Public Works Department - PWD Tender
Civil And Construction
Road Construction
Eprocure
Opening Date12 Mar 2025
Closing Soon26 Mar 2025
Tender AmountRefer Documents
Costs
EMD
₹ 13,46,000Document Cost
₹ 5,000Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2025_PWDAP_2258_1Tender No
DD/2024-25/04Tender Authority
Public Works Department ViewPurchaser Address
-Website
http://arunachaltenders.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
... More
Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately)
-
-
-
... More
By Mechanical Means
-
-
-
... More
a) Bituminous course
281.25
-
-
... More
Preparation of sub grade:Preparation of sub grade by excavating earth to an average depth of 22.50 cm, dressing to camber and consolidating with road roller, making good the undulations etc. and disposal of surplus earth, lead upto 50 m.
3990
-
-
... More
Consolidation of sub-grade with road roller of 8 to 12 tonne capacity including making good the undulations etc. with earth or quarry spoils etc. and rerolling the sub grade.
3990
-
-
... More
Granular Sub-base with Close Graded Material (Table:- 400-1). A Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 )
-
-
-
... More
(ii) for grading- II Material
598.5
-
-
... More
150 Micron Plythene (Providing and fixing 150 micro polythine over sub-base
4000
-
-
... More
Dry Lean Cement Concrete Sub- base: Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.
598.5
-
-
... More
Cement Concrete Pavement : Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing )(Rate is exclusive of cement concrete & transportation) Note: A gap of 1 mtr width for pipe/cable etc across road shall be kept within every 100 mtr length.
892.5
-
-
... More
SH : CC Pavement - Type-A, 5.5m width - 2986.00 mtr
-
-
-
... More
Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately)
-
-
-
... More
By Mechanical Means
-
-
-
... More
a) Bituminous course
600
-
-
... More
Preparation of sub grade:Preparation of sub grade by excavating earth to an average depth of 22.50 cm, dressing to camber and consolidating with road roller, making good the undulations etc. and disposal of surplus earth, lead upto 50 m.
18184.74
-
-
... More
Consolidation of sub-grade with road roller of 8 to 12 tonne capacity including making good the undulations etc. with earth or quarry spoils etc. and rerolling the sub grade.
18184.74
-
-
... More
Granular Sub-base with Close Graded Material (Table:- 400-1). A Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 )
-
-
-
... More
(ii) for grading- II Material
2727.71
-
-
... More
150 Micron Plythene (Providing and fixing 150 micro polythine over sub-base
17318.8
-
-
... More
Dry Lean Cement Concrete Sub- base: Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.
2727.71
-
-
... More
Cement Concrete Pavement : Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing )(Rate is exclusive of cement concrete & transportation) Note: A gap of 1 mtr width for pipe/cable etc across road shall be kept within every 100 mtr length.
3762.36
-
-
... More
SH : RCC Box culvert 2.00 mx 2.00 m, 7 Nos
-
-
-
... More
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.I)Ordinary soil ,A) Manual Means depth upto 3 m depth.
458.5
-
-
... More
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications. A) PCC Grade M15
51.84
-
-
... More
Furnishing and Placing Reinforced/ Prestressed cement concrete in super-structure as per drawing and Technical Specification A)RCC Grade M20 Case I) Using Concrete Mixer (i) For solid slab super-structure, 20-30% of (a+b+c) (p) Height upto 5m
282.31
-
-
... More
Centring and shuttering including strutting proping etc. and removal of form work for:b) Walls(any thickness) including attached buttresses, pilasters,Plinth and string course etc.
602
-
-
... More
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and technical specifications
15.33
-
-
... More
Providing weep holes in Brick masonry/ Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications
280
-
-
... More
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical Specification Granular material
297.5
-
-
... More
SH : CC Drain , 2000 Mtr
-
-
-
... More
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.I Ordinary soil,(i)b upto 3 m depth (with de-watering)
1980
-
-
... More
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
330
-
-
... More
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications. c) RCC Grade M20, Case I Using concrete mixer
2050
-
-
... More
12 mm Cement Plaster 1:3 (1 Cement:3 Fine Sand)
3800
-
-
... More
Neat cement punning
3800
-
-
... More
SH : RCC R/Wall for 40.00 m & 4.00m Height
-
-
-
... More
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.).
277.2
-
-
... More
Providing and laying in foundations and plinth cement concrete 1 : 3 : 6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size) excluding the cost of centring and shuttering
11.2
-
-
... More
Reinforcement of RCC work including bending, binding and placing in position complete
-
-
-
... More
a) Tar/ TMT steel
8312.37
-
-
... More
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications
-
-
-
... More
RCC Grade M20
96.1
-
-
... More
Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications
108
-
-
... More
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification
-
-
-
... More
Granular material
182
-
-
... More
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.)
-
-
-
... More
Ordinary soil, Manual Means, upto 3 m depth
233.02
-
-
... More
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
28.01
-
-
... More
Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification
-
-
-
... More
Random Rubble Masonry
358.27
-
-
... More
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification
-
-
-
... More
Granular material
179.77
-
-
... More
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications
117.15
-
-
... More
Preparation of sub grade:Preparation of sub grade by excavating earth to an average depth of 22.50 cm, dressing to camber and consolidating with road roller, making good the undulations etc. and disposal of surplus earth, lead upto 50 m.
280.5
-
-
... More
150 Micron Plythene (Providing and fixing 150 micro polythine over sub-base
280.5
-
-
... More
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications. (B) PCC Grade M20
56.1
-
-
... More
Chequered terrazzo tiles 22 mm thick with marble chips of sizes upto 6mm in floors on 25 mm thick bed mortar 1 : 3 (1 cement : 3 coarse sand) jointed with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing complete: (C) Dark shade using ordinary cement.
280.5
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements
Past BiddersThis list is curated from the bidders of the similar tenders in the past
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%