Andhra Pradesh Education And Welfare Infrastructure Development Corporation Tender

To know what Andhra Pradesh government has posted about any AP etender, Bidassist helps us to get a one-stop platform where a registered bidder can have access to the details on each and every eprocurement tender. There is no need to provide the details on the AP E-procurement website i.e. https://www.apeprocurement.gov.in as BidAssist helps us find the specific etender we're looking for. BidAassist has collated each and every Eproc Andhra Pradesh Tender on its website.

Andhra Pradesh Education And Welfare Infrastructure Development Corporation - APEWIDC Tender

Civil And Construction
Building Construction
Opening Date3 Apr 2023
Closing Date11 Apr 2023
Tender Amount₹ 16,12,086 
Notes
Download

Costs

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard blasted Granite stones from approved quarry including c/c like Granite stones, cement, sand, water, etc., to site including seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such as cutting stones to required size and shape, mixing of cement mortar, constructing masonry, curing etc., complete for finished item of work for foundation and basement (APSS No. 601 & 615)

10.43

39240

3762.25

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for footings

3.88

38541

9933.45

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for PEDASTALS

2

20305

10132.25

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using , laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) fo columns

4.16

47812

11493.28

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using S laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for plinth beam

3.85

46274

12019.35

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for Roof beam

3.7

36259

9799.96

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering usinglaying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for 115mm Thick Roof Slab

59.05

66743

1130.28

... More
Filling with Gravel in trenches, sides of foundations and basement with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming including cost and conveyence of water to the work site and all operational, incidental, labour charges, seignorage charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)

127.25

57205

449.55

... More
Filling with Sand in trenches, sides of foundations with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming including cost and conveyence of water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)

62.07

87112

1403.45

... More
Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work (APSS No. 402 & 403) for sunshade

10.11

8177

808.9

... More
Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work (APSS No. 402 & 403) for Lintel

0.69

7689

11143.99

... More
Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size 290x225x140mm with compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials like cement, sand, fly ash bricks, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).

15.63

110593

7075.75

... More
Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall but excluding seigniorage charges for finished item of work. (APSS 901,903 & 904)

63.6

28034

440.8

... More
Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, seigniorage charges, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 & 904. Internal walls

108.26

45978

424.7

... More
Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, seigniorage charges, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 & 904 for External walls

123.03

52250

424.7

... More
Flooring with High Polished Granite stones minimum of 15 mm thick set over a base coat of CM (1:8), 12mm thick (joints of stone must be flushed) over C.C. bed already laid or R.C.C. roof slab only after it is properly cured, cleaned, moistered and where necessary treated with neat grey cement slurry of honey like consistency spred at3.3 kgs of cement for 1 sqm. and jointed with neat cement paste to full depth, including cost and conveyance of all materials like cement, sand, water, flooring stones etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges such as dressing of flooring stones to the required sizes, mixing of cement mortar, laying, jointing, curing, lift charges etc., complete for finished item of work.(APSS No.703 & 701)

47.52

158655

3338.7

... More
Providing skirting to internal walls 12.5 Cm high with Polished Kadapa slabs minimum of 16 TO 18 mm thick ) with length equal to flooring stones set over a base coat of CM (1:3), 12mm thick with cement slurry of honey like consistency spread @ 3.3 Kgs per sqm and jointed with neat cement paste mixed with pigment of matching shade to full depth (joints of stone should be flushed), including cost and conveyance of all materials like cement, sand, water, flooring stones etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges such as dressing of flooring stones to the required sizes, mixing of cement mortar, laying, jointing, curing, lift charges etc., complete for finished item of work.(APSS No.701 & 707)

2.85

8198

2876.5

... More
Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs with Medium teak wood Frame of sections size 75mm x 100mm with Flush Door Shutter Solid Bond Wood block board type with commercial ply on both faces of 35mm thick including cost of fixtures such as Aluminium Tower Bolts 250mm long 2 Nos, Aluminium Handles 150mm long 2 Nos, 300mm long Aluminium Aldrops 1No, 125 mm long M.S.Powder Coated butt hinges 6Nos, 300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold fasts 6Nos 300mm long including cost and convenyance of all materials to site all Labour charges such as Fixing of Door Frame and shutter Fixing in position , with Hardware fixtures etc., complete for finsihed item of work.

1

11509

11509.5

... More
Supply and Fixing of Door with Double leaf shutter, Door Size 1.05x2.13 mtrs with medium teak wood Frame of sections size 75mm x 100mm with Flush Door Shutter Solid Bond Wood black board type with commercial ply on both faces of 35mm thick including cost of fixtures such as Alluminium Tower Bolts 250mm long 2 Nos, Alluminium Handles 150mm long 2 Nos, 300mm long Alluminium Aldrops 1No, 125mm long M.S.Powder Coated butt hinges 6Nos, 300 mm long Alluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold fasts 6Nos including cost and convenyance of all materials to site all Labour charges such as Fixing of Door Frame on shutter Fixing in position , with Hardware fixtures etc., complete for finsihed item of work.

3

44188

14729.57

... More
Supply and Fixing of Ventilator of size 1.52 x 0.3 with 32mm x 32mm x 5mm thick equal L angles and 10mm square rods (4H+6V) fixing in position ,complete for finsihed item of work

3

3005

1001.75

... More
Supply and Fixing of Ventilator of size 1.22 x 0.45 with 32mm x32mm x 5 mm thick equal L angles and 10mm square rods (4H+4V) fixing in position ,complete for finsihed item of work

1

818

818.7

... More
Supply and Fixing of Grill Door cum Grill of size2.80 x 2.80 mts with outer angular frame of rolled steel equal angle 35x35x6m and inner shutter angular frame rolled steel equal angle 35 x 35 x 6 mm, MS aldrop 300mm long-2No ,MS Heay Hinges 75mm long-4No safety rods of 10mm Square rods with primary coat of Red oxide paint including cost,conveyance of all materials to site ,sales and other taxes on all materials and labour charges etc complete

180

17656

98.09

... More
Supplying and finishing of Birla ready mix wall putty or equivalent brand) to interior faces of new walls and ceiling of approved colour as per manufacturers specification including cost and conveyance of materials to site and labour charges such as preparing the wall, applying primary coat etc, complete including of Painting with Acrylic emulsion paint of dulux supreme 3 in a or equivalent brand to interior faces of new walls and ceiling with two coats of approved make, shade and colour over a base coat of primer approved make including cost and conveyance of materials like Acrylic emulsion etc., to site and labour charges such as preparing the wall, applying primary coat, applying two coats of Acrylic emulsion etc., sales and other taxes on cost of all materials, complete for finished item of work in all floors as directed by Engineer-in-charge.

159.88

23523

147.13

... More
Painting to New walls with two coats of acrylic emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/liter of superior quality of approved brand and shade over base coat of cement primer grade -I making three coats in all to give an even shade after thoroughly brushing the surface to remove all loose powdered materials, including cost and conveyance of all materials, including cost and conveyance of all materials, cost of brushes, water to site, etc., sales & other taxes, all operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in all floors for Walls.(APSS No. 911) in All Floors Internal walls and Ceiling

152.23

25620

168.3

... More
Painting to New walls with two coats of acrylic emulsion paint weather proof waterbased, modified acrylic with silicon additives exterior grade having VOC (Volatile Organic Compound ) content less than 50 grams/ liter of superior quality of approved brand and shade over base coat of cement primer grade -I making three coats in all to give an even shade after thoroughly brushing the surface to remove all loose powdered materials, including cost and conveyance of all materials, including cost and conveyance of all materials, cost of brushes, water to site, etc., sales & other taxes, all operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in all floors for Walls.(APSS No. 911) fo EXTERNAL

123.03

28143

228.75

... More
Painting to New Iron work with two coats of ready mixed Synthetic Enamel paints in all shades Grade - I having VOC (Volatile Organic Compound ) content less than 50 grams/ liter over an existing steel primer including cost and conveyance of all materials to site, sales & other taxes, incidental, operational and all labour charges etc., complete for finished item of work. (APSS No. 1201, 1207 & 1212).in All Floors

18.9

2071

109.6

... More
Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of approved size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs and drawings including cost and conveyance of bars from approved sources to site of work, including cost and conveyance of binding wire, cover blocks, chairs, overlaps, spacers, dowels, wastage etc., and all operational, incidental, and labour charges such as cutting, bending, placing in position, tying etc., and sales & other taxes,on cost of all materials complete for finished item of work (APSS No.126) in all floors.

2.5

228375

91350.34

... More
Supply and fixing of 25mm dia 2.2mm thick P.V.C. pipe (ISI Mark) concealed in Roof Slabs with all required accessories including masonary work and labour charges including over heads and contractors profit but excluding seigniorage charges for finished item of work.

90

6583

73.15

... More
Supply and fixing of 25mm dia 1.8mm thick P.V.C. pipe (ISI Mark) concealed in wall with all required accessories including masonary work and labour charges including over heads and contractors profit but excluding seigniorage charges for finished item of work.

30

3072

102.4

... More
Wiring with run of 2 of 22/0.3mm (1.5 Sqmm) FRLS / HFFR / ZHFR PVC insulated flexible ISI mark copper cable in existing PVC conduit pipe including Supply and fixing of Jumbo Ceiling rose/BH /SBH and 6A/10A ISI Mark 1way Modular switch with required modular box and cover frame in existing Surface or Concealed pipe wiring including cost and conveyance of all material and all labour charges etc., complete for light and bell points in N.R.B. Copper cable Makes: Gloster/ Polycab / Bonton / V-Guard

7

5096

728.1

... More
Supply and fixing of 1 No. of 6A / 10A 1 Way Modular Switch with 6A / 10A 3/2 Pin Modular Socket with shutter & 1 No of 16A / 20A 1 Way Modular switch with 16A/6A 1 way Combi Modular Socket with shutter on the suitable size Modular box with required cover frame including cost and conveyance of all material and all labour charges etc., complete.

1

905

905.55

... More
Supply of 1 x 36/40W Box type tube light luminaire powder coated CRCA sheet steel housing with Electronic Ballast Chokes and all standard accessories with 36/40W tube. Makes: Wipro / G.E. / Phillips / Crompton / Bajaj/Havells/HPL/Halonix

3

3329

1109.95

... More
Supply and fixing of 4' - 28 w weatherproof streetlight fitting comprising canopy of sheet aluminium in stove enamel finish with energy saving Electronic ballast and 1 no 40/36 W Tube Light to the pole / wall with suitable length of G.I pipe bracket massonry work etc., complete with connections as required at site.

1

1362

1362.25

... More
Supply of 1200mm (48") Sweep 230V, A.C 50 Hz Ceiling Fan with 3 blades and double ball bearings with all standard accseeories including over heads and contractors profit but excluding seigniorage charges and VAT for finished item of work.

4

8080

2020

... More
Labour charges for fixing of ceiling fan and regulator including transportation and giving connections with twin core wire including over heads and contractors profit but excluding seigniorage charges and VAT for finished item of work.

4

555

138.88

... More
Supply and fixing of batten holder / slanting holder in lieu of ceiling rose of light point complete with all connections and all labour charges with 13W CFL bulb (for new installation) including over heads and contractors profit but excluding seigniorage charges and VAT for finished item of work.

2

283

141.75

... More
Providing independent earthing by excavating a trench to a depth of 2.1M in all soils, as per size specified in the Data, using 40mm dia. 'B' class GI pipe of 2.5 Mtrs Length with necessary accessories with hume pipe ring duly providing staggered holes including filling with equal proportion of Salt and Charcoal in layers and all labour charges etc., complete for small quarters.

1

6190

6190.45

... More
Supply and fixing TPN Distribution board with IP-42 protection (Metal Door) suitable for 3 phase ELCB / RCCB / FP Isolator as incomer and 10kA SP MCBs as outing going including internal connection and labour charges for surface / flush mounting etc., complete.

1

9999

9999.4

... More
Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Loamy & Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour charges such as shoring, strutting, sheeting, planking and dewatering including cost of hire charges of T & P, labour charges etc., complete for finished item of work including seignerage charges excluding dewatering charges etc., complete for Foundation of Building.(APSS No. 308) for Toilet block

20.18

4382

217.15

... More
Plain Cement Concrete corresponding to M7.5 grade as per IS 456 equivalent to (1:4:8) proportion nominal mix (C:FA:CA) using 40mm size HBG (IS383, 1970) metal from approved quarry including c/c like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top surface, curing concrete, etc., complete for finished item of work for Foundations (APSS No. 402)

0.9

3883

4315.3

... More
Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5:10) proportion nominal mix (C:FA:CA) using 40mm size HBG (IS383, 1970) metal from approved quarry including c/c like cement, sand, coarse aggregate, water etc. to site, seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top surface, curing concrete, etc., complete for finished item of work for Foundations and Flooring Bed (APSS No. 402)

1.9

7903

4159.95

... More
Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard blasted Granite stones from approved quarry including c/c like Granite stones, cement, sand, water, etc., to site including seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such as cutting stones to required size and shape, mixing of cement mortar, constructing masonry, curing etc., complete for finished item of work for foundation and basement (APSS No. 601 & 615)

2.05

7712

3762.25

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for Footings

1.21

11656

9633.45

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for Pedastals

0.42

4255

10132.25

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using aying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for Columns

0.7

8045

11493.22

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for Plinth beam

0.8

9615

12019.35

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates, etc.,, shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for Roof beam

0.8

7840

9800

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates, etc.,, shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for Roof slab 115mm thick

14.4

16276

1130.3

... More
Filling with Gravel in trenches, sides of foundations and basement with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming including cost and conveyence of water to the work site and all operational, incidental, labour charges, seignorage charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)

9.91

4455

449.55

... More
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates, etc.,, shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work. (APSS No. 402 & 403) for Lintel

0.05

557

11143.99

... More
Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size 290x225x140mm with compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials like cement, sand, fly ash bricks, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).

7.87

55686

7075.75

... More
Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall but excluding seigniorage charges for finished item of work. (APSS 901,903 & 904

11.12

4901

440.8

... More
Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, seigniorage charges, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 & 904. Internal walls

35.44

15051

424.7

... More
Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, seigniorage charges, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 & 904 for External walls

52.67

22368

424.7

... More
Supply and Fixing MS GRILLS including Labour Charges for fixing complete including cost and conveyance of all materials to site, sales and other taxes, all labour charges etc., complete for finished item of work

60

5885

98.09

... More
Painting to New walls with two coats of acrylic emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/liter of superior quality of approved brand and shade over base coat of cement primer grade -I making three coats in all to give an even shade after thoroughly brushing the surface to remove all loose powdered materials, including cost and conveyance of all materials, including cost and conveyance of all materials, cost of brushes, water to site, etc., sales & other taxes, all operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in all floors for Walls.(APSS No. 911) in All Floors Internal walls and Ceiling

6.47

1088

168.3

... More
Painting to New walls with two coats of acrylic emulsion paint weather proof waterbased, modified acrylic with silicon additives exterior grade having VOC (Volatile Organic Compound ) content less than 50 grams/ liter of superior quality of approved brand and shade over base coat of cement primer grade -I making three coats in all to give an even shade after thoroughly brushing the surface to remove all loose powdered materials, including cost and conveyance of all materials, including cost and conveyance of all materials, cost of brushes, water to site, etc., sales & other taxes, all operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in all floors for Walls.(APSS No. 911) fo EXTERNAL

60.55

13850

228.75

... More
Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of approved size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs and drawings including cost and conveyance of bars from approved sources to site of work, including cost and conveyance of binding wire, cover blocks, chairs, overlaps, spacers, dowels, wastage etc., and all operational, incidental, and labour charges such as cutting, bending, placing in position, tying etc., and sales & other taxes,on cost of all materials complete for finished item of work (APSS No.126) in all floors.

0.5

45675

91350.35



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.