Rural Drinking Water And Sanitation Department Tender
... More
Karnataka, also known as Karunadu, is a state in the southwestern region of India. Karnataka was formed originally as Mysore State on 1st November 1956 and currently is the biggest state in south India. Its capital and largest city is Bengaluru. It covers an area of 191,791 km2 (74,051 sq mi) and is the sixth largest state by area comprising 31 districts. Karnataka is also a state of multiple languages; Kannada being the official and most widely spoken language in Karnataka. Other languages spoken in the state include Tamil, Telugu, Malayalam, Kodava, Konkani and much more.Karnataka tenders are issued by the government of Karnataka, public & private sector organisations. The state government issues majority of the Karnataka tenders, which are for goods and services including construction, road and bridge construction, IT services, engineering services, medical services, educational services amongst many others. Bidassist is one of the largest eprocurement portals, which offers all government tenders from across the world in one place. Bidassist offers information on all Karnataka tenders and other state and authority tenders in no time. Bidassist is a platform where users can look for various Karnataka tenders as well as other tenders.
Costs
EMD
₹ 11,900Document Cost
Refer DocumentsTender Fee
₹ 500
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
RWSSD/2024-25/OW/WORK_INDENT8699Tender No
RWSSD/2024-25/OW/WORK_INDENT8699Tender Authority
Rural Drinking Water And Sanitation Department ViewPurchaser Address
-Website
http://https://jalshakti-ddws.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
Tender Document
BOQ Items
... More
GESCOMBSK04 - Labour cost -Head loading of the pole 25 to 105Mtrs
14
285
3990
... More
GESCOMBSK05 - Labour cost -Loading & unloading of 9 mtr RCC/PSC poles
14
142
1988
... More
GESCOMBSK06 - Material cost -27901206-11 kV Horizontal cross arm wit
15
643
9645
... More
GESCOMBSK07 - Labour cost -Fixing of V-Shape/Horizontal cross arm including single top support Braces and Insulators fixing.
15
257
3855
... More
GESCOMBSK08 - Material cost -2811101-Guy with Complete set
3
1170
3510
... More
GESCOMBSK09 - Labour cost -a) Fixing of GUY Sets with break insulators making use of 7/3.15 mm (7/10 SWG) galvanised steel wire with turn buckle and anchoring arrangement as per approved drawing. (Excluding excavation of PIT)
3
266
798
... More
GESCOMBSK10 - Labour cost -Hard Soil
3
629
1887
... More
GESCOMBSK11 - Material cost -281683-Spiral Earth Electrode
14
239
3346
... More
GESCOMBSK12 - Labour cost -providing spiral earth electrode type earthing along with pole (without charcoal, salt etc.,)
14
93
1302
... More
GESCOMBSK13 - Material cost -283008-11kV, 5KN Composite/Polymeric
42
205
8610
... More
GESCOMBSK14 - Material cost -283320-Silcon rubber composite insula
6
186
1116
... More
GESCOMBSK15 - Material cost -284108-Rabbit ACSR Conductor
2250
46
104017.5
... More
GESCOMBSK16 - Labour cost -For Rabbit ACSR
2250
4
9810
... More
GESCOMBSK17 - Material cost -285508-Rabbit to Rabbit (P G Clamps)
6
102
612
... More
GESCOMBSK18 - Material cost -200105-RCC Pole-9.0M Long,145 kg WL
2
7076
14152
... More
GESCOMBSK19 - Labour cost -Erection of RCC/PSC poles 9 to 10 mtr long but in a pit of 1.8 mtr depth
2
1113
2226
... More
GESCOMBSK20 - Labour cost -Hard Soil
2
1132
2264
... More
GESCOMBSK21 - Labour cost -Head loading of the pole 25 to 105Mtrs
2
285
570
... More
GESCOMBSK22 - Labour cost -Loading & unloading of 9 mtr RCC/PSC poles
2
142
284
... More
GESCOMBSK23 - Material cost -279111-25/63kVA T.C.Sets (For star ra
1
17564
17564
... More
GESCOMBSK24 - Labour cost- for 25/63 kVA on the existing 9 mtrs. RCC pole (square section) (excluding erection of pole)
1
1709
1709
... More
GESCOMBSK25 - Material cost -279800-fish plate MS
8
78
624
... More
GESCOMBSK26 - Material cost -281008-8 SWG G.I.Wire
5
75
375.2
... More
GESCOMBSK27 - Material cost -281110-7/10 SWG Guy Wire
10
77
772.3
... More
GESCOMBSK28 - Material cost -2811101-Guy with Complete set
4
1170
4680
... More
GESCOMBSK29 - Labour cost -a) Fixing of GUY Sets with break insulators making use of 7/3.15 mm (7/10 SWG) galvanised steel wire with turn buckle and anchoring arrangement as per approved drawing. (Excluding excavation of PIT)
4
266
1064
... More
GESCOMBSK30 - Labour cost -Hard Soil
4
629
2516
... More
GESCOMBSK31 - Material cost -2811103-Earthing Materials Type for gr
3
1729
5187
... More
GESCOMBSK32 - Labour cost -Hard Soil
3
2990
8970
... More
GESCOMBSK33 - Material cost -284503-LT Spacer for TC Wiring
8
42
336
... More
GESCOMBSK34 - Material cost -284828-Pre Insulated lugs -CPTAU for 5
8
305
2440
... More
GESCOMBSK35 - Material cost -288634-50Sq mm (AI end terminal Lug
8
9
72
... More
GESCOMBSK36 - Material cost -289029-PVC Wire-50 Sq.mm
40
64
2567.6
... More
GESCOMBSK37 - Material cost -301107-L.T.Protection kit
1
2023
2023
... More
GESCOMBSK38 - Labour cost -Fixing of LT Protection Kit
1
356
356
... More
GESCOMBSK39 - Material cost -302122-11kV Class, Solid core (Set/3 nos.)
1
1069
1069
... More
GESCOMBSK40 - Labour cost -HG fuse 11 kv Solid core type(3 nos)
1
237
237
... More
GESCOMBSK41 - Material cost -303200-L.A. 9kV, 5kA, Metal Oxide
3
1584
4752
... More
GESCOMBSK42 - Labour cost -Fixing of 3 Nos lightning
arrestors including wiring.
1
119
119
... More
GESCOMBSK43 - Material cost -304212-11kV G.O.S 200A Single break
1
9450
9450
... More
GESCOMBSK44 - Labour cost -Fixing of GOS including wiring
(11kV SB 200A)
1
1104
1104
... More
GESCOMBSK45 - Material cost -321465-25 Kva,Aluminium wdg,star 2(5
1
105994
105994
... More
GESCOMBSK46 - Labour cost -a) Erection of 25-63 kVA Transformer on Transformer structure.
1
1193
1193
... More
GESCOMBSK47 - Labour cost -Loading of Transformer 25 kVA
1
285
285
... More
GESCOMBSK48 - Labour cost -Un loading of Transformer 25 kVA
1
285
285
... More
GESCOMBSK49 - Material cost -357511-L.T. Electronic Tri-Vector Met
1
3312
3312
... More
GESCOMBSK50 - Labour cost -LT Electroic Tri-Vector Meter 5A, Class-0.5/1.0 Accuracy
1
798
798
... More
GESCOMBSK51 - Material cost -358061-With CT ratio 100/5 for 50/63
1
6293
6293
... More
GESCOMBSK52 - Labour cost -LT Metering Box For Housing ETV Meter with CT
1
650
650
... More
GESCOMBSK53 - Material cost -200103-RCC Pole-8.0M Long,115 kg WL
1
5129
5129
... More
GESCOMBSK54 - Labour cost -Hard Soil
1
1006
1006
... More
GESCOMBSK55 - Labour cost -Head loading of the pole 25 to 105Mtrs
1
285
285
... More
GESCOMBSK56 - Labour cost -Loading & unloading of 8 mtr RCC/PSC poles
1
110
110
... More
GESCOMBSK57 - Labour cost -Same as above but erection of RCC/PCC/PSC poles of 7.5 to 8 mtr long in pit of 1.5 mtr depth.
1
922
922
... More
GESCOMBSK58 - Material cost -27901203-4 pin cross arm with pole clam
2
423
846
... More
GESCOMBSK59 - Labour cost -Fixing of 4 Pin cross arm with insulator and Braces fixing.
2
160
320
... More
GESCOMBSK60 - Material cost -2811101-Guy with complete set
1
1170
1170
... More
GESCOMBSK61 - Labour cost -a) Fixing of GUY Sets with break insulators making use of 7/3.15 mm (7/10 SWG) galvanised steel wire with turn buckle and anchoring arrangement as per approved drawing. (Excluding excavation of PIT)
1
266
266
... More
GESCOMBSK62 - Labour cost -Hard Soil
1
629
629
... More
GESCOMBSK63 - Material cost -281683-Spiral Earth Electrode
1
239
239
... More
GESCOMBSK64 - Labour cost -providing spiral earth electrode type earthing along with pole (without charcoal, salt etc.,)
1
93
93
... More
GESCOMBSK65 - Material cost -283158-No.8 Strain Insulator
8
27
216
... More
GESCOMBSK66 - Material cost -284108-Rabbit ACSR Conductor
200
46
9246
... More
GESCOMBSK67 - Labour cost -For Rabbit ACSR
200
4
872
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements