Search from across the categories, cities, and authorities to find the latest Jharkhand tenders. Every Jharkhand tender is curated from credible sources of government websites (eProcurement Jharkhand portal) and newspapers, thus ensuring the credibility of the information presented to you. For more information on Jharkhand tender bidder registration, the login process and more read the FAQs section on this page.

National Rural Employment Programme - NREP Tender

Works
Civil And Construction
Road Construction
Eprocure
Opening Date7 Mar 2024
Closing Date14 Mar 2024
Tender Amount₹ 25,36,830.87 
This is an estimated amount, exact amount may vary.
Notes
Download

Costs

Summary

Construction Of P.c.c Road

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Supplying and Laying (properly as per design and drawing) rip-rap with good quality of boulder duly packed including the cost of materials, royalty all taxes etc. but excluding the cost of carriage all complete job.

5.77

10134

1756.4

... More
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:3:6 (1 Cement : 3 coarse sand (zone-III): 6 graded stone aggregate 40 mm nominal size)

4.93

19853

4027.14

... More
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering. All work up to plinth level. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size)

269.05

1334953

4961.73

... More
Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: 1:2:4 (1 Cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)

1.55

8720

5626.21

... More
Providing randam rubble stone masonry in CM (1:4) in foundation and plinth with hammer dressed stone of less than 0.03 M3 in volume and clean coarse sand of F.M. 2 to 2.5 including cost of screening raking out joints to 20 mm depth, curing taxes and royalty all complete as per building specification and direction of E/I.

19.65

53834

2739.69

... More
Providing randam rubble stone masonry in CM (1:4) in superstructureincluding cost of screening of materials scaffolding raking out joints to 20 mm depth, curing taxes and royalty all complete as per building specification and direction of E/I.

19.2

55813

2906.96

... More
Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).

3.96

24983

6308.87

... More
providing Tor steel reinforcement of 10mm,12mm,& 16mm. dia bars as per approved design and drawing inclusive carriage of M.S. bars to work site, cutting, bending and binding with annealed wire with cost of the wire, removal of rust, placing the rods in position all complete as per building specification and direction of E/I.

0.44

35263

80879.07

... More
Providing 25mm thick cement plaster (1:4) with clean coarse sand of F.M. 1.5 including screening, curing with all leads and lifts of water, scaffolding taxes and royalty all complete as per building specification and direction of E/I.

26.59

6883

258.87

... More
Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete

177.51

34525

194.5

... More
Centering and shuttering including strutting, propping etc. and removal of form for Suspended floors, roofs, landings, balconies and access platform

12.45

5425

435.82

... More
Earth filling in foundaion trenches and plinth in layers not exceding 150 mm thick well watered, rammed, fully compacted and fine dressed with earth obtained from excavation of foundation trenches within a lead of 50 M and lift of 1.5 M all complete as per building specification and direction of E/I. (mode of measurement compacted volume)

43.73

2417

55.28

... More
Filling in foundation trenches and plinth in layers. Not exceeding 150 mm thick well watered, rammed fully compacted and fine dressed with earth obtained after cutting within a lead of 50 M and lift of 1.5 M all complete as per building specification and direction of E/I (Mode of measurement compacted volume)

107.62

13870

128.88

... More
Carriage of Materials (a) (Cement+Steel) -Lead 5S KM

122.94

56072

456.1

... More
(b) Sand -Lead(1 k+7S) KM

292.63

74105

253.24

... More
(c) Bricks -Lead (1US+25S)KM

54.96

75954

1382

... More
(d) Stone Chips (1k+39S)KM

240.81

171524

712.28

... More
(e) Stone Metal-(1U+39S) KM

4.63

3539

764.54

... More
(f) Stone Boulder-(1U+39S)K M

44.62

32947

738.41

... More
Add 18% for G.S.T.

1

478928

478928.47

... More
Labour Cess

1

31396

31396.42



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.