Road Construction Department Tender

Search from across the categories, cities, and authorities to find the latest Jharkhand tenders. Every Jharkhand tender is curated from credible sources of government websites (eProcurement Jharkhand portal) and newspapers, thus ensuring the credibility of the information presented to you. For more information on Jharkhand tender bidder registration, the login process and more read the FAQs section on this page.

Road Construction Department Tender

Works
Civil And Construction
Eprocure
Opening Date27 Sep 2024
Closing Date4 Oct 2024
Tender Amount₹ 71,77,843 
This is an estimated amount, exact amount may vary.
Notes
Download

Costs

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
(2)- Ordinary repair work of road from Dindayal chowk to Morhabadi Maidan and link road Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

564.47

12

7281.66

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

9.59

10097

96838.48

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

11.18

11560

129247.51

... More
(3)- Ordinary repair work of road from Kanke road Ram Mandir to Morhabadi road upto DC residance Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

700.88

12

9034.34

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

7.11

10093

71808.64

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

12.49

11555

144332.69

... More
4)- Ordinary repair work of road from Nepal house more to Mecon chowk via old high court Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

1555.6

12

20051.68

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

30.91

9964

307940.51

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

28.13

11424

321311.81

... More
(5)- Ordinary repair work of road from AG more to Old Jharkhand High court via Jhanda chowk Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

386

12

4975.54

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

5.13

9944

50965.82

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

8.51

11405

97000.21

... More
(6)- Ordinary repair work of road from Birsa chowk to Tupudana road Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

2845.95

12

36769.61

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

22.69

9874

224068.07

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

51.34

11337

582054.93

... More
(7)- Ordinary repair work of road from Birsa chowk - Tupudana road (Singh More) to Latma Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

670.55

12

8663.51

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

5.72

9853

56312.12

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

16.69

11316

188846.75

... More
(8)- Ordinary repair work of road from Rani Sati mandir to harmu road via Pahari mandir Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

2150.72

12

27722.78

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

9.72

10049

97681.04

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

58.69

11509

675516.62

... More
Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface (Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes.)

60

584

35058

... More
(9)- Ordinary repair work of road from Urdu Library to Bada talab Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

818.8

12

10554.33

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

13.52

10099

136549.43

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

16.45

11556

190098.01

... More
(10)- Ordinary repair work of road from Harmu Chowk to Bhart Mata chowk via Muktidam Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

192.25

12

2480.03

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

4.25

9889

42029.57

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

3.34

11449

38242.73

... More
(11)- Ordinary repair work of drain between 1.0km to 2km in Argora Naya Sarai road Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concree, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with allk lifts and lead of 1000 metres Cement concrete Grade M-15 & M-20

3.38

452

1526.85

... More
Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately By Manual means Bituminous courses

1.35

632

854.15

... More
Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately By Manual means Granular courses

2.7

435

1174.77

... More
Excavation for strucutres Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Manual Means Depth upto 3 m

214.8

138

29706.84

... More
Plain/Reinfoced Cement concrete in open foundation complete as per drwaing and technical specifications. PCC Grade M15 PCC Grade M15 using batching plant & Concrete pump

20.65

4243

87635.71

... More
Stone masonry work in cement mortar 1:3 in foundation complete as per drawing and technical specifications. Random Rubble masonry (coursed/uncoursed)

111.48

4320

481695.05

... More
Plain/Reinforced cement concrete in sub-strucutre complete as per drawing and Technical specifications PCC Grade M15 using batching plant, transit mixer & concrete pump RCC Grade M15 Height upto 5m RCC Grade M15 using batching plant, transit mixer & concrete pump

8.78

4448

39054.84

... More
Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

25.5

12

328.95

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

0.83

10009

8308.28

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

0.64

11470

7341.31

... More
By Mix in Place Method Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. Rate per cum for grading-V Material

1.28

2050

2625.23

... More
Wet Mix Macadam (Plant Mix Method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with grader in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.

1.15

2207

2538.91

... More
Tack Coat on Granular surfaces treated with primer Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

5.1

15

81.45

... More
Plain/Reinforced cement concrete in foundation complete as per drawing and Technical specifications RCC Grade M20 , Height upto 5m using batching plant, transit mixer & concrete pump

5.5

4669

25681.15

... More
Furnishing and Placing Reinforced/ Prestressed cement concrete in sub as per drawing and Technical Specification RCC Grade M30 Using Batching Plant,Transite Mixer and Concrete Pump. Height upto 5m

2.44

5821

14204.46

... More
Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawing and technical specifications

0.33

87854

28992.09

... More
Supplying, fitting and placing HYSD bar reinforcement in sub structure complete as per drawing and technical specifications

0.25

88204

22051.07

... More
12)- Ordinary repair work of road from Sahid chowk to harmu road via Nehru park Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

399.16

12

5145.17

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

9.17

10094

92569.41

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

6.47

11556

74768.03

... More
(3)- Ordinary repair work of road from Chandni chowk to Project building Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

394.04

12

5094.94

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

2.88

9833

28358.43

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

7.5

11296

84664.64

... More
14)- Ordinary repair work of road from Dhurwa check post to Birsa Rajpath Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with approve grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing

101.01

6050

611121.65

... More
Tack Coat on Cement concrete pavement Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

506.03

19

9649.92

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

15.19

11416

173390.46

... More
(15)- Ordinary repair work of road from Dhurwa Golchakkar for the year 2024-25 Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

368.87

12

4769.49

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

2.51

9899

24886.76

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

7.3

11363

82895.2

... More
16)- Ordinary repair work of road from Saheed maidan to Nayasarai Ring road Maintenance of Earthen Shoulder (filling with fresh soil) Making up loss of material/ irregularities on shoulder to the design level by adding fresh approved soil and compacting it with appropriate equipment.

2025

42

85252.5

... More
Excavation in Soil using Hydraulic Excavator and Tippers with Disposal upto 1000 metres. Excavation for road work in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and tranporting to the embankment location within all lifts and lead upto 1000 m

251.25

62

15678

... More
By Mix in Place Method Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. Rate per cum for grading-V Material

61.17

2091

127929.71

... More
Wet Mix Macadam (Plant Mix Method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with grader in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.

45.88

2250

103263.12

... More
Prime Coat over WMM/WBM Providing and applying primer coat with SS1 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means.

305.85

81

24905.37

... More
Tack Coat on Granular surfaces treated with primer Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

305.85

16

4893.6

... More
Tack Coat on Bituminous surfaces Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.

4073.93

12

52635.18

... More
Dense graded Bituminous Macadam Grading-II With VG-30 packed Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Packed Bitumen.

109.5

10069

1102558.81

... More
Bituminous concrete Grading- II With VG-30 Bulk Bitumen Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @4.5 percent by weight of total mix and filler, transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause no. 505 complete in all respects with VG-30 Bulk Bitumen.

65.7

11534

757792.56

... More
Goods & Service Tax (G.S.T.) -

18

1

1449310.67

... More
Labour Cess -

1

95010

1



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.