Search from across the categories, cities, and authorities to find the latest Jharkhand tenders. Every Jharkhand tender is curated from credible sources of government websites (eProcurement Jharkhand portal) and newspapers, thus ensuring the credibility of the information presented to you. For more information on Jharkhand tender bidder registration, the login process and more read the FAQs section on this page.
Costs
EMD
₹ 50,000Document Cost
₹ 5,000Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_BCD_93419_1Tender No
BCD/EE/HAZARIBAG/ 19/17 /2024-25Tender Authority
Building Construction Department ViewPurchaser Address
-Website
http://jharkhandtenders.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size)
18.68
-
-
Chequered terrazo tiles 22 mm thick with graded marble chips of size
up to 6 mm in floors, jointed with neat cement slurry mixed with pigment
to match the shade of the tiles, including rubbing and polishing complete,
on 20 mm thick bed of cement mortar 1:4 (1 cement :4 coarse sand) :Medium shade pigment using 50% white cement, 50%
ordinary cemen
122.68
-
-
Providing and fixing stainless steel ( Grade 304) railing made of Hollow
tubes, channels, plates etc., including welding, grinding, buffing, polishing
and making curvature (wherever required) and fitting the same with
necessary stainless steel nuts and bolts complete, i/c fixing the railing
with necessary accessories & stainless steel dash fasteners , stainless
steel bolts etc., of required size, on the top of the floor or the side of
waist slab with suitable arrangement as per approval of Engineer-in charge, (for payment purpose only weight of stainless steel members
shall be considered excluding fixing accessories such as nuts, bolts,
fasteners etc.).
92.01
-
-
Providing designation 75B brick work in C.M (1:6 ) in foundation and plinth with approved quality of clean coarse sand of F.M. 2 to 2.5 including providing 10mm thick mortar, joints cost of screening materials raking out joints to 15mm depth , curring , taxes and royalty all complete as per builiding specification and direction of E/I.
21.4
-
-
Providing 12mm cement plaster (1:6) with clean coarse sand of F.M. 1.5 including screening, curing with all leads and lifts of water, scaffolding taxes and royalty all complete as per building specification and direction of E/I.
76.67
-
-
Finishing walls with Acrylic Smooth exterior paint of required shade :
13.46.1 New work (Two or more coat applied @ 1.67 ltr/10 sqm
over and including priming coat of exterior primer applied
@ 2.20 kg/10 sqm)
76.67
-
-
Cairrage of Material Sand with lead 13 km
67.95
-
-
S/C with lead 8 km
20.84
-
-
Bricks with lead 25 km
54.12
-
-
Earth work in excavation in foundation trenches in ordinary soil ( vide classification of soil item A) and disposal of excavated earth as obtained to a distance upto 50M including all lifts leveling ramming the foundation treanches, removing roots of trees, and shrubs all complete as per approved design, building specification and direction of E/I.
31.1
-
-
Extra for earthwok in hard soil as per specification and direction of E/I. (Vide classification of soil item - B).
31.1
-
-
Filling in foundation trenches and plinth in layers not exceeding 150mm thick well watered, ………….as per building specification and direction of E/I.
30.33
-
-
Providing coarse clean Sand in Filling in foundation trenches or in plinth …………….as per building specification and direction of E/I.
21.38
-
-
Providing designation 75B brick work in C.M. (1:6) in foundation and plinth ……………………..as per building specification and direction of E/I.
4.82
-
-
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
4.86
-
-
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level.1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size)
7.78
-
-
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level.1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size)
2.84
-
-
Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).
14.8
-
-
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mmnominal size)
5.03
-
-
Providing Toe steel reinforcement of 8mm to 32mm dia rods as approved design and drawing ………...as per building specification and direction of E/I. 8 MM TMT Bar
1.19
-
-
10 MM TMT Bar
0.79
-
-
12 mm and above dia TMT Bar
1.28
-
-
Providing designation 75B one brick flat soling joints filled with local sand including cost of watering taxes royalty all complete as per building specification and direction of E/I.
64.8
-
-
Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. for mass concrete
107.05
-
-
Centering and shuttering including strutting, propping etc. and removal of form for all heights : Lintels, beams, plinth beams, girders, bressumers and cantilevers
64.26
-
-
Centering and shuttering including strutting, propping etc. and removal of form for : Suspended floors, roofs, landings, balconies and access platform
76.28
-
-
Providing 12mm cement plaster (1:6) with clean coarse sand of F.M. 1.5 including screening, curing with all leads and lifts of water, scaffolding taxes and royalty all complete as per building specification and direction of E/I.
66.23
-
-
Providing 6mm cement plaster (1:4) in celling with clean coarse sand of F.M. 1.5 including screening, curing with all leads and lifts of water, scaffolding taxes and royalty all complete as per building specification and direction of E/I.
76.28
-
-
Finishing walls with Acrylic Smooth exterior paint of required shade : 13.46.1 New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied
@ 2.20 kg/10 sqm)
142.51
-
-
Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing
and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing
with necessary accessories & stainless steel dash fasteners , stainless steel bolts etc., of required size, on the top of the floor or the side of
waist slab with suitable arrangement as per approval of Engineer-in charge, (for payment purpose only weight of stainless steel members
shall be considered excluding fixing accessories such as nuts, bolts,
fasteners etc.).
453.6
-
-
Providing and laying Polished Granite stone flooring in required design
and patterns, in linear as well as curvilinear portions of the building all
complete as per the architectural drawings with 18 mm thick stone slab
over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4
coarse sand) laid and jointed with cement slurry and pointing with white
cement slurry admixed with pigment of matching shade including
rubbing, curing and polishing etc. all complete as specified and as
directed by the Engineer-in-Charge.
11.56.1 Polished Granite stone slab colour of Black, Cherry/Ruby
Red or equivalent
77.9
-
-
Providing & fixing on roof pressed clay tile (Mangalore tile) of 20 mm
nominal thickness and of approved size and as per approved pattern
on steel frame work complete (steel frame work to be paid
separately)
76.28
-
-
Finishing walls with water proofing cement paint of required shade. New Work (two or more coats applied @ 3.84 kg/10 Sqm)
142.51
-
-
Add GST 18 %
0.18
-
-
Add L.Cess 1 %
0.01
-
-