To know what Andhra Pradesh government has posted about any AP etender, Bidassist helps us to get a one-stop platform where a registered bidder can have access to the details on each and every eprocurement tender. There is no need to provide the details on the AP E-procurement website i.e. https://www.apeprocurement.gov.in as BidAssist helps us find the specific etender we're looking for. BidAassist has collated each and every Eproc Andhra Pradesh Tender on its website.
Southern Power Distribution Company Of Andhra Pradesh Limited - APSPDCL Tender
Civil And Construction
Water Storage And Supply
Opening Date30 Dec 2023
Closing Date5 Jan 2024
Tender Amount₹ 14,25,635
Costs
EMD
₹ 28,513Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
705560Bid Award Id
ViewTender No
SE/OPN/KDP/91/2023-24Tender Authority
Southern Power Distribution Company Of Andhra Pradesh Limited ViewPurchaser Address
-Website
http://https://www.apspdcl.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Excavation of earth pit, putting cast iron pipe with flange on one end (as per ISS7181/86) of nominal dia 125mm and 2.75 meters long in side the pit including supply and fixing RCC collars 0.75 meter dia (OD), 50mm thick and 0.60meters long in side the pit, backfill the pit in the 25mm size granules of BHcoke for full depth of the pit with alternate layers of BH coke and salt of 300mm thick around the earth pipe of 150mm on all the sides of the pipe including cost and conveyance of BH coke, salt, clamps, C.I.Pipes and RCC collars, labour charges for all operational and incidental items of work etc., complete.
2
33962
16981
Street lighting fixtures -make CGL-LSTN1-150-CDL A or equivalent model in Philips/Bajaj Type A1 with junction box
2
28042
14021
ACSS(TW)Zebra Conductor
0.3
146565
488551
SF6 gas cylinder of 25Kg capacity
2
44500
22250
Laying of control cables for the transformers which are received with non completion of wiring on the transformer and complete wiring of the transformer on the tank.F.C.C,D.M box etc.
2
5186
2593
3 bolted tension hardware for twin moose with 150mm spacing to 33KV bus
12
46440
3870
Earth work excavation in foundations for building
24.92
10890
437
Filling with sand below and sides of foundations
4.37
6642
1520
Plain cement concrete in (1:4:8)
2.49
10410
4181
Plain cement concrete in (1:3:6)
17.8
83188
4673.53
Plain cement concrete in (1:2:4)
15
73672
4911.47
Reinforcement steel supply and labour charges
3.1
253192
81675
Brick masonry for supersturcture
8.7
57698
6632
Plastering 12 mm thick in one coat for basement
22.15
9568
432
Painting two coats of weather proof paint
29
8439
291
Erection of 33 KV AB switch
2
4134
2067
Erection , testing and commissioning of 33KV Breaker
1
11422
11422
Erection and labour 33 kV Isolators-2000 A(Metallic Portion)
2
116098
58049
L/o 33 KV AB switches
2
276
138
U L/o 33 KV AB switches
2
276
138
33 KV LAS(Station Type)
3
126
42
33 KV LAS(Station Type)
3
126
42
T Clamps for single Moose all three ways
12
9000
750
Hoisting of insulators & hardware, paving conductor and stringing of 400kV main bus for three phases with quadruple moose conductor to a tension of 1000kgs for single moose conductor, bus section length is 54mtrs.
1
48266
48266
L/oZebra ACSR
0.3
143
478
U/L Zebra ACSR
0.3
143
478
Laying including termination and providing suitable
960
60480
63
33 kV CTs (400/1-1 A)
3
103350
34450