Southern Power Distribution Company Of Andhra Pradesh Limited Tender
To know what Andhra Pradesh government has posted about any AP etender, Bidassist helps us to get a one-stop platform where a registered bidder can have access to the details on each and every eprocurement tender. There is no need to provide the details on the AP E-procurement website i.e. https://www.apeprocurement.gov.in as BidAssist helps us find the specific etender we're looking for. BidAassist has collated each and every Eproc Andhra Pradesh Tender on its website.
Southern Power Distribution Company Of Andhra Pradesh Limited - APSPDCL Tender
Civil And Construction
Water Storage And Supply
Opening Date24 Jan 2024
Closing Date1 Feb 2024
Tender Amount₹ 1,29,55,427
Costs
EMD
₹ 1,29,555Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
713217Bid Award Id
ViewTender No
SE/OPN/KDP/96/2023-24Tender Authority
Southern Power Distribution Company Of Andhra Pradesh Limited ViewPurchaser Address
-Website
http://https://www.apspdcl.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Number plates
2
387
193.73
Danger boards
2
430
215.25
Anti climbing Devices
2
6664
3332.28
Phase plates
4
984
246
GI Bolts & Nuts,Washers
1.6
161410
100881.53
ACSR Panther Conductor confirming to the IS of latest issue and as detailed in the specification including cost of all materials and labour, transportation etc, complete
4.5
836015
185781.25
7/3.15mm HTGS Earth Wire
1
32671
32671.88
Supply of following transmission line Hardware as per confirming to the IS of latest issue suitable to ACSR Panther conductor and as detailed in the specification including cost of all materials and labour, transportation etc, complete
-
-
-
Single Tension Hardware
12
24464
2038.73
Double Tension hard ware
12
48462
4038.5
Vibration Dampers
24
12915
538.13
Mid span compression joints
10
4643
464.33
Supply of SRC Insulators confirming to the IS of latest issue and as detailed in the specification including cost of all materials and labour, transportation etc, complete
-
-
-
132 KV 120 KN SRC Insulators
36
107010
2972.5
Single tension hardware for Earthwire
4
3202
800.53
Erection Portion for Electrical works :
-
-
-
Conducting detailed survey by taking the levels along the route to acorridor of 15 mts. Width on either side of alignment, at every 20 mtrs.intervel and whereever there is steep increase/decrease in groung profile duly indicating the chainage between angle points, river crossings, railway crossings and major highway crossings and plotting the profiles and preparation of vicinity maps to the standard scales. The survey includes clearing of bushes, branches of trees, crops and shrubs whereever encourtered for detailed survey for viewing,for fixing anchor towers and aslo taking levels etc. required for conducting for detail survey.
1
17681
17681
Check survey,peg marking the tower positions on ground ,confirming to the approved profile and tower schedules using GPS,Total stations, Digital theodolites,etc.,
1
5670
5670
Setting of stubs with stub setting template:-Erection of stubs, stub template, fixing of jacks for supporting template, allignment and levelling for exact location of stubs of stub setting template, dismantling of template after completion of initial curing of CC movement of template from one location to other location of 220 KV towers.
2
29494
14747
Erection of tower structures ,including all types of extensions except JC type towers (stub template erection and dismantling not to be included) (including 3 mtr.,6mtr.,9mtr.,&12 mtr.,extensions) in full towers completed with all accesssories such as step bolts, number plates and punching the bolts after full tightening and check the tower vertically, fixing of phase plates, bird guard etc.,) and anticlimbing devices are also to be fixed whereeven necessary for all type of towers.
44
294756
6699
Earthing of towers including cost of excavation,back filling, including cost of 25mm dia 2.5mm thick,class 'C'G.I.Pipe of 3mtrs length with 50x6mm GI Flat 4.05 mtrs long,char coal salt etc., and measuring tower footing resistance.
2
11628
5814
Stringing of Panther Conductor:Hoisting of tension insulators and suspension insulators, Paving out conductor, rough sagging, jointing, tensioning, clipping and fixing of preformed armour rods and vibration dampers,measuring ground clearances where ever necessary.which excludes the works involved in the crossing of LT,11KV & 33KV power lines viz dismantling and restinging of conductor complete. (i) 6 Nos ACSR Panther conductors
0.75
54273
72364
Stringing of 7/3.15mm Earth wire
1
9144
9144
Hiring of car charges for TLC officers
5000
40000
8
Half round welding of G.I.Bolts and nuts of towers in the section between ground level and upto bottom x-arm level including all boltsconnecting the bracings at bottom x-arm level and painting the welded portion with one coat of zinc rich paint.
4040
96960
24
20% extra amount for scattered work for Data-II
-
111921
-
Labour portion for Civil works : Earth work excavation in all types of soils , PCC ,RCC for tower foundations wherever necessary including cost and conveyance of all materials, labour charges, tools & tackles, all leads & lift sand etc. taken as Lumpsum.
2
3652973
1826486.7
NOTE: The maximum permissible limit to quote by the bidder is 5% excess over the estimate value
-
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements