Public Works Roads Department Tender

BidAssist is a very user-friendly website which helps in finding the specific Assam e-tender that one is looking for. For getting any information or detail about any e-tender the Assam government must have posted, BidAssist is designed in such a manner so as to provide information on all government tenders in one place without any inconvenience.

Public Works Roads Department - PWRD Tender

Works
Civil And Construction
Bridge Construction
Eprocure
Opening Date30 Mar 2024
Closing Date22 Apr 2024
Tender Amount₹ 1,98,55,000 
Notes
Download

Costs

Summary

Construction Of Bridge In Karbi-anglong District I) Br. No. 1/1 On Ramnagar To Japarajan

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Bored cast-in-situ M35 grade R.C.C. Pile excluding reinforcement complete as per drawing and technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1200mm)

228

-

-

... More
Providing placing and driving in position for RCC piles 6mm permanent M.S Liner upto required depth including fabricating and setting out as per detailed drawing

2.02

-

-

... More
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. (B) Mechanical Means (II) With dewatering (i) Depth upto 3 m

199.37

-

-

... More
Levelling course for Pile cap

9.43

-

-

... More
Cement concrete for reinforced concrete in Pile cap complete as per drawing and Technical Specification.RCC Grade M35 (Using Batching Plant, Transit Mixer and Concrete Pump)

159.73

-

-

... More
Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal steel/Shyam steel/RINL) in foundation complete as per drawings and technical specifications Clauses 1000 and 1202 Piles,Pile caps

51

-

-

... More
Plain/Reinforced cement concrete,(Return wall/Retaining Wall Foundation & Stem, Abutment shafts and Abutment cap) in complete as per drawing and technical specification and steel shuttering formwork Without plasticiser H. RCC Grade M35 b. Height 5m to 10m Case II. Using Batching Plant, Transit Mixer and Concrete Pump

64

-

-

... More
Plain/Reinforced cement concrete, (Pedestal & Sesmic Arrestor) in complete as per drawing and technical specification and steel shuttering formwork Without plasticiser RCC Grade M40 Height 5m to 10m

2.66

-

-

... More
Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal steel/Shyam steel/RINL) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 Abutment , Abutment Cap,Dirt walls, Pier, Pier cap, Pedestals, Sesmic arrestor, Riding return walls, U return wall / Fly Return walls

10.24

-

-

... More
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size toeards the wall and provided over the entire surfaces behind the abutement, wing wall and return wall to the full height compacted to firm condition complete as per drawing and technical specification

30.22

-

-

... More
Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8 Granular material

212.44

-

-

... More
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications (1000 mm c/c)

16

-

-

... More
Rebound Hammer test Non-Destructive tecting with rebound hammer for detection of damage zone in reinforced concrete structures and furnishing the finding in proper comprehensing format.

4

-

-

... More
Ultrasonic pulse velocity test Non-Destructive tecting with ultrasonic pulse velocity meter with data storage facility for detection of cracks voids and other imperfections in reinforced concrete structure and furnishing the finding thereof in proper comprehnsible format complete as directed by the department

4

-

-

... More
Plain/Reinforced cement concrete, (PSC I Girder) in complete as per drawing and technical specification and steel shuttering formwork Without plasticiser D. PSC Grade M40 Case II Using Batching Plant, Transit Mixer and Concrete Pump II. For T-beam & slab b Height 5m to 10m

46.64

-

-

... More
Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing and Technical Specification' including steel shuttering formwork.Without Plasticiser M35 Deck Slab & M35 RCC Crosss Girder Height 5m to 10m Case II Using Batching Plant, Transit Mixer and Concrete Pump

44.23

-

-

... More
PCC M15 Grade leveling course below approach slab complete as per drawing and Technical specification

7.98

-

-

... More
Reinforced cement concrete approach slab (M30) including reinforcement and formwork complete as per drawing and Technical specification. TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/ Jindal panther steel/ Shyam steel or equivalent)

15.96

-

-

... More
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches to bridge structures and medians, constructed with M-40 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bar 25mm dia, 450mm long at expansion joints filled with pre moulded asphalt filler board, keyed to the structure on which it is built and installed as per design given in the enclouser to MOST circular No. RW/NH - 33022/1/94-DO III dated June 1994 as per dimension in the approved drawing and at locations directed by the engineer, all as specified.

60.51

-

-

... More
Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal steel/Shyam steel/RINL) in superstructure complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 RCC Girder, End Diaphragm, Deck slab

16.47

-

-

... More
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications

15.67

-

-

... More
Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. ) For Plain surface

1017.94

-

-

... More
Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface sliding against stainlesssteel matting surfaces, complete assembly to be of cast steel/fabricated structural steel, meatal and elastomer elements to be as per IRC:83 part-I &II respectively and parts conforming to BS:5400, section 9.1 & 9.2 and clause 2006 of MORTH&S Specification complete as per drawing and approved technical specification. FIX ,FREE,LONG,TRANS150 MT

540

-

-

... More
Strip Seal Expansion Joint : (Providing and laying of a strip seal expansion joint catering to maximum horizontal movement upto 70 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instruction for installation).

17

-

-

... More
Providing and fixing drainage spouts as per MORT & H specifications.

8

-

-

... More
Span Load Test Load testing of one or more spans of bridge as selected by the engineer as per approved load test procedure following relevant IS/IRC/Railway codes with contractor's labour, deflection measuring instruments, loading materials, recording and analyzing the load testing results including all leads and lifts etc. complete as required. The rates are all inclusive and will be paid after load test is finished and girder is cleared of the kentledges/loading materials etc. The load shall be 1.25 times the stipulated design load based on Design load & not span (Extra for every increase of 100.00mt or part there for in the span load capacity upto 800.00 mt

1

-

-

... More
Providing and laying filter material underneath pitching in slopes complete as per drawing and technical specifications Clause 1302

55.25

-

-

... More
Providing and laying pitching on slopes laid over prepared filter media as per drawing and technical specifications Clause 1302

110.51

-

-

... More
Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire conforming to IS:280 and IS:4826 in 100 mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 25 kg each as per drawing and technical specifications Clause 1301

143.63

-

-

... More
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201.

0.19

-

-

... More
Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting p g to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5

4529.96

-

-

... More
Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.

948.73

-

-

... More
Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401.

186.1

-

-

... More
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical Specification Clause 405. By Mechanical Means

87.47

-

-

... More
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. By Mechanical Means

87.47

-

-

... More
Providing and laying interlocking concrete block pavement with M40 grade grade of concrete blocks having thickness 80mm as per technical specification clause 1504 complete including carriage.

1016.75

-

-

... More
Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other locations shown on the drawing or asdirected by the Engineer including preparation of ground, fetching of sods and watering as per Technical Specification Clause 309.

1275.8

-

-

... More
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical Specification Clause 801 ii) 600mm equilateral triangle

2

-

-

... More
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical Specification Clause 801 iv) 800mm x 600mm rectangular

4

-

-

... More
Metal Beam Crash Barrier, Type - A: "W" Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2m center to center, 1.8 m high, 1.1m below ground/road level, all steel parts and fitments to be galvanized by hot dip process, all fitting to conform to IS:1367 and IS:1364, metal beam rail to be fixedon the vertical post with a spacer of channel section 150mm x 75mm x 5mm, 330mm long complete as per clause 810.)

80

-

-

... More
Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface

51

-

-

... More
Tree Plantation Planting of Trees and their Maintenance for three Year (Planting of trees by the road side (Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil with decayed farm yard/sludge mannure, planting the saplings, backfilling the trenches, watering , fixing the tree guatrd and maintaining the plants for three year.

6

-

-

... More
Labour for dismantling all members of the timber bridge (excluding piles) with necessary scaffolding, jati bamboos, jumper ropes etc, complete and stacking them at suitable places as directed (all members will be under custody of the contractor till taken over by the department)

15.4

-

-

... More
Air quality monitoring At 3 locations for 2seasons for 2 consecutive years. (Construction Stage)

12

-

-

... More
Air quality monitoring at 3 locations for 2 seasons for 1year. (Operation Stage)

6

-

-

... More
Water quality monitoring at 3 locations for 2 seasons for 2 consecutive years. (Construction Stage)

12

-

-

... More
Water quality monitoring at 3l locations for 2 seasons for 1 year. (Operation Stage)

6

-

-

... More
Noise quality monitoring at 3 Locations for 2 seasons for 2 consecutive years. (Construction Stage)

12

-

-

... More
Noise quality monitoring at 3 locations for 2 seasons for 1 year. (Operation Stage)

6

-

-

... More
Soil quality monitoring at 3 locations for 2 seasons for 2 consecutive years. (Construction Stage)

12

-

-

... More
Soil quality monitoring at 3 locations for 2 seasons for 1 year.(Operation Stage)

6

-

-

... More
Training related to Capacity Building

2

-

-

... More
A Provisional sum (fixed amount) for items of Utility Shifting & Tree cutting of Rs. 4,56,903.00 (not to be changed by the Bidder in BOQ)

1

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.