Search from over 12139+ business opportunities that have been announced from the biggest Mahatenders, e tender Maharashtra, Maharashtra government tenders, and the Online Tender Notices posted on Maharashtra e tenders till date. Find opportunities that have come in from the multiple corporations, Maharashtra government departments, State PSUs, and Private companies from the state.
Tourism And Cultural Affairs Department Tender
Civil And Construction
Civil Works Others
Eprocure
Opening Date5 Dec 2024
Closing Date20 Dec 2024
Tender Amount₹ 9,14,59,072
Costs
EMD
₹ 4,57,295Document Cost
₹ 3,540Tender Fee
₹ 500
Summary
Conservation And Repair Of Janjhala Taltam Fort Chhatrapati Sambhajinagar
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_TCADM_1121325_1Bid Award Id
ViewTender No
Etender/Notice21/2024-25Tender Authority
Tourism And Cultural Affairs Department ViewPurchaser Address
-Website
http://mahatenders.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Dismantling stone masonry in lime or cement
mortar including stacking the materils as directed
with all leads, lifts etc.
381.54
418
159483.72
... More
Desilting the Supply Well, Intake Well / Head
Works, Sump of water supply / sewerage works etc. in wet or dry condition including lifts upto 9 M and lead upto 150 M as required beyond the work site, stacking, spreading, including necessary guarding, etc. complete, as directed by Engineer- in-charge.
747.45
818
611414.1
... More
Scientific Excavation for debris soil as scientific
excavation/ clearance in earth, soils of all types,
sand, gravel, soft murum including shoring and
strutting, dewatering as necessary and disposing
off excavated stuff as directed etc. complete. ( By
/manaual Means ) - a) Upto 1.50m lift Normal Rate,
b) 1.50m to 3.00m lift, Add 10% c) 3.00m to 4.50m
lift, Add 20% d) 4.50m to 6.0m lift, Add 30%
1339.2
382
511574.4
... More
Excavation for foundation in earth, soils of all
types, sand,gravel and soft murum, including
removing the excavated material upto a distance of 50 metres beyond the building area and
stacking and spreading as directed, dewatering,
preparing the bed for the foundation and
necessary back filling, ramming, watering including
shoring and strutting etc. complete. (Lift from 1.5m
to 3.0m) By Manual Means
1771.98
345
611333.1
... More
Conveying the excavated materials, debris of brick or stone masonry, RCC, Slab, Water proofing, stone members/ materials, cement/ lime concrete,
tiles/ marbles / stone slab/ brick bat coba, etc. upto
5 km, away from the site and cleaning the site
properly.
4240.17
277
1174527.09
... More
Shiffting the heavy stone from 50 to 100m distance
by male mazdoor (havey) with all necessary
equipments, tools etc, complete.
1512
802
1212624
... More
Specialised Bricks,Stone cleaning to remove oil or
emulsion paint, stains or dark patches, layers of
Impervious coatings cementatious layers, rust
stains from surface of stone with chemicals,
thinners, solvents, or soft Teepol type soap
solution or by pressure jet machine or equivalant.
A gentle use of air abrasive tools may be permitted
as long as no damage to the original surface is
ensured. It may include usage of mechanical
tapping, chemical surfactant or solvents, patent
cleaning product or use of pressurised micro
abrasives as necessary Test patches would need
to be undertaken to assess efficiency of technique
prior to work. Removal to be followed by water
washing. The surface shall finally be cleaned by
hand rubbing and rinsing with clean water to obtain
nearly original surface, colour and texture.
7037.7
147
1034541.9
... More
Crack Stitching 8mm Helibar Providing and fixing
of Helifix Hi-fin reinforcement Helibars of 8mm dia,
single bar in one slot, MOC Austenitic stainless
steel, ASTM 304, having cross section area of
10.5sqmm, pitch 38/40, with ultimate tensile
strength not less than 1370 N/sqmm, shear
strength 7.2kN, along with Helibond Grout, a
special cementitious grout with low expansion, non
gassing and injectable with exceptional non shrink
thixotropic properties having compressive strength at 28 days of not less than 45 N/sqmm. Including
chasing of slot in mortar bed upto a depth of 40mm
for HeliBars, cleaning the dust and debris from the
slot, making damp with water to achieve good
bonding of HeliBar with HeliBond grout in the
groove of brick/stone masonry ensuring that it
remains tight at the joint after curing, including all
tools, tackles and equipments using specified
machines, excluding Staging & Scaffolding, at
various places where there is crack in brick/
stone/ block masonry as directed by structural
engineer in charge/ Helifix
70.6
4653
328501.8
... More
Creating HeliBeam (A structural barrier between
the strucutrual crack) using two 6mm Helibars
Providing and fixing of Helifix Hi-fin reinforcement
Helibars of 6mm dia, two bars in one slot, MOC
Austenitic stainless steel, ASTM 304, having cross
section area of 8sqmm, pitch 29/30, with ultimate
tensile strength not less than 980 N/sqmm, shear
strength 5.5 kN of single bar, along with Helibond
grout, a special cementitious grout with low
expansion, non gassing and injectable with
exceptional non shrink thixotropic properties
having compressive strength at 28 days of not
less than 45 N/sqmm. Including chasing of slot in
mortar bed upto a depth of 50mm for HeliBars,
cleaning the dust and debris from the slot, making
damp with water to achieve good bonding of
HeliBar with HeliBond grout in the groove of
brick/stone masonry ensuring that it remains tight
at the joint after curing, including all tools, tackles
and equipments using specified machines,
excluding Staging & Scaffolding, at various places
where there is crack in brick/ stone/ block
masonry as directed by structural engineer in
charge/ Helifix.
79.75
5417
432005.75
... More
Providing injection grouting with a slurry of lime and
fine screened sand in proportion 1 : 1 with a proper
pressurized jet pump, including cleaning, washing
and packing the exisitng cracks or holes in the
brick or stone masonry properly upwards with the
slurry, scaffolding, curing etc. complete
10444.1
120
1253292
... More
Providing soling using 80 mm size trap metal in 15
cm. layer including filling voids with Crushed
sand/grit, ramming, watering etc. complete.
173.52
3164
549017.28
... More
Providing and laying cast in situ 1:2:4 Lime
Concrete of trap/ granite/ quartzite/ gneiss metal
for foundation and bedding as per detailed
specifications and drawings or as directed
including bailing out water, centring, formwork,
laying/pumping, compacting, roughening them if
special finish is to be provided, finishing if required
with fine aggregate, preparing the lime mortar in
lime miller and then mixing with coursed aggregate
in drum mixer as per specifications including
bailing out water, watering etc. complete.
266.19
9923
2641403.37
... More
Providing dry rubble stone pitching 23 cm (about 9
) thick including all material, quarry spalls, labour
etc. complete.
740
454
335960
... More
Re-setting Ashlar Rough-tooled Masonry of reuse-
stones in lime mortar 1:11⁄2 in superstructure as
per detailed specifications and drawings or as
directed including all beds or joints, which shall not
exceed 6 mm. (1⁄4′′), the stones shall be set in
mortar, the stone shall be laid in regular course,
the face stone shall be laid header and stretcher
alternately, preparing the lime mortar in lime miller,
scaffolding, watering and all masonry work when
handed over to be perfectly clean and free from all
mortar stains etc. complete.
407.4
8465
3448641
... More
Providing Un-coursed Rubble Masonry of trap /
granite stones in lime mortar 1:1½, in foundation
and plinth as per detailed specifications and
drawings or as directed including the stones to be
set in the work as received from the quarry, after
merely knocking off weak corners and edges with
the masons hammer, the stones shall be carefully
laid so as to break joints, no joint shall exceed 12.5
mm. (½″) in thickness, every stone shall be set
flush in mortar, the face stone shall be for greater
size, and good beds, one through stone shall be
inserted at least every 0.80 sq. mete (1 square
yard), the joints shall be racked out carefully at
least 25 mm. (1″) where pointing or plastering to
be done, striking joints where no pointing or
plastering is to be done, preparing the lime mortar
in lime miller, bailing out water, watering and all
exposed masonry work when handed over to be
perfectly clean and free from all mortar stains etc.
complete.
735.91
10631
7823459.21
... More
Providing Un-coursed Rubble Masonry of trap /
granite stones in lime mortar 1:11⁄2, in
superstructure as per detailed specifications and
drawings or as directed including the stones to be
set in the work as received from the quarry, after
merely knocking off weak corners and edges with
the masons hammer, the stones shall be carefully
laid so as to break joints, no joint shall exceed 12.5
mm. (1⁄2′′) in thickness, every stone shall be set
flush in mortar, the face stone shall be for greater
size, and good beds, one through stone shall be
inserted at least every 0.80 sq. mete (1 square
yard), the joints shall be racked out carefully at
least 25 mm. (1′′) where pointing or plastering to be
done, striking joints where no pointing or plastering
is to be done, preparing the lime mortar in lime
miller, scaffolding, watering and all masonry work
when handed over to be perfectly clean and free
from all mortar stains etc. complete.
1826.47
10631
19417202.57
... More
Providing Ashlar Rough-tooled Masonry (Newasa
stone ) of trap / granite stones in lime mortar 1:1½
with size of stone is 60 cm. x 30 cm. x 23 cm.
in superstructure as per detailed specifications
and drawings or as directed including the stones
be of approved quality, colour, hard and free from
defect of any kind, the faces exposed to view shall
have fine dressed chisel draft, 25 mm. (1″) wide all
around the edges and rough tooled between the
drafts, and on all beds or joints, which shall not
exceed 6 mm. (¼″), the stones shall be set in
mortar, the stone shall be laid in regular course not
less than 30 cm. (12″) in height averaging 4½ c. ft.,
the face stone shall be laid header and stretcher
alternately, preparing the lime mortar in lime miller,
scaffolding, watering and all masonry work when
handed over to be perfectly clean and free from all
mortar stains etc. complete.
616.74
58669
36183519.06
... More
Providing Rectangular Coping Cut-stone Second
Sort, 20 cm. height and 60 cm. wide of trap /
granite stones in lime mortar 1:1½ with size of
stone 60 cm x 60 cm x 20 cm. as per detailed
specifications and drawings or as directed
including the stones be of approved quality, colour,
hard and free from defect of any kind. the stone
shall be dressed full or to template, exposed face
of the stones shall be fine rough tooled, all joints
shall be in line and close and not more than 3 mm.
(1/8") thick, preparing the lime mortar in lime miller,
scaffolding, watering and all coping work when
handed over to be perfectly clean and free from all
mortar stains etc.
680.17
8729
5937203.93
... More
Providing Ashlar Rough-tooled Stone Steps of trap
/ granite stones in lime mortar 1:11⁄2 with size of
stone 45 cm. x 30 cm. x 20 cm. as per detailed
specifications and drawings or as directed
including the stones be of approved quality, colour,
hard and free from defect of any kind, the stones
shall be of exact size and shape, the shall be
rough-tooled on exposed surface, holes for
balusters should be cut in the steps before they
are laid, each stone shall rest at least 3.8 cm.
(11⁄2′′) on that below it, the beds or joints being in
no case more than 3 mm. (1⁄8′′), preparing the lime
mortar in lime miller, watering and all steps work
when handed over to be perfectly clean and free
from all mortar stains etc. complete.
5.62
54865
308341.3
... More
Making of moulding/ grooving/ chamfering on the
surface of the formed stone member, as per given
design or drawing, by an expert, artisan
craftsman, including light sand papering of the
finished member if required.
106927.67
7
823343.06
... More
Providing Soil Bag Support to the monument with
contractor´s soil in proper layers carefully as
directed by Engineer in-charge including filling,
tying and conveying the bags, removing the soil
bags after work up to a distance of 50 meter
beyond the monument area and cleaning the site
etc. complete.
198.94
1597
317707.18
... More
Providing Lime Pointing to stone work in lime
mortar 1:1 in superstructure, as per detailed
specifications and drawings or as directed
including all face or visible work shall be pointed,
unless otherwise specified and shall be done while
the mortar is fresh, the mortar shall consists of
lime and fine sand shall not be ground fine but
sand should be finer, the joints of the pointed work
shall be neatly defined by the pointing, the lines
shall be regular and uniform in breadth and the
joints shall be raised or flat as may directed,
preparing the lime mortar with 640 gram pulp of
wood apple (Belfruit) per cubic metre of lime
mortar as a bonding material, scaffolding, watering
and all work when handed over to be perfectly
clean and free from all mortar stains etc. complete
5568.3
398
2216183.4
... More
Providing and fixing Stone Paving, Second Sort in
lime mortar 1:1, with size of stone 45 cm. x 30 cm.,
as per detailed specifications and drawings or as
directed including all stone slabs to of approved
quality, hard, even, sound, durable and uniform
thickness, the stones to be very finely chisel-
dressed on the surface and the course to be of
prescribed width, the joints running true, the
stones to be laid with joints not exceeding 6 mm.
(1⁄4′′) thick and to be evenly and firmly bedded
flush in mortar on the concrete and no hollow left,
side to be dressed true and as per shape at least
half the depth from the face, preparing the lime
mortar in lime miller, watering and all paving work
when handed over to be perfectly clean and free
from all mortar stains etc. complete.
325.71
8446