To know what Andhra Pradesh government has posted about any AP etender, Bidassist helps us to get a one-stop platform where a registered bidder can have access to the details on each and every eprocurement tender. There is no need to provide the details on the AP E-procurement website i.e. https://www.apeprocurement.gov.in as BidAssist helps us find the specific etender we're looking for. BidAassist has collated each and every Eproc Andhra Pradesh Tender on its website.
Andhra Pradesh Education And Welfare Infrastructure Development Corporation - APEWIDC Tender
Civil And Construction
Building Construction
Opening Date1 Jan 2024
Closing Date8 Jan 2024
Tender Amount₹ 7,73,930
Costs
EMD
₹ 7,739Document Cost
Refer DocumentsTender Fee
₹ 11,800
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
705415Tender No
175/2023-24, Dt:29.12.2023Tender Authority
Andhra Pradesh Education And Welfare Infrastructure Development Corporation ViewPurchaser Address
-Website
http://tender.apeprocurement.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
... More
Filling with useful available excavated earth (excluding rock) in trenches, sides of foundations and basement with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming including all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)
9
258
28.7
... More
Vibrated Reinforced Cement Concrete M 25 Design Mix (by weigh batching) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs.of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for Footings (APSS No. 402 & 403)
1.1
10402
9455.94
... More
Vibrated Reinforced Cement Concrete M 25 Design Mix (by weigh batching) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs.of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering, machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for Pedastals (APSS No. 402 & 403)
0.25
2479
9916.89
... More
Vibrated Reinforced Cement Concrete M 25 Design Mix (by weigh batching) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs.of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for Plinthbeam (APSS No. 402 & 403)
0.1
1166
11660.94
... More
Vibrated Reinforced Cement Concrete M 25 Design Mix (by weigh batching) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs.of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering, machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for Columns for Ground Floor (APSS No. 402 & 403)
1
11174
11173.66
... More
Vibrated Reinforced Cement Concrete M 25 Design Mix (by weigh batching) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs.of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering, machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for Columns in First Floor (APSS No. 402 & 403)
2.8
34879
12456.72
... More
Vibrated Reinforced Cement Concrete M 25 Design Mix (by weigh batching) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs.of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering, machine mixing, laying concrete, vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for Beams for Ground Floor (APSS No. 402 & 403)
0.2
1922
9609.84
... More
Vibrated Reinforced Cement Concrete M 25 Design Mix (by weigh batching) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs.of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering, machine mixing, laying concrete, vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for Roof Slab 125 mm thick for Ground Floor (APSS No. 402 & 403)
13
15242
1172.48
... More
Reinforced Cement Concrete M 25 Design Mix (by weigh batching) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs.of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering, machine mixing, laying concrete, vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for Lintels for First Floor (APSS No. 402 & 403)
0.3
3409
11362.22
... More
Reinforced Cement Concrete M 25 Design Mix (by weigh batching) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs.of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering, machine mixing, laying concrete, vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for Sunshade 0.60mm wide for First Floor (APSS No. 402 & 403)
5
4839
967.75
... More
Brick Masonry in superstructure with CM (1:8) prop: using second class bricks from approved source having minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work for GF. (APSS No. 501 & 504)
2
13936
6968.03
... More
Brick Masonry in superstructure with CM (1:8) prop: using second class bricks from approved source having minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work in First Floor. (APSS No. 501 & 504)
20.5
149487
7292.03
... More
Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to (1:3:6) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size HBG (SS5) metal from from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing, laying, curing concrete, etc., complete for finished item of work for bed blocks in First Floor (APSS No. 402)
0.2
1162
5809.44
... More
Vibrated Reinforced Cement Concrete M 25 Design Mix (by weigh batching) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs.of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering, machine mixing, laying concrete, vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for Tie Beams in First Floor (APSS No. 402 & 403)
0.5
5681
11362.22
... More
Providing high yield strength deformed (HYSD) steel bars (Fe 500 grade as per IS 1786-1985) of different diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of approved size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs and drawings including cost and conveyance of bars from approved sources to site of work, including cost and conveyance of binding wire, cover blocks and all operational, incidental, and labour charges such as cutting, bending, placing in position, tying etc., and sales & other taxes,on cost of all materials complete for finished item of work (APSS No.126) in ground floor
0.5
40558
81116.09
... More
Providing high yield strength deformed (HYSD) steel bars (Fe 500 grade as per IS 1786-1985) of different diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of approved size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs and drawings including cost and conveyance of bars from approved sources to site of work, including cost and conveyance of binding wire, cover blocks and all operational, incidental, and labour charges such as cutting, bending, placing in position, tying etc., and sales & other taxes,on cost of all materials complete for finished item of work (APSS No.126) in First floors.
0.4
32935
82337.24
... More
Ornamental plastering to ceiling 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat of 4mm thick in CM (1:3) with dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing mortar, finishing, scaffolding, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, curing, etc., complete for finished item of work in Ground Floor. (APSS 901, 903 & 904).
15
6153
410.21
... More
Ornamental plastering to ceiling 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat of 4mm thick in CM (1:3) with dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing mortar, finishing, scaffolding, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, curing, etc., complete for finished item of work in First Floor. (APSS 901, 903 & 904).
3
1356
452.06
... More
Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, seigniorage charges, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer -in- charge, finishing, curing, etc., complete for finished item of work in Ground Floor. (APSS 901,903 & 904)
20
7906
395.28
... More
Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, seigniorage charges, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer -in- charge, finishing, curing, etc., complete for finished item of work in First Floor. (APSS 901,903 & 904)
94
40749
433.5
... More
Plastering 20mm thick in two coats with base coat of 16mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing mortar,scaffolding charges, lift charges, finishing,including cutting of Grooves wherever necessary as directed by Engineer - in - charge, curing, etc., complete for finished item of work in Ground Floor. (APSS 901,903 & 904)
25
10340
413.61
... More
Plastering 20mm thick in two coats with base coat of 16mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing mortar,scaffolding charges, lift charges, finishing,including cutting of Grooves wherever necessary as directed by Engineer -in- charge, curing, etc., complete for finished item of work in First Floor. (APSS 901,903 & 904)
100
45183
451.83
... More
In -situ- Granolithic Concrete Flooring 20mm thick with CC(1:1:2) Prop: using 6mm to 12mm size HBG machine crushed metal laid monolithically over 100mm thick CC flooring bed (1:5:10) with 40mm HBG metal in alternate panels of size not exceeding 1.50m x 1.50m and finishing the top surface to required smoothness and slopes, thread lining as directed by the Engineer-in-charge including cost and conveyance of all materials like cement, sand, water, etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges such as mixing of cement concrete, laying, curing, lift charges etc., complete for finished item of work (APSS No.701 & 710)
47
37775
803.72
... More
Supply & fixing of Flush Door with double shutter of size 1.22x2.13 mtrs using Medium teak wood frame of size 75x100mm for horizontals & verticals with flush door shutter of 35mm thick solid bond wood block board type with commercial play on both faces including cost and conveyance of all materials and fixtures such as 6 nos.of 300mm long MS Z Hold Fasts, 6 Nos.of 125mm long MS Butt hinges, 2 nos.of 250mm long Aluminum Tower bolts, 1 No.of 300mm long Aluminum Alldrop, 2 Nos.of 150mm long Aluminum Handles & 2 Nos.of Door stoppers including all labour charges for fixing in position etc., complete for finished item of work
1
10622
10622.07
... More
Providing and fixing of Openable Windows with Fly-mesh made of pre-painted steel (Base steel as per IS 513 of 0.60mm thick galvanized as per IS 277 with Zinc if 150 GSM), primer coated with epoxy primer of 5-7 microns thick, finish painted with a polyster paint of 12-16 microns thick and back coated with 5-7 microns thick alkyd backer and section for outer frame of 72x55 mm, centre mullion of 72x50mm, section for fixed glass beading section should be 12x12mm and section for shutters of 47x20mm and outer frame and mullions sections with rebate for glazed shutters, fly mesh and a 20mm provision for guard bars / grills and fly mesh shutter sections of 20x40mm and the sections cut to length meter jointed with corner bracket, centre mullion fixed with mullion cap, handle, stay, 2 nos, of stainless steel heavy duty pivot hinges provided per shutter and panelled with 4mm thick plain headed glass and S.S.Mesh for fly mesh shutter (304 grade), fitted using rubber gaskets including fixing the windows in the concrete / masonry wall by means of self expanding screws, including 10mm Square guard bars with 6" (152.4mm) pitch etc.., complete for finished item of work (Center fixed both side openble shutter outer frame of size 72x50mm and shutter frame 48x25mm mullion section size of 72x50 mm and fixed beeding section of 12x12mm).
6
37151
6191.85
... More
Whiting to walls and ceiling in two coats with Birla / Surya cem or equavalent quality to give an even shade after thoroughly brushing the surface to remove all loose powdered materials including cost and conveyance of all materials and water to site, sales & other taxes, all operational, incidental and labour charges such as cleaning the surface, painting, curing etc., complete for finished item of work for internal walls. (APSS No.901 & 908)
257
8879
34.55
... More
Painting to Wood work with two coats of ready mixed synthetic enamel paint first quality all shades over a base coat of wood primer with Luppam Finishing in all to give an even shade after thouroughky brushing the surface to remove all reamains of loose powdered materials including cost and conveyance of all materials to site, sales & other taxes, incidental, operational and all labour charges etc., complete for finished item of work. (APSS No. 1201, 1207 & 1212)
8
1444
180.53
... More
Painting to New iron work with two coats of ready mixed synthetic enamel paint first quality all shades over an existing steel primer including cost and conveyance of all materials to site, sales & other taxes, incidental, operational and all labour charges etc., complete for finished item of work. (APSS No. 1201, 1207 & 1212).
23.5
2380
101.29
... More
Roofing:- Roofing will be provided with 0.5mm thick Galvinized / Prepainted GI Profile Sheets fixed to the purlins with 14mm size self drilling screws with neoprene washers, side laps or stiched with self taping / drilling scrwos, end laps are to seeled with 25x3mm botyl tape. The sheets are provided with anti campillary grove Including cost and conveyance of all materials and all labour charges etc.., complete for finished item of work.
64.5
56618
877.8
... More
supply and Fixing MS Purlins 50 mm dia mediam grade including Labour Charges for fixing complete including cost and conveyance of all materials to site, sales and other taxes all labour charges etc., complete for finished item of work
65
34982
538.18
... More
Providing and fixing Thermocole False Ceiling in true horizental level 600mm x 600mm using 19 mm thick Thermocole sheet anodised Aluminium Tee Sections of size 24.50mm x 24.00mm x 2.4mm in grid with cross tee of size 24x24.50mm at every 600 mm C/C and adnodised aluminium wall angle of size 24x24 mm fixed to periphery of the wall and the above gid is suspended at every 1200 mm c/c in both directions using 2.0mm thick GI wire for finished of size 600 x 600 mm including cost and conveyance of all materials and labour charges such as cutting. fixing of standing of frame work exposing roof making complete for finished item of work
45.9
40841
889.79
... More
Electrification
-
-
-
... More
Supply and fixing of 25mm dia using 2.20mm thick PVC pipe (ISI) Mark concealed Ceiling with all required accessories including masonary work and labour charges etc., complete including cost and conveyance of all materials and all labour charges etc.., complete for finished item of work Make Sudhakar/ Marqury plast/ Avon plast
60
5355
89.25
... More
Supply and fixing of 25mm dia using 1.80mm thick PVC pipe (ISI) Mark concealed wall with all required accessories including masonary work for light fan and separate plug point with well seasoned wooden deep box including all labour charges etc., complete including cost and conveyance of all materials and all labour charges
100
10551
105.51
... More
Supply and erecting of MS Galvanised fan hook box with hook in RCC slab including all labour charges etc.., complete
4
420
105
... More
Wiring with 2 runs of 22/0.3 mm (1.50sq.mm) fire Retardant (FR) PVC insulated fexible copper cable (ISI Make) and 1 run of 1.50sqmm of 22/0.3mm flexible copper cable for run of earth in existing pipe with 6 A one way one modular switch, modular ceiling rose, and 8 modular covering plate to switch control box including all labour charges etc., complete for modular light, bell, fan and exhaust fan points, in NON -Residential Building .
15
11114
740.95
... More
Supply and fixing of 6A ISI Mark 3/2 pin modular socket with 6A 1 Way 1 Modular switch, 3 Module box with cover frame and GI switch box on common switch board with connections etc., complete for finished item of work.
Accessories Makes: Legrand Lyncus / Havells Coral or Fabio / L&T / HPL / Schneider Livia / GM-(G Nine / GX) C&S/Goldmedal (Curve / Air) / Million Mway / Logus Platina / Panasonic VIsion / Salzer S90 series / Precision / Koncept (Smart / Qura) / Polycab (Levana) / Anchor - Roma/ Indoasian / Pointer
2
504
251.75
... More
Supply and fixing of 16A / 6A Modular type power outlet 6 Nos with front cover plates including 16A socket 1 No., 16A switch 1No., 6A sockets 2 Nos., 6A switches 2 Nos and 8 Module Hot Dip Galvanized Modular Metal Box size covered with 6 Modular Cover Frame including earth connections and all labour charges etc., complete for finished item of work.
4
4092
1022.96
... More
Supply and run of 1 of 1.5 sq.mm ( 22/0.30 ) PVC insulated flexible copper cable in existing MS conduit pipe for circuits including labour charges (phase neutral and earth) etc., complete as required for switch board circuit mains.
30
936
31.21
... More
Supply and run of 3 of 2.5 sq.mm ( 36/0.30 face, nutral & earth) PVC insulated flexible copper cable in existing MS conduit pipe for circuits including labour charges (phase neutral and earth) etc., complete as required for switch board circuit mains.
100
12869
128.69
... More
Supply and run of 3 of 4.00 sq.mm ( 56/0.30 face, nutral & earth) PVC insulated flexible copper cable in existing MS conduit pipe for circuits including labour charges (phase neutral and earth) etc., complete as required for switch board circuit mains.
60
11078
184.64
... More
Supply and fixing (8+12) 4 Way TPN Distribution board Horizontal with IP-43 protection suitable for 12 Nos S.P. out goings and supply and fixing of 1 No.of 32A FP MCB as incomer and 12 Nos 6-32A 10kA SP MCBs for 1 No 4 pole incommer etc.., complete as per IS 8623: IS 13032; IEC 61439-3 Makes: Makes: Legrand (Ekinox 3) / Schneider-A9/ Hanger - Novello + / Seimens / Havells STADx / L&T- Newranges and labour charges for FLUSH mouning etc.., complete for finished item of work.
1
10452
10451.7
... More
Providing independent earthing by excavating a trench to a depth of 2.1M in all soils, as per size specificified in the Data, using 40mm dia 'B' class GI pipe of 2.5Mtrs length with necessary accessories with hume pipe ring duly providing staggered holes including filling with equal proportion of Salt and Charcoal in layera and all labour charges etc.., complete for small quarters.
1
5438
5437.73
... More
Supply and run of No.8 SWG G.I.wire including cost of all accessories and labour charges etc.., complete
5
470
93.9
... More
Supply and run of 25mm x 6mm G.I Strip including cost of all accessories and labour charges etc.., complete
5
517
103.3
... More
Supply, Fixing and transportation of 20W/24W, not less than 1100mm length LED batten light with extruded alluminium housing and polycarbonate cover, input voltage AC 220-260 Volts with PF0.9, Surge protection:2KV,THD15%, with inbuilt driver and forsted cover CCT: 3000K - 5700K, minimum CRI70, etc.., complete. with Fixing of 18W/20W LED luminaire on wall / Ceiling with TW round blocks with all accessories including giving connections and all labour charges etc.., complete.
LUMINAIRE MAKE: Philips /GE-Venture/ Crompton / Wipro / Bajaj / Havells / Halonix / Jaquar / HPL/GM/Green LItes/Gold Medal/Evereday b) LED MAKE: Philips Lumileds / CREE / NICHIA / OSRAM SAMSUNG / Everlight.
6
4637
772.8
... More
Supply and fixing of Batten holder/slenting holder in lieu of ceiling rose of light point and fixing of 0.50 W LED Lamp complete with all connection and labour charges etc., complete .for finished item of work
5
684
136.76
... More
Supply of 1200 mm (48" ) sweep 230V AC 50Hz High Speed ceiling fan with three blades and double ball bearings croption make with all standard accessories etc., including cost and conveyance of all materials andall lablur charges etc., complete
4
10741
2685.19
... More
Supply and fixing of Electronic step type modular regulator for ceiling fans 1200mm sweep complete erected on existing board including and giving connections complete including all lablur charges etc., complete for finished item of work.
4
1688
422.1
... More
Labour charges for fixing of ceiling fan and regulator including transportation and giving connections with twin core wire etc.., complete
4
716
179.1
... More
Supply and fixing of fresh air exhaust fan of heavy duty 250V A.C.50Hz. 300mm size (12") 900 R.P.M. etc.. on wall with necessary connections including cost and conveyance of all materials and all lablur charges etc., complete
1
1947
1947.08
... More
Labour charges for fixing of exhaust fan and regulator including transportation and giving connections with twin core wire etc.., complete
1
773
773