Smart City Thiruvananthapuram Limited Tender
Everything can be found here in your one-stop destination for all types of Kerala tenders online - be it Kerala PWD tenders or an LSGD Kerala tender. Search from across the categories, cities, and authorities while having the option to download tender-related documents. Also, get to know how to register as a bidder and how to bid online for Kerala tenders.
Smart City Thiruvananthapuram Limited Tender
Civil And Construction
Consultancy Services
Civil And Architectural Services
Eprocure
Opening Date18 May 2023
Closing Date29 May 2023
Tender Amount₹ 11,06,237
Costs
EMD
₹ 27,656Document Cost
₹ 3,252Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2023_SCTLT_575170_2Bid Award Id
ViewTender No
SCTL/PRJ/210/2019/M(PMM)/RFP- 013Tender Authority
Smart City Thiruvananthapuram Limited ViewPurchaser Address
-Website
http://etenders.kerala.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Lifting, conveying and fixing the newly casted RCC covering slabs of any thickness on top of drain in position including all labour charges and miscellaneous expenses etc complete
7.5
-
-
STORM WATER DRAINS (DSR)
-
-
-
Providing, hoisting and fixing up to floor level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but excluding cost of reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone - III) : 3 graded stone aggregate 20 mm nominal size)
0.24
-
-
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
24
-
-
Taking out of existing drain slab and stacking within 1000m lead including all labour charges and miscellaneous expenses etc complete
200
-
-
Providing and fixing PVC pipes includes jointing of pipes with one step PVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. 25 mm dia 10KGF/cm2
20
-
-
Providing and fixing PVC pipes includings jointing of pipes with one step PVC solvent cement, trenching,refilling & testing of Joints complete as per direction of engineer in charge.110 mm dia 6Kgf/cm2
3
-
-
Providing and fixing heavy duty DI grating with frame of size 450mm x 300mm for road gully chamber
having minimum 30Kg weight with hinges etc. complete as per design & drawings.
5
-
-
3 ROAD & JUNCTION IMPROVEMENT
-
-
-
Dismantling of existing interlocking tile including stacking of material within 50 meters lead.For thickness of tiles 60 mm to 80 mm
675
-
-
Laying old cement concrete interlocking paver blocks of any design/ shape laid in required line, level,curvature, colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. (Old CC paver blocks shall be supplied by the department free of cost.)
675
-
-
Construction of sub-grade and earthern shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and comapcted to meet requirement of table No. 300-2.
22.5
-
-
Construction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mixing in place method with rotovator at OMC, and compacting with vibratory roller to acheive the desired density, complete as per clause 401. br Grading-V-For sub base cum drainage layer - Mix in place method.
52.5
-
-
Providing , laying spreading and compacting graded stone aggregate ( size range 53 mm to 0.075 mm) to wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant, carriage of mixed material by tipper to site, for all leads & lifts, laying in uniform layers with mechanical paver finisher in sub - base / base course on well prepared surface and compacting with vibratory roller of 8 to 10 tonne capacity to achieve the desired density, complete as per specifications and directions of Engineer - in- Charge.
101.25
-
-
Supplying and laying interlocking tile 80mm or nearest size thickness, minimum strength M30 including providing a layer of 6mm aggregate for 5cm thickness, then laying interlock cobbles in lines and levels as per the directions of the departmental officers at site inclusive of all cost & conveyance charges etc. complete.
16.25
-
-
Providing and laying 60 mm thick factory made cement concrete interlocking paver block of M - 30 grade made by block making machine with strong vibratory compaction, of approved size, design & shape, laid in required colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge
17.5
-
-
UNDER GROUND DUCTING OF UTILITIES (CIVIL)
-
-
-
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
3.5
-
-
Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 ( 1 cement : 4 coarse sand):Medium shade pigment 50% white cement, 50 % ordinary cement
60
-
-
Construction of cement concrete kerb with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC Using Concrete Mixer on M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 409
50
-
-
Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces
15
-
-
Providing & laying Selection no. 1 grass turf with earth 50mm to 60mm thickness of existing ground prepared with proper level and ramming with tools wooden and than rolling the surface with light roller make the surface smoothen and light watering the same, with sprinkler and maintenance for 30 days or more till the grass established properly as per direction of officer in charge.
25
-
-
Removal of unserviceable soil including excavation including loading and disposal of the unserviceable materials away from the work site at suitable location identified by the contractor
20
-
-
WATER SUPPLY WORKS
-
-
-
Supply of PVC Pipe, 8kg/cm2, 90mm Dia conforming to IS 4985:2000 Including all Specials.(KWA Data-100.98.223)
10
-
-
Laying UPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipe line to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipe line with water to the required test pressure (excluding cost of pipes and specials).90 mm nominal outer dia pipes."
10
-
-
Boring RCC slab above 8cm and upto 10cm thick for providing pipes or fittings of size 50 to 60mm and rectifying slab with cement concrete 1:2:4 using 20mm broken stone and finishing the top and bottom with cement mortar after placing the pipe or fittings.
brNEW DATA (Prepared based onbrPHED SDB Vol II - Item No.1063) (As per KWA Data 100.41.22)
40
-
-
Inter connection to the branch lines from newly laid PVC main lines
1
-
-
Supply of CI Double Flanged Sluice Valve Conforming to IS 14846 - 2000, Sluice Valve with Cap PN 1.6, Size 80mm.(KWA Data- 100.98.457)
2
-
-
Conveying and fixing C.I. sluice valves (with cap) by providing complete with bolts, nuts, rubber etc. excluding the cost of valve (the tail pieces if required will be paid separately) :80 mm diameter. Class I Observed Data derived from item no.18.31.of DAR(KWA Data-100.31.1.1)
2
-
-
Engaging Coolie for Controlling Valves and rectification of damages to the existing connection (From KWA Data-100.98.1008)
5
-
-
Engaging Assistant Fitter or 2nd Class fitter for rectification of damages to the existing line (As per KWA Data-100.98.1010).
5
-
-
Engaging Fitter ( grade 1) for giving Interconnection and Rectification of leak during Works (From KWA Data- 100.98.1009)
5
-
-
Providing New/Alteration of house connection from the existing main including earth work excavation,supplying and fitting suitable saddle piece,supplying and fitting 20 mm brass ferrule1 no,20 mm GM full way wheel valve 1no,bend 1no union 1no etc. and connecting the newly laid main,testing the joints etc complete but excluding cost of pipe.(Data as per the data from KWA).
10
-
-
Disconnecting water connection from service mains along Asphalt road without causing any damage to the existing line including charges of earth work excavation in all kinds of soil for exposing connection point including tar cutting / conrete cutting, making the disconnection point water tight charging and testing to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other existing utilities, including the charges of hire for tools and plant, conveyance of tools and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion but excluding cost of materials and as per the direction of departmental officers etc. complete.(KWA Data-100.51.3).
5
-
-
od250528/2019_2020
Supply and Conveying 20mm ASTM Pipe, conforming to IS 4985:2000(Rate as per date from KWA).
120
-
-
Laying UPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipe line to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipe line with water to the required test pressure (excluding cost of pipes and specials).
20 mm nominal outer dia pipes. (100.9.1)
120
-
-
Taking out existing CC interlocking paver blocks from footpath/central verge, including removal of rubbish, dispossal of unserviceable material within 50 metre lead and relaying the interlocking paver blocks including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc, all complete as per the direction of engineer in charge. (OD)
20
-
-
Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth upto 1.5 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth,including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m :
All kinds of soil
20
-
-
Bailing out water with 5 HP engine and pumpset including conveyance to the site, errection, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc. complete. NEW DATA (Prepared based on PHED SDB
- Item No.1070
20
-
-
Operation and Maintenance Cost
-
-
-
Maintenance charges of road work and other components except land scaping per month for fourth year
12
-
-
Maintenance charges of road work and other components except land scaping per month for fifth year
12
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements