Power Development Department Tender
Search from the latest JKtenders and find a business opportunity fitting your SME on the online platform of BidAssist. If you're wondering how to find the latest JK tenders or from where to get all the documents without the hassles, this is what we explain here. Find the best opportunities coming to the surface via the JK government, PSUs and state corporations.
Power Development Department - PDD Tender
Electrical and Electronics
Electrical Works
Eprocure
Opening Date31 Jan 2023
Closing Date17 Feb 2023
Tender Amount₹ 50,37,903
Costs
EMD
₹ 1,01,000Document Cost
₹ 2,000Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2023_PDD_203776_1Bid Award Id
ViewTender No
ED-II/30 of 2022-23 Dated 30/01/23 (Short Term)Tender Authority
Power Development Department ViewPurchaser Address
-Website
http://http://www.jkpdd.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
Approved Drawings for 11 KV GO Set, 11 KV Horn Gap Fuse Set, Sub Stn, Earthing, Channels etc
Signed and Stamped Copy of SBD to be uploaded by the Bidder
e NIT Notice (Tender Fees (TR), Date Wise Schedule, EMD, Performance Security etc)
BOQ Items
Supply, Installation, Testing and Commissioning of 11 kV Horn Gap Fuse Set 3 Phase 200A
2
-
-
Supply, Laying, Testing and Commissioning of 300 mm² single core Cable,1.1kV Grade, XLPE Insulated Stranded Conductor FRLS type (44mtr for 1 Ckt)
44
-
-
Supply, Laying, Testing and Commissioning of 400 mm² single core Cable,1.1kV Grade, XLPE Insulated Stranded Conductor FRLS type (44mtr for 1 Ckt)
88
-
-
Supply, Laying, Testing and Commissioning of 630 mm²(2Ckt) for 630 kVA single core Cable,1.1kV Grade, XLPE Insulated Stranded Conductor FRLS type (44mtr for 1 Ckt)
30
-
-
Providing and Erection of ST Pole 9 mtr. long (ST-410 SP33) including loading from factory unit, carriage and unloading upto site (Poles shall be got tested at the cost of bidder in any registered SSI unit, Sgr prior to its delivery at site for erection)
4
-
-
Providing, Fabrication and Erection of 10' Steel Pole butt support with 6" inner dia and 6mm thickness(including base plates).
3
-
-
Providing and Fixing of 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80 kV negative, creepage distance 320mm
6
-
-
Providing and Fixing of GI Channel/Angle/Flat of sizes including clamps/collars
500
-
-
Providing and Fixing of Galvanized Nuts and Bolts.
30
-
-
Providing and Laying of Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover.
8
-
-
Providing and Fixing of 11 kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm
6
-
-
Supply, Installation, Testing and Commissioning of LT Distribution Box with 400 Amp MCCB 3P 35 kA for incomer & 200 Amp MCCB 3P 16 kA 2 No. and 160 Amp MCCB 3P 16 kA 1 No.s for Outgoing Circuits and 200 Amp 09 No. Outgoing Link Disconnectors. 16 Amp Single Pole MCB 02 No. also included. (Aluminium Bus Bar 40x10 for Phase and Neutral also)
1
-
-
Supply, Installation, Testing and Commissioning of LT Distribution Box for 630 kVA DTR with 1000 Amp MCCB 3P 36 kA for incomer & 400 Amp MCCB 3P 16 kA 2 No.s for Outgoing Circuits and 200 Amp 06 No. Outgoing Link Disconnectors. 16 Amp Single Pole MCB 02 No. also included. (Aluminium Bus Bar 40x15 for Phase and Neutral also)
1
-
-
Providing and Fixing of Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6) mm, nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete
4
-
-
Providing and Fixing of Wedge Connectors / PG Clamps
12
-
-
Providing and Fixing of Danger Plates with Clamps
2
-
-
Providing and Fixing of GI Barbed Wire for Anti Climbing
30
-
-
Providing and Laying of Earthing of ST Pole 9 mtr. Long Complete by GI Pipe 40 mm 3 mtr long through GI Strip 25x3 mm
4
-
-
Providing and Laying of Cement Bottoming of ST Pole 9 mtr. Long in the ratio 1:2:4 mix as per Standards (0.5cum/pole)
4
-
-
Providing and Laying of Cement Bottoming of Pole Butts in the ratio 1:2:4 mix as per Standards (0.25cum/pole)
3
-
-
Providing and Painting of ST Poles 9 mtr long with 1 coat Red Oxide and 2 coats of Aluminium Paint
4
-
-
Providing and Painting of 10' Steel Pole butt support (complete) with 1 coat Red Oxide and 2 coats of Aluminium Paint
3
-
-
Providing and Fixing of Sundry items like Aluminium lugs, Jumpers, Binding Tape
2
-
-
Dismantling/Shifting & Re-installation of existing 250(315) kVA, 11/0.433 KV, 3-phase Distribution Transformer along with accessories* (*Returnable to Divisional Stores at Bemina. The Job shall include loading of same from respective sites, their carriage and unloading upto Divisional Stores, Bemina)
1
-
-
Dismantling/Shifting & Re-installation of existing 630 kVA, 11/0.433 KV, 3-phase Distribution Transformer along with accessories* (*Returnable to Divisional Stores at Bemina. The Job shall include loading of same from respective sites, their carriage and unloading upto Divisional Stores, Bemina)
1
-
-
Providing, Fabrication and Fixing of Signage Board (Florescent type) displaying work title G-20 Summit Works under Srinagar Smart City Project, Executing Department, Name of Work, Cost of Work etc of size 2mx1.5m fixed over GI Angle Iron duly grouted
1
-
-
Levelling and Appropriate Surface Work at existing Sub-Station Site of Dismantaling
2
-
-
PART-B : Shifting of HT/LT electrical utilities/Assets including Dismantaling from from Bakshi Stadium to Zero Bridge for making symmetrical Alignment of HT/LT Infrastructure
-
-
-
Providing and Erection of ST Pole 13 mtr. long (ST-410 SP69) including loading from factory unit, carriage and unloading upto site (Poles shall be got tested at the cost of bidder in any registered SSI unit, Sgr prior to its delivery at site for erection)
2
-
-
Providing and Erection of ST Pole 11 mtr. long (ST-410 SP56) including loading from factory unit, carriage and unloading upto site (Poles shall be got tested at the cost of bidder in any registered SSI unit, Sgr prior to its delivery at site for erection)
16
-
-
Providing and Erection of ST Pole 9 mtr. long (ST-410 SP33) including loading from factory unit, carriage and unloading upto site (Poles shall be got tested at the cost of bidder in any registered SSI unit, Sgr prior to its delivery at site for erection)
12
-
-
Providing and Erection of ST Pole 8 mtr. long (ST-410 SP15) including loading from factory unit, carriage and unloading upto site (Poles shall be got tested at the cost of bidder in any registered SSI unit, Sgr prior to its delivery at site for erection)
30
-
-
Providing, Fabrication and Fixing of GI V cross-arm/GI Ch. With GI Angle Iron with top Bracket including clamp
1380
-
-
Supply, Laying, Testing and Commissioning of 0.1 ACSR Conductor
8500
-
-
Supply, Laying, Testing and Commissioning of 0.05 ACSR Conductor
2000
-
-
Providing and Fixing of PG Clamps for 100 mm² ACSR Conductor
30
-
-
Providing and Fixing of 11 kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm
154
-
-
Providing and Fixing of 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80 kV negative, creepage distance 320mm
36
-
-
Providing and Fixing of 16 kN Polymer Shackle Insulators LT
180
-
-
Providing and Fixing of G.I Mukhi for Shackle Insulators with bolt of (50x6)mm
180
-
-
Providing and Fixing of LT Spacers
91
-
-
Providing and Fixing of Galvanized Nuts and Bolts.
116
-
-
Providing and Fixing of Danger Plates with Clamps
60
-
-
Providing and Fixing of Anti-Climbing Device with Clamps
60
-
-
Providing and Laying of Earthing of ST Poles 13 mtr long Complete by GI Pipe 40 mm 3 mtr long through GI Strip 25x3 mm
2
-
-
Providing and Laying of Earthing of ST Poles 11 mtr long Complete by GI Pipe 40 mm 3 mtr long through GI Strip 25x3 mm
16
-
-
Providing and Laying of Earthing of ST Poles 9 mtr long Complete by GI Pipe 40 mm 3 mtr long through GI Strip 25x3 mm (including 03 for existing ST poles)
15
-
-
Providing and Laying of Earthing of ST Poles 8 mtr long Complete by GI Pipe 40 mm 3 mtr long through GI Strip 25x3 mm (including 03 for existing ST poles)
33
-
-
Providing and Painting of ST Poles 13 mtr long with 1 coat Red Oxide and 2 coats of Aluminium Paint
2
-
-
Providing and Painting of ST Poles 11 mtr long with 1 coat Red Oxide and 2 coats of Aluminium Paint
16
-
-
Providing and Painting of ST Poles 9 mtr long with 1 coat Red Oxide and 2 coats of Aluminium Paint
12
-
-
Providing and Painting of ST Poles 8 mtr long with 1 coat Red Oxide and 2 coats of Aluminium Paint
30
-
-
Providing and Laying of Cement Bottoming of ST Pole 13 mtr. Long in the ratio 1:2:4 mix as per Standards (0.7cum/pole)
2
-
-
Providing and Laying of Cement Bottoming of ST Pole 11 mtr. Long in the ratio 1:2:4 mix as per Standards (0.6cum/pole)
16
-
-
Providing and Laying of Cement Bottoming of ST Pole 9 mtr. Long in the ratio 1:2:4 mix as per Standards (0.5cum/pole) including for 25 no. existing ST poles also
37
-
-
Providing and Laying of Cement Bottoming of ST Pole 8 mtr. Long in the ratio 1:2:4 mix as per Standards (0.45cum/pole)
30
-
-
Providing and Fixing of Aluminium Jointing Sleeves
100
-
-
Supply, Laying, Testing and Commissioning of 16 sqmm Cable (2 core) for meter shifting
250
-
-
Providing and Fixing of Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (300x 300 x 8) mm, nut-bolts, 2 Nos turn-buckles, 1.8m long,20 mm diameter solid GS stay rod & 7/4 mm dia GI stranded wire complete
15
-
-
Dismantaling of old STP/PCC poles along with all accessories (Channels/insulators) including Loading/transportation/Unloading upto Divisional Stores at Bemina
74
-
-
Straighting of existing tilted poles including cement bottoming/muffing
2
-
-
Dismantaling of existing ACSR (0.1/.05)
8000
-
-
Dismantaling and Re-laying of existing ACSR (0.1/.05)
5000
-
-
Shifting of Smart meters from Old poles to New ones
55
-
-
Shifting of Street lights from Old poles to New ones
30
-
-
Painting of existing ST poles/allied channels (2 Coats Al Coating with surface cleaning)
75
-
-
Providing, Fabrication and Fixing of Signage Board (Florescent type) displaying work title G-20 Summit Works under Sgr Smart City, executing department, name of work, cost of work etc of size 2mx1.5m fixed over GI Angle Iron duly grouted
1
-
-
Providing/Submission of both Pre and Post Work Execution Geo-Tagged Coloured Photographs of subjected work on A4 sized photopaper