The PHED has issued a formal invitation for competitive bids for the Public Health Engineering Department project, for Wbphed/ee/md/niet_12 Of 2025-2026, Sl.no.16 in Malda, West Bengal, with an estimated contract value of Rs. 61,34,600. The bid opening date for this tender is 30-04-2025 and the last date for bid submission is 16-06-2025. Interested bidders for Public Health Engineering Department tender can download the important documents here to check the scope of work, eligibility criteria and technical requirements.

Public Health Engineering Department - PHED Tender

Works
Civil And Construction
Civil Works Others
Eprocure
Opening Date30 Apr 2025
Closing Date16 Jun 2025
Tender Amount₹ 61,34,600 
Notes
Download

Costs

Summary

Wbphed/ee/md/niet_12 Of 2025-2026, Sl.no.16

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Iron door ring of approved quality fitted and fixed with nut and washer complete. A) 50 mm dia

4

17

68

... More
Making flange joint to DI/CI pipes, specials and valves where necessary with supply of required rubber insertion and nut bolts, washers etc. of approved quality and type all complete as per specification and direction of EIC (Nut and bolts shall be of TATA/GKW make).

-

-

-

... More
a) 160 mm(OD)

160

1

276.8

... More
(a) Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc.

10

29

290

... More
Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in ground floor as per relevant IS codes.

4.5

5011

22552.43

... More
(b)40mmx6mm. 125 mm length.

8

20

160

... More
Supply & delivery of following nominal sizes C.I. Specials as per I.S. 1538 ( Part XXI ) 1976 with latest amendment up to date including all taxes & other incedental charges what so ever, carriage, loading unloading & stacking as per direction of EIC.(as per site requirement).

-

-

-

... More
Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in ground floor as per relevant IS codes. a) Pakur Variety

195

5055

985884.9

... More
(A) Pressure Rating : Class - III (ii) Laying of pipe line including cost of pipe & fittings /specials but excluding cost of valves.

-

-

-

... More
Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc.

7.2

29

208.8

... More
Plaster to wall, floor etc with sand and cement morter (1:6) including rounding off or champhering corners as directed and racking out joints or roughing of concrete surface including throating, nosing and drip course where necessary (In all floors).

-

-

-

... More
b) on steel or other metal surface. iv) Two coats ( with any shade except white).

20

79

1580

... More
Cleaning thoroughly the inner surface of pipe line including specials and valves by flushing with water and subsequently disinfection of the same pipe line by flushing again with water containing bleaching powder resulting in residual chlorine not less than 15mg/ltrs. after 24hrs. of such filling including laboratory testing of water samples obtain from the disinfested pipe line and disposal of water from the pipe line after completion of the work. The rates including of cost of requisite water to be arranged by the contractor) (The rate of water @Rs. 10/m3 may be recovered, if the contractor used water from deptt. source).

-

-

-

... More
b) 80x15cm.Long C.l.D.F.Short Piece

10.37

61

632.57

... More
a) 160 mm(OD)

160

974

155840

... More
Cleaning thoroughly the inner surface of pipe line including specials and valves by flushing with water and subsequently disinfection of the same pipe line by flushing again with water containing bleaching powder resulting in residual chlorine not less than 15mg/ltrs. after 24hrs. of such filling including laboratory testing of water samples obtain from the disinfested pipe line and disposal of water from the pipe line after completion of the work. The rates including of cost of requisite water to be arranged by the contractor) (The rate of water @Rs. 10/m3 may be recovered, if the contractor used water from deptt. source).

-

-

-

... More
Construction of different dia Sluice valve /Air valve /Washout chamber in different sizes for village road where light traffic run and for main road where heavy traffic run as deptt.approved drawing with 25cm thick brick work (1:6) over cement concrete (4:2:1) over a single B/F soling over150mm.thick sand filling in foundation including earth work in excavation and disposal of excess earth from work site with RCC (1:1.5:3) cover slab 100mm / 150mm thick slab on top of chamber with 1% reinforcement in roof slab including supply of 150mmx150mm C.I. surface box embedded into RCC cover slab all complete including cost of labour & materials.

-

-

-

... More
Single brick flat soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with powdered earth or local sand.

70

322

22540

... More
d) 90 mm(OD)

900

342

307800

... More
a) 160 mm(OD)

160

4

764.8

... More
(a) with 100mm thick RCC cover slab for village road where light traffic run.

-

-

-

... More
c) 110 mm dia

250

3

945

... More
Supplying anodised aluminium catch hook with eye fitted and fixed to shutter and chowkat complete of best quality: (i) 150mm long.

4

37

148

... More
Earthwork in excavation in foundation trenches or drain in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading & stacking the spoil within a lead of 75m as directed. The item includes necessary trimming the sides of trenches. Levelling, dressing and ramming the bottom, bailing out of water as required complete. (a) Depth of excavation not exceeding 1500 mm.

5

119

596.35

... More
Carriage of different type of departmental pipes from Divisional/Sub-divisional store to the work site by truck including loading, unloading, stacking etc. including cost of fuel, lubricant and also cost of driver, helper etc. and all other taxes and charges as applicable as per direction of EIC

-

-

-

... More
Extra for work in grill gate: For hanging and locking arrangements including supply of materials and labour complete.

250

14

3685

... More
Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. (i) Pakur Variety. (Ref: P-26, It-10i PWD SOR) 3rd Corrigendum, Pg-13, it-33.i

11

5516

60676.33

... More
N.B. i) Manufacturer’s test certificate for UPVC pipe & specials to be produced before laying of pipe line. ii) 3rd party inspection of UPVC pipe & specials to be done by CEPET or (India) SGS/NTH Kolkata or as per direction of EIC as per approved vender list. iii) No part payment at any stage on account of supply of materials shall be entertained. iv) Payment will be made on actual consumption of materials. v) UPVC pipes for the works to be supplied as per approved vendor list and as per direction & satisfaction of EIC. No pipes will be allowed beyond recommendated vendor list. vi) Submission of drawing of pipe line with statement of materials consumed between node to node points against each R.A. & final bill.if so. vii) Any deviation from required clear cover of 1.10mtr.due to site adverse condition, prior permission is to be obtained from EIC and payment for such work will be made on prorate basis over the rate of entire item. viii) All pipe connection shall be completed in all respect and as per directionof EIC. Decision of EIC in this respect is final & binding. In case of any deviation/or any left out pipe connections an amount of Rs.10,000.00 for each pipe connection will be realized/recovered from the bill. ix) No payment will be made without hydraulic test of the pipe line either part or full

-

-

-

... More
Dismantling all type of plain cement concrete works, stacking serviceable materials of site and removing rubbish as directed within a lead of 75mtr. for laying all dia pipe line in ground floor, a) upto 150mm thick.

195

939

183105

... More
Filling the pipe line with water, testing hydraulically as per I.S 3114-1965 (Article-6) in section of a length not exceeding 500mtr. for head of pressure as per specification including supplying installing and fixing all equipments such as diesel pump set, blank flange, pressure gauge, valve, pressure pump and all other tools and plants including drilling topping and plugging of necessary holes to pipes, blocking ends providing temporary thrust block and subsequent blocking of holes and other jointing materials and dismantling and removal of the same including disposal of water etc. all complete as per specification and direction of EIC. The rate is inclusive of cost of requisite water to be arranged by the contractor (Recovery rate of water @ Rs.10.00/m3, if contractor used water from deptt. source).

-

-

-

... More
Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer's specification and as per direction of EIC to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost of primer. In Ground floor (Two Coat). a) Normal Acrylic Emulsion.

145

67

9715

... More
40 mm. thick damp proof course with cement concrete(1:1.5:3) (with graded stone chips 20 mm nominal size) with water proofing compound of approved brand @ 0.2% weight of cement including cost of materials over two coats of non toxic acrylic polymer modified cementitious waterproofing slurry coat completed (cost of water proofing compound and non toxic paint to be paid seperately) for underground water retaining structures.

4

268

1072

... More
b) With 6:1 cement morter. (i) 20 mm thick plaster in Ground Floor.

405.28

159

64702.95

... More
Hire charges for shuttring with centering and necessary staging upto 4 m. using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beam, columns, lintles curved or straight including fitting, fixing and striking out after completion of works.(In all floors): 25mm to 30mm thick wooden shuttering as per decision and direction of Engineer-In-Charge.a) 25mm to 30mm thick wooden shuttering without staging in foundation

230.18

328

75499.04

... More
Reinforcement for reinforced work in all sorts of structures including distribution bars, stirrups, binders etc intial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every inersection, complete as per drawing and direction.(Rate Analysis).(i) Other than SAIL/TATA/RINL (a) For works in foundation, basement and upto roof of ground floor/upto 4 m. (i) Tor steel/Mild Steeel.

3.4

86674

294694.35

... More
Applying Exterior grade Acrylic primer of approved quality and brand on plastered or cencrete surface old or new surface to receive decorative textured(matt finish) or smooth finish acrylic exterior emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer's specification and as per direction of the EIC. In Ground Floor: a) One Coat.

145

31

4553

... More
Supplying, laying, fiting, fixing and jointing of UPVC pipes conforming to IS:4985-2000 with latest revision and amendments, if any, with necessary UPVC/CI specials, CIDF sluice valves, as per relevant I.S. specification including labour charges for earth work in excavation in any kind of soil including mixed soil with boulder ,road sub-grade and its flanks but excluding moorum and laterite or sand stonehard arock including cutting of brick payment without damaging the existing telephone/electrical cable line etc.(in case of damage of any type of cable line during excavation, necessary damaged charges as applicable by the respaective authority will be borne by the agency in his own cost. Loading, unloading, carrying of pipes, specials, valves from the local store to work site and lowering laying of pipes specials valves carefully in trenches maintaining proper levels and alignment ,jointing the pipe and specials including supplying of good quality/approved brand solvent cement (as per IS:14182-1994 including cost of all fabricated PVC fitting i.e. tees,bend, reducers, adopter etc.as per IS:101-1988 and making flange joints including supplying required quantity of nuts, bolts and rubber insertion (CIDF sluice valves will be supplied by the department free of cost) as required at site by adopting suitable method so as to facilate the maintenance of pipe line locally as per conventional method including back filling the trenches with good earth obtained from excavation of trenches including consolidation with watering in layer not exceeding 150mm thk. with maintaining an average depth of cushion of 1.10mtr. from the top of pipe line including making interconnection with distribution pipes etc. all complete as per drawing direction and satisfaction of the E.I.C.

-

-

-

... More
For DI pipe:

-

-

-

... More
Brick work with 1st class Bricks in sand cement Morter (6:1) including raking out joints scaffolding & curing etc. completed as directed by Engineer- in- Charge.

-

-

-

... More
Add GST 18.00 %

5147340.38

-

926521.27

... More
Cement concrete with graded stone ballast (40 mm size excluding shuttering) In ground floor (A) [Pakur Variety]. (a) 1:3:6 proportion

5.67

4299

24378.85

... More
e) Above 40 Km upto 50 Km

1

3754

3754

... More
Iron haspbolt of approved quality fitted and fixed complete (oxidised) with 16mm. Dia. rod with centre bolt and round fitting. (a) 300mm. Long.

1

166

166

... More
Supply fitting approved type ventilator in position after cutting holes in walls, setting in cement mortar, mending damages to wall & plaster & two coats of paint of approved brand sandshade, payment of mending two damages of wall plaster and painting to be made separately. a) R.C.C. Ventilator of 20 mmthick. i) upto 0.10 sqm. area.

4

108

432

... More
Hire and labour charges for shoring work (including necessary close plank walling, framing, Eucalyptus/Jhou bulla piling, strutting etc) complete as per direction of the Engineer-in-charge for foundation excavation (vertical surface are in contact with supported earth is to be measured.) (This item should be executed on specific direction of the Enginner in charge). (a) Depth upto 1.5 m

985

376

370360

... More
Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary : With super gloss (hi-gloss): on steel or other metal surface. With super gloss (hi-gloss) :Two coats ( with any shade except white).

7.2

79

568.8

... More
b) With 6:1 cement morter. i) 20 mm thick plaster in Ground Floor. (Out side )

80

159

12772

... More
Filling in foundation or plinth by fine sand in layers not exceeding 150mm as directed and consolidating same by thorough saturation with water ramming complete. Including the cost of supply of sand.( Payment to be made on measurment of finished quantity )

15.11

431

6517.09

... More
Artificial stones in floor, dado, stair case etc. with cement concrete (4:2:1) with stone chips, laid in panels as directed, with topping made with ordinary or white cement (as necessary) and murble dust in proportion (2:1) including smooth finishing and rouding off corners and including application of cement slurry before flooring works, using cement @1.75 kg./sq.m. all complete including all materials and labour. In ground floor. 3 mm. thick topping (High polishing grinding on this item is not permitted with ordinary cement). Using grey cement. a) 25mm. Thick.

12

251

3012

... More
M.S.or W.I. Ornamental grill of approved design joints continuously welded with M.S, W.I. Flats and bars of windows, railing etc. fitted and fixed with necessary screws and lugs in ground floor. (ii) Grill weighing above 16 Kg./sq.mtr and above

60

98

5896.2

... More
Design, Supply, laying, fitting of pipeline from different unit to nearby Drain/ Water body/ Pond/ upto 100m. Length for proper disposal of backwash water. (Payment will be made as per actual length of executed works.)

100

500

50000

... More
125 mm thick Brick work of 1st class bricks with cement morter (1:4). a) in Superstructure.

8

668

5346.64

... More
a) 150 mm dia D.I,

10

220

2200

... More
Supplying fitting & fixing UPVC Pipes A - Type and fittings conforming to IS : 13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc. if necessary and mending good damages including joining with jointing materials (Spun Yarn, Valamoid/Bitumen/M-Seal etc.) complete. a) UPVC Pipe. i) 110 mm dia.

12

251

3012

... More
Ordinary cement concrete ( mix 1:1.5:3 ) with graded stone chips ( nominal 20 mm size) excluding shuttering and reinforcement. If any, Variety

7

5530

38713.36

... More
Earthwork in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm including watering and ramming etc. layer by layer complete. a) with earth obtained from excavation of foundation.

1.9

77

147.33

... More
a) In foundation and Plinth :

6.09

4872

29675.84

... More
HORIZONTAL ROAD CROSSING: Horizontal road crossing by Augor-boring including boring charge, pipe laying and jointing, making baricates, lighting arrangement etc. all complete as per direction of E.I.C. For 80 mm dia. to 200 mm dia. pipes.

2

4970

9940.38

... More
c) 110 mm(OD)

250

471

117750

... More
c) FLANGE SPIGOT 150

4

3044

12179.68

... More
Brick work with 1st class Bricks in sand cement Morter (6:1) including raking out joints scaffolding & curing etc. completed as directed by Engineer- in- Charge. a) In foundation and Plinth :

5

4872

24364.4

... More
Anodised aluminium barral/tower/socket bolt (full covered) of approved manufactured from extruded section conforming to I.S.I. specification (I.S.204/74) fitted & fixed with cadmium plated screws. (a)225mm.long x10mm. Dia. Bolt

2

84

168

... More
White washing with stone lime only including cleaning smoothly surface throughly. (a) Three coats.

130

20

2601.3

... More
Approach Road

-

-

-

... More
Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in ground floor as per relevant IS codes.

30.55

5516

168514.72

... More
M.S.clamp for fixing door, windows frame made of flat iron end bifarcated mixed in cement concrete with stone chips(1:2:4) fitted and fixed complete as per direction. (a)40mmx6mm. 200 mm length.

6

25

150

... More
Neat cement punning in wall /dado, window sills, floor drains etc. in all floors about 1.5mm thick.

54.6

32

1787.06

... More
b) In Superstructure :

15

5095

76438.2

... More
Plaster to wall, floor etc with sand and cement morter (1:6) including rounding off or champhering corners as directed and racking out joints or roughing of concrete surface including throating, nosing and drip course where necessary (In all floors). a) With 6:1 cement morter. i) 15 mm thick plaster in Ground Floor.

60

139

8368.8

... More
(b) SHOE i) 110 mm dia.

3

111

333

... More
d) 90 mm dia

900

-

792

... More
Filling the pipe line with water, testing hydraulically as per I.S 3114-1965 (Article-6) in section of a length not exceeding 500mtr. for head of pressure as per specification including supplying installing and fixing all equipments such as diesel pump set, blank flange, pressure gauge, valve, pressure pump and all other tools and plants including drilling topping and plugging of necessary holes to pipes, blocking ends providing temporary thrust block and subsequent blocking of holes and other jointing materials and dismantling and removal of the same including disposal of water etc. all complete as per specification and direction of EIC. The rate is inclusive of cost of requisite water to be arranged by the contractor (Recovery rate of water @ Rs.10.00/m3, if contractor used water from deptt. source).

-

-

-

... More
a) With CArried earth arranged by the contractor within a radius of 3 km. including cost of carried earth

352.2

379

133772.6

... More
Carrying CI/DI pipes with specials and valves and lowering placing in position and laying carefully inside the trenches in proper alignment and gradient etc. including earth work in excavation of adequate width as per specification having min. clear cover from top of pipe is 1.10mtr. below existing ground level in any kind of soil including mixed with boulder, road sub-grade and its flank,but excluding moorum and laterite and stone etc.without damaging the exisiting telephone/electric cable etc.(in case of damaged if any type of cable line during excecution , necessary damaged charges as applicable by the respective authority will be borne by the agency in his own cost) preparing the bottom surface for continuous bedding of pipe line and laying pipes, fitting, fixing specials and valves with bailing out water if any including carriage of pipes, specials and valves from local deptt. store within 8KM and back filling the trenches with excavated earth in layers to original condition as per specification and direction of EIC. The surplus materials after execution of work are to be return to the deptt. store. N.B: i) Any deviation from required clear cover of 1.10mtr., due to site adverse condition, prior permission is to be obtained from the EIC in exceptional situation and payment will be made on prorate basis over the rate of entire item ii) No payment will be made without hydraulic test of the pipe line either part or full iii) The pipes, specials and valves , rubber gasket will be supplied deptt. free of cost.

-

-

-

... More
Chamfering the spigot end of all type/class of DI pipe for proper using of push joint by means of grinder set at site for proper joint etc. all complete as per direction of EIC.

-

-

-

... More
b)Priming one coat on timber or plastered surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc.

20

38

760

... More
Earthwork in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm including watering and ramming etc. layer by layer complete. a) with earth obtained from excavation of foundation.

71.3

77

5528.6

... More
M.S.or W.I. Ornamental grill of approved design joints continuously welded with M.S, W.I. Flats and bars of windows, railing etc. fitted and fixed with necessary screws and lugs in ground floor. (ii) Grill weighing above 16 Kg./sq.mtr and above.

250

98

24567.5

... More
Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. (a) For works in foundation and upto roof of ground floor/upto 4 m. i) Tor steel/Mild Steel. II. JSW/JSPL/SHYAM/ SRMB/BMASL/ELECROSTEEL/SSL

0.98

86674

84941.31

... More
Single brick flat soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with powdered earth or local sand.

95.88

322

30873.36

... More
Earthwork in excavation in foundation trenches or drain in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading & stacking the spoil within a lead of 75m as directed. The item includes necessary trimming the sides of trenches. Levelling, dressing and ramming the bottom, bailing out of water as required complete. (a) Depth of excavation not exceeding 1500 mm.

119.74

119

14281.39

... More
Making rubber gasket joint to CI/DI pipes maintaining proper alignment level etc. by mechanical arrangement with or without using mobile cranes where necessary and with help of all other equipment stools and tackles etc. as required providing lubricants of approved quality and direction of EIC. (rubber gasket will be supplied deptt. free of cost)

-

-

-

... More
a) 80 mm to 150 mm dia pipe

2

11990

23980

... More
a) 150 mm dia D.I,

16.5

112

1848

... More
Earth work in filling in compound, tank, low land,ditches etc. with good earth, in layers not exceeding 150 mm. including breaking clods and consolidating the same by ramming and dressing complete. (Payment will be made on profile measurement before and after the work): With carried earth arranged by the contractor within a radius of 3 km. Including cost of carried earth.

25.85

379

9818.35

... More
Earthwork in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm including watering and ramming etc. layer by layer complete. a) with earth obtained from excavation of foundation.

2

77

155.08

... More
Applying Exterior grade Acrylic primer of approved quality and brand on plastered or cencrete surface old or new surface to receive decorative textured(matt finish) or smooth finish acrylic exterior emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer's specification and as per direction of the EIC. In Ground Floor: a) One Coat.

405.28

31

12725.79

... More
Supply and delivery of CIDF sluice valve (Special type) PW-1.00 of different dia make with CI double flanged non rusting spindle sluice valves conforming to IS 14846 -2000 with latest emended having body dome/bonnet and cover of C.I.Gr-F.G 210mtr. spindle of IS-6603 G.R-12/Gr-13 non-magnetic, nuts seat rings are of Gunonetal as per IS:318 LTB-2 flanges and drilled to IS:1538 Part IV & VI valves are suitable for max. working pressure of 10kg/cm2(seat test) and body tested to 15kg/cm2. N.B: The above item should be procured from the reputed manufactures as per deptt. approved vender list.

-

-

-

... More
a) 150 mm dia D.I,

3

38

114

... More
Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer's specification and as per direction of EIC to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost of primer. In Ground floor (Two Coat) a) Normal Acrylic Emulsion

405.28

67

27153.76

... More
HORIZONTAL ROAD CROSSING: Horizontal road crossing by Augor-boring including boring charge, pipe laying and jointing, making baricates, lighting arrangement etc. all complete as per direction of E.I.C. For 80 mm dia. to 200 mm dia. pipes.

1

4970

4970.19

... More
(C) With (4:1) Cement mortar. (i ) 10mm. Thick plaster

22

125

2757.04

... More
Panel shutters of door & window as per design (each panel consisting of single plank without joint) including fitting & fixing the same in position but excluding the cost of other fittings in G.F. a) 35 mm thick shutter with 19 mm thick panel. (b) Sishu, Gamar, Champ,Badam,Bhola, Mogra, Hallak.

3.5

2789

9761.5

... More
Supply and delivery of different dia. D I specials including loading unloading and carriage inclusive of taxes and all charges whatsoever

-

-

-

... More
a) 150mm dia.

4

108

432

... More
b) 140 mm(OD)

200

1

288

... More
a) With earth obtained from excavation of fundation

48.45

77

3756.81

... More
Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary : With super gloss (hi-gloss) a) on Timber or plaster surface. Two coats ( with any shade except white).

10

81

810

... More
Cutting DI pipe (all class & type) to required length with cutting device etc. and grinding the cutting portion with file as per direction and satisfaction of EIC.

-

-

-

... More
b) 150 mm dia D.I

16.5

1

25.41

... More
Earthwork in excavation in foundation trenches or drain in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading & stacking the spoil within a lead of 75m as directed. The item includes necessary trimming the sides of trenches. Levelling, dressing and ramming the bottom, bailing out of water as required complete. (a) Depth of excavation not exceeding 1500 mm.

12

119

1431.24

... More
Earth work in filling in compound, tank, low land,ditches etc. with good earth, in layers not exceeding 150 mm. including breaking clods and consolidating the same by ramming and dressing complete. (Payment will be made on profile measurement before and after the work)

-

-

-

... More
c) 80x90° C.L.D.F.Bend

13

61

793

... More
Neat cement punning in wall /dado, window sills, floor drains etc. in all floors about 1.5mm thick.

21

32

687.33

... More
Construction of Boundary Wall

-

-

-

... More
Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches.

76

24

1824

... More
a) 150mm.dia.to 200mm.dia pipe

4

141

564

... More
Iron butt hinges of approved quality fitted and fixed with steel screws with I.S.I. Mark(oxidised fitting). (a) 100mm. X 50mm. X 1.25mm.

6

43

258

... More
c) 110 mm dia

250

1

270

... More
(b)100mm. Longx 10mm. Dia. Bolt

4

53

212

... More
Supplying, Fabrication, Erection on suitable RCC foundation and Commissioning with 3 (three) months Trial Run (including cost of routine testing of water sample for performance evaluation) of pressure type Iron removal plant as per design norms of the P.H.E. Dte. with necessary accessories viz. MS fabricated shell with minimum 10 mm thick MS plate with 2 (two) coats of anticorrosive paint & minimum 12 mm thick MS media supporting plate fitted with required no. of pot strainer, MS fabricated oxidation chamber with minimum 10 mm thick plate with necessary pipe connection, valves, Gauges & other instruments as required as per departmental approved design & drawing including cost of filter media, Air Compressor & Air blower with motor, starter, main switch etc. of required capacity & approved specification including power connection from main line etc. all complete. (Rate excludes the cost of Concrete Platform & drain, and the cost of Blower Room): 40 m³/hr. capacity

1

1027900

1027900

... More
125 mm thick Brick work of 1st class bricks with cement morter (1:4). in Ground Floor.

121.88

668

81456.06

... More
Filling in foundation or plinth by fine sand in layers not exceeding 150mm as directed and consolidating same by thorough saturation with water ramming complete. Including the cost of supply of sand.( Payment to be made on measurment of finished quantity )

6

431

2587.86

... More
b) 150 mm dia D.I

16.5

4

69.3

... More
b) 140 mm(OD)

200

785

157000

... More
b) Double Flanged Short Piece 150X1.0 M

4

6393

25572.88

... More
a) 150mm. da.C..Duck Foot Bend

47

61

2867

... More
Hire charges for shuttring with centering and necessary staging upto 4 m. using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beam, columns, lintles curved or straight including fitting, fixing and striking out after completion of works.(In all floors). 25mm to 30mm thick wooden shuttering as per decision and direction of Engineer-In-Charge.

95

328

31160

... More
Wood work in door & window frame fitted & fixed in position complete including a protective coat of painting at the contact surface of the frame. (h) Neem, Jam, Jackfruits. In Ground Floor:

0.11

53057

5836.27

... More
Single brick flat soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with powdered earth or local sand.

40

322

12880

... More
a) Mechanical Collar 150

6

3806

22840.68

... More
d) 150x80C.LDFReducer

23

61

1403

... More
a) 150 mm dia

3

9174

27522

... More
Box cutting or filling in Road embankment in all sorts of soil including spreading the soils properly over the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power roller to proper camber and grade as per direction and satisfaction of Engineer-in-charge including uprooting and removing plants and jungles when and where necessary.: Depth up to 150 mm.

90

14

1296

... More
Iron door handle of approved quality fitted & fixed complete. (a) 100mm. X 5mm

2

40

80

... More
Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand.

500

322

161000

... More
b) 140 mm(OD)

200

4

848

... More
Hire charges for shuttring with centering and necessary staging upto 4 m. using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beam, columns, lintles curved or straight including fitting, fixing and striking out after completion of works.(In all floors): 25mm to 30mm thick wooden shuttering as per decision and direction of Engineer-In-Charge.a) 25mm to 30mm thick wooden shuttering without staging in foundation

6

328

1968

... More
d) 90 mm dia

900

3

3240

... More
Add Labour Welfair Cess 1%

6073861.65

-

60738.62

... More
Interconnection of Tube well

-

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements

Past Bidders
This list is curated from the bidders of the similar tenders in the past

Unlock the Tender details for free
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.