Know all about the latest MP tenders along with the tender details and downloadable document on BidAssist. Here, on this page, we shall help you search for every MPtender posted on the official website of mptenders.gov.in according to authority, district, etc. Be it an irrigation tender or MP PWD tender, and we will tell you how to bid for these and more.

MP Power Transmission Company Limited - MPPTCL Tender

Works
Civil And Construction
Civil Works Others
Eprocure
Opening Date15 Feb 2024
Closing Date20 Mar 2024
Tender Amount₹ 5,87,379 
Notes
Download

Costs

  • EMD

    ₹ 14,000
  • Document Cost

    ₹ 590
  • Tender Fee

    ₹ 295

Summary

Dismantling And Shifting Of 20mva Bbl Make Transformer Sr. No. 3201-1 And Other Associated Work Of 132kv And 33kv Bay Of Proposed 50mva Transformer Bays At Julwaniya 220kv Substation Ts-19-2023

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Control & Relay Panel for 132 KV Feeder/X-mer/ Bus Coupler: Unloading of C&R Panel, shifting up to control room (including storage if required) and placement complete with all relays & accessories. The placement of C&R panel to be done on MS channel frame and MS channel frame will suitable grouted in control room as per drawing. The cutting welding & fabrication of MS Channel frame is to done as per drawing. Proper alignment of C&R panel to be done. The earthing of control & relay panel to be done. Making of all inter connection for the control & relay panel on terminal block as per drawing including all AC & DC connections.

1

9600

9600

... More
Erection of 132 KV Isolator : Unloading of Isolator from the from Civil foundation and removing of complete isolator in all three phase of isolator structure and dismantling of mechanism box, Interconnection piping, alignment of contacts and all associated activities to make the installation completed including checking of successful technical and electrical operation.

1

18000

18000

... More
Erection of 33 KV Current Transformer: Unloading of C.T. from the carriage and Shifting of 33 KV C.T. up to Civil foundation and placement on structure and fixing of junction Box, including all accessories, making all jumpers etc.

9

32400

3600

... More
Erection of 33 KV Surge Lightning Arrester: Unloading of L.A. from the carriage and Shifting of 33 KV Surge Lightning Arrester and placement on structure and fixing of all accessories, making all connections, checking and installation of insulator base and Surge counters, making all jumpers etc.

3

7200

2400

... More
Erection of 33 KV Isolator without Earth switch (3phase): Unloading of Isolator Without Earth switch from the carriage and shifting up to Civil foundation and placement of complete isolator in all three phase of isolator structure and Erection/mounting of mechanism box, interconnection piping, alignment of contacts, with solid core Insulator and all associated activities to make the installation completed including checking of successful technical and electrical operation.

6

64800

10800

... More
Erection of 33 KV Circuit Breaker (3 Phase): Unloading and shifting of Circuit Breaker from the carriage and placement of C.B. on structure. Complete assembly of C.B. including Erection of control cabinet and mechanism box. Erection of all accessories for the Equipment

1

12000

12000

... More
Laying of cables on rack/cable trays/angle support overhead racks, conducts including dressing of cables with accessories for copper conductor and armour control cables: 8 Core x 2.5 sq.mm.

500

7000

14

... More
Laying of cables on rack/cable trays/angle support overhead racks, conducts including dressing of cables with accessories for copper conductor and armour control cables: 12 Core x 2.5 sq.mm.

1000

18000

18

... More
Laying of cables on rack/cable trays/angle support overhead racks, conducts including dressing of cables with accessories for copper conductor and armour control cables: 19 Core x 2.5 sq.mm.

500

15000

30

... More
Cable terminations including fixing of cable glands, lugs etc. for each type of control / Power cables, including terminations at both end: 8 Core x 2.5 sq.mm.

8

1440

180

... More
Cable terminations including fixing of cable glands, lugs etc. for each type of control / Power cables, including terminations at both end: 12 Core x 2.5 sq.mm.

10

2400

240

... More
Cable terminations including fixing of cable glands, lugs etc. for each type of control / Power cables, including terminations at both end: 19 Core x 2.5 sq.mm.

8

3360

420

... More
EARTHING INSTALLATION: Installation of steel risers and making earth mat (duly buried at a depth of 0.5 mtrs.) including back filling welding etc. and bolting of risers to the structures/ equipments at desired place: 65x8mm

250

19500

78

... More
EARTHING INSTALLATION: Installation of steel risers and making earth mat (duly buried at a depth of 0.5 mtrs.) including back filling welding etc. and bolting of risers to the structures/ equipments at desired place: 50x6mm

250

15000

60

... More
DISMANTLING OF STRUCTURES Dismantling of structures including shifting within Sub-station premises, fixing and alignment of templates for grouted/bolted type structures foundations, lighting of nuts, bolts, washers etc. and including alignment and levelling of structures (a) Dismantling of 132 KV CT structures (03 nos.) (b) Dismantling of 33 KV CT structures (03 nos.)

1.22

4626

3808

... More
ERECTION OF STRUCTURES Erection of structure from the carriage including shifting within Sub-station premises, fixing and alignment of templates for grouted/bolted type structures foundations, lighting of nuts, bolts, washers etc. and including alignment and levelling of structures (a) Erection of 132 KV CTstructures (03 no.) (b) Erection of 33 KV CT structures (03 no.) (c) Erection of 33 KV Gantry Beam (1 No.)

1.27

9702

7616

... More
Dismantling of 132/33KV 20 MVA CGL make Transformer Sr. no. 24400 Complete dismantling of 20 MVA 132/33KV Transformer, along with its accessories, like headers, Radiators, Conservators, Breathers, cooling fans, Marshalling box, OLTC mechanism. Thermosyphon, etc. after preliminary inspection.

1

45000

45000

... More
Dragging of 132/33KV 20 MVA CGL make Transformer Sr. no. 24400 along with oil 36MT and all accessories 3MT from existing plinth to the place with in Substation premises (Rs/MT/Mtr.) (` 35 x 39MT x 80 Mtr.); rates taken from CE (Procurement) MPPTCL Transport order no. 04-01/TR-40/2020/SE-II/04796-9 Dtd. 12.05.2021

3120

109200

35

... More
Dismantalling of (33/0.4 KV) Station Transformer with structure by shifting & unloading up to the carriage and shifting from structure by removing jumpers in all three phase, structure and dismantling of mechanism box, interconnection piping, alignment of contacts as per directive of substation incharge.

1

11400

11400

... More
Erection of (33/0.4 KV) Station Transformer with structure Unloading of Xmer from the carriage and Shifting of Transformer and placement on structure and fixing of all accessories, making all connections, checking and installation of insulator base and Surge counters, making all jumpers etc. as per directive of substation incharge.

1

22800

22800

... More
DISMANTLING OF ACSR CONDUCTOR ON OVERHEAD GANTRIES, VERTICAL DROPPERS ETC ACSR Single Zebra conductor

300

9750

32.5

... More
DISMANTLING OF ACSR CONDUCTOR ON OVERHEAD GANTRIES, VERTICAL DROPPERS ETC ACSR Single Panther conductor

200

3000

15

... More
Dismantling of 132 KV CT by shifting & unloading up to the carriage and Shifting of 132 KV CT from structure and removing of all accessories, all connections, checking and dismantling of insulator base and Surge counters, removing all jumpers etc.

3

27000

9000

... More
Dismantling of 132 KV C&R Panel by shifting & unloading up to the carriage and removing of all accessories, all connections, checking, wire and dismantling etc.

1

4800

4800

... More
Dismantling of 33 KV CT by shifting & unloading up to the carriage and Shifting of 33 KV CT from structure and removing of all accessories, all connections, checking and dismantling of insulator base and Surge counters, removing all jumpers etc.

9

16200

1800

... More
Dismantling of 33 KV CB by shifting & unloading up to the carriage and Shifting of 33 KV CB from structure and removing of all accessories, all connections, checking and dismantling of insulator base and Surge counters, removing all jumpers etc.

1

6000

6000

... More
Dismantling of 33 KV LA by shifting & unloading up to the carriage and Shifting of 33 KV LA from structure and removing of all accessories, all connections, checking and dismantling of insulator base and Surge counters, removing all jumpers etc.

3

3600

1200

... More
Dismantling of 33 KV Isolator by shifting & unloading up to the carriage and shifting from structure by removing isolator in all three phase of isolator structure and dismantling of mechanism box, interconnection piping, alignment of contacts.

3

16200

5400



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.