Public Works Department Tender
BidAssist is a very user-friendly website that lets us explore new opportunities which further helps in the growth of the business. We can get any information regarding any e-tender the Chhattisgarh government has posted on its website in a very hassle-free manner.
Public Works Department - PWD Tender
Civil And Construction
Bridge Construction
Opening Date31 Dec 2024
Closing Date14 Jan 2025
Tender Amount₹ 1,10,97,000
Costs
EMD
₹ 83,500Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
163579Bid Award Id
ViewTender No
163579Tender Authority
Public Works Department ViewPurchaser Address
-Website
http://https://pwd.cg.nic.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and technical pecifications Clauses 1002, 1010 and 1202
54.14
76384
4135429.76
... More
Providing weepholes in brick masonry/stone masonry, plain/ reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
132
335
44220
... More
Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8 I) Granular material
1105.36
1025
1132994
... More
Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm ondition complete as per drawing and technical specification Clause 1204.3.8
131.32
1807
237295.24
... More
Filler Joint (II) Providing and fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing and technical specifications
33.6
431
14481.6
... More
Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5
II. R.C.C M 25 (Design mix
142.46
7312
1041667.52
... More
Drainage spouts complete as per drawing and technical specifications Clause 1209
8
2115
16920
... More
Providing and laying cement concrete wearing course M 30 grade including reinforcement complete as per drawing and technical specifications Clauses 800 and 1206.3
16.63
12727
211650.01
... More
Cement Concrete Pavement (i) Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including eveling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days, using curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501.
22.5
8264
185940
... More
Providing and laying pitching on slopes laid over prepared filter media as per drawing and technical specifications Clause 1302 I. Stone/Boulder
153.03
2016
308508.48
... More
Providing and laying filter material underneath pitching in slopes complete as per drawing and technical specifications Clause 1302
37.2
2324
86452.8
... More
Sub Divisional Officer
-
-
-
... More
PWD Sub Dn. Konta
-
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements