Water Resources Department Tender

... More
The WRD has issued a formal invitation for competitive bids for the Water Resources Department project, for Nid-216-construction Of Vr Bridge Over Cghandanpur Branch Canal At Rd 9.250km. in Puri, Odisha, with an estimated contract value of Rs. 83,87,062. The bid opening date for this tender is 07-11-2026 and the last date for bid submission is 21-11-2026. Interested bidders for Water Resources Department tender can download the important documents here to check the scope of work, eligibility criteria and technical requirements.

Water Resources Department - WRD Tender - Orissa Tender

Opening Date7 Nov 2026
Closing Soon21 Nov 2026
Tender Amount₹ 83,87,062 
Notes
Download

Costs

Summary

Nid-216-construction Of Vr Bridge Over Cghandanpur Branch Canal At Rd 9.250km.

Description

Construction Of Vr Bridge Over Chandanpur Branch Canal At Rd 9.250km.

Contact

Unlock the Tender details

GEM & Bid Advisory Services

Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

Unlock the Tender details
... More
cement concrete M15 with 20 mm downgraded crusher broken hard granite chips with concrete mixture, hoisting and laying manually compacting by vivrator including cost conveyance royalty, EMF,DMF,Additional charges of materials etc.complete including watering etc. as directed by the Engineer in charge.

184.5

6421

1184840.55

... More
RCC/Cement concrete M25 with 20 mm downgraded crusher broken hard granite chips with concrete mixture, hoisting and laying manually compacting by vivrator including cost conveyance royalty, EMF,DMF,Additional charges of materials etc.complete including watering etc. as directed by the Engineer in charge.

367.9

7329

2696486.26

... More
Supplying, cutting and placing in position of uncoated HYSD reinforcement for RCC work including cost, carriage & cess of all materials ,labour,T&P and cost of binding wire etc.complete as per direction of the Engineer-in-charge.

300.1

9658

2898365.8

... More
Rigid smooth centering shuttering for R.C.C.work including dismantling then after casting .(Plinth band, Footing, Pre Cast slab etc) with cost of all materials,labour,T&P,hire and running charges of machinaries,welfare cess etc.complete as per direction of the Engineer-in-charge.

215.96

250

54097.98

... More
Rigid smooth centering shuttering for R.C.C.work including dismantling then after casting including cost of all materials & T&P etc with cost of all materials,labour,T&P,hire and running charges of machinaries,welfare cess etc.complete as per direction of the Engineer-in-charge.(RCC walls, Fins etc)

584.48

1096

640706.98

... More
Rigid Smooth centring & Shuttring for RCC floor and roof slab, landings etc including false work & dismantling them after casting with all cost, carriage, royalty, curing, labour welfare cess etc. complete with cost of all materials,labour,T&P,hire and running charges of machinaries,welfare cess etc.complete as per direction of the Engineer-in-charge.

82.13

767

63010.14

... More
Providing, weep holes in concrete works in abutments/ wing walls/return walls with 100mm diaAC pipe extending through the full width of the structure with slope of 1 V: 20 H towards drawing face with cost of all materials, all labour all taxes, T & P etc.Complete including labour welfarecess as per specification and direction of the Engineer-in-Charge

88.8

111

9910.08

... More
Providing 40mm metal in inverted filter including supplying of good quality HG metal including cost, conveyance, royalty if any, labour welfare cess etc. complete in all respect and as per specification and direction of the Engineer-In-Charge.

15.25

3298

50296.03

... More
Earthwork in all kinds of soil except sand, sandy or slushy soil in borrow area by mechanical means and transportation of excavated earth by mechanical means with all leads, lifts, delfts, rehandling, conveyance, royalty,EMF,DMF,Additional charges of materials, labour cess, including loading and unloading the same on prepared and approved surface including rough dressing and breaking the clods to maximum 5 cm. to 7 cm. in size and laying in layers not exceeding 22.5 cm.layers to make ready for watering and compaction with sheep foot rollers and dozers but excluding watering and compaction in dams and dykes for all heights including construction, maintenance, watering and lighting of haul road and borrow area with labour, T & P etc. complete as per direction of the Engineer-in-charge. (Earth will be arranged by the bidder at his own cost and risk. Earth should be free from clods, roots, brickbats and other debris.. Measurement of the fill to be taken on the finished level section) only

960.47

300

288717.28



Evaluation Notes How It Works ?

Related Tenders

Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.