Roads And Buildings Department Tender
To know what Andhra Pradesh government has posted about any AP etender, Bidassist helps us to get a one-stop platform where a registered bidder can have access to the details on each and every eprocurement tender. There is no need to provide the details on the AP E-procurement website i.e. https://www.apeprocurement.gov.in as BidAssist helps us find the specific etender we're looking for. BidAassist has collated each and every Eproc Andhra Pradesh Tender on its website.
Roads And Buildings Department Tender
Civil And Construction
Excavation
Opening Date23 Dec 2023
Closing Date2 Jan 2024
Tender Amount₹ 10,18,279
Costs
EMD
₹ 10,200Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
703614Tender No
SHORT NIT NO 20(7)/TO/2023-24, dt.11.12.2023 (4th call)Tender Authority
Roads And Buildings Department ViewPurchaser Address
-Website
http://tender.apeprocurement.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size 290x225x140mm with compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials like cement, sand, fly ash bricks, water etc., to site, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).
7.64
71380
9343
Plastering with CM(1:5) Prop: 12mm thick in single coat including cost and conveyance of all materials like cement, sand, water etc., to site, all operational, incidental charges and labour charges such as mixing mortar, finishing, curing, etc., complete for finished item of work. (APSS 901,906)
232
97904
422
Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of approved size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs and drawings including cost and conveyance of bars from approved sources to site of work, including cost and conveyance of binding wire, cover blocks, chairs, overlaps, spacers, dowels, wastage etc., and all operational, incidental, and labour charges such as cutting, bending, placing in position, tying etc., complete for finished item of work (APSS No.126) in all floors.
2.2
198369
90168
Painting to New walls with two coats of arcylic Emulsion paint of superior quality of approved brand and shade over base coat of cement primer grade -I making three coats in all to give an even shade after thoroughly brushing the surface to remove all loose powdered materials, including cost and conveyance of all materials, including cost and conveyance of all materials, cost of brushes, water to site, etc., all operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in all floors for Walls.(APSS No. 912) in All Floors
340
55420
163
Cast - In - situ - Granolithic Concrete Flooring 20mm thick with CC(1:1:2) Prop: using 6mm to 12mm size HBG machine crushed metal laid monolithically over 100mm thick CC flooring bed (1:5:10) with 40mm HBG metal in alternate panels of size not exceeding 1.50m x 1.50m and finishing the top surface to required smoothness and slopes, thread lining as directed by the Engineer - in - charge including cost and conveyance of all materials like cement, sand, water, etc. to site, all operational, incidental and labour charges such as mixing of cement concrete, laying, curing, lift charges etc., complete for finished item of work (APSS No.701 & 710)
86
41022
477
Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5:10) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, all operational, incidental, and labour charges such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top surface, curing concrete, etc., complete for finished item of work for Foundations and Flooring Bed (APSS No. 402)
14.41
74730
5186
Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 & 904)
90.55
39208
433
Brick Masonry in Basement with CM (1:6) prop: using Fly ASH Bricks of size 290x225x140mm with compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials like cement, sand, fly ash bricks, water etc., to site, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work. for Basement (APSS No. 501 & 504). For Cremation shelter & shed
14.67
128421
8754
Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size 290x225x140mm with compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials like cement, sand, fly ash bricks, water etc., to site, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).
3.67
34288
9343
Filling with useful available excavated earth (excluding rock) in trenches, sides of foundations and basement with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming including cost and conveyance of water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310).
20.99
1154
55
Filling with Gravel with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming including cost and conveyence of water to the work site and all operational & incidental charges, labour charges, hire and opertaional charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)
68
27948
411
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for foundation, plinth , pedastals(below plinth)(APSS No. 402 & 403) For Footings
3.87
45391
11729
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for foundation, plinth , pedastals(below plinth)(APSS No. 402 & 403) For Columns
3.09
46427
15025
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for foundation, plinth , pedastals(below plinth)(APSS No. 402 & 403) For Plinth Beam
5.39
77529
14384
Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work(below plinth)(APSS No. 402 & 403) for LINTELS
0.08
1201
15018
Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for foundation, plinth , pedastals(below plinth)(APSS No. 402 & 403) For Sunshades
0.54
514
953
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements