To know what Andhra Pradesh government has posted about any AP etender, Bidassist helps us to get a one-stop platform where a registered bidder can have access to the details on each and every eprocurement tender. There is no need to provide the details on the AP E-procurement website i.e. https://www.apeprocurement.gov.in as BidAssist helps us find the specific etender we're looking for. BidAassist has collated each and every Eproc Andhra Pradesh Tender on its website.
Municipality Tender
Opening Date5 Sep 2020
Closing Date21 Sep 2020
Tender Amount₹ 9,87,893 This is an estimated amount, exact amount may vary.
Costs
EMD
Refer DocumentsDocument Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
348905Bid Award Id
ViewTender No
e-Proc. NIT No.1899/11/E/TO/2020-21, Dt.03-09-2020, S.No.15Tender Authority
Municipality ViewPurchaser Address
-Website
http://tender.apeprocurement.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
Construction of CC Road CC Drains From Success Institute;Collection, supply & spreading of crusher dust including stacking for pre measuerments at site of work and consolidation with hand roller or any device other than power rolling, cost of materials, labour charges for loading, unloading & stacking, watering, tamping etc., complete as per SS and as directed by the Engineer-in-charge
32
-
27017.28
Construction of CC Road CC Drains From Success Institute;Construction of un-reinforced Plain Cement Concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates, maximum in a concrete mixer of not less than 0.2 cum capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes, compacted using needle and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, primer, sealant, as approved, curing for 14- days, and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 MORD. RBR-CCPV-5
45
-
247950
Construction of CC Road CC Drains From Success Institute;Filling of Side Berms with Gravel and Sand in the ratio of 70 % & 30% respectively (Mixed uniformly), in uniform layers and compacting with Hand ramming to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408 MORD. as per SS and as directed by the departmental officer incharge of the work. But excluding seigniorage charges - For Side Berms
30
-
15363.3
Construction of CC Road CC Drains From Success Institute;By Mechnical Means 70% - CC Drain - Earthwork in excavation for Structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and base filling in trenches with excavated suitable material as per Tech. Specification 305 MORD, 304 MORTH. This rate including cost of all labour charges and other incidental charges etc., complete as per SS and as directed by the departmental officer incharge of work.
112.74
-
11036.12
Construction of CC Road CC Drains From Success Institute;By Manual Means 30% - CC Drain - Earthwork in excavation for Structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and base filling in trenches with excavated suitable material as per Tech. Specification 305 MORD, 304 MORTH. This rate including cost of all labour charges and other incidental charges etc., complete as per SS and as directed by the departmental officer incharge of work.
48.32
-
9870.33
Construction of CC Road CC Drains From Success Institute;Carting away the surplus excavated earth from the work site with a lead of 2.0 KM beyond initial lead including loading, unloading and conveyance and spreading the same in low laying areas etc., complete to relevant standard specifications and as directed by the officer-in-charge of the work
161.05
-
31453.07
Construction of CC Road CC Drains From Success Institute;Collection, supply & spreading of crusher dust including stacking for pre measuerments at site of work and consolidation with hand roller or any device other than power rolling, cost of materials, labour charges for loading, unloading & stacking, watering, tamping etc., complete as per SS and as directed by the Engineer-in-charge
24
-
20262.96
Construction of CC Road CC Drains From Success Institute;VCC-M10 Providing concrete for plain/reinforced concrete in open foundations using 20 mm SS5 M/c HBG Metal, mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH.
92.5
-
393931.6
Construction of CC Road CC Drains From Success Institute;Providing of VCC M15 Grade Design Mix Concrete in open foundations and side walls using 20 mm SS 5 M/c HBG Graded Metal, mechanically mixed, placed in foundation and compacted by vibration including curing for 28 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH for Drains
1
-
4477.27
Construction of CC Road CC Drains From Success Institute;Plastering in Cement Mortar (1:3) 12 mm thick using sand from approved quarry including cost and conveyance of all materials and all labour charges etc., complete as per SS and as directed by the departmental officer in charge of the work.
415.5
-
124309.29
Construction of CC Road CC Drains From Success Institute;V R.C.C. M 30 grade Concrete using 20 mm HBG Down graded metal including centring charges, laying , levelling , machine mixing but exculding cost of steel in reinforcement, etc complete as per relevant standard specifications and as directed by the engineer-in-charge of the work (For Cover Slabs) Note : Quantity of cement proposed for various design mixes is for estimating purpose only. Actual quantity of cement will be as per approved mix design. Similarly quantity for coarse and fine aggregates is for estimating purpose and the exact quantity shall be as per the mix design.
4.5
-
30053.38
Construction of CC Road CC Drains From Success Institute;Supply and delivery of Steel Reinforcement H.Y.S.D.confirming to I.S.S. including cost & conveyance of all materials , cost of binding wire and its fabrication charges, placing in position tying grills etc., complete as per relevant standard specifications and as directed by the engineer-in-charge of the work
315
-
18414.9
Construction of CC Road CC Drains From Success Institute;Centering charges for VCC vertical walls of plane surface (rate is for both sides centering) including open drains including cost and conveyance of all materials and labour charges and other incidental charges as per SS as directed by the departmental engineer in charge of the work.
180
-
200417.4