Directorate Of Urban Local Bodies Tender

If you want to inquire about any e-tender the Haryana government has posted, Bidassist gives a one-stop solution i.e. being a registered bidder you will find every eprocurement Haryana tender on BidAssist.There is no need to enter all the details on the website of etender.up.nic.in as BidAssist helps you find the specific Haryana etender you're looking for. Read further to learn how to search and bid for etender Haryana.

Directorate Of Urban Local Bodies - DULB Tender

Works
Civil And Construction
Road Construction
Eprocure
Opening Date28 Oct 2024
Closing Date5 Nov 2024
Tender Amount₹ 14,20,230 
Notes
Download

Costs

  • EMD

    ₹ 32,000
  • Document Cost

    ₹ 1,000
  • Tender Fee

    ₹ 1,180

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
[17.70]Removal of existing IPB by manual means and disposal of dismantled material with all lead and lift as per technical specification clause 202.3. [Through Rate]

280

26

7280

... More
[17.71]Relaying of available (removed and stacked) Interlocking Paver Block Pavement having thickness 100mm/80 mm/ 60 mm (average = 80mm) as per drawings and Technical Specification Clause 1504 [Through Rate]

280

66

18480

... More
[17.8.1]Compaction 1. Extra for laying earth/fly ash as per specifications in 20 cm layers and dressing but excluding the cost of rolling [Through Rate]

1769

48

84912

... More
[17.8.2]Compaction 2. Extra for watering the earth/fly ash laid in 20 cm layers as per specifications [Through Rate]

1769

27

47763

... More
[17.8.3]Compaction 3. Extra for rolling to specifications [Through Rate]

1769

27

47763

... More
[21.53]Constructing standard drain type I drain moulded and laid over lime concrete foundation rendered and finished smooth with 6 mm thick rendering concrete to be of 1.3.6 parts by volume of cement sand stone bajri and rendering to be 1:1 cement sand mortar [Through Rate]

180

160

28800

... More
[3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [5km]

2018.49

83

167534.67

... More
[3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [Beyond 5km up to 10km per KM]

12790

6

76740

... More
[4.12.1]Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge. 1. All kinds of soil [Through Rate]

16.2

78

1263.6

... More
[5.23.2]Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 2. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix) [Through Rate]

7.2

1149

8272.8

... More
[5.70]Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. [Through Rate]

7.2

86

619.2

... More
[6.1.1]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 1. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate]

2.32

3978

9228.96

... More
[6.1.6]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 6. 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) [Through Rate]

2.32

2444

5670.08

... More
[6.1.8]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 8. 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) [Through Rate]

2.7

2165

5845.5

... More
[6.14.1]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) [Through Rate]

22.5

4374

98415

... More
[6.29.2]Centering and shuttering including strutting, propping etc. and removal of form work for : 2. Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. [Through Rate]

264

282

74448

... More
[6.34.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect above plinth level Note:- Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more. [Through Rate]

2475

68

168300

... More
[7.21.2]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 2. Cement mortar 1:6 (1 cement : 6 coarse sand) [Through Rate]

21.11

3969

83785.59



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.