Kerala State IT Infrastructure Limited Tender
Everything can be found here in your one-stop destination for all types of Kerala tenders online - be it Kerala PWD tenders or an LSGD Kerala tender. Search from across the categories, cities, and authorities while having the option to download tender-related documents. Also, get to know how to register as a bidder and how to bid online for Kerala tenders.
Kerala State IT Infrastructure Limited - KSITIL Tender
Eprocure
Opening Date10 Jan 2020
Closing Date27 Jan 2020
Tender Amount₹ 1,49,35,223 This is an estimated amount, exact amount may vary.
Costs
EMD
₹ 50,000Document Cost
₹ 5,950Tender Fee
Refer Documents
Summary
Widening Of Existing Panchayat Road Infront Of It Building At Technocity Campus, Pallippuram, Thiruvananthapuram
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2020_KSITI_334940_1Bid Award Id
ViewTender No
KSITIL/TP/2019-20/25Tender Authority
Kerala State IT Infrastructure Limited ViewPurchaser Address
-Website
http://etenders.kerala.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
od153382/2019_2020 : Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, with all leads and lifts (breaking clods, watering, rolling each layer with 1/2 tonne roller or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes) as per direction of site Engineer-in-charge.
1320
-
-
... More
2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
1000
-
-
... More
ROAD WORK
-
-
-
... More
2.31 : Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
2200
-
-
... More
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
792
-
-
... More
16.1 : Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earth with lead upto 50 metres.
1760
-
-
... More
16.78.2 : Construction of granular sub- base by Providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, Carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in- Charge.With material conforming to Grade-II (size range 53 mm to 0.075 mm ) having CBRValue-25
264
-
-
... More
16.79 : Providing , laying spreading and compacting graded stone aggregate ( size range 53 mm to 0.075 mm) to wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant, carriage of mixed material by tipper to site, for all leads & lifts, laying in uniform layers with mechanical paver finisher in sub - base / base course on well prepared surface and compacting with vibratory roller of 8 to 10 tonne capacity to achieve the desired density, complete as per specifications and directions of Engineer - in- Charge.
352
-
-
... More
od30408/2019_2020 : Providing and applying primer coat by using bituminous emulsion complying to IS 8887 over prepared surface of granular base with emulsion at a temperature between 20-60 deg. C and applying a uniform coat with the aid of self propelled bitumen pressure sprayer with self heating arrangement and spraying bar with nozzles of constant volume or pressure system at the rate of 10kg/10m2 including all material,labour,machinery, with all leads and lifts complete.
1584
-
-
... More
od30409/2019_2020 : Providing and applying tack coat by using bituminous emulsion complying to IS 8887 over prepared surface preheated to a temperature between 20-70 deg C of granular base with emulsion at a temperature between 20-60 deg. C and applying a uniform coat with the aid of self propelled bitumen pressure sprayer with self heating arrangement and spraying bar with nozzles of constant volume or pressure system at the rate of 3kg/10m2 on primed /blacktop surface and curing etc including all material, labour, machinery, with all leads and lifts complete.
6834
-
-
... More
od30411/2019_2020 : Providing and laying bituminous macadam using crushed stoneaggregates of specified grading premixed with bituminous binder,transported to site by tippers, laid overa previously prepared surfacewith paver finisher equiped with electronic sensor to the requiredgrade, level and alignment and rolling with smooth wheeled, vibratoryand tandem rollers as per specifications to achieve the desiredcompaction and density, complete as per specificatons and directionsof Engineer-in-Charge.50 average compacted thickness with bitumen of grade VG-30 @ 3.50% (percentage by weight of total mix) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity
79.2
-
-
... More
od30410/2019_2020 : Providing and laying semi- dense Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminousbinder and filler, transporting the hot mix to work site by tippers,laying with paver finisher equiped with electronic sensor to the requiredgrade, level and alignment and rolling with smooth wheeled, vibratoryand tandem rollers to achieve the desired compaction and densityas per specification, complete and as per directions of Engineer-in-Charge 25 mm compacted thickness with bitumen of grade VG-;30 @ 5% (percentage by weight of total mix) and lime;filler @ 2% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity.
6834
-
-
... More
od30412/2019_2020 : Supplying and stacking quarry dust of 3mm and down particle size upto 150 micron minimum size and stacking in standard heaps for measurement including cost and conveyance to site etc. complete.
3.96
-
-
... More
od30413/2019_2020 : Spreading quarry dust 3mm and down particle size upto 150 micron minimum size already stacked at site over the premix chipping carpet etc. complete.
3.96
-
-
... More
od30414/2019_2020 : Supplying and fixing of precast kerb from Basant beton or equivalent make as approved by Client/Consultant for the following sizes .The cost is inclusive of all fixing works inlcuding labour etc and conveyance of all materials to site watering for curing, hire and labour charges for all equipment, complete.etc CC Kerb splay ( Model no BFCCK 02 of size 610 x 305x 100 mm
370
-
-
... More
DUCT & DRAIN,RETAINING WALL
-
-
-
... More
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
573.75
-
-
... More
4.1.11 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size)
82.25
-
-
... More
5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
421.625
-
-
... More
5.9.1 : Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
175.8
-
-
... More
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
2000
-
-
... More
5.9.3 : Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
159.501
-
-
... More
od154593/2019_2020 : Conveying the RCC slab from the casting yard to the drain site and placing in position at a distance of 50m incluidng hire charges of all appliances labour charges for loading and unloading etc. complete
370
-
-
... More
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
35540
-
-
... More
4.7.1 : Providing and fixing up to floor five level precast cement concrete solid block, including hoisting and setting in position with cement mortar 1:3 ( 1 cement : 3 coarse sand), cost of required centering, shuttering complete:1:1.5:3 ( 1 cement : 1.5 coarse sand (Zone III): 3 graded stone aggregate 20 mm nominal size)
27
-
-
... More
od30416/2019_2020 : Supplying, laying and jointing 160 mm OD rigid PVC pipe (ISI approved brand), pipes conforming to IS:13592 for working pressure of 6kg/sqcm to line and level in trenches to required depths and jointing together with solvent cement etc. as per the requirements at site including forming a catch to collect the water from the road surface etc. complete earthwork excavation in all classes of soil wherever necessary etc. complete. Weep holes pipes , 75 mm dia, 30mm length
25.5
-
-
... More
19.6.4 : Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 ( 1 cement : 2 fine sand) including testing of joints etc. complete:300 mm dia R.C.C. pipe
20
-
-
... More
19.6.5 : Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 ( 1 cement : 2 fine sand) including testing of joints etc. complete:450 mm dia R.C.C. pipe
20
-
-
... More
13.4.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 coarse sand)
360
-
-
... More
10.1 : Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
2250
-
-
... More
16.48.1 : Painting road surface marking with adequate nos of coats to give uniform finish with ready mixed road marking paint conforming to IS: 164, on bituminous surface in white / yellow shade, including cleaning the surface of all dirt, scales oil, grease and foreign material etc. complete.New work (Two or more coats)
50
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements