Steel Industries Kerala Limited Tender
Everything can be found here in your one-stop destination for all types of Kerala tenders online - be it Kerala PWD tenders or an LSGD Kerala tender. Search from across the categories, cities, and authorities while having the option to download tender-related documents. Also, get to know how to register as a bidder and how to bid online for Kerala tenders.
Costs
EMD
₹ 50,000Document Cost
₹ 5,900Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2020_SILK_365679_1Tender No
SILK/GEW/SP/2020-21/05Tender Authority
Steel Industries Kerala Limited ViewPurchaser Address
-Website
http://https://steelindustrials.net/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Providing and fixing double scaffolding system (cup lock type) on the exterior side, upto seven story hight made with 40 mm dia. M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staricase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required location with essential safety features for the workmen etc. complete as per directions and approval of Engineer- in Charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. Note:- This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done .
2530.08
-
10
Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge.
51.07
-
10
Drilling suitable holes in reinforced or plain cement concrete with power drivendrill machine to a minimum depth of 100mm upto 200mm in RCC beams, lintels,columns and slabs to introduce steel bars for sunshades / balconies includingfixing the steel bars in position using epoxy resin anchor grout of approvedmake but excluding the cost of reinforcement, all complete as per direction ofEngineer-In-Charge.Upto and including 12mm dia.
4832
-
100
Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
568.4
-
100
Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 150 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).
51.05
-
10
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
1136.8
-
10
Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer
1136.8
-
10
CONSTRUCTION OF RESEARCH BLOCK
-
-
-
Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
185.94
-
10
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
13.14
-
10
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size).
52.76
-
10
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size)
6.89
-
10
Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 150 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement :
1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).
53.02
-
10
Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
245.37
-
10
Centering and shuttering including strutting, etc. and removal of form for:Stairs, (excluding landings ) except spiral - staircases)
19.72
-
10
Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, and access platform.
20.4
-
10
Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers.
25.5
-
10
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
11959.2
-
100
Item Shifted to head 14 as item 14.74Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
12237.46
-
100
Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete.Hot finished seamless type tubes
12588.5
-
10
Solid block masonry using pre cast solid blocks (Factory made) of size 40x20x15cm or nearest available size confirming to IS 2185 part I of 1979 for super structure up to floor two level with thickness 15cm in: CM 1:6 ( 1 cement : 6 coarse sand etc complete
75.38
-
10
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
1126.25
-
10
Providing wood work in frames of doors, windows, clerestory windows and other frames, wrought framed and fixed in position with hold fast lugs or with dash fasteners of required dia & length (hold fast lugs or dash fastener shall be paid for separately), using good quality Anjili wood /jack wood
1.29
-
10
Providing and fixing paneled or paneled and glazed shutters for doors, windows and clerestory windows, 30 mm thick shutters including ISI marked M.S. pressed butt hinges bright finished of required size with necessary screws, excluding paneling which will be paid for separately, all complete as per direction 0f
Engineer in- charge. using Anjili/ Jack wood
66.72
-
10
Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer
1068.45
-
10
Finishing with Deluxe Multi surface paint system for interiors and exteriors using primer as per manufacturers specifications: Painting wood work with Deluxe Multi Surface Paint of required shade. Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @ 0.75 ltr/10 sqm of
approved brand and manufacture
133.44
-
10
Finishing with Deluxe Multi surface paint system for interiors and exteriors using primer as per manufacturers specifications : Painting Steel work with Deluxe Multi Surface Paint to give an even shade.Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @ 0.80 ltr/10 sqm of approved brand and manufacture
500.66
-
10
Providing and laying of Steel Composite Decking Sheet , fastening, including labor all complete as per direction of Engineer in charge
1
-
10
Electrification
1
-
10
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements