If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search &amp; bid for etender UP.

North Central Railway - NCR Tender

Works
Transportation and Logistics
Ireps
Opening Date16 Dec 2024
Closing Date6 Jan 2025
Tender Amount₹ 6,01,45,893.57 
Notes
Download

Costs

Summary

A- Idh-bxn - Trr(p) 9.186 Kms Under Aden-line/idh. B- Complete Track Renewal (p) Of18.57 Kms With Contractors Pqrs Portal In Idh-bxn Section Under Aden- line/idh Section. C- Agc-dho Through Sleeper Renewal (p) Of19.205 Kms With contractors Pqrs Portal In Agc-dho Section Under Aden-dho Section

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Drilling holes of 16 mm to 32 mm dia. with Rail Drilling machine including chamfering 4 with appropriate chamfering tools in all types of rail section with contractor's tools & plants, equipment, consumable with all lead & lift etc. complete, as directed by Engineer in-charge. Rail Drilling Machine will be as per RDSO Specification No. TM/SM/3, dated 24.04.1991. Outside Track

100

47

4345.6

... More
Drilling holes of 16 mm to 32 mm dia. with Rail Drilling machine including chamfering with appropriate chamfering tools in all types of rail section with contractor's tools & plants, equipment, consumable with all lead & lift etc. complete, as directed by Engineer in-charge. Rail 5 Drilling Machine will be as per RDSO Specification No. TM/SM/3, dated 24.04.1991. On Running Line

200

62

11529.12

... More
Drilling holes of specified size for bond holes with 7.2mm dia drill twist to correct spacing and location on 60kg/52kg rails on cess or under traffic block with contractor's tools and plant, equipment, consumable, labour etc complete as directed by the Engineer in charge at site.

100

37

3432.3

... More
Pulling & positioning of rails accurately on cess including supporting rails, providing required gap and squaring at ends for renewal preparation, as directed by Engineer in-charge. More than 40 m long rail panel

20000

13

247924.08

... More
Pulling & positioning of rails accurately on cess including supporting rails, providing required gap and squaring at ends for renewal preparation, as directed by Engineer in-charge. Extra to Item no. 061011 for working on bridge

400

3

1368.11

... More
Dismantling and removing rail of all section & length from track, laid on any type & 9 density of sleeper by removing fish plates, fastenings & fish bolts and other materials including stacking all released materials within an average distance of 500 metres as directed by Engineer in- charge. Note: 1.Cutting of rails shall be paid separately. 2.Work to be done under traffic block. For Through Rail Renewal work

9986

41

384473.58

... More
Insertion of rails of all types & length in track, laid on any type & density of sleeper to 10 the specified gauge under traffic block. Rates include fastening of rail with sleepers with standard set of fastenings and fixing of fish plates and bolts or, if required, providing gap for welding and stacking of released material without infringement within 250m as directed by Engineer-in-Charge. Note: Rail drilling and cutting to be paid separately. For Through Rail Renewal work

9986

42

396381.65

... More
De-stressing of LWR/CWR track of any density under traffic line block with contractor's labours, tools, equipments and consumables inclusive of all lead & lift. Activities include cutting of LWR/CWR into convenient panels of specified length, removal of ERCs, liners, greasing of ERCs and liner contact area, lifting rails and keeping them on rollers provided at every 15 sleepers, working out 11 elongation of rail ends depending on prevailing site conditions, pulling rails with the help of Hydraulic Tensor to achieve the desired elongation, cutting rails, as required, removing rollers and placing rail in position, re-fixing ERCs & liners and adjustment of gap at SEJs : Note: (1) Welding of rail joints will be paid separately. (2) Rail cutting and Hole drilling shall be paid separately. (3) Opening and closing of LC if required will be paid separately. (4) As per procedure prescribed in latest edition of IRPWM & CE's Circulars for destressing of LWR/CWR, if any. Without Rail tensor

9986

32

301578.68

... More
Erection or removal of temporary Engineering Indicator Board or any other board at specified locations without causing infringement to track etc. complete and as directed. For erection

200

237

43942.28

... More
Erection or removal of temporary Engineering Indicator Board or any other board at specified locations without causing infringement to track etc. complete and as directed. For removal

200

192

35644.86

... More
Anti-corrosive painting of rail on running track of any sleeper density on web, foot etc. including liner contact area (excluding bottom of foot) and fishing plane as per requirement with two 14 coats of thickness of 100 microns each by bituminous black paint confirms to IS-9862 of reputed make including painting of liners, ERCs and including surface preparation, as a complete job as per procedure prescribed in latest edition of IRPWM Note: 60% of payment shall be made if painting on only gauge face side is done. For 60 Kg Rails

9986

73

677005.82

... More
Loading, leading and unloading of all types of P.Way fittings and all other 15 miscellaneous material except Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: Lead shall be the shortest motorable road length between the points of loading and unloading. Lead up to 5 Km

250

159

36828.1

... More
Loading, leading and unloading of all types of P.Way fittings and all other 16 miscellaneous material except Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: Lead shall be the shortest motorable road length between the points of loading and unloading. Lead beyond 5 Km and up to 10 km 172043 250.00 MT 256.56 64140.00 (-) 7.56 59291.02

250

200

46344.79

... More
Loading, leading and unloading of all types of P.Way fittings and all other miscellaneous material except Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: Lead shall be the shortest motorable road length between the points of loading and unloading. Lead beyond 10 Km and up to 20 km

-

-

17

... More
Loading, leading and unloading of all types of P.Way fittings and all other 18 miscellaneous material except Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: Lead shall be the shortest motorable road length between the points of loading and unloading. Lead beyond 30 Km and up to 50 km

250

419

96923.34

... More
Loading, leading and unloading of all types of P.Way fittings and all other 19 miscellaneous material except Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: Lead shall be the shortest motorable road length between the points of loading and unloading. Lead beyond 20 Km and up to 30 km

250

324

75049.73

... More
Loading, leading and unloading of all types of P.Way fittings and all other 20 miscellaneous material except Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: Lead shall be the shortest motorable road length between the points of loading and unloading. Lead beyond 50 Km and up to 100 Km

250

625

144525.32

... More
Linking of BG track (except at LC, Bridges and SEJs) with any type of rail section and sleeper of specified density, on ballast bed spread and compacted with suitable roller, over prepared formation including leading free rails/welded panels available along the alignment on to formation, leading and spreading all fittings and fastenings, spreading of sleepers at specified spacing, squaring, 21 placing of rails over sleepers and fixing rails to sleepers with all types of fittings and fastenings to correct gauge & alignment, lubrication of fittings and fastenings with contractor's grease as per IRPWM standards with contractors labour, tools, consumables, with all lead, lifts etc. complete and raising, levelling and initial packing of track to make it fit for 30 kmph and meet other prerequisites prescribed in Indian Railway Track Machine Manual for deployment of Tamping Machine. Note: 1.Rail cutting and Hole drilling shall be paid separately. 2.Spreading of ballast and compaction shall be paid separately under relevant item. For sleeper density of 1660 sleepers per km

200

258

47808.12

... More
Quick cutting with abrasive rail cutter of all types of rail sections including wear resistant, head hardened rails up to 110 UTS, with contractors tools & plants, equipment, consumable 22 with all lead & lift etc. complete as directed by Engineer in-charge. Abrasive Rail Cutter will be as per RDSO Specification No. TM/SM/1 (Rev. 01 of 2012) with latest status of RDSO; Rail Cutting Wheel Abrasive Disc will be as per RDSO Specification No.TM/SM/2 (Rev. 01 of 2020) 60 Kg - 110/90 UTS - Outside Track

50

258

11948.79

... More
Quick cutting with abrasive rail cutter of all types of rail sections including wear resistant, head hardened rails up to 110 UTS, with contractors tools & plants, equipment, consumable 23 with all lead & lift etc. complete as directed by Engineer in-charge. Abrasive Rail Cutter will be as per RDSO Specification No. TM/SM/1 (Rev. 01 of 2012) with latest status of RDSO; Rail Cutting Wheel Abrasive Disc will be as per RDSO Specification No.TM/SM/2 (Rev. 01 of 2020) 60 Kg - 110/90 UTS - On Running Line

50

329

15233.65

... More
Under Traffic Block: Dismantling of existing BG turnouts, diamond crossings and derailing switches with all types of rails and sleeper layout, removing rails, switches, crossings, sleepers & fastenings, leveling of ballast to correct profile & stacking all the released materials, sleepers, fastenings, rails, switches & crossings including segregating & stacking at specified locations 24 in a neat and countable manner, within the lead of 250m & all lift, clear of infringements, crossing of track, if any complete, as directed. Note: 1. This item shall be operated only when existing turnout is replaced either with new turnout in case of TTR or with plain track when existing turnout is no more required at that location. 2. Rail cutting will be paid extra under relevant item. 3. Laying of new turnout or plain track on prepared ballast bed, as required, shall be paid separately under relevant item. 1 in 12 Turnout (Under Traffic Block)

2

32788

60619.75

... More
Assembling on temporary staging and insertion of all types of turnouts including diamond crossings and derailing switches on prepared ballast bed during traffic block, manually or by contractor's cranes, at specified location with 52Kg / 60Kg rail section on PSC sleepers with Railways rails/sleepers available anywhere within 500m as per standard drawing, duly leading sleepers, rails, 25 switches, crossings, fastenings etc. including rail cutting, drilling, fixing of all components, fittings etc. with housing of tongue rails as per requirement of signaling including crossing of track, filling and spreading of ballast in crib and shoulder as required, linking of turnout with existing track, attending track parameters including lifting, providing one round of packing to make track fit for 20 kmph speed including lubrication of fittings/fastenings, complete in all respect and as directed by Engineer in- charge. Note: Required P.Way fittings shall be supplied at the SSE/P.Way stores. 1 in 12 Turnouts

2

63270

116975.18

... More
Assembling and Laying of Improved Switch Expansion Joint (SEJ) on PSC sleepers of any rail section as per RDSO drawing including leading of SEJ rails, sleepers, fittings for a free lead of 250 26 metres, cutting of rails, drilling of holes as required and lubrication of SEJ, gauging, aligning rails, providing temporary connection with adequate welding gap with adjoining rails, providing reference posts at SEJ, first through packing of SEJ portion to make track geometry fit for 30 kmph speed and making ballast profile as per IRPWM. Note: (1) Rail cutting and hole drilling shall be paid separately.(2) One set comprise complete SEJ on both rails at SEJ. Under Traffic Block Conditions

4

6808

25174.11

... More
Dismantling & removing existing SEJ (Switch Expansion Joint) assembly during line block and its replacement with plain track as of adjoining section with all fittings including rail cutting 27 and drilling of holes and renewal of special sleepers with PSC Sleepers as directed and aligning rails, providing fishplates and bolts/ temporary connection with adequate welding gap with adjoining rail and ensuring proper track geometry for 30 kmph speed. The release material shall be stacked as directed by Engineer in charge.

4

8346

30862.76

... More
Loading of tongue rail, stock rail, switch assembly and crossings of any section and 28 length, SEJ, Glued joint etc. with / without P.Way fittings and fastenings, in Wagon / Truck / trailer including lead up to 250 metre and lift up to 5 metre. In Wagon where mechanical handling is possible and traffic block is not required or in Truck/trailer.

40

115

4262.22

... More
Transportation of Rails, sleepers, switches, crossings, SEJs and Glued Joints by road 29 vehicles for different leads. Note: 1 . Lead shall be the shortest motorable road length between the points of loading and unloading. 2. Loading and unloading shall be paid extra under relevant items. Lead up to 5 Km

40

52

1959.36

... More
Transportation of Rails, sleepers, switches, crossings, SEJs and Glued Joints by road 30 vehicles for different leads. Note: 1 . Lead shall be the shortest motorable road length between the points of loading and unloading. 2. Loading and unloading shall be paid extra under relevant items. Lead beyond 5 Km and up to 10 km

40

94

3482.4

... More
Transportation of Rails, sleepers, switches, crossings, SEJs and Glued Joints by road 31 vehicles for different leads. Note: 1 . Lead shall be the shortest motorable road length between the points of loading and unloading. 2. Loading and unloading shall be paid extra under relevant items. Lead beyond 10 Km and up to 20 km

40

150

5553.8

... More
Transportation of Rails, sleepers, switches, crossings, SEJs and Glued Joints by road 32 vehicles for different leads. Note: 1 . Lead shall be the shortest motorable road length between the points of loading and unloading. 2. Loading and unloading shall be paid extra under relevant items. Lead beyond 20 Km and up to 30 km

40

218

8075.19

... More
Transportation of Rails, sleepers, switches, crossings, SEJs and Glued Joints by road 33 vehicles for different leads. Note: 1 . Lead shall be the shortest motorable road length between the points of loading and unloading. 2. Loading and unloading shall be paid extra under relevant items. Lead beyond 30 Km and up to 50 km

40

313

11574.6

... More
Unloading of Switches / Crossings / SEJ Rails / Glued Joints of any rail section and 34 length with or without P.Way fittings & fastenings in neat manner for Railway usage from departmental material train (DMT) or contractor's / Railway's Truck/Trailer with lead up to 250 metre & lift up to 5 metres. From Truck / Trailer

40

117

4360.58

... More
Manufacturing and fixing buffer stop with Railway supplied rails, cutting, including 35 bending of rails as per plan ,with all contractor's labour, materials, tools, plants etc. and all lead and lift including crossing of track where necessary and as directed by Engineer in charge at site. Note: Excavation, fixing rails in cement concrete, drilling of holes will be paid separately.

1

-

14029.03

... More
Spreading of ballast, from existing stacks available along formation on top or at cess, in required uniform thickness, compaction of ballast layer laid on new formation at all the locations with smooth wheeled power roller of 8-10 tonne capacity to sufficient number of passes to form 36 consolidated ballast bed of approximately 250mm thickness to a width of 4m symmetrical to centre line of proposed track in correct line & level with all ascents & descents, as directed by Engineer in- charge. Note: Item is inclusive of (a) providing ramp for taking roller to formation and removing the same & making good formation after completion of work; (b) redistribution & leveling of excess ballast while rolling to obtain uniform plane cambered surface.

400

45

16853.66

... More
a) Running track site:- Replacement of old sleepers and rails (CTR) by dismantling existing track of all types of sleepers by making 13m loose rail panel (or any suitable length panel) with existing sleepers & SH rail (for removing existing track) with wider base sleepers/revised wider base sleepers at density of 1660 sleepers per Km assembled with loose rail panel (or any suitable rail length panel of SH rail) in PQRS Depot and placing over ballast properly during traffic block after removing panels of old sleeper and SH rail of 13 m loose rail panel (or any suitable length panel) with the use of contractor's PQRS Machine by providing auxilary track with gauge of 3400mm (either with the use of existing rail from existing track or with new rail unloaded by contractor from EUR in block as instructed by SSE/P-way, (if required) over metal/ wooden sleepers, to be provided by Railway, 500 Nos./rail km on both rails at the interval of 2M) and providing fish plates for joining loose SH rail over wider base sleeper for continuity of track and maintaining track parameters as per Para 522 of IRPWM 2020 to keep the track fit for 30kmph. SH rail over new wider base sleepers/revised wider base sleepers to be replaced with new/earlier existing rail on running track (with replacement of rubber pad, liner & greased ERC and greasing of liner contract area. Grease to be used should be of 'o' graphite grease as per IS code 408). As soon as loose rail length of track reaches 500m/750m (as per decision of Railway site engineer i.e. SSE/JE/ P-Way), loading of track panel (SH rail over old normal sleeper and tied with ERC) of approximately 13 m length over Railway wagons and unloading of track 1 panels of the length of 13 m (or any suitable length) and wider base sleepers/revised wider base sleepers will be done during traffic block. TRR with the rail of the length of 250 m to 500m (preferably 20rail panel) will have to be done as soon as track of loose rail exceeds 500m length. Further the contractor will follow instructions of SSE/P-way to relax speed of track upto maximum speed of section as per schedule laid down in IRPWM 2020 para 708 for Machine Tamping with all machine packing related works such as recoupment of crib ballast, shoulder ballast, boxing and dressing. The whole process will continue till completion of work. Auxilary Track (AT) will have to be removed with advancement of CTR work as per direction of Railway (SSE/JE/P-Way). b) PQRS Depot: - Track panel with SH rail of 13 m or any suitable length over wider base sleepers/revised wider base sleepers/revised wider base sleepers will be made with necessary fittings in PQRS Depot. Loading of these panels over Railway Wagons and unloading of released track panels (released from running track) consisting of all types of rails & sleepers from Railway wagon at PQRS depot using Contractor's own portal crane including dismantling and stacking each component of track properly at designated locations. (Note: This item of Complete Track Renewal with wider base sleeper is a composite item and all activities as required will have to be done by the contractor with his/her own PQRS Machine & other machines, tools and plants including all other resources as per requirement of the work (in PQRS depot and during traffic block in running track). Railway will provide wagons and locomotives free of cost for loading/unloading and transportation to/from PQRS Depot/work site (running track) for loose rail panels with normal old sleepers and with wider base sleepers/revised wider base sleepers. Nothing extra will be paid except the rates as mentioned against the item. See full item in Annexure-A

18.57

1523775

28296516.98

... More
a) Running track site:- Replacement of old sleepers ( TSR) by dismantling existing track of all types of sleepers by making 13m loose rail panel (or any suitable length panel) with old sleepers & SH rail (for removing existing track) with wider base sleepers / revised wider base sleepers at density of 1660 sleepers per Km assembled with loose rail panel (or any suitable rail length panel of 1 SH rail)in PQRS Depot and placing over ballast properly during traffic block after removing panels of old sleeper and SH rail of 13 m loose rail panel (or any suitable length panel) with the use of contractor's PQRS Machine by providing auxiliary track with gauge of 3400mm(either with the use of existing rail from existing track or with new rail over metal/ wooden sleepers, to be provided by Railway, 500 Nos./rail km on both rails) and providing fish plates for joining loose SH rail over wider base sleepers / revised wider base sleepers for continuity of track and maintaining track parameters as per Para 522 of IRPWM 2020 to keep the track fit for 30kmph. SH rail over new wider base sleepers /revised wider base sleepers to be replaced with new/earlier existing rail on running track (with replacement of rubber pad, liner & greased ERC and greasing of liner contract area. Grease to be used should be of servogem RR3 from Indian oil) as soon as loose rail length of track reaches 500m/750m (as per decision of Railway site engineer i.e. SSE/JE/ P Way). Loading of track panel( SH rail over old normal sleeper and tied with ERC) of approximately 13 m length over Railway wagons and unloading of track panels of the length of 13 m( or any suitable length) and wider base sleeper / revised wider base sleeper will be done during traffic block. TRR with the rail of the length of 250 m to 500m which was removed initially for AT, will have to be done as soon as track of loose rail exceeds 500m length. The whole process will continue till completion of work. Auxiliary Track (AT) will have to be removed with advancement of TSR work as per direction of Railway (SSE/JE/P Way). b) PQRS Depot: - Track panel with SH rail of 13 m or any suitable length over wider base sleepers / revised wider base sleepers will be made with necessary fittings in PQRS Depot. Loading of these panels over Railway Wagons and unloading of released track panels( released from running track) consisting of all types of rails & sleepers from Railway wagon at PQRS depot using Contractor's own portal crane including dismantling and stacking each component of track properly at designated locations. Note: This item of Through sleeper renewal with wider base sleeper / revised wider base sleeper is a composite item and all activities as required will have to be done by the Contractor with his/her own PQRS Machine & other machines, tools and plants including all other resources as per requirement of the work ( in PQRS Depot and during traffic block in running track). Railway will provide wagons and locomotive free of cost for loading/unloading and transportation to/from PQRS Depot/ work site (running track) for loose rail panels with normal old sleepers and with wider base sleepers / revised wider base sleepers. Nothing extra will be paid except the rate as mentioned against the item. Railway will also provide metal/wooden sleepers required for AT, free of cost.(For Final product and Notes refer Annexure-A)

19.21

1484810

28523203.17



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements

Past Bidders
This list is curated from the bidders of the similar tenders in the past

Unlock the Tender details for free
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.