Sewage And Infrastructure Development Corporation Of Goa Limited Tender

View complete overview of Goa SIDCGL Tender

Sewage And Infrastructure Development Corporation Of Goa Limited - SIDCGL Tender

Works
Civil And Construction
Road Construction
Eprocure
Opening Date18 Nov 2022
Closing Date24 Nov 2022
Tender Amount₹ 37,88,514 
Notes
Download

Costs

  • EMD

    ₹ 75,770
  • Document Cost

    ₹ 4,000
  • Tender Fee

    ₹ 6,000

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Refilling the pipeline/foundation trenches plinth sides,foundation etc with available excavated earth in layers not exceeding 20 cm depth consolidating each layer ramming and watering lead upto 50 m and all lifts and disposal of surplus earth directed by Engineer-in-charge

271.59

-

218.4

... More
Cutting the bituminous road for laying the pipeline in trenches including labour, tools etc, and disposing the excavated excess material from the trench to a distance of 1000 meters, including making level the trench of road, by compacting, watering ramming with rolling with road roller after completion of laying of pipe and refilling the trenches etc. complete as per the direction of engineer incharge.

27

-

530.4

... More
Construction of Composite type Manholes of various diameters and depth , as per the detailed specification of items of work annexed vii) 1500mm dia x 4000 to 4500mm depth

1

-

463810

... More
Providing and laying in position cement concrete below foundation M15(1:2:4) (1 cement : 2 coarse sand: 4 graded granitic or basaltic stone aggregate 40 m nominal size) excluding cost of centering, shuttering and finishing :

22.94

-

7080

... More
supplying of laterite stone soling of size 150-200 mm and murum having P.I value not more than 6 and laying including packing with smaller stones and consolidation with power road roller including spreading, watering & consolidation of binding material etc (measurements shall be considered on finished item)

19.98

-

1549.2

... More
Repairs and reinstatement to the road for trenches made by laying water supply pipeline, by removing the refilled material in the trench for the total depth of 0.42m and making good the road surface by providing laying rollling by road roller compacting for laterite soling 30cm thick, two layer of full grout of 50mm thick each, tack coat and open graded premix carpet of 20mm thickness as per specifications mentioned in item nos 14086, 14093, 14051 & 14068 of road GSR respectively, complete as per the direction of the engineer incharge

27

-

1483.2

... More
Extra for additional depth of 1.5m or part thereof in All types of soil Depth from 1.50 to 3.00m

99.9

-

376.8

... More
Earthwork in excavation in foundation pipeline trenches, drain in saturated soil up to a depth of 0.60 m lift up to 1.50 m including disposing the excavated soil within a lead of 50 m Disposed earth to be neatly dressed and levelled, as directed by the Departmental Officer

-

-

-

... More
Excluding planking, timbering in trenches and dewatering. Depth from 0.00 to 0.60m

39.96

-

763.2

... More
Extra for earthwork excavated in saturated soil

-

-

-

... More
Depth from 0.60 to 0.90m

19.98

-

858.2

... More
Depth from 0.90 to 1.20m

19.98

-

953.2

... More
Depth from 1.20 to 1.50m

19.98

-

1048.2

... More
Depth from 1.50 to 1.80m

19.98

-

1143.2

... More
Depth from 1.80 to 2.10m

19.98

-

1238.2

... More
Add extra for excavation in or under water and on liquid mud including cost of pumping and complete (extra rate per co.. of excavation qty. in saturated soil strata considering actual water table level during the construction as datum ) c) Excavation work upto 1.50m. depth from datum

99.9

-

484.8

... More
d) Excavation work upto 3.00m & above depth from datum

39.96

-

854.4

... More
Extra for planking and strutting and packing material for cavities (in close timbering) if required to be left permanently in position (face area of timbering to be left permanently in position is to be measured)

231.44

-

1291.2

... More
Pumping of sewage Using 6 no 5 HP pumps

768

-

1704

... More
Jointing of HDPE pipes by heating the two ends of the pipe with electrically heated mirror, to the required temperature, including the hire charges of heating mirror and the generator set for the electricity for the heating mirror etc complete as per the direction of the engineer in- charge 500 mm OD

6

-

295.2

... More
Carriage of Materials

60.42

-

206.4

... More
Pumping of sewage for prevent overflows when sewer are at peak flow Using 2 no 10 HP pumps

256

-

907

... More
Transporting 0f pipe, Supply of Pipe by SIDCGL

42

-

581

... More
Making of CONNECTION for New & old NTM manhole with braking of concrete ,steel ,brick work and restore same

8

-

49174



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.