02

... More
HDPE PN6 180 mm DIA

1440.18

-

808.17

... More
HDPE PN6 160 mm DIA

2164.73

-

651.75

... More
HDPE PN6 140 mm DIA

1446.64

-

497.48

... More
HDPE PN6 125 mm DIA

9886.99

-

396.92

... More
Labour for laying D.I. pipes in the excavated trenches to required level and grade, with proper jointing, including cost of all materials, labour, machineries, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc. (excluding GST) complete including all lifts and delifts, as per the specifications and directions of the Engineer- in-charge. For the following nominal Diameters;

-

-

-

... More
DI K7 600 mm DIA

1403.24

-

354.4

... More
DI K7 500 mm DIA

327.3

-

264.1

... More
DI K7 400 mm DIA

305.2

-

208.1

... More
DI K7 350 mm DIA

214.6

-

184

... More
DI K7 300 mm DIA

579

-

134.4

... More
DI K7 250 mm DIA

68.89

-

114.3

... More
Labour for fixing & laying H.D.P.E. pipes with its fittings & Specials including Ball valves in the excavated trenches, proper to required level and grade with proper jointing of pipes having electro fusion jointing systems, including cost of all materials, labour, machineries, equipment, T&P, with all taxes, including transportation of pipes to worksite from the staking yard, handling, rehandling, loading, un-loading & labour cess, etc.(excluding GST) complete including all lifts and delifts, as per the specifications and directions of Engineer- in-charge. for the following nominal Diameters;

-

-

-

... More
HDPE PN6 225 mm DIA

723.25

-

305.3

... More
HDPE PN6 200 mm DIA

3437.53

-

274.3

... More
HDPE PN6 180 mm DIA

1440.18

-

274.3

... More
HDPE PN6 160 mm DIA

2164.73

-

199.3

... More
HDPE PN6 140 mm DIA

1446.64

-

171.7

... More
HDPE PN6 125 mm DIA

9886.99

-

155.2

... More
Supply of D.I. Pipe Fittings required for proper alignment of pipe lines as per approved drawing such as bends, Tees, reducers, Cross etc of required specification , at work site, including cost of materials, carriage, labour, all taxes ,labour cess & duties, loading, un- loading, handling, rehandling, etc.(excluding GST) complete as per the specification and directions of the Engineer-in charge.

12.88

-

14118.36

... More
Supply of H.D.P.E. Pipe Fittings required for proper alignment of pipe line as per approved drawing ,such as bends, Tees, Reducers, Cross etc of required specifications, at work site, including cost of materials, carriage, labour, all taxes , labour cess & duties, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge.

510

-

616.68

... More
Labour for fitting & fixing of all D.I. pipe fittings such as Bends, Tees, Reducers, cross etc at required location of D.I. pipe line Network in the trenches as per the Approved specifications and Drawing including all machineries, sundries, T&P, carriage of fittings, loading, unloading, handling, rehandling, etc. at work site including all lifts and delifts, with all taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of the Engineer-in-charge.

12.88

-

516.5

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Butter Fly Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P,including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

20

-

32773

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Air Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

12

-

33636

... More
Construction of Precast RCC (M-25 Grade) Valve chambers for Sluice Valves, of different sizes, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

1

-

32559

... More
Construction of Precast RCC (M-25 Grade) Outlet chambers, as per Approved Drawing including cost of excavation of chamber pit, cost of PCC (M- 15 Grade) for base of the chamber, cost and carriage of all materials, including precasting at casting yard with RCC M25 grade, including cost of shuttering, reinforcement, all materials complete, transporting the precast unit to designated work site and placing in position as per the Approved Drawing with all labour, T&P, including all lifts and delifts, including royalties, taxes of all materials, labour cess, etc. (excluding GST) complete as per the specification and directions of the Engineer-in-charge.

-

-

-

... More
a) 2 Ha Outlets

60

-

10810

... More
b) 1 Ha Outlet

88

-

7576

... More
Supply of D.I. Double Flanged (short body) Butter Fly Valve with EPDM liner conforming to IS:13095-2020 (latest version) with Stainless Steel shaft and pin with manual operation & required specifications at work site including testing and inspection charges, including cost of materials & all fittings, Specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge For the following sizes.

-

-

-

... More
125 mm

9

-

15522.25

... More
150 mm

7

-

17239.4

... More
200 mm

4

-

19023

... More
Supply of D.I. Tamper Proof Combination Air Valve PN 1.0 conforming to IS:14845-2000( latest revision) as per mfg.std with isolating Sluice valve as per Sluice Valve specifications, at work site, including cost of materials, all fittings, specials, all taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in charge. For the following sizes.

-

-

-

5

-

17942.85

2

-

22563.3

... More
100 mm

1

-

28923.67

... More
150 mm

4

-

46105.74

... More
Supply of D.I. Double Flanged gland-less Sluice Valve of PN-1.0 (IS:14846- 2000 Latest version) with non rising Stainless Steel spindle and EPDM Liner stem seal of required specifications as Scour Valve at work site, including testing and inspection charges, including cost of materials, all fittings and specials, all insurance, taxes & duties, transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
150 mm

1

-

21557.44

... More
Supply of HDPE Ball Valves of material PE100 pressure rating PN 6.0 of required specifications to site of work, including testing and inspection charges, including cost of materials, all fittings and specials, all taxes, insurances & duties, stacking at site transportation, loading, un- loading, handling, rehandling, etc. (excluding GST) complete as directions of the Engineer-in charge. For the following sizes.

-

-

-

... More
i) 125mm

120

-

2854.68

... More
ii) 110mm

88

-

2854.68

... More
Labour for fittings & fixing of different sizes of D.I. Butterfly valves, D.I. Air valves, D.I. Sluice valve, HDPE Ball valve as per the Approved specifications and Drawing at required designated location of the underground pipe line laid in the trenches including all materials, sundries, T&P,including all lifts and delifts, loading, unloading, handling, rehandling with all Taxes, duties, labour cess, etc. (excluding GST)complete as per the specification and directions of Engineer-in-charge for the following sizes.

-

-

-

... More
Butterfly valves

-

-

-

... More
125 mm

9

-

876.4

... More
150 mm

7

-

1204.6

... More
200 mm

4

-

1563

... More
Air Valves

-

-

-

5

-

315.9

2

-

315.9

... More
100 mm

1

-

622

... More
150 mm

4

-

756.3

... More
Sluice Valves

-

-

-

... More
150 mm

1

-

1204.6

... More
Construction of Road Crossing such as SH/MDR/ODR/VR etc. for the under ground pipe line with the pipe line laid inside RCC NP- 3 Hume Pipe of Diameter minimum 300mm larger than the outer Diameter of distribution pipe line, below the road as per the Approved Drawing with minimum 1.50m.earth cover above the top of RCC Hume Pipe up to the road surface, including cost of diversion of traffic, including cost of restoration of dismantled road work, with cost & carriage of RCC NP-3 Hume Pipe, all leads, lifts and delifts, including cost of excavation, all materials, carriage, handling, rehandling, laying and aligning of the RCC Hume Pipe including all taxes, labour cess, etc. (excluding GST) complete as per the specifications and directions of the Engineer-in-charge.

14

-

47221

... More
Construction of River/Nallah Crossing of the under ground pipe line with RCC lining of pipe &Thrust Block as per the Approved Drawing including cost of Earthwork, RCC, PCC, Reinforcement & Shuttering, including cost of diversion work, including restoration of the Nallah/stream, including dewatering of foundation pit, including cost of all materials, labour, T&P, carriage, including all leads, lifts and delifts, all taxes, labour cess, etc. (excluding GST) complete as per the directions of the Engineer-in-charge.

1

-

47470

... More
Construction of Horizontal Thrust Blocks at different location of the distribution network, as per approved Drawings and specifications including Excavation of foundation, dressing and levelling the bed, depositing the surplus excavated material after backfilling away from work site, including all PCC, RCC, reinforcements, shuttering and centering, , including cost of all materials, Carriage, Handling and rehandling, fixing the pipe line in proper position, including all leads, lifts and delifts, including all labour,T&P, machineries etc, including royalty, all taxes (excluding GST), including labour cess, . complete as per the specification and direction in Engineer-in-charge.

16

-

5358.53

... More
Construction of Intake Well Chamber near the existing Diversion Weir to facilitate off taking of the Distribution network Main Pipe including cost of excavation of foundation by mechanical means, including all RCC work, PCC work, as per the Approved Drawing including cost of fixing the off taking pipe and silt excluder pipe, including cost of RCC Cover Slab of the intake Well Chamber with man-holes, including fixing of the Galvanised rungs all complete as per the Approved Drawings, including all materials, labour, T&P,HYSD Reinforcement, Shoring, Centring and Shuttering, including all leads, lifts and delifts, including disposal of surplus earth away from work site, levelling and finishing the work site, including all taxes, royalties, labour cess(excluding GST), with transportation, handling and rehandling of all materials, complete as per the specifications and direction of Engineer-in-charge (Payment to be made through following items of work)

-

-

-

... More
Excavation of Foundation of Intake well by mechanical means in all kinds of Soil, including Stoney earth, gravel, moorum, D.I. Rock, fractured rock, soft rock, laterite rock, Hard Rock, etc. with use of Rock Breaker or suitable machineries & equipment's (blasting is not allowed) as per the approved drawing, including loading ,unloading and carriage within a lead of 1Km, with all leads, lifts and delifts, including cost of all labour, machineries, T&P including all taxes, labour cess, etc. (excluding GST) complete as per approved drawing, specification and the directions of the Engineer - in- charge.

120.81

-

72.72

... More
Providing PCC M15 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area , as per approved drawing, to proper level and thickness, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per the specification and direction of Engineer-in-charge.

4.12

-

4398.74

... More
Providing RCC M25 concrete with 20mm downgraded crusher broken hard granite chips and suitable sand free from silt and clay, cement 43 grade of approved manufacturer, properly mixed in a concrete mixer, laying in designated area to proper level and thickness, as per approved drawing, with proper compaction, including cost of all materials, carriage of all materials and royalty, entering, shuttering, dismantling the shuttering after specified period, including curing, including all leads, lifts, delifts, labours, including all taxes, labour cess (Excluding GST) etc complete as per approved drawing, the specification and direction of Engineer-in-charge.

42.25

-

5066.97

... More
Providing rigid and smooth centring and shuttering to all concrete works , PCC and RCC, as per approved drawings, for F1 finish of the concrete surfaces, for all heights, including cost of all shuttering and centring materials, including dismantling of the centring and shuttering after specified period, including carriage, handling and rehandling, all leads, lifts and delifts, all taxes, labour cess etc (excluding GST) complete as per approved drawing, specification and direction of Engineer-in-Charge.

230.65

-

675.2

... More
Providing HYSD bars for Reinforcement, cutting, bending and binding the reinforcement bars to proper grill as per the approved drawing, including cost and carriage of HYSD bars to work site, including cost of binding wire, all labour ,T&P etc, complete to receive the concrete, including all taxes, labour cess etc (excluding GST), including all leads, lifts and delifts, handling and rehandling as per the approved drawing, specification and Engineer-in- Charge.

22.61

-

7694.95

... More
Backfilling the excavated foundation, after completion of the intake structure, with suitable excavated materials (Top 0.6m depth shall be suitable for cultivation) in layers and compacting the same by rammers, including borrowing of earth wherever required , including disposal of the surplus excavated earth away from work site, finishing the site clean, with all leads, lifts and delifts, including all labour, carriage, cost of borrow earth, T&P, all taxes, labour cess, cost of transportation, loading, un-loading, handling, rehandling, etc. (excluding GST) complete as per the specification and directions of the Engineer- in- charge.

76.9

-

31.3

... More
Operation & Maintenance for UGPL Irrigation Network for 198.14 Ha of CCA including CAD network for Five kharif/five Rabi crop season which ever is later after commissioning UGPL Irrigation system including cost of all material, labour cess, all taxes etc. complete to provide successful irrigation to ayacut 198.14 Ha. as directed by the Engineer-in-Charge.(excluding GST)

198.14

-

1955



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.