Costs
EMD
₹ 2,44,070Document Cost
₹ 8,000Tender Fee
₹ 6,000
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2022_SIDCG_5323_1Bid Award Id
ViewTender No
SIDCL/Admn-7/F.No.TN- 03 / 591 / 22-23 Line01Tender Authority
Sewage And Infrastructure Development Corporation Of Goa Limited ViewPurchaser Address
-Website
http://eprocure.goa.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Extra for additional depth of 1.5m or part thereof in a) All types of Soil
74.25
-
352.8
Conveying carefully from stack at site, 250m from both sides rolling and lowering in trenches, laying true to line and level and perfect linking for joints for P.V.C / H.D.P.E complete in all respects as per the direction of the engineer in charge f) 160 mm OD
550
-
7.08
Jointing of rigid / SEL FIT PVC pipes by cleaning the pipe with solvent cement including the cost of solvent cement and hydraulic testing of joints etc. complete as per IS:7634-1975 Part 3, including hydraulic testing of joints as directed by the engineer in charge. f) 160 Outer Diameter in mm
100
-
79.2
Making connection of drain or sewer line with existing manhole including breaking and making good the walls, floors with cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded stone aggregate 20mm nominal size) 12mm thick cement plaster on both sides with cement mortar 1:3 (1 cement:3 coarse sand) finished with a floating coat of neat cement and making necessary channels for drains etc. complete. a) For pipes 100 to 230mm dia.
100
-
330
Providing & laying cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded granitic or basaltic stone aggrt. 40 mm. nominal size)
excluding cost of centering, shuttering and finishing in:.a) With granitic or basaltic stone plums in: 1. foundation and plinth
742.5
-
6114
Refilling the pipeline/foundation trenches plinth sides, foundation etc. with available excavated earth in layers not exceeding 20cm depth consolidating each layer ramming and watering lead upto 50M and all lifts and disposal of surplus earth as directed by the Engineer in charge.
74.25
-
218.4
Carriage of materials by tipper truck including loading and unloading and stacking upto 5 Km II) Earth
767.5
-
245.54
Constrcution of Manhole (Bricks) conical in shape including Road Cutting, Earthwork excavation, Refilling, Carriage & Road Restoration (Rate Analysis I) 1.2m Dia and 2.0m Depth
5
-
127249
Constrcution of Manhole (Bricks) conical in shape including Road Cutting, Earthwork excavation, Refilling, Carriage & Road Restoration (Rate Analysis II) 1.2m Dia and 2.5m Depth
5
-
145475
Add extra for conical brick masonry manhole for fractional depth of each one centimetre or part thereof b) 1.2m dia manhole
100
-
258
Laying of PVC Pipe sewerline using open trech including Supply, Excavtion, Conveying, Laying, Jointing, encasing, refilling and road restoration Pipe size 160 mm OD
350
-
7645
Laying of HDPE Sewerline using open trench including Excavtion, Laying, Jointing HDPE 355mm dia
90
-
11143
Constrcution of Composite Conical Manhole including Road Cutting, Earthwork excavation, Refilling, Carriage & Road Restoration (Rate Analysis V) 1.5m Dia and 4.0m Depth
3
-
259122