GAIL India Limited Tender

Search for the latest Gujarat tenders online related to civil works, road & transport, pipelines and more easily here on BidAssist. Here you can get any and every tender that is posted on the eProcurement Gujarat website, minus the clutter. No need for a tender ID, as on BidAssist, you can view any Gujarat tender by merely typing Gujarat in the search box.

GAIL India Limited - GAIL Tender

Works
Civil And Construction
Eprocure
Opening Date20 Nov 2024
Closing Date9 Dec 2024
Tender AmountRefer Documents 
Notes
Download

Costs

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

  • Tender Id

    2024_GAIL_215267_1
  • Tender No

    GAIL/HZR/CNP/124422/FL-52C
  • Tender Authority

    GAIL India Limited View
  • Purchaser Address

    -
Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Repair of Holiday in 3-Layer PE Coating Supply of all coating repair materials as per specification to be compatible with line pipe coating material and as per the requirements of the relevant specifications, supply of all consumables, utilities, equipment, and all manpower required, pipe cleaning and surface preparation repairing of coating defects (resulting in holiday in coating) and testing including all handling, transportation, etc. for line pipes, performing all works necessary for the completion of the works strictly in accordance with the relevant specification and instructions of Owner. This rate shall be applicable per sq. cm of the exposed steel area.

100

-

-

... More
Repair of Defects in Pipes of all sizes and thickness

-

-

-

... More
Cutting and rebevelling of each end of pipe (dents / damage in bevels exceeding 3mm in depth)

1

-

-

... More
Jack out (dents in bevels ranging between 1mm and 3mm in depth)

1

-

-

... More
LEAKS/ BURSTS (ATTRIBUTABLE TO OWNER) Major Leak/ Bursts which can be located by visual observation occured during pre-hydrotesting. All works for locating & detection of leak/ burst including necessary repairing/ replacing defective pipe lengths, including cutting out and removing the defective pipe, pretesting the replacement pipe, welding into pipeline string subjected for re-testing and NDT of welds, clean-up, retesting the full test section of pipeline including providing all labour, materials, consumables and inputs other than Owner supplied materials and performing all works as per drawings, specifications enclosed with the tender/ contract document and directions of Owner.

-

-

-

... More
For pipeline size 30" NB Note: (1) This rate is applicable for manufacturing defects in Owner supplied material only. (2) Leak detection, its rectification and successfully re-hydrotesting shall be carried out as per approved procedure by Contractor with a view that completion of all activity for successful hydrotesting is not inordinalely extended which will hamper the overall project schedule.

1

-

-

... More
MAGNETIC CLEANING AND ELECTRONIC GEOMETRY PIGGING Mobilisation/demobilisation of pigging tools, tackles, consumables, accessories and personnel by contractor at work site including but not limited to magnet pig, electronic geometry pigs and pig tracking device, temporary launcher and receiver as per specification and other provision of the bid document including supply of material, quipment, manpower, etc. as required for geometry inspection and magnet cleaning including calibration of magnetic and caliper tools at works site, running of adequate no. of magnet pigs and electronic geometry pigs (caliper) including pig tracking, preparation of site report on pipeline, data analysis at Contractors facility as per specification and provisions of the Bid Document.

1

-

-

... More
IDLE TIME PRESERVATION

-

-

-

... More
Preservation of complete pipeline sections for pipeline size 30" NB and its maintenance upto (01) one month by filling and pressurising the pipeline section with nitrogen to a positive pressure of 2 bars (g). Supply and maintenance of nitrogen at required pressure, including supply of all consumables, nitrogen, all equipment, manpower, tc., complete as per requirement of specifications, other provisions of contract document and instruction of Engineer In-charge.

330

-

-

... More
Preservation for pipeline size 30"NB and maintenance of pipeline at positive pressure of 2 (two) bars(g) beyond 1 month

1

-

-

... More
SUPPLY AND INSTALLATION OF LONG RADIUS BENDS Supply And Installation of Long Radius Bends (R = 6D) for 30" dia. pipe, X-70 (thk. 15.9 mm) as per Technical Specification & Datasheet enclosed in Tender Document (3LPE Coated pipe for LR Bends shall be free issue to the contractor) including all taxes, duties, transportation and inspection charges but not limited to, the following items in accordance with relevant specifications indicated in scope of work indicated in SCC, drawings, specification and instructions of Engineer-in-charge and as per all provisions of the CONTRACT DOCUMENT. Rate to include Handling including lifting, transportation from Contractor's Store to workshop for fabrication and/ or to work site.

-

-

-

... More
20° - 30°

2

-

-

... More
31° - 45°

4

-

-

... More
PURGING WITH NITROGEN OF EXISTING UNDERGROUND PIPELINE SYSTEM Complete work of Purging of Nitrogen for existing 30" underground pipeline section between SV-06 and SV-07 to the specified acceptance criteria, carrying out shutdown/hot work, providing assistance during the complete duration of shutdown/hot work operations for entire pipeline network system in various sections including supply of all equipment, man-power, consumables (including nitrogen required for purging/filling ) materials for all temporary works and performing all associated works, complete as per the relevant specifications, other provisions of Contract document and instructions of Engineer-in-charge(EIC). Nitrogen vaporizer capacity 3000 m3/hr, pressure will be min. 2 barg. Note: Venting activity shall be carried out by GAIL. However all necessary assistance shall be provided by the contractor and deemed to be included in above quoted rate.

1

-

-

... More
HOOK UP WITH EXISTING PIPELINE /HOT WORK Complete work of carrying out tie-in and hook-up of the installed HDD sections including laying of transition piping up to 12 m for hook-up with existing 30# DAHEJ-URAN pipeline section at both end of canal crossing including identification of location, trenching up torequired depth and exposing the entire surface required for the proposed hook -up in such away that it shall not damage either pipeline or its coating, cutting of test header, cleaning, removal of coating, cold cutting of pipe section, re-beveling as required , survey for determining the bend angle before fabrication of LR Bends of required degree, pretesting of assembly, fabrication and installation of LR bends, welding, radiography, UT and other NDT examination, repair of defects, sleeve joint coating (heat shrinkable sleeves), holiday checking & repair, backfilling and restoration and clean-up of area, disposal of waste, handing over of balance material etc to GAIL at their designated store etc as per specification and to the satisfaction of Engineer-in-charge and /or as directed by Concerned Authority. Obtaining NOC from concern authority. Note - Rate for supply and fabrication of LR Bends shall be excluded and same shall be paid as per relevant SOR item

2

-

-

... More
TRANSITION, PIPE LAYING / INSTALLATION Laying/ installation of coated line pipe as per specifications, drawings, other provisions of Contract and instructions of Engineer-in-Charge of the sizes mentioned herein, including but not limited to carrying out the following: "Receiving and taking-over", handling, loading , transportation and unloading of Owner supplied externally corrosion coated line pipes from Owner designated place(s) of issue to Contractor's own stock-yard(s)/ workshop(s)/ work-site(s) including stringing of the pipeline Right-of-Use (ROU); Arrangement of all additional land required for Contractor's storage, fabrication, access for construction (other than Owner provided ROU/ROW); supply of all materials (except Owner supplied materials), consumables, equipment, labour, etc. and other incidental works; carrying out all temporary and auxiliary works required to make the pipeline ready for pre-commissioning; Staking and installation of temporary construction markers, clearing, grubbing, grading (as required) of Right of Use; Counting the number and type of trees cut in presence of concerned authorities and keeping record thereof; shifting of all obstruction within the ROU / pipeline route alignment viz. electrical line / pole, telephone line (poles), foreign pipeline; coordination with concerned authorities.Trenching to all depths and to a width in all type of soil strata to accommodate the pipeline and/or optical fiber cable/cable conduit during lowering & backfilling as specified in scope document and as per the relevant standards, specifications, etc. by excavation in all types of soils strata; providing depth of padding in trench bed & above and around the pipeline HDPE duct and OFC as required with sand / graded earth approved by Engineer-in Charge; Carrying out repairs of pipe defects/ replacement in case of irreparable defects and repairs of defects of pipe coating not attributable to Owner including defects/ damages occurring during transportation/ handling after taking over from Owner by Contractor ; Thorough internal cleaning of all pipes by suitable methods to remove debris, hots, grits etc. to the satisfaction of Engineer-in- Charge; Stringing of line pipes along ROU including providing straw and sand. Aligning, bending, cutting and bevelling (as required) of pipes for welding and field adjustments, NDT of relevelled area, welding, carrying out non-destructive testing (100%) by AUT/ X-Ray of welds and providing all requisite equipment, labor, supervision, materials, films, consumables, all facilities and personnel to process, develop, examine and interpret radiographs and other tests as required; carrying out repairs of weld joints found defective by Engineer-In- Charge, carrying out re-radiography and other non-destructive tests such as ultrasonic test etc. as required on repaired joints, etc. as mentioned in specification. Supply of coating materials for all field joints (heat shrinkable sleeves) and high build liquid epoxy etc. as per specifications compatible with 3-Layer PE Coating as per tender specifications with prior approval of Engineer-in-charge. Coating of all field weld joints, long radius bends, buried fittings, valves etc.; Crossing all the foreign pipeline / HT line / cable / any other utilities etc. with necessary concrete / PVC protection including coordination with all agencies. Installation of LR Bend, as per specification wherever required depending on site condition. Supply and Installation of warning mat on the entire length of the pipeline Carrying out cleaning, pigging and hydrostatic testing including air cleaning, flushing, filling, gauging, pressurization of complete pipeline in various test sections as approved by Engineer-In-Charge to the specified test pressure, providing all equipment, pumps, fittings, instruments, dead weight tester, test headers, pressure recorder, all types of pigs etc., and services, supervision, labour, consumables, water including supply of corrosion inhibitor, air, etc. as required, locating of leaks, if any, occured during hydrotesting attributable to contractor either by further sectionalising or any other suitable standard recommended practice with due approval of Engineer-in-Charge and rectification of defects, retesting after rectification, successful completion of hydrotesting of pipeline to acceptance criteria defined in the specifications. (Note : Leak detection, its rectification and successfully re-hydrotesting shall be carried out by Contractor with a view that completion of all activity for successful hydrotesting is notinordinately extended, which will hamper the overall project schedule. Further, no extra payment claim shall be entertained for re-hydrotesting and leak detection if defects foundattributable to Contractor. Repair of defects recorded during EGP/Gauge plate run or otherwise including cutting, bevelling, welding, radiography, field joint coating etc; as applicable, ROU management as required for ensuring hindrance-free construction works at site; Obtaining work permits/ NOC from various statutory authorities having jurisdiction, before and after execution of the work, and complying with all stipulation/conditions/recommendation of the authorities before and after execution of the work Carrying out all temporary, ancillary, auxiliary works and all incidental works required to make the pipeline ready for pre-commissioning; Complete work for Duct (2 Nos.), testing after completion of laying of HDPE Duct pipe, laying/ blowing & testing of OFC in both the ducts, supply of all materials , consumables, labour and other incidental works; carrying out all temporary, ancillary, auxiliary works required for duct integrity testing as per drawings, specifications, scope of work indicated in SCC and other provisions of Contract document and instructions of EIC. Installation of 40mm OD,permanently lubricated HDPE Telecom ducts, in same pipeline trench direct buried in all type of soil & terrain, all work as defined in mainline work, padding, backfilling, supply & laying of common warning mat (as provided for main pipeline),cleaning and sealing of ducts at the end of laid lengths, jointing (wherever deemed necessary by EIC) of HDPE conduit, installation of Joint Closures in joint pit, splicing/ Jointing of OFC as per the requirement and as per the direction of EIC, installation of erection accessories (HDPE accessories required including Plastic Couplers, End Plugs, Cable Sealing Plugs, End Caps, etc suitable & sufficient for supplied Duct.),testing of laid permanently lubricated HDPE ducts, rectification / modification if required, cleaning and sealing of ducts at the end of laid lengths, preparation of report all complete as per specifications provided in the bid document & as per direction of EIC. For payment purpose running transition pipe laying / installation shall be considered. Jointing of HDPE Ducts shall be avoided as much as possible. All activities pertaining to Blowing / Laying of optical fiber cable in the laid 40 mm HDPE telecom duct (after testing of OFC drum at site), Blowing/Laying of OFC cable to be done in both the ducts, testing of OFC before Blowing/laying, cable sealing etc. using all materials required complete as per specifications and drawing provided in the bid document & as per direction of EIC. (spare loop of 10 Meter at Blowing Pit, 20 Meter at Jointing Pit shall be provided- No payments for laying shall be made for these spare loops). The Optical Fibre Cable shall be free issue to the contractor. OTDR Test of the laid OFC, end to end Power Testing of laid OFC, Identification of the fault, Rectification, preparation of reports, reconciliation of free issued OFC etc., all testing reports in the format provided in the tender, CD of all fibre OTDR traces, work complete n all respect with all necessary accessories for all location, final acceptance / Handing over of the same to GAIL and as per the direction of Engineers in charge, as per specification & contract agreement. For Testing details, Refer Scope of Work. Final clean-up and restoration of right of use including obtaining NOC from respective land owner / farmers and statutory authorities as required and disposal of debris, as directed by Engineer-In-Charge; Restoration of land, facilities, boundary wall and roads etc. and associated facilities dismantled/damaged by the Contractor during construction; Complying with all stipulation/conditions/recommendation of the authorities before and after execution of the work; Preparation of As-Built drawings, Pipe book and other records as per pecifications etc.;

-

-

-

... More
Length of Line Pipe, size: 30 inch NB wall thickness: 11.2 mm /15.9 mm, Material: API 5L Gr. X-70, Length of Each Pipeline: 11.5 to 12.5 m & Bevel end, Coating type: 3 Layer PE Notes: (i) Liability of Owner to provide ROU to contractor shall be limited to the extent between the hook-up points with existing pipeline including for laying transition pipeline section. Additional space required by contractor beyond the above limits, including for access to site, shall be arranged by contractor at his own cost & initiative. (ii) Payment under this item shall be made only for the transition pipe laid more than 12 m length. Transition Pipe laying up to 12 m length on both sides is included in the SOR item for Hook up with existing pipeline / Hot Work. (iii) 3LPE coated Line pipe, HDPE Duct and OFC cable will be supplied as free issue material to contractor. (iv) Transportation of Free issue materials from Owner's designated store is covered elsewhere and deemed to be excluded from above quoted rate

50

-

-

... More
PRECOMMISSIONING AND COMMISSIONING ASSISTANCE Pre-commissioning activities and pre-commissioning checks to the specified acceptance criteria, making the entire pipeline system ready for commissioning, providing assistance during the complete duration of commissioning operations, supply of all equipment, manpower, consumables (including pigs and required quantity of nitrogen) materials for all temporary works performing all associated works, complete as per the relevant specifications, other provisions of Contract document and instructions of Engineer-in-Charge.

25

-

-

... More
TRANSPORTATION OF OTHER FREE ISSUE MATERIAL EXCLUDING LINE PIPE "Receiving and taking over", handling, lifting, loading on truck, transportation and unloading of Company supplied free issue material (excluding line pipe) from any storage yard to worksite / contractor's storage yard/ any other storage yard or as decided by EIC. The above work also includes stacking the material properly. Above work shall be carried out as per standard drawing, specification, instruction of Owner and other provision of contract document.

500

-

-

... More
TEMPORARY CATHODIC PROTECTION WORKS. Supply, packing, transportation to site, storage, installation, testing & commissioning of the Temporary Cathodic Protection system using Mg (Min 5.0 Kg Each) galvanic anodes to protect the external surface of 3LPE Coated pipe at crossings by HDD against corrosion for a design life of minimum 2 year or connection of HDD segment with mainline whichever is later as per standard specification for temporary cathodic protection system, scope of work & tender drawings. Scope shall also include but not limited to the following for completion of jobs:

-

-

-

... More
Prepacked Magnesium anodes (Sacrificial Anodes) for carrier pipe protection (Min 5.0 Kg Each) as per tender specification (1/2/3/4 Nos. of anodes) at both side of HDD crossing.

4

-

-

... More
Supply, laying, termination, glanding and ferruling TCP Cables--The Cables shall be annealed high conductivity, stranded copper conductor, 650/1100V grade, XLPE Insulated & PVC Sheathed in new/existing test stations.

100

-

-

... More
1 core x 6 mm2 - Anode tail cable unarmored

100

-

-

... More
1 core x 6 mm2 - Potential Measurement Ref Cell & Measurement Cable- armored

100

-

-

... More
1 core x 10 mm2 - Current Measurement cable & Pipeline to Test station- armored

2

-

-

... More
Test Lead Points (TLP) Normal Size (Weather Proof with IP-55) as per tender drawings with name plate

4

-

-

... More
All Cable to pipe connections by Exothermic Process or Pin Brazing for all sizes (Upto 1C x 25mm2)

-

-

-

... More
Demoblization and Re- Mobilization for hook-up activity Note: This item is applicable if delay in shut down more than 15 days from the date of completion of all post HDD activities at site. Then Contractor can demobilize from site with all equipment's, machinery, manpower etc. after taking permission from GAIL EIC. When pipeline shut down will be finalized, GAIL EIC will intimate contractor to re-mobilize along with their equipment's, manpower, machinery, PPE, tools, tackles, etc. as per tender conditions and contractor shall mobilize with 7 days. (De-mobilization & Re-mobilization charges shall be payable to the contractor on successful completion of works at site).

1

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements

Past Bidders
This list is curated from the bidders of the similar tenders in the past

Unlock the Tender details for free
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.