Kerala State Electricity Board Tender

... More
Everything can be found here in your one-stop destination for all types of Kerala tenders online - be it Kerala PWD tenders or an LSGD Kerala tender. Search from across the categories, cities, and authorities while having the option to download tender-related documents. Also, get to know how to register as a bidder and how to bid online for Kerala tenders.

Kerala State Electricity Board - KSEB Tender

Works
Civil And Construction
Civil Works Others
Electrical Generators And Transformers
Electrical and Electronics
Eprocure
Opening Date19 Feb 2025
Closing Soon28 Feb 2025
Tender Amount₹ 51,75,236 
Notes
Download

Costs

Summary

Capacity Enhancement By Providing 1 No. Of 12.5 Mva, 110/11 Kv Transformer Constructing Additional Bays At 110 Kv Substation, Cherpulassery Construction Of Foundations, Trenches And Earth Mat Works Including Yard Metaling

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and 2 nd additional lift (3m to 4.5m), disposed earth to be levelled and neatly dressed All kinds of soil

53

424

22478.89

... More
Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and 1st additional lift (1.5m to 3m, disposed earth to be levelled and neatly dressed.Ordinary rock

19

518

9842.19

... More
Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and 2nd additional lift l3m to 4.5m), disposed earth to be levelled and neatly dressed.Ordinary rock

8

623

4989.76

... More
Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil

416

295

122761.6

... More
Excavation work by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m.Ordinary rock

245

524

128438.8

... More
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil. Extra for every additional lift of 1.5m or part thereof in excavation / banking excavated or stacked materials

5

400

2004.2

... More
Excavation work by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, additional lift up to 1.5 m (1.5m to 3m), including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m Ordinary rock

5

629

3149.9

... More
Filling with Quarry Muck Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade

21

902

18944.94

... More
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)

28

6772

189634.76

... More
Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns

47

333

15662.28

... More
DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.

36

2590

93250.8

... More
DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site

9

3469

31228.29

... More
Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)

13

7160

93081.82

... More
Pointing on stone work with cement mortar 1:3 ( 1 cement : 3 fine sand):Flush/ Ruled pointing

24

333

8013.84

... More
Hand picking, collecting and stacking the 40mm metal spread in the switch yard at a convenient place in heaps for measurements as per direction of department officers at site up to 50m.

15

1009

15143.7

... More
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)

32

8535

273128.64

... More
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size

80

9028

722308.8

... More
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)

3

10886

32658.54

... More
Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 150 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).

1.5

11421

17132.52

... More
Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete

151

333

50319.24

... More
Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.

588

712

419102.88

... More
Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers

18

645

11624.22

... More
Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts

105

858

90120.45

... More
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more

10100

97

986669

... More
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more

410

97

40052.9

... More
Stub setting or fixing foundation bolts in position in correct line and levels for 110kV CT/CVT/LA/PT by using the templates supplied departmentally and taking back the templates after setting etc., complete as directed by the departmental officers at site.

7

856

5993.4

... More
Stub setting or fixing foundation bolts in position in correct line and levels for 110kV Isolator by using the templates supplied departmentally and taking back the templates after setting etc., complete as directed

1

2650

2650.38

... More
Stub setting or fixing foundation bolts in position to correct lines and levels for 110kV circuit breaker by using templates and taking back the templates after setting excluding the cost of foundation bolts but including the cost/hire charges of template etc. complete as directed by the departmental officers at site.

1

1675

1675.78

... More
Stub setting or fixing foundation bolts in position in correct line and levels for columns by using the templates supplied departmentally and taking back the templates after setting etc., complete as directed by the departmental officers at site

3

8400

25200.48

... More
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.

755

256

194012.35

... More
Brick work with common burnt clay machine moulded F.P.S. (non modular) bricks of class designation 12.5 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12 mm deep complete in cement mortar 1:6 ( 1 cement : 6 coarse sand)Above plinth level and upto floor V level

4.5

9242

41589.45

... More
Solid block masonry using pre cast solid blocks (Factory made) of size 30x20x15 cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth with thickness 15cm in: CM 1:6 ( 1 cement :6 coarse sand) etc complete

5

6218

31092.15

... More
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)

95

312

29654.25

... More
Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. (Using Departmentally Supplied Sections)

130

25

3257.8

... More
Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works

2800

153

428988

... More
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete.On steel work

280

221

62140.4

... More
Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts , bolts and washers as required complete as per the direction of Engineer-in- charge.Made of G.I. wire of dia 4 mm

65

932

60619

... More
Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts , bolts and washers as required complete as per the direction of Engineer-in- charge.brMade of G.I. wire of dia 4 mm (Using Departmentally supplied Chain link.)

22

472

10393.46

... More
Fencing with angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 metres (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for serarately) :- Payment to be made per metre cost of total length of barbed wire used.With G.I. barbed wire

325

22

7247.5

... More
Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge.

1.5

2965

4447.67

... More
Extra for cutting reinforcement bars manually/ by mechanical means in R.C.C. or R.B. work ( Payment shall be made on the cross sectional area of R.C.C. or R.B work) as per direction of Engineer-in-charge.

1

1009

1009.95

... More
Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In lime mortar

5

710

3553.35

... More
Dismantling steel work in single sections including dismembering and stacking within 50 metes lead in:Channels, angles, tees and flats

145

1

282.75

... More
Finishing walls with Acrylic Smooth exterior paint of required shade:New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm)

95

192

18305.55

... More
Applying priming coat: With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanised iron /steel works

135

59

8004.15

... More
Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work

135

142

19191.6

... More
Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m.All kinds of soil

580

28

16530

... More
Supply and laying tarpaulin sheet of thickness 150GSM of approved make and quality over levelledbr surface including cost of tarpaulin sheet, wastage overlaps, conveyance and labour charges etc.br complete

580

86

50146.8

... More
Supply of 20mm stone aggregate (metalling of substation yard) including carriage for 5.0 km lead by Mechanical Transport including loading, Unloading and stacking.

90

2275

204779.7

... More
Spreading 40mm stone aggregate/20mm stone aggregate in the yard about thickness of 15cm as per the direction of department officers at site

105

600

63045.15

... More
Cutting 32mm MS rod in required length etc complete as per the direction of the departmental officers.

170

85

14560.5

... More
Bending 32mm MS rod for crossing cable trench/foundations/risers etc.

120

125

15079.2

... More
Laying of earth mat of required size as specified using 40/32/25mm MS rod including levelling lowering and placing in trenches, complete as per the direction of departmental officers.

53

1034

54805.18

... More
Drilling bore holes of sizes 150mm or nearest in all classes of soil including hire charges of plant and machinery, cost of oil, fuel, tool etc. and taking all necessary precautions for safety to the substation equipments etc. as per the direction of departmental officers at site

10

630

6300

... More
Driving down the ground electrode upto a depth of 3m from the already taken earth pit as directed by the departmental officers.

35

169

5930.05

... More
Welding of overlapping joints for mat,riser lap joints with 32/25mm MS rod placed in trenches, having 150mm in length 6mm in thick on both sides of the rod and both ends of overlapped MS rods with 6mm welding thickness after cleaning the surfaces neatly. Charges includes cost of low hydrogen DC electrode (No. E7018), hire charges of DC arc welding set and tools and plants required, current charges including labour charges for holding MS rod in position and applying two coats of anti corrosive paints at the welded joints etc. complete as per the directions of department officers

70

633

44354.1

... More
Welding the nodal points (cross joints) in the trenches at two sides to a thickness of 6mm after cleaning the surface neatly. Charges includes cost of low hydrogen DC electrodes (No. E7018), hire charges of DC welding set and tools and plants required, current charges, labour charges for holding MS rod in position and applying two coats of anti corrosive paints at the welded joints etc. complete as per the directions of departmental officers.

250

299

74887.5

... More
Welding the ground electrode with the main electrode , after cleaning the surface neatly. Charges includes cost of low hydrogen content DC electrodes (No. E7018), hire charges of DC arc welding set, tools and plants, current charges, labour charges for holding MS rod in position and applying two coats of anti corrosive paints at the welded joints etc. complete as per the directions of departmental officers.

28

383

10731.84

... More
Drilling holes and driving down MS ground electrode from the bottom level of trench in all classes of soil including rock etc. complete as per the directions of department officers

12

213

2561.28

... More
Fabrication of structures for erecting equipments. The GI & MS angles will be supplied departmentally

50

3613

180661.5



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements

Past Bidders
This list is curated from the bidders of the similar tenders in the past

Unlock the Tender details for free
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.