Public Works Roads Department Tender
BidAssist is a very user-friendly website which helps in finding the specific Assam e-tender that one is looking for. For getting any information or detail about any e-tender the Assam government must have posted, BidAssist is designed in such a manner so as to provide information on all government tenders in one place without any inconvenience.
Costs
EMD
₹ 2,41,000Document Cost
₹ 2,400Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2023_PWD_34955_96Tender No
CE/Maint/MMPNA/01/2023-24/13Tender Authority
Public Works Roads Department ViewPurchaser Address
-Website
http://https://pwdroads.assam.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
17181.95
-
13.33
Semi - Dense Bituminous Concrete: Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5% of mix and filler transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment,rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no.508. complete in all respect. including carriage of mixed materials up to 10.0 Km initial lead from mixing plant ) (Including cost of testing of materials at site and laboratory as directed by the deptt.) (a) With hydrated lime/cement as filler ( refer table 500-9 of MoSRT&H specification)
(I)'with 60/70 or VG-30 grade bitumen for GradingII(10 mm nominal size)
429.55
-
9331.22
Providing Hump type speed breaker:
Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504
9.16
-
7943.74
Semi - Dense Bituminous Concrete: Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5% of mix and filler transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment,rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no.508. complete in all respect. including carriage of mixed materials up to 10.0 Km initial lead from mixing plant ) (Including cost of testing of materials at site and laboratory as directed by the deptt.) (a) With hydrated lime/cement as filler ( refer table 500-9 of MoSRT&H specification)
(I)'with 60/70 or VG-30 grade bitumen for GradingII(10 mm nominal size)
3.05
-
9331.22
Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes and conforming to the MoSrt&H specifications
(80% length of the Road is considered)
541.05
-
566.13
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical Specification Clause 801
600mm equilateral triangle
16
-
3933.19
(2)Periodic Renewal of Haripara ali to Latum (PMGSY) Making up loss of material/irregularities on shoulders to the design level by adding fresh approved selected soil and compacting it with appropriate equipment at OMC upto a lead of 1000 m as per technical specification Clause 1903
(existing width of shoulder is considered 1.00 m to 1.125 m)
1628.16
-
83.28
Maintenance of WBM road including filling up of pot holes, ruts and rectifying corrugated surface, damaged edges and ravelling as per technical specification Clause 1906.
1282.79
-
337.64
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
(Provided only on WBM surface)
1282.79
-
39.78
Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
2850
-
13.33
Semi - Dense Bituminous Concrete: Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5% of mix and filler transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment,rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no.508. complete in all respect. including carriage of mixed materials up to 10.0 Km initial lead from mixing plant ) (Including cost of testing of materials at site and laboratory as directed by the deptt.) (a) With hydrated lime/cement as filler ( refer table 500-9 of MoSRT&H specification)
(I)'with 60/70 or VG-30 grade bitumen for GradingII(10 mm nominal size)
71.25
-
9269.34
Providing Hump type speed breaker:
Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504
2.08
-
7884.18
Semi - Dense Bituminous Concrete: Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5% of mix and filler transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment,rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no.508. complete in all respect. including carriage of mixed materials up to 10.0 Km initial lead from mixing plant ) (Including cost of testing of materials at site and laboratory as directed by the deptt.) (a) With hydrated lime/cement as filler ( refer table 500-9 of MoSRT&H specification)
(I)'with 60/70 or VG-30 grade bitumen for GradingII(10 mm nominal size)
0.69
-
9269.34
Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes and conforming to the MoSrt&H specifications
(80% length of the Road is considered)
135.48
-
566.13
Brick masonry work in cement mortar in foundation of wall complete excl. pointing and plastering as per drawing and technical specification clause 1100(in prop. 1:4)
10
-
7450.77
Plastering with cement mortar(1:6) 15mm thick on brick work for substructure as per technical specification
55.26
-
146.41
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical Specification Clause 801 600mm equlateral triangle
4
-
3933.19
(3)Periodic Renewal of NH 37 to Nazira Ali (Bahgarh Ali) (PMGSY) Making up loss of material/irregularities on shoulders to the design level by adding fresh approved selected soil and compacting it with appropriate equipment at OMC upto a lead of 1000 m as per technical specification Clause 1903
(existing width of shoulder is considered 1.00 m to 1.125 m)
3122.62
-
83.28
Maintenance of WBM road including filling up of pot holes, ruts and rectifying corrugated surface, damaged edges and ravelling as per technical specification Clause 1906.
2435.74
-
337.64
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
(Provided only on WBM surface)
2435.74
-
39.78
Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
5625
-
13.33
Semi - Dense Bituminous Concrete: Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5% of mix and filler transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment,rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no.508. complete in all respect. including carriage of mixed materials up to 10.0 Km initial lead from mixing plant ) (Including cost of testing of materials at site and laboratory as directed by the deptt.) (a) With hydrated lime/cement as filler ( refer table 500-9 of MoSRT&H specification)
(I)'with 60/70 or VG-30 grade bitumen for GradingII(10 mm nominal size)
140.62
-
9541.61
Providing Hump type speed breaker:
Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504
2.08
-
8146.25
Semi - Dense Bituminous Concrete: Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5% of mix and filler transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment,rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no.508. complete in all respect. including carriage of mixed materials up to 10.0 Km initial lead from mixing plant ) (Including cost of testing of materials at site and laboratory as directed by the deptt.) (a) With hydrated lime/cement as filler ( refer table 500-9 of MoSRT&H specification)
(I)'with 60/70 or VG-30 grade bitumen for GradingII(10 mm nominal size)
0.69
-
9541.61
Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes and conforming to the MoSrt&H specifications
(80% length of the Road is considered)
347.75
-
566.13
Maintenance of Hume pipe Culvert by way of Clearing, Cleaning, Erosion repair, repairs to cracks, parapet wall and protection work as per drawing and technical specification Clause 1908
4
-
41299.24
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical Specification Clause 801
600 mm equilateral triangle
10
-
3933.19