- Home/
- Canada/
- Alberta Public Sector/
- Overview
Alberta Public Sector Tender
Alberta Public Sector Tender
Costs
Description
General .1 Requirements Specified In This Section Apply To The Scope And Measurement Of Work For Purposes Of Determining Payment Under The Contract. 2. Measurement Schedule 2.1 Extra Work Allowances .1 Unforeseen Work: .1 Scope: Includes Unforeseen Work For Which Payment Is Not Included Elsewhere. Unforeseen Work Shall Be Approved By Owner. .2 Measurement: Shall Be Made By The Owner After Assessment Of The Nature Of The Unforeseen Work. Method Of Measurement, Extent Of Work And The Limit Of Work Shall Be Agreed To Prior To Commencing The Unforeseen Work. .3 Payment: Shall Be Made By An Approved Change Order Describing The Unforeseen Work And Setting Out The Method Of Payment (ie. Lump Sum, Unit Price And/or Force Account). Payment Amount Shall Be Taken From The Extra Work Allowance Provided For In The Contract. 2.2 Schedule ‘a’ – General Items .1 General Requirements – Item 1 .1 Scope: Includes The Following: Division 0; Division 1; And All Related Work For Which Payment Is Not Included Elsewhere. .2 Measurement: General Requirements Will Not Be Measured For Payment. .3 Payment: Lump Sum Payment As Follows: .1 When 5% Of Schedule A Is Earned, 10% Of Lump Sum Bid For General Requirements Will Be Paid. .2 When 10% Of Schedule A Amount Is Earned, 25% Of Lump Sum Bid For General Requirements Will Be Paid. .3 When 25% Of Schedule A Is Earned, 25% Of Lump Sum Bid For General Requirements Will Be Paid. .4 When 50% Of Schedule A Amount Is Earned, 10% Of Lump Sum Bid For General Requirements Will Be Paid. .5 Upon Substantial Performance The Unpaid Balance Of The Lump Sum Bid In The Schedule Of Prices For General Requirements Will Be Paid. .2 Erosion And Sediment Control – Item 2 .1 Scope: Includes, But Is Not Limited To, All Labour, Material, And Equipment To Supply, Install, Maintain, And Remove All Fabric Filtration Tubes, Check Dams, And/or Sediment Traps Or Other Measures As Required To Prevent Sediment From Entering Natural Watercourses Including The Sheep River, Whether Specifically Shown On The Section 01280 Measurement And Payment Schedule 2371-002-00 Page 2 Drawings Or Not. Includes Submittal And Adherence To Erosion And Sediment Control Plan And Other Related Work For Which Payment Is Not Included Elsewhere. .2 Measurement: This Bid Item Will Not Be Measured For Payment. .3 Payment: Lump Sum, As Follows: (a) When 5% To 70% Of The Original Contract Amount Is Earned, A Corresponding Portion Of The Lump Sum Bid For “erosion & Sediment Control” Will Be Paid; (b) Upon Total Performance Of All Work On The Project, The Remaining Unpaid Balance Of The Lump Sum Will Be Paid. .3 Care Of Water – Item .1 Scope: Includes, But Is Not Limited To, All Labour, Material, And Equipment To Supply, Operate, Maintain, And Remove Materials And Equipment Required For Drainage Directing, Site Dewatering, Pumping, And Proper Discharge Of Ground And Surface Water, And Other Related Work For Which Payment Is Not Included Elsewhere. .2 Measurement: Care Of Water Will Not Be Measured For Payment. .3 Payment: Payment For Care Of Water Will Be As Follows: (a) When 5% Of The Original Contract Amount Is Earned, 25% Of The Lump Sum Bid For “care Of Water” Will Be Paid. (b) When 25% Of The Original Contract Amount Is Earned, 50% Of The Lump Sum Bid For “care Of Water” Will Be Paid. (c) When 50% Of The Original Contract Amount Is Earned, 70% Of The Lump Sum Bid For “care Of Water” Will Be Paid. (d) Upon Total Completion Of All Work On The Project, The Remaining Unpaid Balance Of The Lump Sum Bid For “care Of Water” Will Be Paid. The Total Payments For This Item Shall Not Exceed The Original Amount Bid For This Item. 2.3 Schedule ‘b’ – River Crossing .1 Connection To Existing Water Distribution System – Item 4 .1 Scope: Provision Of All Equipment Materials And Labour Required For The Supply And Installation Of The Connections To The Existing Water Distribution System, Complete. The Work Includes Excavation; Waste Excavation; Location, Isolation And Dewatering Of Existing Water Main; Modification To Existing Mains; Removal Of Existing Thrust Blocks, Fittings And Pipes; Supply And Installation Of Fittings, Couplers, Adaptors, Mechanical Restrainers, Thrust Blocks C/w Polyethylene Sheets, Stainless Steel Nuts/bolts/washers, Denso Tape & Paste System, Anodes And Granular Materials; Swabbing And Disinfection; Flushing; Testing; Utility Crossings; Backfilling; Clean-up; And All Related Work For Which Payment Is Not Included Elsewhere. Section 01280 Measurement And Payment Schedule 2371-002-00 Page 3 .2 Measurement: Will Be On A Per Unit Basis For Each Complete Connection To The Existing Water Distribution System In Accordance With The Size And Type Specified In The Schedule Of Prices. .3 Payment: Will Be At The Unit Price Bid According To The Size And Type Specified In The Schedule Of Prices. .2 Lean To Structure – Item 5 .1 Scope: Provision Of All Equipment Materials And Labour Required For The Removal And Replacement Of The Lean To Structure, Complete. The Work Includes Removal And Disposal Of The Existing Structure; Excavation; Waste Excavation, Location Of Existing Water Main; Shoring; Crushed Gravel Base Course; Concrete Foundation; Rebar; Rough Carpentry; Fibreglass Insulation; Air Barrier; Metal Cladding; Flashing; Drip Edge; And All Related Work For Which Payment Is Not Included Elsewhere. .2 Measurement: Will Be On A Lump Sum Basis As Specified In The Schedule Of Prices. .3 Payment: Will Be At The Lump Sum Price In Accordance With The Schedule Of Prices. .3 250 Mm Hdpe Water Main– Items 6a) And B) A) River Crossing – Directional Drill B) Connection To Existing System – Open Cut .1 Scope: Includes But Is Not Limited To All Labour, Material And Equipment For The Supply And Installation Of Hdpe Water Main Pipe, Complete. The Work Includes: Excavation; Waste Excavation; Removal, Pipe Materials; Air Compressor Supply; Fittings; Couplers; Adaptors; Corrosion Protective Paste And Tape System, Sacrificial Anodes; Thrust Blocks; Restrainers; Granular Materials; Swabbing And Disinfection; Chlorination Points; Installation; Flushing; Utility Crossings; Pressure Testing; Backfilling; Clean-up; And Other Related Work For Which Payment Is Not Included Elsewhere. .2 Measurement: Will Be On A Per Linear Metre Basis Of Hdpe Water Pipe Installed At The Sizes Noted In The Schedule Of Prices. The Length Will Be Measured Horizontally To The Nearest Tenth Of A Metre Of Water Main Pipe Installed. .3 Payment: Will Be At The Unit Price Bid Therefor In The Schedule Of Prices. .4 250mm Isolation Valve – Item 7 .1 Scope: Provision Of All Equipment, Material And Labour Required For The Supply And Installation Of A 250 Mm Water Main Isolation Valve, Complete. The Work Includes: Excavation; Waste Excavation; Fittings; Couplers; Isolation Valve; Concrete Base; Valve Box; Casing; Operating Rod; Top Box; Lid; Granular Materials; Corrosion Protective Paste And Tape System, Sacrificial Anodes; Swabbing; Flushing; Disinfection; Testing; Backfilling; Clean-up; And Other Related Work For Which Payment Is Not Included Elsewhere. .2 Measurement: Shall Be On A Per Unit Basis For Complete Isolation Valve Installed. .3 Payment: Shall Be At The Unit Price Bid Therefor In The Schedule Of Prices. Section 01280 Measurement And Payment Schedule 2371-002-00 Page 4 .5 Air Release Valve – Item 8 .1 Scope: Provision Of All Equipment, Material And Labour Required For The Supply And Installation Of An Automatic Air-vacuum Release Valve, Complete. The Work Includes: Excavation; Waste Excavation; Fittings; Couplers; Concrete Base; Curb Stop, Valve Box; Casing; Operating Rod; Top Box; Lid; Granular Materials; Concrete Structure, Hdpe Pipe, Vacuum Release Valve Assembly, Insulation, Locking Lid, Flushing; Disinfection; Testing; Backfilling; Clean-up; And Other Related Work For Which Payment Is Not Included Elsewhere. .2 Measurement: Shall Be On A Per Unit Basis For Complete Air Release Valve Installed. .3 Payment: Shall Be At The Unit Price Bid Therefor In The Schedule Of Prices. .6 Local Gravel Road Structure – Item 9 .1 Scope: Provision Of All Equipment, Material And Labour For Installation Of Local Gravel Road In Accordance With Limit Lines, Compacted Depths, Densities, Moisture Contents And Grades; Complete. The Work Includes Excavation; Subgrade Preparation; Base Granular Materials; Proof Rolling; Moisture Conditioning Of Granular Surfaces; Ramping; Backfilling; Compaction; Proof Rolling; Utility Crossings; Tipping Fees; Clean-up; And All Related Work For Which Payment Is Not Included Elsewhere. .2 Measurement: Will Be On A Per Square Metre Basis Of Gravel Road Restoration, In Accordance With The Type And Road Structure Specified In The Schedule Of Prices. .3 Payment: Will Be At The Unit Price Bid Therefor In The Schedule Of Prices. .7 Sod – Item 10 .1 Scope: Provision Of All Equipment, Material And Labour For Sodded Areas, Complete. The Work Includes Mulch, Water, Supply And Installation Of Sod; Initial Watering Of Seed; And All Related Work For Which Payment Is Not Included Elsewhere. .2 Measurement: Will Be On A Per Square Metre Basis Of Placed Sod Within The Designated Limits. .3 Payment: Will Be At The Unit Price Bid Therefor In The Schedule Of Prices. .8 Hydro Mulch And Dryland Seed – Item 11 .1 Scope: Provision Of All Equipment, Material And Labour For Hydro Mulch Of Seeded Areas, Complete. The Work Includes Mulch, Water, Tackifiers, Additives, Application; Supply And Installation Of Seed; Initial Watering Of Seed; Maintenance Of Seeded Area Until Successful Grass Catch Is Achieved; And All Related Work For Which Payment Is Not Included Elsewhere. No Separate Payment Will Be Made For Repairs To Topsoil Due To Erosion Damage, And/or Gullies, And/or Washouts, Or Reapplication Of Hydro Mulch To Bare Areas During The Maintenance Period. Section 01280 Measurement And Payment Schedule 2371-002-00 Page 5 .2 Measurement: Will Be On A Per Square Metre Basis Of Placed Hydro Mulch And Seed Within The Designated Limits. .3 Payment: Will Be At The Unit Price Bid Therefor In The Schedule Of Prices. 2.4 Schedule ‘c’ – Calkins Building Site .1 Pressure Reducing Valve – Item 12 .1 Scope: Includes The Removal And Disposal Of Existing Piping And Valves. Includes The Removal And Disposal Of The Existing Pressure Reducing Valve; The Supply And Installation Of Pressure Reducing Valve, Couplings, Fittings, Valves, Temporary Pipe Supports, Commissioning Of All Mechanical Equipment And Piping Including Disinfection, Flushing And Bacteriological Testing; And All Other Related Work For Which Payment Is Not Included Elsewhere. .2 Measurement: This Item Will Not Be Measured For Payment. .3 Payment: Lump Sum Payment. End Of Sectio
Contact
Tender Id
43097286870Tender No
AB-2024-02974Tender Authority
Alberta Public Sector ViewPurchaser Address
-Website
www.merx.com