Electricity Department Tender
View complete overview of Goa Electricity Department Tender
Costs
EMD
₹ 1,05,306Document Cost
₹ 1,000Tender Fee
₹ 6,000
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_ED_15954_1Bid Award Id
ViewTender No
Tender No.03(24-25)Tender Authority
Electricity Department ViewPurchaser Address
-Website
http://eprocure.goa.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
Supply of HDGI, 6.0 mts long octagonal poles alongwith 1.5 mts long triple arm bracket
4
78400
19600
Supply of HDGI, 6.0 mts long octagonal poles alongwith 1.5 mts long double arm bracket
13
245960
18920
Supply of HDGI, 6.0 mts long octagonal poles alongwith 1.5 mts long single arm bracket
3
53490
17830
Supply of LED lights fixture fitting 130W
24
368160
15340
Supply of 3 ½ Core x 25 sq.mm Al. XLPE, 1.1KV Grade, armoured cable
800
213600
267
Supply of 415V straight through joint kit for 4 core 16 Sq.mm/ 3.5 core 25 Sq.mm
97
142105
1465
Supply of Aluminum crimping lugs of size:16sqmm / 25 sqmm
776
7760
10
Supply of 2 Core x 2.5 sq.mm.1.1 KV grade, PVC, armoured Copper Control Cable
1072
127568
119
Earthing complete with 40mm GI Pipe, 2.5 mts long alongwith 20 kgs each salt, charcoal complete
32
87360
2730
12mm cement plaster 1:4 (1 cement : 4 fine sand)
77.6
11407
147
Supply of RCC protective covers of size 600mm long x 250mm width and 50mm thick
933
118491
127
Providing and laying in position cement concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded granitic or basaltic stone aggregate 40 m nominal size)
56.53
314024
5555
Supply of outdoor end termination kit for cable of size 3C, 400 sqmm XLPE cable
219.22
123420
563
COST OF ERECTION
-
-
-
Erection of HDGI, 8.0 mts long octagonal poles alongwith 1.5 mts long triple arm bracket
8
41928
5241
Erection of HDGI, 8.0 mts long octagonal poles alongwith 1.5 mts long single arm bracket
69
361629
5241
Erection of HDGI, 6.0 mts long octagonal poles alongwith 1.5 mts long triple arm bracket
4
18848
4712
Erection of HDGI, 6.0 mts long octagonal poles alongwith 1.5 mts long double arm bracket
13
61256
4712
Erection of HDGI, 6.0 mts long octagonal poles alongwith 1.5 mts long single arm bracket
3
14136
4712
Removal of existing old/deteriorated 8.0 mts long poles
77
201778
2620.5
Removal of existing old/deteriorated 6.0 mts long poles
20
47120
2356
Installation of LED lights fixture fitting 130W
24
24960
1040
LED lights fixture removal (130W)
110
57200
520
LED lights fixture fitting (130W)
110
114400
1040
Laying of 3 ½ Core x 25 sq.mm Al. XLPE, 1.1KV Grade, armoured cable
800
66400
83
Installation of 415V straight through joint kit for 4 core 16 Sq.mm/ 3.5 core 25 Sq.mm
97
48500
500
Erection of Aluminum crimping lugs of size:16sqmm / 25 sqmm
776
34144
44
Laying of 2 Core x 2.5 sq.mm.1.1 KV grade, PVC, armoured Copper Control Cable
1072
45024
42
Earthing complete with 40mm GI Pipe, 2.5 mts long alongwith 20 kgs each salt, charcoal complete
32
78208
2444
Supplying of Sand and filling in trenches including watering ramming consolidating, dressing, complete.
25.2
54684
2170
Laying of RCC protective covers of size 600mm long x 250mm width and 50mm thick
933
78372
84
Earthwork in excavation by mechanical means (hydraulic excavator)/manual means in All kinds of soil
486.43
227649
468
Refilling the trenches, plinth sides, foundation etc. with available excavated earth and disposal of surplus earth
322.98
38757
120
Transportation of removed poles from site to Fatorda Substation/ Central stores
1
25000
25000