The Rural Development And Panchayat Raj Department has issued a formal invitation for competitive bids for Renewal Of Bt Road 03 Nos Package No 01 in Nagapattinam, Tamil Nadu. The bid opening date for this tender is 16-05-2025 and the last date for bid submission is 30-05-2025. Interested bidders for Rural Development And Panchayat Raj Department tender can download the important documents here to check the tender amount, scope of work, eligibility criteria and technical requirements.

Rural Development And Panchayat Raj Department Tender

Works
Civil And Construction
Road Construction
Eprocure
Opening Date16 May 2025
Closing Date30 May 2025
Tender AmountRefer Documents 
Notes
Download

Costs

Summary

Renewal Of Bt Road 03 Nos Package No 01

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 A including laying and spreading in layers of 250 mm loose thick each , sectioning , watering and compacting etc, complete as per MOST 301 - 305.

-

-

-

... More
in Km. 0/0-2/621

314.17

-

-

... More
Providing and laying Tack coat over BT surface using 3.0 Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat

-

-

-

... More
Km 0/0-2/621

7863

-

-

... More
Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 25 mm using 13.20 mm IRC size HBG metal with 44 kg of Bitumen for 1 CUM mixed in hot mix plant laying at site including cost and conveyance of metal from approved quarry labour charges for tamping to required level line and grade etc completed complaying with standard specification

-

-

-

... More
Km 0/0-1/0

7.94

-

-

... More
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II)-Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5

-

-

-

... More
Km 0/0-2/621

235.89

-

-

... More
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS

-

-

-

... More
Km 0/0-1/0

120

-

-

... More
Km 1/0-2/0

120

-

-

... More
Km 2/0-2/621

74.17

-

-

... More
Provision for Hectametre Stones Size 0.90m x 0.15m x 0.15m

11

-

-

... More
Provision for KM Stones Size 1.65m x 0.45m x 0.15m

2

-

-

... More
Provision for Refixing/Repainting for Signboard

2

-

-

... More
Provision for Refixing/Repainting for Logo board

2

-

-

... More
Provision for Refixing/Repainting forCitizen information board

1

-

-

... More
Provision for Refixing/Repainting for Information board/Name board

1

-

-

... More
Provision for Refixing/Repainting for Maintenance board

1

-

-

... More
Provision for Incentive Board

1

-

-

... More
For the First Year from the date of completion of work

2.621

33613

88099.673

... More
For the Second Year from the date of cpmpletion of work

2.621

50420

132150.82

... More
For the Third Year from the date of completion of work

2.621

67227

176201.967

... More
For the Fourth Year from the date of completion of work

2.621

84034

220253.114

... More
For the Fifth Year from the date of completion of work

2.621

100840

264301.64

... More
02.Periodic Renewal of Black Topping to L - 37 VV Road to Keelapudhupalli Road KM 0/0-2/850 in Keelaiyur block

-

-

-

... More
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201.

-

-

-

... More
in Km. 0/0-2/850

2047.68

-

-

... More
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders SS 20 A including laying and spreading in layers of 250 mm loose thick each , sectioning , watering and compacting etc, complete as per MOST 301 - 305.

-

-

-

... More
in Km. 0/0-2/850

341.28

-

-

... More
Providing and laying Tack coat over BT surface using 3.0 Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat

-

-

-

... More
Km 0/0-2/850

8550

-

-

... More
Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 25 mm using 13.20 mm IRC size HBG metal with 44 kg of Bitumen for 1 CUM mixed in hot mix plant laying at site including cost and conveyance of metal from approved quarry labour charges for tamping to required level line and grade etc completed complaying with standard specification

-

-

-

... More
Km 2/0-2/850

4.9

-

-

... More
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II)-Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5

-

-

-

... More
Km 0/0-2/850

256.5

-

-

... More
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS

-

-

-

... More
Km 0/0-1/0

120

-

-

... More
Km 1/0-2/0

120

-

-

... More
Km 2/0-2/850

101.28

-

-

... More
Provision for Hectametre Stones Size 0.90m x 0.15m x 0.15m

12

-

-

... More
Provision for KM Stones Size 1.65m x 0.45m x 0.15m

1

-

-

... More
Provision for Refixing/Repainting for Cautionary board

2

-

-

... More
Provision for Refixing/Repainting for Logo board

3

-

-

... More
Provision for Refixing/Repainting forCitizen information board

1

-

-

... More
Provision for Refixing/Repainting for Information board/Name board

1

-

-

... More
Provision for Refixing/Repainting for Maintenance board

1

-

-

... More
Provision for Incentive Board

1

-

-

... More
For the First Year from the date of completion of work

2.85

33613

95797.05

... More
For the Second Year from the date of cpmpletion of work

2.85

50420

143697

... More
For the Third Year from the date of completion of work

2.85

67227

191596.95

... More
For the Fourth Year from the date of completion of work

2.85

84034

239496.9

... More
For the Fifth Year from the date of completion of work

2.85

100840

287394

... More
03.Periodic Renewal of Black Topping to L - 022 Prathaparamapuram Kamachipuram road in Prathaparamapuram Panchatat KM 0/0- 0/876 in Keelaiyur block .

-

-

-

... More
Providing and laying Tack coat over BT surface using (0.2+0.25) Kg of bitumen vg30 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat

-

-

-

... More
Km 0/0-0/876

2648.5

-

-

... More
Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50 mm using 45 mm IRC size HBG metal with 44 kg of Bitumen for 1 CUM mixed in hot mix plant laying at site including cost and conveyance of metal from approved quarry labour charges for tamping to required level line and grade etc completed complaying with standard specification

-

-

-

... More
Km 0/0-0/876

1.58

-

-

... More
Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 25 mm using 13.20mm IRC Size HBG metal Bitumen for 1 CUM mixed in hot mix plant laying at site including cost and conveyance of metal from approved quarry labour charges for tamping to required level line and grade etc completed complaying with standard specification

-

-

-

... More
Km 0/0-0/876

7.49

-

-

... More
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II)-Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5

-

-

-

... More
Km 0/0-0/876

79.46

-

-

... More
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS

-

-

-

... More
Km 0/0-0/876

78.32

-

-

... More
Provision for Hectametre Stones Size 0.90m x 0.15m x 0.15m

4

-

-

... More
Provision for Refixing/Repainting for Cautionary board

3

-

-

... More
Provision for Refixing/Repainting for Logo board

2

-

-

... More
Provision for Refixing/Repainting forCitizen information board

1

-

-

... More
Provision for Refixing/Repainting for Information board/Name board

1

-

-

... More
Provision for Refixing/Repainting for Maintenance board

1

-

-

... More
Provision for Incentive Board

1

-

-

... More
For the First Year from the date of completion of work

0.876

33613

29444.988

... More
For the Second Year from the date of cpmpletion of work

0.876

50420

44167.92

... More
For the Third Year from the date of completion of work

0.876

67227

58890.852

... More
For the Fourth Year from the date of completion of work

0.876

84034

73613.784

... More
For the Fifth Year from the date of completion of work

0.876

100840

88335.84

... More
GST Amount for providing Service to Government Contract Works for the above RENEWAL & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount above this row in column "BB" for all works in this package}(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)

1

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.