The TANGEDCO has issued a formal invitation for competitive bids for the Tamil Nadu Generation And Distribution Corporation Limited project, for Uedc/udumalpet - Providing Chain Link Fencing Around The Quarters Campus At Iyerpady 110/22 Kv Ss in Coimbatore, Tamil Nadu, with an estimated contract value of Rs. 19,19,820. The bid opening date for this tender is 14-03-2025 and the last date for bid submission is 29-03-2025. Interested bidders for Tamil Nadu Generation And Distribution Corporation Limited tender can download the important documents here to check the scope of work, eligibility criteria and technical requirements.

Tamil Nadu Generation And Distribution Corporation Limited - TANGEDCO Tender

Works
Electrical and Electronics
Electrical Works
Eprocure
Opening Date14 Mar 2025
Closing Date29 Mar 2025
Tender Amount₹ 19,19,820 
Notes
Download

Costs

Summary

Uedc/udumalpet - Providing Chain Link Fencing Around The Quarters Campus At Iyerpady 110/22 Kv Ss

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Providing Steel reinforcement MS/RTS rods for reinforced concrete works, including cost of steel MS/RTS rods, binding wire, labour charges for cutting, straightening bending as per type design drawing, placing aligning, and tying properly with all leads and lift,etc., complete.

240

-

-

... More
Plain cement concrete in CC 1:2:4, using 20mm HBG metal without formwork including cost of all materials, labour charges including consolidation, curing, all lead, lift,etc., complete as per standard specification

15

-

-

... More
Improvement works

-

-

-

... More
Disposal of excess surplus earth away in low lying area with a lead of 100 mts including spreading and levelling labour, lead, lift, etc., complete.

16

-

-

... More
Supply & fixing of GI 10 gauge Chain link fencing of size 2" x 2", tie with GI flat using GI bolt and nuts at a interval of 25 cm including cost of chain link fencing, labour for fixing, transportation charges, lead, lift, etc., complete

1000

-

-

... More
Colour washing two coats using cement paint of approved quality over one coat of cement primer including cost of all materials,labour,lead,lift, etc.,complete

16

-

-

... More
White Washing two coat with shell based white cement as instructed by the departmental officers including cost of all materials,lead,lift,scaffolding charges,lead,lift, etc., complete complying with standard specifications

310

-

-

... More
Supplying and fixing of MS gate with suitable angles for Main and wicket gate including two coat of enamel paint over one coat of primer of approved quality and colour, cost of all materials,labour charges of fabrication, fixing, lead, lift, etc., complete.

700

-

-

... More
Reinforced cement concrete in C.C. 1:1 ½ :3 mix using 12 to 20mm HBG machine crushed metal for raft footing Column up to GL and above GL including cost of cement, all materials, labour, curing, vibration charges, without shuttering all lead, lift,etc., complete as per standard specification. (but excluding cost of steel reinforcement.) -Above G.L

1.5

-

-

... More
Supplying and fixing of 10 gauge GI barbed wire of two ply and four pronged of approved quality and gauge including of cost of barbed wire and labour for tensioning of 4 rows in horizontal , lead, lift,etc., complete

1700

-

-

... More
Reinforced cement concrete in C.C. 1:1 ½ :3 mix using 12 to 20mm HBG machine crushed metal for raft footing Column up to GL and above GL including cost of cement, all materials, labour, curing, vibration charges, without shuttering all lead, lift,etc., complete as per standard specification. (but excluding cost of steel reinforcement.) -Below G.L

0.45

-

-

... More
Flush pointing in CM 1:3 for RR masonry including plasticiser at the rate of 100 ml per bag, cost of all materials, labour, lead, lift, etc., complete

60

-

-

... More
Earthwork excvation and depositing on bank with intial lead of 10m and lift of 2m in Soft Disintegrated Rock (SDR), laterite, soft rock or kankar, not requiring blasting including cost of all materials, T&P's, labour charges, all lead, lift, etc., complete as per standard specification

5.5

-

-

... More
Plain cement concrete in CC 1:2:4, using 20mm HBG metal with formwork including cost of all materials, labour charges including consolidation, curing, all lead, lift, etc., complete as per standard specification

11

-

-

... More
Reinforced cement concrete in C.C. 1:1 ½ :3 mix using 12 to 20mm HBG machine crushed metal for raft footing Column up to GL and above GL including cost of cement, all materials, labour, curing, vibration charges, without shuttering all lead, lift,etc., complete as per standard specification. (but excluding cost of steel reinforcement.) - Raft footing

1

-

-

... More
Earthwork excvation and depositing on bank with intial lead of 10m and lift of 2m in hard gravelly soil, stiff black cotton soil, hard red earth, shales, murram, gravel, stoney earth mixed with samll sized boulders, including cost of all materials, T&P's, labour charges, all lead, lift, etc., complete as per standard specification

9

-

-

... More
Plastering1:3, 12 mm thick including the cost of all material, cement, labour charges, all lead, lift etc., complete as per standard specification.

16

-

-

... More
Earthwork excvation and depositing on bank with intial lead of 10m and lift of 2m in MR & DMR not requiring blasting including cost of all materials, T&P's, labour charges, all lead, lift,etc., complete. as per standard specification

3.5

-

-

... More
SGST to be quoted in percentage (value alone), Ex.9%, it should be entered as 9 only

1

-

-

... More
Plain cement concrete 1:3:6, using 40 mm HBG metal including cost of all materials, labour charges including consolidation, curing, all lead, lift, as per standard specification etc., complete.

0.4

-

-

... More
Inter-State GST @ 18% for other than Tamil Nadu supplier. If the contractor is within Tamilnadu may be quoted as "0" only

1

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.