The Paradip Port Trust has issued a formal invitation for competitive bids for Repair And Restoration To The Damaged Berth And Diaphragm Wall Of Nq-ii Berth Inside Harbour Area. in Kendrapara, Odisha, with an estimated contract value of Rs. 6,25,35,060. The bid opening date for this tender is 10-11-2023 and the last date for bid submission is 30-11-2023. Interested bidders for Paradip Port Trust tender can download the important documents here to check the scope of work, eligibility criteria and technical requirements.

Paradip Port Trust Tender

Works
Civil And Construction
Civil Works Others
Eprocure
Opening Date10 Nov 2023
Closing Date30 Nov 2023
Tender Amount₹ 6,25,35,060 
Notes
Download

Costs

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Under water micro concrete for walls:Sufficient quantity of RENDROC WG shall be stocked along with 12 mm downgraded chips at site to enable completion of pouring in a continuous operation. An approved grout concrete mixer of slow speed heavy duty drill shall be used for the mixing of the micro concrete. Exact quantity of water as recommended by codal provisions should be poured in to mixing vessel along with the RENDROC WG and 12 mm cleaned chips (in the ratio of 1:0.50 or 0.75) slowly. The mix shall be mixed thoroughly in forced action. The mixed material should be placed immediately in the formwork continuously without any gap through the PVC pipe fixed or any other alternatives from the top of the deck including cost of all labour, materials, T&P, Port entry fees, cost of hire charges barges, pontoon, boat, all machineries diving equipment and divers etc. all complete but excluding GST as directed by Engineer in charge.

920

-

-

... More
Supplying, fabricating and providing 10mm thick M.S plate to the required depth, as shown in the drawing including gas cutting ,bending, welding at yard & site, transporting, driving of liners, all labour, materials, T&P, Port entry fees, equipment’s, fuel etc. all complete excluding GST as directed by Engineer in charge.

129.53

-

-

... More
Surface preparation: The cover concrete shall be chipped and removed up to rear side of the steel bar shall be exposed using the electrically operated c hammer chipping machine and hand chiselling. It is recommended to use water jet for the removal of all loose particles, fungal and marine growth ncluding the cost of all labour, materials, T&P, Port entry fees, hire charges of comproser, pnumatic tools, hire charges of barge, boat, waterjet etc. all complete excluding GST as directed by Engineer in charge

460

-

-

... More
Surface Preparation: Labour charges for chipping the joint portion between the walls. Clean the surface and make sure that surface is clean and free from loose particle. The rate shall include cost of equipments, plants, labour, materials, T&P, Port entry fees, sand, instrumentation, hiring of boat, catamaran, pontoon etc. all complete excluding GST as directed by Engineer in charge.

788

-

-

... More
Anchoring shear connectors: In order to fix the shear connectors (secondary reinforcement) of 10 mm dia, holes shall be drilled at the required locations as per the drawings. The pilot holes shall be drilled using 10mm dia hammer drill bit. The holes shall be widened using the appropriate drill bit size 16/18 mm dia. Drilling shall be carried out without much of vibration so as not to disturb adjacent concrete. The holes shall be roughened for better bonding including the cost of all labour, materials, T&P, Port entry fees, hire charges hammer drilling machine and all consumables etc. all completeexcluding GST as directed by Engineer in charge.

11500

-

-

... More
PU Grouting: The suitable PU resin mechanically using a slow speed heavy duty drilling machine. Inject the same using an electrically operated pressure grouting machine (pressure not to exceed 4-5 kg/cm2) until the nipple refuses the grout or the grout comes out of the nearby nipple. In case the grout comes out of the adjacent nipples, the same may be closed and those nipples need not be grouted again. Continue the operation until all the nipples are grouted. Cut the nipple and finish the surface to match the nearby surface. The rate shall include cost of all labour, materials, T&P, Port entry fees, operations etc. all complete excluding GST as directed by Engineer in charge.

126

-

-

... More
Additional reinforcement: MS or RTS rebars as per the drawing shall be fabricated and placed in position including cost of all labour, materials, T&P, Port entry fees, fabrication charges etc. all complete excluding GST as directed by Engineer in chare.

56

-

-

... More
Form work:Slurry tight formwork which should not deform or leak due to pressure of micro concrete shall be fabricated and erected in position. Provision shall be made for pouring micro concrete into the form work, which shall be coated with mould release agent. Proper supporting arrangement shall be made for keeping the shutter in correct line and length including cost of all labour, materials, T&P, Port entry fees, hire charges of all machineries, boat, barge, pontoon, divers etc. all complete excluding GST as directed by Engineer in charge.

460

-

-

... More
Access platform/working platform: The working platform above the Ground/water level shall be erected using the friction and hanging support. The above fixing and erection work shall be carried out with the help of floating pontoon and boats etc. including the cost of all materials, hire charges of boat, T&P, Port entry fees, all labour charges and divers etc. all complete excluding GST as directed by Engineer in charge.

3300

-

-

... More
Drilling and fixing in underwater: Drill 20 mm dia holes in to the concrete surface to a depth of 100 mm. The spacing of the holes should not be more than 500 mm centre to centre. Provision of 16mm dia bolt and fix the same using equipment’s. The rate shall include cost of all labour, materials, T&P, Port entry fees, operations etc. all complete excluding GST as directed by Engineer in charge.

2000

-

-

... More
Placing, Driving the M.S liners of the specifications as per item 12 above for walls. The cost inclusive of charges for transporting to the pile location, aligning, lowering, pitching and driving the liners as per standard specification, labour, materials, T&P, Port entry fees etc. all complete and excluding GST as directed by Engineer in charge.

360

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.