Know all about the latest MP tenders along with the tender details and downloadable document on BidAssist. Here, on this page, we shall help you search for every MPtender posted on the official website of mptenders.gov.in according to authority, district, etc. Be it an irrigation tender or MP PWD tender, and we will tell you how to bid for these and more.
MP Power Transmission Company Limited - MPPTCL Tender
Civil And Construction
Civil Works Others
Eprocure
Opening Date18 Jul 2024
Closing Date13 Aug 2024
Tender AmountRefer Documents
Costs
EMD
₹ 8,000Document Cost
₹ 590Tender Fee
₹ 295
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_MPPTC_358299_1Bid Award Id
ViewTender No
3373000/NIT/TS-02/2024-25Tender Authority
MP Power Transmission Company Limited ViewPurchaser Address
-Website
http://https://mptenders.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
complete erection work of 01 No. 132KV and 01 No. 33KV Bus Coupler Bay at 132 KV Sub-Station Berasiya under EE Testing Dn. MPPTCL Vidisha, against NIT Tender Specification No. 3373000/2024-25/TS-02.
complete erection work of 01 No. 132KV and 01 No. 33KV Bus Coupler Bay at 132 KV Sub-Station Berasiya under EE Testing Dn. MPPTCL Vidisha, against NIT Tender Specification No. 3373000/2024-25/TS-02.
BOQ Items
... More
Erection of structure including shifting within Sub-station premises, fixing and alignment of templates for grouted/bolted type structures foundations, tightening of nuts, bolts, washers etc and including alignment and leveling of structures of132 KV Solid core Structure (03 No.)
0.58
4409
7616
... More
Erection of structure including shifting within Sub-station premises, fixing and alignment of templates for grouted/bolted type structures foundations, tightening of nuts, bolts, washers etc and including alignment and leveling of structures of 33 KV Isolator (02 No.)
0.54
4112
7616
... More
Erection of structure including shifting within Sub-station premises, fixing and alignment of templates for grouted/bolted type structures foundations, tightening of nuts, bolts, washers etc and including alignment and leveling of structures of 33 KV CT Structure (03 No.)
0.26
1987
7616
... More
Erection of structure including shifting within Sub-station premises, fixing and alignment of templates for grouted/bolted type structures foundations, tightening of nuts, bolts, washers etc and including alignment and leveling of structures of 33 KV Solid core Structure (03 No.)
0.26
1987
7616
... More
Stringing of over head gantries vertical droppers with ACSR conductor including fixing of insulator string spares, clamps etc (Twin Zebra Conductor).
100
12600
126
... More
Shifting & Placement of all the three circuit breaker Poles on structure including shifting with in Substation premises. Complete assembly of 132 KV Circuit Breaker including erection of mechanism Box interconnections piping work, erection of all accessories of the equipments & making interconnections and its earthing
1
18000
18000
... More
Shifting of 132 KV Current Transformer from Sub-station premises to Civil foundation and placement on structure and Erection of CT ,fixing of junction Box , including all accessories , making all jumpers etc.
3
21600
7200
... More
Shifting and placement of complete 132KV isolator without Earth switch (Three Phase) in all three phase of isolator on structure and its earthing along with mounting of mechanism Box, interconnections piping, alignment of contacts & all accessories along with application of Petroleum Jelly on Jaws & Contracts
2
36000
18000
... More
132 KV C&R Panel for Bus coupler, shifting up to control room (including storage if required) and placement complete with all relays & accessories . The placement of C&R panel to be done on MS channel frame and MS channel frame will suitable grouted in control room as per drawing . The cutting welding & fabrication of MS Channel frame is to done as per drawing. Proper alignment of C&R panel to be done. The earthing of control & relay panel to be done . Making of all inter connection for the control & relay panel on terminal block as per drawing including all AC & DC connections
1
9600
9600
... More
132 KV Solid core Insulator Shifting up to Civil foundation and placement on structure and fixing of all accessories, making all connections, Checking and installation of insulator base and Surge counters, making all jumpers etc...
6
8640
1440
... More
Stringing of over head gantries vertical droppers with ACSR conductor including fixing of insulator string spares, clamps etc (Single Zebra Conductor).
300
19500
65
... More
Stringing of Screening Conductor/OH shield wire
200
5000
25
... More
Shifting & Placement of all the three circuit breaker Poles on structure including shifting with in Substation premises. Complete assembly of 33 KV Circuit Breaker including erection of mechanism Box interconnections piping work, erection of all accessories of the equipments & making interconnections and its earthing
1
12000
12000
... More
Shifting of 33 KV Current Transformer from Sub-station premises to Civil foundation and placement on structure and Erection of CT ,fixing of junction Box , including all accessories , making all jumpers etc.
3
10800
3600
... More
Shifting and placement of complete 33 KV isolator without Earth switch (Three Phase) in all three phase of isolator on structure and its earthing along with mounting of mechanism Box, interconnections piping, alignment of contacts & all accessories along with application of Petroleum Jelly on Jaws & Contracts
2
21600
10800
... More
33 KV C&R Panel for Bus couler, shifting up to control room (including storage if required) and placement complete with all relays & accessories . The placement of C&R panel to be done on MS channel frame and MS channel frame will suitable grouted in control room as per drawing . The cutting welding & fabrication of MS Channel frame is to done as per drawing. Proper alignment of C&R panel to be done. The earthing of control & relay panel to be done . Making of all inter connection for the control & relay panel on terminal block as per drawing including all AC & DC connections
1
7800
7800
... More
33 KV Solid core Insulator Shifting up to Civil foundation and placement on structure and fixing of all accessories, making all connections, Checking and installation of insulator base and Surge counters, making all jumpers etc...
3
2160
720
... More
Laying of cables 2 Core x 2.5 Sq.mm Unarmoured on racks/cable trays/angle support overhead racks, conduits including dressing of cables with accessories for copper conductor and armor control cables
500
5000
10
... More
Laying of cables 4 Core x 2.5 Sq.mmUnarmoured on racks/cable trays/angle support overhead racks, conduits including dressing of cables with accessories for copper conductor and armor control cables
500
6000
12
... More
Laying of cables 8 Core x 2.5 Sq.mmUnarmoured on racks/cable trays/angle support overhead racks, conduits including dressing of cables with accessories for copper conductor and armor control cables
500
7000
14
... More
Laying of cables 12 Core x 2.5 Sq.mmUnarmoured on racks/cable trays/angle support overhead racks, conduits including dressing of cables with accessories for copper conductor and armor control cables
500
9000
18
... More
Cable terminations consisting the work of providing holes for cable entry, fixing of cable glands, lugs etc. for 2 Core x 2.5 Sq.mm Unarmoured control / Power cables, including terminations at both end
10
1020
102
... More
Cable terminations consisting the work of providing holes for cable entry, fixing of cable glands, lugs etc. for 4 Core x 2.5 Sq.mm Unarmoured control / Power cables, including terminations at both end
8
960
120
... More
Cable terminations consisting the work of providing holes for cable entry, fixing of cable glands, lugs etc. for 8 Core x 2.5 Sq.mm Unarmoured control / Power cables, including terminations at both end
8
1440
180
... More
Cable terminations consisting the work of providing holes for cable entry, fixing of cable glands, lugs etc. for 12 Core x 2.5 Sq.mm Unarmoured control / Power cables, including terminations at both end
8
1920
240
... More
Laying of Flat (65 mm x 8 mm) duly buried at a depth of 0.5 mtr. providing or risers for structures earthing including back filling welding etc. structure earthing of following length.
200
15600
78
... More
Laying of Flat (50 mm x 6 mm ) duly buried at a depth of 0.5 mtr. providing or risers for structures earthing including back filling welding etc. structure earthing of following length.
300
18000
60
... More
25mm dia x 3000 mm long M.S. rod earth electrodes installation directly driven/drilled (6’’ dia) into earth including excavation (inrespective of type of soil encountered) backfilling with betonite soil (to be arranged by contractor) welding to earth conductor etc.
10
10800
1080
... More
Preparation of earthing pits (1.5x1.5x3 Mtrs) as per boards drawing No. XII-8-774b, which includes excavation (Irrespective of the soil encountered) embading of 4 No GI Pipes of size 40mm dia, 3 Mtrs long back filling with B.C. soil (to be arranged by the contractor) free from boulders and harmful mixture. These GI pipes are to be welded with MS flats by making mesh frame and cutting of pipes as also making holes in the pipe for water seepage. The earth pit is to be connected with earth mesh of MS flat
2
21600
10800
... More
Installation of HPSV/HPMH light fixtures (250 Watt) on gantry columns in supply connection to the light fitting from the nearest lighting board in the yard etc.
5
2400
480