MP Power Transmission Company Limited Tender

Know all about the latest MP tenders along with the tender details and downloadable document on BidAssist. Here, on this page, we shall help you search for every MPtender posted on the official website of mptenders.gov.in according to authority, district, etc. Be it an irrigation tender or MP PWD tender, and we will tell you how to bid for these and more.

MP Power Transmission Company Limited - MPPTCL Tender

Works
Electrical and Electronics
Electrical Works
Eprocure
Opening Date7 Feb 2024
Closing Date28 May 2024
Tender Amount₹ 1,07,69,667 
Notes
Download

Costs

  • EMD

    ₹ 2,54,200
  • Document Cost

    ₹ 5,900
  • Tender Fee

    ₹ 1,271

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
Erection work related to installation of 220 kV/ 132KV/ 33 kV feeder bays/ transformer bay/ Additional/ Augmentation transformer/ Capacitor Bank bay at various 400kV/ 220 kV/ 132 kV Substations under EHT Construction Division Balaghat
Erection work related to installation of 220 kV/ 132kV/ 33 kV feeder bays/ Transformer bays/ Additional Transformers/ Augmentation Transformers/ Capacitor Bank bay at various 400kV/ 220 kV/ 132 kV Substations under EHT Construction Division Balaghat
Report Missing Document

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Complete assembly & erection of 63 MVA 132/33 KV Power Xmer with connection etc. including installation of marshelling boxes , control cabinet, air sealing radiators , cooling fan ,all accessories etc. for Xmer including there preliminary checks. unloading / handling of Transformer assessories & vaccum creation , handlling & filling of xmer oil / Filtration alongwith associated equipment ( Filter machine & Vaccum pump will be provide by MPPTCL) (with oil and associated equipments)

2

408000

204000

... More
COMPLETE ASSEMBLY & ERECTION OF 160 MVA 220 / 132 KV POWER TRANFORMER WITH CONNECTION / WIRING ETC. INCLUDING INSTALLATION OF MARSHALLING BOXES, CONSERVATORS, THERMOSIPHONS / RTCC PANEL, RADIATORS, COOLING FANS, CONTROL CABELS AND ALL REMAINING ACCESSORIES ETC FOR TRANSFORMER INCLUDING THEIR PRELIMINARY CHECKS, UNLOADING / HANDLING OF TRANSFORMERS ACCESSORIES, HANDLING AND FILLING OF TRNAFORMER OIL, ALONG WITH ASSOCIATED EQUIPMENT. (FILLTER MACHINE OPERATING STAFF AND VACUUM PUMP SHALL BE PROVIDED BY THE COMPANY) (with oil and associated equipments)

1

420000

420000

... More
UNIT RATE FOR UNLOADING, STORAGE, INSTALLATION AND ERECTION OF OUTDOOR EQUIPMENTS - ERECTION OF 33 kV CB - Erection of structures and alignment, shifting of breaker upto the place and placement of circuit breaker on structure and alignment. Complete assembly of circuit breaker including erection of control cabinet & mechanism box, interconnecting piping work erection of all accessories for the equipment and making interconnections.

10

120000

12000

... More
220kV Circuit Breaker 3 -phase ( Shifting of breaker up to the place & placement of all 3 circuit breaker poles on structures including shifting within S/s premises. Complete assembly of circuit breaker including erection of control cabinet & machenism box interconnecting piping works,erection of all accessories of the equipments and making interconnections)

2

74400

37200

... More
220 KV CT ( Shifting & placement on structure including fixing of junction box & all accessories, making all interconnections)

6

72000

12000

... More
220 KV Isolator without E/S ( Placement of complete isolator in all 3 phase of isolator structure,including shifting within S/s premises. Erection / mounting of mechanism box, interconnection, piping, alingment of contacts & all associated activities)

2

60000

30000

... More
220 KV Isolator with E/S ( Placement of complete isolator in all 3 phase of isolator structure,including shifting within S/s premises. Erection / mounting of mechanism box, interconnection, piping, alingment of contacts & all associated activities)

8

240000

30000

... More
220 KV LA ( Shifting & placement of LA equipment on structure including all accessories, making all interconnections, checking installation of insulator base and surge counters.)

6

43200

7200

... More
220 KV C&R Panel (Unloading of control & relay panel and placement of panel complete with all relays and their accessories. Making of all connections for the control and relay panel on terminal block as per drawing all AC & DC connection)

2

31200

15600

... More
220 KV PI/Solid Core Insulators (Shifting & placement of PI equipment on structure )

18

32400

1800

... More
Carrier Cabinet

4

57600

14400

... More
Set of Coupling devices line matching unit for PLCC purposes

4

24000

6000

... More
220 kV CVT

6

72000

12000

... More
Coaxial Cable

2000

360000

180

... More
Total Weight (in MT) Erection of various types of structures including fixing & alignment of templates for grouted/bolted type structure foundations, nuts, bolts, washers etc & including alignment & leveling of structure (220 kV Structures)

236.35

1800041

7616

... More
UNIT RATE FOR UNLOADING, STORAGE, INSTALLATION AND ERECTION OF OUTDOOR EQUIPMENTS - ERECTION OF 132 kV VCB - Erection of structures and alignment, shifting of breaker upto the place and placement of circuit breaker on structure and alignment. Complete assembly of circuit breaker including erection of control cabinet & mechanism box, interconnecting piping work erection of all accessories for the equipment and making interconnections.

7

126000

18000

... More
Dismentaling of 132 kV CONTROL & RELAY PANEL-Dismentaling of Old 132KV Contorl and Relay Panel and Shifting at suitable place in Substation Premises.

1

4800

4800

... More
132 KV C&R Panel-Unloading/Shifting up to control room (including storage if required) and placement complete with all relays & accessories. The placement of C&R Panel to be done on MS channel frame and MS channel frame will suitable grouted in control room as per drawing. Proper alignment of C&R Panel to be done. The earthing of C&R Panel to be done, Making of all interconnections for the control & relay panel on terminal block as per drawing including all AC&DC connections

8

76800

9600

... More
36 kV 12 MVAR Capacitor Bank with structs and accessories (SET)

1

42000

42000

... More
33KV NCT Shifting NCT upto Civil foundation and placement on structure and fixing of Junction Box, including all accessories, making all jumpers atc.

1

3600

3600

... More
Erection of Special P.I set,

1

720

720

... More
132 kV Wave Trap - Dismantling of 132 kV Wave trap

1

3000

3000

... More
ERECTION OF COUPLING CAPACITOR 132 kV (CC)

1

7200

7200

... More
132 kV Coupling Capacitor - Dismantling of 01 No. CC

1

3600

3600

... More
Dismantling of CURRENT TANSFORMER 33 kV (CT) 400/ 1-1-1A 33 kV kV CT

8

14400

1800

... More
ERECTION OF CURRENT TANSFORMER 33 kV (CT) - Erection shifting and placement of 1200/1-1-1Amp and 400/1-1-1 Amp CTs on structure including fixing of junction box & all accessories making all interconnections etc.

33

118800

3600

... More
132 kV Current Transformer (CT) - Dismantling of 03 Nos. 132 kV CTs

3

10800

3600

... More
132 kV Current Transformer (CT) -Erection shifting and placemnt of 132 kV CTs on structure including fixing of junction Box and all accessories making on interconnection etc

24

172800

7200

... More
Dismantling of 33 kV Isolator 3Ph W/o E/S

18

97200

5400

... More
ERECTION OF 33 KV ISOLATORS WITHOUT EARTH SWITCH (3-Phase) - Erection, Shifting & placement of complete 1200A/ 800A isolator in all 3 phases of isolator structure including shifting within substations premises and erection/ mounting of mechanism box interconnection, pipings, aligments contracts and all associated activities

11

118800

10800

... More
ERECTION OF 33 KV ISOLATORS WITH EARTH SWITCH (3-Phase) - Erection, Shifting & placement of complete 1200A/ 800A isolator in all 3 phases of isolator structure including shifting within substations premises and erection/ mounting of mechanism box interconnection, pipings, aligments contracts and all associated activities

22

237600

10800

... More
ERECTION OF 132 KV ISOLATORS WITH EARTH SWITCH (1-Phase)

12

216000

18000

... More
ERECTION OF 132 KV ISOLATORS WITHOUT EARTH SWITCH(3-Phase)

9

162000

18000

... More
ERECTION OF 33 kV LA

30

72000

2400

... More
ERECTION OF 132 kV LA

24

115200

4800

... More
Dismantling of 132 kV LA

9

21600

2400

... More
Dismantling of 33 kV LA

5

6000

1200

... More
ERECTION OF 33 kV SOLID CORE INSULATORS

30

21600

720

... More
132 KV Solid Core Insulator-Shifting & placement of 132 KV LA's on structure including all accessories, making all Interconnections checking & Installation of insulator base and surge counters

57

82080

1440

... More
Dismentaling of 33 kV CONTROL & RELAY PANEL-Dismentaling of Old 33KV Contorl and Relay Panel and Shifting at suitable place in Substation Premises.

1

3900

3900

... More
C&R PANEL FOR 33KV Feeder/X-mer/Bus coupler: Shifting up to control room (including storage if required) and placement complete with all relays & accessories. The placement of C&R panel to be done on MS channel frame and MS Channel frame will suitable grouted in control room as per drawing. The cutting, welding& fabrication of of MS channel frame is to be done as per drawing. Proper alignment of C&R panel to be done. The earthing of C&R Panel to be done. Making of all interconnections for the control & relay panel on terminal block as per drawing including all AC & DC connections. (33 kV)

11

85800

7800

... More
Fitting of lighting fixtures on structures in yard

90

108000

1200

... More
CABLE LAYING - 2 core 2.5 sq.mm unarmoured (in mtrs.)

8600

86000

10

... More
CABLE LAYING 4 core 2.5 sq.mm unarmoured (in mtrs.)

12600

151200

12

... More
CABLE LAYING 8 core 2.5 sq.mm unarmoured (in mtrs.)

9100

127400

14

... More
CABLE LAYING 12 core 2.5 sq.mm unarmoured (in mtrs.)

9000

162000

18

... More
CABLE LAYING 19 core 2.5 sq.mm unarmoured (in mtrs.)

11600

348000

30

... More
Cable Termination 2 core 2.5 sq.mm unarmoured (in mtrs.)

106

10812

102

... More
Cable Termination 4 core 2.5 sq.mm unarmoured (in mtrs.)

364

43680

120

... More
Cable Termination 8 core 2.5 sq.mm unarmoured (in mtrs.)

121

21780

180

... More
Cable Termination 12 core 2.5 sq.mm unarmoured (in mtrs.)

509

122160

240

... More
Cable Termination 19 core 2.5 sq.mm unarmoured (in mtrs.)

421

176820

420

... More
CABLE LAYING - 2 core 2.5 sq.mm armoured (in mtrs.)

1000

14000

14

... More
CABLE LAYING 4 core 2.5 sq.mm armoured (in mtrs.)

1500

27000

18

... More
CABLE LAYING 4 core 4 sq.mm armoured (in mtrs.)

4000

56000

14

... More
CABLE LAYING 4 core 10 sq.mm armoured (in mtrs.)

1000

24000

24

... More
CABLE LAYING 12 core 2.5 sq.mm armoured (in mtrs.)

2000

60000

30

... More
CABLE LAYING 19 core 2.5 sq.mm armoured (in mtrs.)

2000

96000

48

... More
3.5 Core X 300 Sq.mm Power Cable ( Laying)

1250

120000

96

... More
Cable Termination 2 core 2.5 sq.mm armoured (in mtrs.)

10

1500

150

... More
Cable Termination 4 core 2.5 sq.mm armoured (in mtrs.)

8

1440

180

... More
Cable Termination 4 core 4 sq.mm armoured (in mtrs.)

20

4800

240

... More
Cable Termination 4 core 10 sq.mm armoured (in mtrs.)

8

3840

480

... More
Cable Termination 12 core 2.5 sq.mm armoured (in mtrs.)

8

2880

360

... More
Cable Termination 19 core 2.5 sq.mm armoured (in mtrs.)

8

4800

600

... More
3.5 Core X 70/300 Sq.mm Power Cable ( Terminations-Both Ends)

10

9000

900

... More
installation of 25 mm dia X 3000 mm long M.S. rod earth electrodes directly driven/drilled (40 to 50 mm dia) into earth including excavation (irrespective of type of soil encountered) ,backfilling with bentonite soil (to be arranged by contractor) and welding to earth conductor /MS flat of earthing mesh.etc.

190

205200

1080

... More
M.S.Flat for earthing (75X8)/(in Mtr)

400

38400

96

... More
M.S.Flat for earthing (65X8)/(in Mtr)

3020

235560

78

... More
Providing steel risers and making earth mesh (duly buried at a depth of 0.5 mtrs) by MS flat of different size, including backfilling, welding etc. and bolting of risers to the structures/equipments at desired places.(50X6)/ (in Mtr)

6464

387840

60

... More
Preparation of Earth pits 1.5x1.5x3 m as per MPPTCL’s drawing which includes excavation and associated Brick Messonary Work (irrespective of the soil encountered ) embedding of 4nos. GI pipe of size 40mm dia 3m long, back filling with black cotton soil free from stones

34

367200

10800

... More
Stringing of Overhead conductors between the Main bus structure, fixing of 220 kV/ 132 kV/ 33 kV string /disc insulator, providing jumpers between equipment, fixing of clamps and connectors, including shifting within the s/s premises. - Single/Double Zebra conductor

7880

512200

65

... More
Stringing of Overhead conductors between the Main bus structure, fixing of 220 kV/ 132 kV/ 33 kV string /disc insulator, providing jumpers between equipment, fixing of clamps and connectors, including shifting within the s/s premises. Twin Zebra Conductors

4710

593460

126

... More
ACSR Twin Moose

450

72000

160

... More
Overhead Earth Wire of 220 kV/ 132 kV/ 33 kV (in Mtrs)- Stringing of overhead shield wire with 7/3.66 mm standard galvanized steel complete with fixing of strain clamps at the structures.

6000

150000

25

... More
Station Transformer

5

114000

22800

... More
Erection of DP along with LA & DO

5

6000

1200

... More
Junction Box/ Shifting and erection of 36 way and 64 way junction box with all interconnector

46

55200

1200

... More
Drilling of 150 mm diameter perfectly vertical holes in all types of rock including all drilling arrangements , such as assembling of tripod extension of pressure pipe for drilling at the location and shifting pf tripod assembly along with drilling machine with compressor and all other required machinery bits, and assembling the same for drilling of 150 mm dia vertical holes at different locations including all handling labour, T&P equipments and all expenditure whatsoever required as per direction of Engineer-in charge. a.Drilling depth upto 1 meter

1

819

819

... More
Drilling of 150 mm diameter perfectly vertical holes in all types of rock including all drilling arrangements , such as assembling of tripod extension of pressure pipe for drilling at the location and shifting pf tripod assembly along with drilling machine with compressor and all other required machinery bits, and assembling the same for drilling of 150 mm dia vertical holes at different locations including all handling labour, T&P equipments and all expenditure whatsoever required as per direction of Engineer-in charge. b. for every additional depth beyond 1 meter

1

540

540

... More
Supplying assembling lowering and fixing in vertical Position in bore well 150 mm (SOR No. 16.6.2)

1

1500

1500

... More
structure steel work using M.S. flats, angles, channels I-section, H- section etc. riveted,bolted or welded in build up sections,trusses and framed work, including cutting, hoising, fixing in position and applying a priming coat of approved steel primer all complete (SOR No. 10.2)

1

69

69

... More
Supply of 65X8 mm MS Flate

1

52

52.89

... More
Laying of doble M.s. flat, size 75x8 mm inside bore well and connecting end of one flat to earth mesh (including excavation & back filling for M.S. flat wherever necessary upto min 55cm) back filling should be done by black cotton soil only (to be arranged by the contractor) a. M.S, flat ( (75x8)

1

118

118.8

... More
Laying of 65X8 mm MS Flate up to 30 m depth

1

54

54

... More
Transportation of dismental material (MT per 100 km)

1

7200

7200



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.