Everything can be found here in your one-stop destination for all types of Kerala tenders online - be it Kerala PWD tenders or an LSGD Kerala tender. Search from across the categories, cities, and authorities while having the option to download tender-related documents. Also, get to know how to register as a bidder and how to bid online for Kerala tenders.
Costs
EMD
₹ 14,825Document Cost
₹ 1,310Tender Fee
Refer Documents
Summary
Project No.- 82/25-tarring And Retarring Works To Nalam Peedika Kumbleri Kuzhichal Road Remaining Portion In Kolachery Grama Panchayath Under Annual Plan 2024-25
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_LSGD_705171_4Tender No
AE/LSGD/KGP/eT/2024-25(2)Tender Authority
Local Self Government Department ViewPurchaser Address
-Website
http://https://lsgkerala.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
3.15.2:Compacting Original Ground (ii) Compacting original ground supporting subgrade Loosening of the ground upto a level of 300 mm below the subgrade level, watered, graded and compacted in layers to meet requirement of Tables 300.1 and 300.2 for subgrade construction as per Technical Specification Clause 303.5.2.
81.45
-
-
OD101549/2024-2025: Construction of granular sub-base by providing scarified material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408. <br>(ii) Using Departmental material.
1.44
-
-
4.11.2:Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal. Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408. (ii) Using Gravel mix soil.
32.91
-
-
4.9:Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. By Mechanical Means with 1 km lead
52.43
-
-
75.5.1.1pb:Prime Coat - Low porosity - With Packed Bitumen Rates Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
355.5
-
-
75.5.2.3pb:Tack Coat - With Packed Bitumen Rates Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503.
355.5
-
-
75.5.5.B.2pb:Modified Penetration Macadam 75 mm thick using Bitumen S-65 - Packed Bitumen Rates Construction of penetration macadam over prepared base by providing a layer of compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a three wheel 80-100 kN static roller to achieve the desired degree of compaction as per Technical Specification Clause 506.
69.7
-
-
75.5.5.A.1pb:Modified Penetration Macadam 50 mm thick using Bitumen S-65 - Packed Bitumen Rates Construction of penetration macadam over prepared base by providing a layer of compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a three wheel 80-100 kN static roller to achieve the desired degree of compaction as per Technical Specification Clause 506.
55.2
-
-
75.5.2.1pb:Tack Coat - With Packed Bitumen Rates Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to 0.25 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
626.4
-
-
75.5.11.1.A.2pb:Mix Seal Surfacing - Manual Means - Type A - Bitumen S-65 - Packed Bitumen Rates Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 8-10 kN static roller and finishing to required level and grades as per Technical Specification Clause 509 By Manual Means Type A (II) Bitumen (S-65)
981.9
-
-
3.14:Construction of Subgrade and Earthen Shoulders<br> Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.
18.55
-
-