Transportation Tenders
Transportation Tenders
Municipality Of Mapanas, Northern Samar Tender
Civil And Construction...+1Civil Works Others
Philippines
Details: Description Bidding Documents Procurement Of Infrastructure Projects Name Of Project: Construction Of Siljagon Multi-purpose Gym Phase 2 Barangay Siljagon, Mapanas Northern Samar Contract Reference No. 2024-11-103 Table Of Contents Section I. Invitation To Bid 3 Section Ii. Instructions To Bidders 7 Section Iii. Bid Data Sheet 35 Section Iv. General Conditions Of Contract 38 Section V. Special Conditions Of Contract 70 Section Vi. Specifications 72 Section Vii. Drawings 75 Section Viii. Bill Of Quantities Error! Bookmark Not Defined. Section Ix. Bidding Forms 77 Section X. Foreign-assisted Projects Error! Bookmark Not Defined. Section I. Invitation To Bid Bid Notice Abstract Invitation To Bid (itb) Republic Of The Philippines Province Of Northern Samar Municipality Of Mapanas Invitation To Bid For Project: Construction Of Siljagon Multi-purpose Gym Phase-2, Brgy. Siljagon, Mapanas, Northern Samar The Lgu- Mapanas, Northern Samar, Through The 20% Economic Development Fund (edf) Of Fy 2025 Intends To Apply The Sum Of Two Million Nine Hundred Eighty One Thousand Three Hundred Thirty Two Pesos 95/100 Only (p2,981,332.95) Being The Approved Budget For The Contract (abc) To Payments Under The Contract For : Construction Of Siljagon Multi-purpose Gym Phase 2, Brgy. Siljagon, Mapanas, Northern Samar Bids Received In Excess Of The Abc Shall Be Automatically Rejected At Bid Opening. 1. The Lgu- Mapanas, Northern Samar Now Invites Bids For The Following Description Of Works To Be Procured: Item No. Scope Of Work Quantity Unit Construction Of Siljagon Multi-purpose Gym Phase 2, Brgy. Siljagon, Mapanas, Northern Samar B.3 Permits And Clearances 1.00 Lot B.5 Projects Billboard/signboard 1.00 Lot B.7 Construction Safety And Health 1.00 Lot B.9 Mobilization And Demobilization 1.00 Lot 903 Formworks And Falseworks 66.36 Sq.m. 1047 Metal Structures 1,218.00 In.m. 1013 Corrugated Metal Roofing, Gauge 24 618.28 Sq.m. 1046 Masonry Works 138.60 Sq.m. Completion Of The Works Is Required 120 Calendar Days. Bidders Should Have Completed, Within Ten (10) Years From The Date Of Submission And Receipt Of Bids, A Contract Similar To The Project. The Description Of An Eligible Bidder Is Contained In The Bidding Documents, Particularly, In Section Ii. Instructions To Bidders. Section Ii. Instructions To Bidders. 2. Bidding Will Be Conducted Through Open Competitive Bidding Procedures Using Non-discretionary Pass/fail Criterion As Specified In The Implementing Rules And Regulations (irr) Of Republic Act 9184 (ra 9184), Otherwise Known As The “government Procurement Reform Act”. Bidding Is Restricted To Filipino Citizens/sole Proprietorships, Partnerships, Or Organizations With At Least Seventy Five Percent (75%) Interest Or Outstanding Capital Stock Belonging To Citizens Of The Philippines. 4. Interested Bidders May Obtain Further Information From Lgu- Bac Mapanas, Northern Samar And Inspect The Bidding Documents At The Address Given Below From November 26, 2024-december 13, 2024, 8:00 A.m. To 5:00 Pm. A Complete Set Of Bidding Documents May Be Purchased By Interested Bidders From The Address Below And Upon Payment Of A Nonrefundable Fee For The Bidding Documents In The Amount Of P5,000.00. It May Also Be Downloaded Free Of Charge From The Website Of The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity, Provided That Bidders Shall Pay The Fee For The Bidding Documents Not Later That The Submission Of Their Bids. 5. The Lgu- Mapana, Northern Samar Will Hold A Pre-bid Conference On December 5, 2024 At 10:00 A.m. At Executive Conference, 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar, Which Shall Be Open Only To All Interested Parties Who Have Purchased The Bidding Documents. 6. Bids Must Be Delivered To The Address Below On Or Before 9:00 A.m. Of December 16, 2024 At Bac Office, @ Municipal Planning & Development Office (mpdo), Mapanas, Northern Samar. All Bids Must Be Accompanied By A Bid Security In Any Of The Acceptable Forms And In The Amount Stated In Itb Clause 18. Bids Will Be Opened In The Presence Of The Bidders’ Authorized Representatives Who Choose To Attend At The Address Below. Late Bids Shall Not Be Accepted. The Bidder May Request That The Bid Documents Be Sent To Them By Mail Or Courier, And For This, The Bidder Shall Pay The Amount In Philippine Peso To Cover The Cost Of Mail Or Courier Delivery. The Fee For Obtaining A Copy Of The Bid Documents And The Cost Of Mail Or Courier Shall Be Paid By The Bidder Thru S Cashier’s Check Or Manager’s Check Issued In Favor Of The Municipality Of Mapanas. 7. The Lgu- Mapanas, Northern Samar Reserves The Right To Accept Or Reject Any Bid, To Annul The Bidding Process, And To Reject All Bids At Any Time Prior To Contract Award, Without Thereby Incurring Any Liability To The Affected Bidder Or Bidders. 8. For Further Information, Please Refer To: Reno C. Salazar Bac Secretary Mapanas, Northern Samar Mobile # 09459852914 Ma. Teresa L. Minguez Bac Chairperson Mapanas, Northern Samar Mobile # 09778033758 Section Ii. Instructions To Bidders 1. The Bids Must Be Delivered On Or Before December 16, 2024 At 9:00 A.m And Failure To Submit The Bid Proposal May Ground For Disqualification Of The Bid. 2. Bids Received In Excess Of The Abc Shall Be Automatically Rejected At Bid Opening. 1. The Lgu- Mapanas, Northern Samar Now Invites Bids For The Following Description Of Works To Be Procured: Item No. Scope Of Work Quantity Unit Construction Of Siljagon Multi-purpose Gym Phase 2 B.3 Permits And Clearances 1.00 Lot B.5 Projects Billboard/sign Board 1.00 Lot B.7 Construction Safety And Health 1.00 Lot B.9 Mobilization And Demobilization 1.00 Lot 903 Formworks And Falseworks 66.36 Sq.m. 1047 Metal Structures 1,218.00 In.m. 1013 Corrugated Metal Roofing, Gauge 24 618.28 Sq.m. 1046 Masonry Works 138.60 Sq.m. Completion Of The Works Is Required 120 Calendar Days. Bidders Should Have Completed, Within Ten (10) Years From The Date Of Submission And Receipt Of Bids, A Contract Similar To The Project. The Description Of An Eligible Bidder Is Contained In The Bidding Documents, Particularly, In Section Ii. Instructions To Bidders. 2. Bidding Will Be Conducted Through Open Competitive Bidding Procedures Using Non-discretionary Pass/fail Criterion As Specified In The Implementing Rules And Regulations (irr) Of Republic Act 9184 (ra 9184), Otherwise Known As The “government Procurement Reform Act”. Bidding Is Restricted To Filipino Citizens/sole Proprietorships, Partnerships, Or Organizations With At Least Seventy Five Percent (75%) Interest Or Outstanding Capital Stock Belonging To Citizens Of The Philippines. 3. Interested Bidders May Obtain Further Information From Lgu- Bac Mapanas, Northern Samar And Inspect The Bidding Documents At The Address Given Below From November 26, 2024-december 13, 2024, 8:00 A.m. To 5:00 Pm. A Complete Set Of Bidding Documents May Be Purchased By Interested Bidders From The Address Below And Upon Payment Of A Nonrefundable Fee For The Bidding Documents In The Amount Of P5,000.00. It May Also Be Downloaded Free Of Charge From The Website Of The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity, Provided That Bidders Shall Pay The Fee For The Bidding Documents Not Later That The Submission Of Their Bids. 4. The Lgu- Mapanas, Northern Samar Will Hold A Pre-bid Conference On December 5, 2024 At 10:00 A.m. At Executive Conference, 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar, Which Shall Be Open Only To All Interested Parties Who Have Purchased The Bidding Documents. 5. Bids Must Be Delivered To The Address Below On Or Before 9:00 A.m. Of December 16, 2024 At Bac Office, @ Municipal Planning & Development Office (mpdo), Mapanas, Northern Samar. All Bids Must Be Accompanied By A Bid Security In Any Of The Acceptable Forms And In The Amount Stated In Itb Clause 18. Bids Will Be Opened In The Presence Of The Bidders’ Authorized Representatives Who Choose To Attend At The Address Below. Late Bids Shall Not Be Accepted. The Bidder May Request That The Bid Documents Be Sent To Them By Mail Or Courier, And For This, The Bidder Shall Pay The Amount In Philippine Peso To Cover The Cost Of Mail Or Courier Delivery. The Fee For Obtaining A Copy Of The Bid Documents And The Cost Of Mail Or Courier Shall Be Paid By The Bidder Thru S Cashier’s Check Or Manager’s Check Issued In Favor Of The Municipality Of Mapanas. 6. The Lgu- Mapanas, Northern Samar Reserves The Right To Accept Or Reject Any Bid, To Annul The Bidding Process, And To Reject All Bids At Any Time Prior To Contract Award, Without Thereby Incurring Any Liability To The Affected Bidder Or Bidders. 7. For Further Information, Please Refer To: Reno C. Salazar Bac Secretary Mapanas, Northern Samar Mobile # 09459852914 Ma. Teresa L. Minguez Bac Chairperson Mapanas N. Samar Mobile # 09778033758 Table Of Contents A. General 11 1. Scope Of Bid 11 2. Source Of Funds 11 3. Corrupt, Fraudulent, Collusive, And Coercive Practices 11 4. Conflict Of Interest 12 5. Eligible Bidders 14 6. Bidder’s Responsibilities 15 7. Origin Of Goods And Services 17 8. Subcontracts 17 B. Contents Of Bidding Documents 17 9. Pre-bid Conference 17 10. Clarification And Amendment Of Bidding Documents 18 C. Preparation Of Bids 18 11. Language Of Bids 18 12. Documents Comprising The Bid: Eligibility And Technical Components 18 13. Documents Comprising The Bid: Financial Component 21 14. Alternative Bids 21 15. Bid Prices 22 16. Bid Currencies 22 17. Bid Validity 23 18. Bid Security 23 19. Format And Signing Of Bids 25 20. Sealing And Marking Of Bids 26 D. Submission And Opening Of Bids 26 21. Deadline For Submission Of Bids 26 22. Late Bids 26 23. Modification And Withdrawal Of Bids 27 24. Opening And Preliminary Examination Of Bids 27 E. Evaluation And Comparison Of Bids 28 25. Process To Be Confidential 28 26. Clarification Of Bids 29 27. Detailed Evaluation And Comparison Of Bids 29 28. Post Qualification 30 29. Reservation Clause 31 F. Award Of Contract 32 30. Contract Award 32 31. Signing Of The Contract 33 32. Performance Security 33 33. Notice To Proceed 34 A. General 1. Scope Of Bid 1.1. The Procuring Entity As Defined In The Bds, Invites Bids For The Construction Of Works, As Described In Section Vi. Specifications. The Name And Identification Number Of The Contract Is Provided In The Bds. 1.2. The Successful Bidder Will Be Expected To Complete The Works By The Intended Completion Date Specified In Scc Clause 1.16. 2. Source Of Funds The Procuring Entity Has A Budget Or Has Applied For Or Received Funds From The Funding Source Named In The Bds, And In The Amount Indicated In The Bds. It Intends To Apply Part Of The Funds Received For The Project, As Defined In The Bds, To Cover Eligible Payments Under The Contract For The Works. 3. Corrupt, Fraudulent, Collusive, And Coercive Practices 3.1. Unless Otherwise Specified In The Bds, The Procuring Entity, As Well As Bidders And Contractors, Shall Observe The Highest Standard Of Ethics During The Procurement And Execution Of The Contract. In Pursuance Of This Policy, The Funding Source: (a) Defines, For Purposes Of This Provision, The Terms Set Forth Below As Follows: (i) "corrupt Practice" Means Behavior On The Part Of Officials In The Public Or Private Sectors By Which They Improperly And Unlawfully Enrich Themselves, Others, Or Induce Others To Do So, By Misusing The Position In Which They Are Placed, And Includes The Offering, Giving, Receiving, Or Soliciting Of Anything Of Value To Influence The Action Of Any Such Official In The Procurement Process Or In Contract Execution; Entering, On Behalf Of The Procuring Entity, Into Any Contract Or Transaction Manifestly And Grossly Disadvantageous To The Same, Whether Or Not The Public Officer Profited Or Will Profit Thereby, And Similar Acts As Provided In Republic Act 3019; (ii) "fraudulent Practice" Means A Misrepresentation Of Facts In Order To Influence A Procurement Process Or The Execution Of A Contract To The Detriment Of The Procuring Entity, And Includes Collusive Practices Among Bidders (prior To Or After Bid Submission) Designed To Establish Bid Prices At Artificial, Non-competitive Levels And To Deprive The Procuring Entity Of The Benefits Of Free And Open Competition; (iii) “collusive Practices” Means A Scheme Or Arrangement Between Two Or More Bidders, With Or Without The Knowledge Of The Procuring Entity, Designed To Establish Bid Prices At Artificial, Non-competitive Levels; And (iv) “coercive Practices” Means Harming Or Threatening To Harm, Directly Or Indirectly, Persons, Or Their Property To Influence Their Participation In A Procurement Process, Or Affect The Execution Of A Contract; (v) “obstructive Practice” Is (aa) Deliberately Destroying, Falsifying, Altering Or Concealing Of Evidence Material To An Administrative Proceedings Or Investigation Or Making False Statements To Investigators In Order To Materially Impede An Administrative Proceedings Or Investigation Of The Procuring Entity Or Any Foreign Government/foreign Or International Financing Institution Into Allegations Of A Corrupt, Fraudulent, Coercive Or Collusive Practice; And/or Threatening, Harassing Or Intimidating Any Party To Prevent It From Disclosing Its Knowledge Of Matters Relevant To The Administrative Proceedings Or Investigation Or From Pursuing Such Proceedings Or Investigation; Or (bb) Acts Intended To Materially Impede The Exercise Of The Inspection And Audit Rights Of The Procuring Entity Or Any Foreign Government/foreign Or International Financing Institution Herein. (b) Will Reject A Proposal For Award If It Determines That The Bidder Recommended For Award Has Engaged In Corrupt Or Fraudulent Practices In Competing For The Contract; And (c) Will Declare A Firm Ineligible, Either Indefinitely Or For A Stated Period Of Time, To Be Awarded Contract Funded By The Funding Source If It At Any Time Determines That The Firm Has Engaged In Corrupt Or Fraudulent Practices In Competing Or, Or In Executing, A Contract Funded By The Funding Source. 3.2. Further, The Procuring Entity Will Seek To Impose The Maximum Civil, Administrative, And/or Criminal Penalties Available Under The Applicable Laws On Individuals And Organizations Deemed To Be Involved In Any Of The Practices Mentioned In Itb Clause 3.1(a). 3.3. Furthermore, The Funding Source And The Procuring Entity Reserve The Right To Inspect And Audit Records And Accounts Of A Contractor In The Bidding For And Performance Of A Contract Themselves Or Through Independent Auditors As Reflected In The Gcc Clause 34. 4. Conflict Of Interest 4.1. All Bidders Found To Have Conflicting Interests Shall Be Disqualified To Participate In The Procurement At Hand, Without Prejudice To The Imposition Of Appropriate Administrative, Civil, And Criminal Sanctions. A Bidder May Be Considered To Have Conflicting Interests With Another Bidder In Any Of The Events Described In Paragraphs (a) Through (c) And A General Conflict Of Interest In Any Of The Circumstances Set Out In Paragraphs (d) Through (g) Below: (a) A Bidder Has Controlling Shareholders In Common With Another Bidder; (b) A Bidder Receives Or Has Received Any Direct Or Indirect Subsidy From Any Other Bidder; (c) A Bidder Has The Same Legal Representative As That Of Another Bidder For Purposes Of This Bid; (d) A Bidder Has A Relationship, Directly Or Through Third Parties, That Puts Them In A Position To Have Access To Information About Or Influence On The Bid Of Another Bidder Or Influence The Decisions Of The Procuring Entity Regarding This Bidding Process. This Will Include A Firm Or An Organization Who Lends, Or Temporarily Seconds, Its Personnel To Firms Or Organizations Which Are Engaged In Consulting Services For The Preparation Related To Procurement For Or Implementation Of The Project If The Personnel Would Be Involved In Any Capacity On The Same Project; (e) A Bidder Submits More Than One Bid In This Bidding Process. However, This Does Not Limit The Participation Of Subcontractors In More Than One Bid; (f) A Bidder Who Participated As A Consultant In The Preparation Of The Design Or Technical Specifications Of The Goods And Related Services That Are The Subject Of The Bid; Or (g) A Bidder Who Lends, Or Temporary Seconds, Its Personnel To Firms Or Organizations Which Are Engaged In Consulting Services For The Preparation Related To Procurement For Or Implementation Of The Project, If The Personnel Would Be Involved In Any Capacity On The Same Project. 4.2. In Accordance With Section 47 Of The Irr Of Ra 9184, All Bidding Documents Shall Be Accompanied By A Sworn Affidavit Of The Bidder That It Is Not Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), Members Of The Technical Working Group (twg), Members Of The Bac Secretariat, The Head Of The Project Management Office (pmo) Or The End-user Unit, And The Project Consultants, By Consanguinity Or Affinity Up To The Third Civil Degree. On The Part Of The Bidder, This Clause Shall Apply To The Following Persons: (a) If The Bidder Is An Individual Or A Sole Proprietorship, To The Bidder Himself; (b) If The Bidder Is A Partnership, To All Its Officers And Members; (c) If The Bidder Is A Corporation, To All Its Officers, Directors, And Controlling Stockholders; And (d) If The Bidder Is A Joint Venture (jv), The Provisions Of Items (a), (b), Or (c) Of This Clause Shall Correspondingly Apply To Each Of The Members Of The Said Jv, As May Be Appropriate. Relationship Of The Nature Described Above Or Failure To Comply With This Clause Will Result In The Automatic Disqualification Of A Bidder. 5. Eligible Bidders 5.1. Unless Otherwise Indicated In The Bds, The Following Persons Shall Be Eligible To Participate In This Bidding: (a) Duly Licensed Filipino Citizens/sole Proprietorships; (b) Partnerships Duly Organized Under The Laws Of The Philippines And Of Which At Least Seventy Five Percent (75%) Of The Interest Belongs To Citizens Of The Philippines; (c) Corporations Duly Organized Under The Laws Of The Philippines, And Of Which At Least Seventy Five Percent (75%) Of The Outstanding Capital Stock Belongs To Citizens Of The Philippines; (d) Cooperatives Duly Organized Under The Laws Of The Philippines, And Of Which At Least Seventy Five Percent (75%) Of The Interest Belongs To Citizens Of The Philippines; And (e) Persons/entities Forming Themselves Into A Jv, I.e., A Group Of Two (2) Or More Persons/entities That Intend To Be Jointly And Severally Responsible Or Liable For A Particular Contract: Provided, However, That, In Accordance With Letter Of Instructions No. 630, Filipino Ownership Or Interest Of The Joint Venture Concerned Shall Be At Least Seventy Five Percent (75%): Provided, Further, That Joint Ventures In Which Filipino Ownership Or Interest Is Less Than Seventy Five Percent (75%) May Be Eligible Where The Structures To Be Built Require The Application Of Techniques And/or Technologies Which Are Not Adequately Possessed By A Person/entity Meeting The Seventy Five Percent (75%) Filipino Ownership Requirement: Provided, Finally, That In The Latter Case, Filipino Ownership Or Interest Shall Not Be Less Than Twenty Five Percent (25%). For This Purpose Filipino Ownership Or Interest Shall Be Based On The Contributions Of Each Of The Members Of The Joint Venture As Specified In Their Jva. 5.2. The Procuring Entity May Also Invite Foreign Bidders When Provided For Under Any Treaty Or International Or Executive Agreement As Specified In The Bds. 5.3. Government Corporate Entities May Be Eligible To Participate Only If They Can Establish That They (a) Are Legally And Financially Autonomous, (b) Operate Under Commercial Law, And (c) Are Not Dependent Agencies Of The Gop Or The Procuring Entity. 5.4. (a) Unless Otherwise Provided In The Bds, The Bidder Must Have Completed, Within Ten (10) Years From The Submission Of Bids, A Single Contract That Is Similar To This Project, Equivalent To At Least Fifty Percent (50%) Of The Abc Adjusted To Current Prices Using The National Statistics Office Consumer Price Index. (b) For Foreign-funded Procurement, The Procuring Entity And The Foreign Government/foreign Or International Financing Institution May Agree On Another Track Record Requirement, As Specified In The Bds. For This Purpose, Contracts Similar To The Project Shall Be Those Described In Thebds, And Completed Within The Period Stated In The Invitation To Bid And Itb Clause 12.1(a)(iii). 5.5. The Bidder Must Submit A Computation Of Its Net Financial Contracting Capacity (nfcc) Or A Commitment From A Universal Or Commercial Bank To Extend A Credit Line In Its Favor If Awarded The Contract For This Project (clc). The Nfcc, Computed Using The Following Formula, Must Be At Least Equal To The Abc To Be Bid: Nfcc = [(current Assets Minus Current Liabilities) (k)] Minus The Value Of All Outstanding Or Uncompleted Portions Of The Projects Under Ongoing Contracts, Including Awarded Contracts Yet To Be Started Coinciding With The Contract For This Project. Where: K = 10 For A Contract Duration Of One Year Or Less, 15 For A Contract Duration Of More Than One Year Up To Two Years, And 20 For A Contract Duration Of More Than Two Years. The Clc Must Be At Least Equal To Ten Percent (10%) Of The Abc For This Project. If Issued By A Foreign Bank, It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank. In The Case Of Local Government Units (lgus), The Bidder May Also Submit Clc From Other Banks Certified By The Bangko Sentral Ng Pilipinas (bsp) As Authorized To Issue Such Financial Instrument. 6. Bidder’s Responsibilities 6.1. The Bidder Or Its Duly Authorized Representative Shall Submit A Sworn Statement In The Form Prescribed In Section Ix. Bidding Forms As Required In Itb Clause 12.1(b)(iii). 6.2. The Bidder Is Responsible For The Following: (a) Having Taken Steps To Carefully Examine All Of The Bidding Documents; (b) Having Acknowledged All Conditions, Local Or Otherwise, Affecting The Implementation Of The Contract; (c) Having Made An Estimate Of The Facilities Available And Needed For The Contract To Be Bid, If Any; (d) Having Complied With Its Responsibility To Inquire Or Secure Supplemental/bid Bulletin/s As Provided Under Itb Clause 10.3. (e) Ensuring That It Is Not “blacklisted” Or Barred From Bidding By The Gop Or Any Of Its Agencies, Offices, Corporations, Or Lgus, Including Foreign Government/foreign Or International Financing Institution Whose Blacklisting Rules Have Been Recognized By The Gppb; (f) Ensuring That Each Of The Documents Submitted In Satisfaction Of The Bidding Requirements Is An Authentic Copy Of The Original, Complete, And All Statements And Information Provided Therein Are True And Correct; (g) Authorizing The Head Of The Procuring Entity Or Its Duly Authorized Representative/s To Verify All The Documents Submitted; (h) Ensuring That The Signatory Is The Duly Authorized Representative Of The Bidder, And Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary And/or To Represent The Bidder In The Bidding, With The Duly Notarized Secretary’s Certificate Attesting To Such Fact, If The Bidder Is A Corporation, Partnership, Cooperative, Or Joint Venture; (i) Complying With The Disclosure Provision Under Section 47 Of The Act In Relation To Other Provisions Of Republic Act 3019; And (j) Complying With Existing Labor Laws And Standards, If Applicable. Failure To Observe Any Of The Above Responsibilities Shall Be At The Risk Of The Bidder Concerned. 6.3. The Bidder, By The Act Of Submitting Its Bid, Shall Be Deemed To Have Inspected The Site, Determined The General Characteristics Of The Contract Works And The Conditions For This Project And Examine All Instructions, Forms, Terms, And Project Requirements In The Bidding Documents. 6.4. It Shall Be The Sole Responsibility Of The Prospective Bidder To Determine And To Satisfy Itself By Such Means As It Considers Necessary Or Desirable As To All Matters Pertaining To This Project, Including: (a) The Location And The Nature Of The Contract, Project, Or Work; (b) Climatic Conditions; (c) Transportation Facilities; (c) Nature And Condition Of The Terrain, Geological Conditions At The Site Communication Facilities, Requirements, Location And Availability Of Construction Aggregates And Other Materials, Labor, Water, Electric Power And Access Roads; And (d) Other Factors That May Affect The Cost, Duration And Execution Or Implementation Of The Contract, Project, Or Work. 6.5. The Procuring Entity Shall Not Assume Any Responsibility Regarding Erroneous Interpretations Or Conclusions By The Prospective Or Eligible Bidder Out Of The Data Furnished By The Procuring Entity. 6.6. Before Submitting Their Bids, The Bidders Are Deemed To Have Become Familiar With All Existing Laws, Decrees, Ordinances, Acts And Regulations Of The Philippines Which May Affect The Contract In Any Way. 6.7. The Bidder Shall Bear All Costs Associated With The Preparation And Submission Of His Bid, And The Procuring Entity Will In No Case Be Responsible Or Liable For Those Costs, Regardless Of The Conduct Or Outcome Of The Bidding Process. 6.8. Bidders Should Note That The Procuring Entity Will Only Accept Bids Only From Those That Have Paid The Nonrefundable Fee For The Bidding Documents At The Office Indicated In The Invitation To Bid. 7. Origin Of Goods And Services There Is No Restriction On The Origin Of Goods, Or Contracting Of Works Or Services Other Than Those Prohibited By A Decision Of The United Nations Security Council Taken Under Chapter Vii Of The Charter Of The United Nations. 8. Subcontracts 8.1. Unless Otherwise Specified In The Bds, The Bidder May Subcontract Portions Of The Works To An Extent As May Be Approved By The Procuring Entity And Stated In The Bds. However, Subcontracting Of Any Portion Shall Not Relieve The Bidder From Any Liability Or Obligation That May Arise From The Contract For This Project. 8.2. Subcontractors Must Submit The Documentary Requirements Under Itb Clause 12 And Comply With The Eligibility Criteria Specified In The Bds. In The Event That Any Subcontractor Is Found By The Procuring Entity To Be Ineligible, The Subcontracting Of Such Portion Of The Works Shall Be Disallowed. 8.3. The Bidder May Identify The Subcontractor To Whom A Portion Of The Works Will Be Subcontracted At Any Stage Of The Bidding Process Or During Contract Implementation. If The Bidder Opts To Disclose The Name Of The Subcontractor During Bid Submission, The Bidder Shall Include The Required Documents As Part Of The Technical Component Of Its Bid. B. Contents Of Bidding Documents 9. Pre-bid Conference 9.1. (a) If So Specified In The Bds, A Pre-bid Conference Shall Be Held At The Venue And On The Date Indicated Therein, To Clarify And Address The Bidders’ Questions On The Technical And Financial Components Of This Project. (b) The Pre-bid Conference Shall Be Held At Least Twelve (12) Calendar Days Before The Deadline For The Submission Of And Receipt Of Bids. If The Procuring Entity Determines That, By Reason Of The Method, Nature, Or Complexity Of The Contract To Be Bid, Or When International Participation Will Be More Advantageous To The Gop, A Longer Period For The Preparation Of Bids Is Necessary, The Pre-bid Conference Shall Be Held At Least Thirty (30) Calendar Days Before The Deadline For The Submission And Receipt Of Bids, As Specified In The Bds. 9.2. Bidders Are Encouraged To Attend The Pre-bid Conference To Ensure That They Fully Understand The Procuring Entity’s Requirements. Non-attendance Of The Bidder Will In No Way Prejudice Its Bid; However, The Bidder Is Expected To Know The Changes And/or Amendments To The Bidding Documents As Recorded In The Minutes Of The Pre-bid Conference And The Supplemental/bid Bulletin. 9.3. Any Statement Made At The Pre-bid Conference Shall Not Modify The Terms Of The Bidding Documents Unless Such Statement Is Specifically Identified In Writing As An Amendment Thereto And Issued As A Supplemental/bid Bulletin. 10. Clarification And Amendment Of Bidding Documents 10.1. Bidders Who Have Purchased The Bidding Documents May Request For Clarification(s) On Any Part Of The Bidding Documents Or For An Interpretation. Such A Request Must Be In Writing And Submitted To The Procuring Entity At The Address Indicated In The Bds At Least Ten (10) Calendar Days Before The Deadline Set For The Submission And Receipt Of Bids. 10.2. Supplemental/bid Bulletins May Be Issued Upon The Procuring Entity’s Initiative For Purposes Of Clarifying Or Modifying Any Provision Of The Bidding Documents Not Later Than Seven (7) Calendar Days Before The Deadline For The Submission And Receipt Of Bids. Any Modification To The Bidding Documents Shall Be Identified As An Amendment. 10.3. Any Supplemental/bid Bulletin Issued By The Bac Shall Also Be Posted On The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity Concerned, If Available. Unless, Otherwise Provided In The Bds, It Shall Be The Responsibility Of All Bidders Who Secure The Bidding Documents To Inquire And Secure Supplemental/bid Bulletins That May Be Issued By The Bac. However, Bidders Who Have Submitted Bids Before The Issuance Of The Supplemental/bid Bulletin Must Be Informed And Allowed To Modify Or Withdraw Their Bids In Accordance With Itb Clause 23. C. Preparation Of Bids 11. Language Of Bids The Bid, As Well As All Correspondence And Documents Relating To The Bid Exchanged By The Bidder And The Procuring Entity, Shall Be Written In English. Supporting Documents And Printed Literature Furnished By The Bidder May Be In Another Language Provided They Are Accompanied By An Accurate Translation In English Certified By The Appropriate Embassy Or Consulate In The Philippines, In Which Case The English Translation Shall Govern, For Purposes Of Interpretation Of The Bid. 12. Documents Comprising The Bid: Eligibility And Technical Components 12.1. Unless Otherwise Indicated In The Bds, The First Envelope Shall Contain The Following Eligibility And Technical Documents: (a) Eligibility Documents – Class "a" Documents: (i) Registration Certificate From The Securities And Exchange Commission (sec), Department Of Trade And Industry (dti) For Sole Proprietorship, Or Cooperative Development Authority (cda) For Cooperatives, Or Any Proof Of Such Registration As Stated In The Bds; (ii) Mayor’s Permit Issued By The City Or Municipality Where The Principal Place Of Business Of The Prospective Bidder Is Located; (iii) Statement Of All Its Ongoing And Completed Government And Private Contracts Within Ten (10) Years From The Submission Of Bids, Including Contracts Awarded But Not Yet Started, If Any. The Statement Shall Include, For Each Contract, The Following: (iii.1) Name Of The Contract; (iii.2) Date Of The Contract; (iii.3) Contract Duration; (iii.4) Owner’s Name And Address; (iii.5) Nature Of Work; (iii.6) Contractor’s Role (whether Sole Contractor, Subcontractor, Or Partner In A Jv) And Percentage Of Participation; (iii.7) Total Contract Value At Award; (iii.8) Date Of Completion Or Estimated Completion Time; (iii.9) Total Contract Value At Completion, If Applicable; (iii.10) Percentages Of Planned And Actual Accomplishments, If Applicable; (iii.11) Value Of Outstanding Works, If Applicable; (iii.12) The Statement Shall Be Supported By The Notices Of Award And/or Notices To Proceed Issued By The Owners; And (iii.13) The Statement Shall Be Supported By The Constructors Performance Evaluation System (cpes) Rating Sheets, And/or Certificates Of Completion And Owner’s Acceptance, If Applicable; (iv) Unless Otherwise Provided In The Bds, Valid Philippine Contractors Accreditation Board (pcab) License And Registration For The Type And Cost Of The Contract For This Project; (v) Audited Financial Statements, Showing, Among Others, The Prospective Total And Current Assets And Liabilities, Stamped “received” By The Bir Or Its Duly Accredited And Authorized Institutions, For The Preceding Calendar Year Which Should Not Be Earlier Than Two (2) Years From The Date Of Bid Submission; (vi) Nfcc Computation Or Clc In Accordance With Itb Clause 5.5; And Class "b" Document: (vii) If Applicable, Valid Joint Venture Agreement (jva) Or, In Lieu Thereof, Duly Notarized Statements From All The Potential Joint Venture Partners Stating That They Will Enter Into And Abide By The Provisions Of The Jva In The Instance That The Bid Is Successful Shall Be Included In The Bid. (b) Technical Documents – (i) Bid Security As Prescribed In Itb Clause 18. If The Bidder Opts To Submit The Bid Security In The Form Of: (i.1) A Bank Draft/guarantee Or An Irrevocable Letter Of Credit Issued By A Foreign Bank, It Shall Be Accompanied By A Confirmation From A Universal Or Commercial Bank; Or (i.2) A Surety Bond Accompanied By A Certification Coming From An Authorized Insurance Commission That A Surety Or Insurance Company Is Authorized To Issue Such Instrument; (ii) Project Requirements, Which Shall Include The Following: (ii.1) Organizational Chart For The Contract To Be Bid; (ii.2) List Of Contractor’s Personnel (viz, Project Manager, Project Engineers, Materials Engineers, And Foremen), To Be Assigned To The Contract To Be Bid, With Their Complete Qualification And Experience Data; And (ii.3) List Of Contractor’s Equipment Units, Which Are Owned, Leased, And/or Under Purchase Agreements, Supported By Certification Of Availability Of Equipment From The Equipment Lessor/vendor For The Duration Of The Project; And (iii) Sworn Statement In Accordance With Section 25.2(b)(iv) Of The Irr Of Ra 9184 And Using The Form Prescribed In Section Ix. Bidding Forms. 13. Documents Comprising The Bid: Financial Component 13.1. Unless Otherwise Stated In The Bds, The Financial Component Of The Bid Shall Contain The Following: (a) Financial Bid Form In Accordance With The Form Prescribed In Section Ix. Bidding Forms; And (b) Any Other Document Related To The Financial Component Of The Bid As Stated In The Bds. 13.2. (a) Unless Indicated In The Bds, All Bids That Exceed The Abc Shall Not Be Accepted. (b) Unless Otherwise Indicated In The Bds, For Foreign-funded Procurement, A Ceiling May Be Applied To Bid Prices Provided The Following Conditions Are Met: (i) Bidding Documents Are Obtainable Free Of Charge On A Freely Accessible Website. If Payment Of Bidding Documents Is Required By The Procuring Entity, Payment Could Be Made Upon The Submission Of Bids. (ii) The Procuring Entity Has Procedures In Place To Ensure That The Abc Is Based On Recent Estimates Made By The Engineer Or The Responsible Unit Of The Procuring Entity And That The Estimates Are Based On Adequate Detailed Engineering (in The Case Of Works) And Reflect The Quality, Supervision And Risk And Inflationary Factors, As Well As Prevailing Market Prices, Associated With The Types Of Works Or Goods To Be Procured. (iii) The Procuring Entity Has Trained Cost Estimators On Estimating Prices And Analyzing Bid Variances. In The Case Of Infrastructure Projects, The Procuring Entity Must Also Have Trained Quantity Surveyors. (iv) The Procuring Entity Has Established A System To Monitor And Report Bid Prices Relative To Abc And Engineer’s/procuring Entity’s Estimate. (v) The Procuring Entity Has Established A Monitoring And Evaluation System For Contract Implementation To Provide A Feedback On Actual Total Costs Of Goods And Works. 14. Alternative Bids 14.1. Alternative Bids Shall Be Rejected. For This Purpose, Alternative Bid Is An Offer Made By A Bidder In Addition Or As A Substitute To Its Original Bid Which May Be Included As Part Of Its Original Bid Or Submitted Separately Therewith For Purposes Of Bidding. A Bid With Options Is Considered An Alternative Bid Regardless Of Whether Said Bid Proposal Is Contained In A Single Envelope Or Submitted In Two (2) Or More Separate Bid Envelopes. 14.2. Bidders Shall Submit Offers That Comply With The Requirements Of The Bidding Documents, Including The Basic Technical Design As Indicated In The Drawings And Specifications. Unless There Is A Value Engineering Clause In The Bds, Alternative Bids Shall Not Be Accepted. 14.3. Each Bidder Shall Submit Only One Bid, Either Individually Or As A Partner In A Jv. A Bidder Who Submits Or Participates In More Than One Bid (other Than As A Subcontractor If A Subcontractor Is Permitted To Participate In More Than One Bid) Will Cause All The Proposals With The Bidder’s Participation To Be Disqualified. This Shall Be Without Prejudice To Any Applicable Criminal, Civil And Administrative Penalties That May Be Imposed Upon The Persons And Entities Concerned. 15. Bid Prices 15.1. The Contract Shall Be For The Whole Works, As Described In Itb Clause 1.1, Based On The Priced Bill Of Quantities Submitted By The Bidder. 15.2. The Bidder Shall Fill In Rates And Prices For All Items Of The Works Described In The Bill Of Quantities. Bids Not Addressing Or Providing All Of The Required Items In The Bidding Documents Including, Where Applicable, Bill Of Quantities, Shall Be Considered Non-responsive And, Thus, Automatically Disqualified. In This Regard, Where A Required Item Is Provided, But No Price Is Indicated, The Same Shall Be Considered As Non-responsive, But Specifying A "0" (zero) For The Said Item Would Mean That It Is Being Offered For Free To The Government. 15.3. All Duties, Taxes, And Other Levies Payable By The Contractor Under The Contract, Or For Any Other Cause, Prior To The Deadline For Submission Of Bids, Shall Be Included In The Rates, Prices, And Total Bid Price Submitted By The Bidder. 15.4. All Bid Prices For The Given Scope Of Work In The Contract As Awarded Shall Be Considered As Fixed Prices, And Therefore Not Subject To Price Escalation During Contract Implementation, Except Under Extraordinary Circumstances As Specified In Gcc Clause 48. Price Escalation May Be Allowed In Extraordinary Circumstances As May Be Determined By The National Economic And Development Authority In Accordance With The Civil Code Of The Philippines, And Upon The Recommendation Of The Procuring Entity. Furthermore, In Cases Where The Cost Of The Awarded Contract Is Affected By Any Applicable New Laws, Ordinances, Regulations, Or Other Acts Of The Gop, Promulgated After The Date Of Bid Opening, A Contract Price Adjustment Shall Be Made Or Appropriate Relief Shall Be Applied On A No Loss-no Gain Basis. 16. Bid Currencies 16.1. All Bid Prices Shall Be Quoted In Philippine Pesos Unless Otherwise Provided In The Bds. However, For Purposes Of Bid Evaluation, Bids Denominated In Foreign Currencies Shall Be Converted To Philippine Currency Based On The Exchange Rate Prevailing On The Day Of The Bid Opening. 16.2. If So Allowed In Accordance With Itb Clause 16.1, The Procuring Entity For Purposes Of Bid Evaluation And Comparing The Bid Prices Will Convert The Amounts In Various Currencies In Which The Bid Price Is Expressed To Philippine Pesos At The Exchange Rate As Published In The Bsp Reference Rate Bulletin On The Day Of The Bid Opening. 16.3. Unless Otherwise Specified In The Bds, Payment Of The Contract Price Shall Be Made In Philippine Pesos. 17. Bid Validity 17.1. Bids Shall Remain Valid For The Period Specified In The Bds Which Shall Not Exceed One Hundred Twenty (120) Calendar Days From The Date Of The Opening Of Bids. 17.2. In Exceptional Circumstances, Prior To The Expiration Of The Bid Validity Period, The Procuring Entity May Request Bidders To Extend The Period Of Validity Of Their Bids. The Request And The Responses Shall Be Made In Writing. The Bid Security Described In Itb Clause 18 Should Also Be Extended Corresponding To The Extension Of The Bid Validity Period At The Least. A Bidder May Refuse The Request Without Forfeiting Its Bid Security, But His Bid Shall No Longer Be Considered For Further Evaluation And Award. A Bidder Granting The Request Shall Not Be Required Or Permitted To Modify Its Bid. 18. Bid Security 18.1. The Bid Security In The Amount Stated In The Bds Shall Be Equal To The Percentage Of The Abc In Accordance With The Following Schedule: Form Of Bid Security Amount Of Bid Security (equal To Percentage Of The Abc) (a) Cash Or Cashier’s/manager’s Check Issued By A Universal Or Commercial Bank. Two Percent (2%) (b) Bank Draft/guarantee Or Irrevocable Letter Of Credit Issued By A Universal Or Commercial Bank: Provided, However, That It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank. (c) Surety Bond Callable Upon Demand Issued By A Surety Or Insurance Company Duly Certified By The Insurance Commission As Authorized To Issue Such Security; And/or Five Percent (5%) (d) Any Combination Of The Foregoing. Proportionate To Share Of Form With Respect To Total Amount Of Security For Biddings Conducted By Local Government Units, The Bidder May Also Submit Bid Securities In The Form Of Cashier’s/manager’s Check, Bank Draft/guarantee, Or Irrevocable Letter Of Credit From Other Banks Certified By The Bsp As Authorized To Issue Such Financial Statement. 18.2. The Bid Security Should Be Valid For The Period Specified In The Bds. Any Bid Not Accompanied By An Acceptable Bid Security Shall Be Rejected By The Procuring Entity As Non-responsive. 18.3. No Bid Securities Shall Be Returned To Bidders After The Opening Of Bids And Before Contract Signing, Except To Those That Failed Or Declared As Post-disqualified, Upon Submission Of A Written Waiver Of Their Right To File A Motion For Reconsideration And/or Protest. Without Prejudice On Its Forfeiture, Bid Securities Shall Be Returned Only After The Bidder With The Lowest Calculated Responsive Bid Has Signed The Contract And Furnished The Performance Security, But In No Case Later Than The Expiration Of The Bid Security Validity Period Indicated In Itb Clause 18.2. 18.4. Upon Signing And Execution Of The Contract, Pursuant To Itb Clause 31, And The Posting Of The Performance Security, Pursuant To Itb Clause 32, The Successful Bidder’s Bid Security Will Be Discharged, But In No Case Later Than The Bid Security Validity Period As Indicated In Itb Clause 18.2. 18.5. The Bid Security May Be Forfeited: (a) If A Bidder: (i) Withdraws Its Bid During The Period Of Bid Validity Specified In Itb Clause 17; (ii) Does Not Accept The Correction Of Errors Pursuant To Itb Clause 27.3(b); (iii) Fails To Submit The Requirements Within The Prescribed Period, Or A Finding Against Their Veracity, As Stated In Itb Clause 28.2; (iv) Submission Of Eligibility Requirements Containing False Information Or Falsified Documents; (v) Submission Of Bids That Contain False Information Or Falsified Documents, Or The Concealment Of Such Information In The Bids In Order To Influence The Outcome Of Eligibility Screening Or Any Other Stage Of The Public Bidding; (vi) Allowing The Use Of One’s Name, Or Using The Name Of Another For Purposes Of Public Bidding; (vii) Withdrawal Of A Bid, Or Refusal To Accept An Award, Or Enter Into Contract With The Government Without Justifiable Cause, After The Bidder Had Been Adjudged As Having Submitted The Lowest Calculated And Responsive Bid; (viii) Refusal Or Failure To Post The Required Performance Security Within The Prescribed Time; (ix) Refusal To Clarify Or Validate In Writing Its Bid During Post-qualification Within A Period Of Seven (7) Calendar Days From Receipt Of The Request For Clarification; (x) Any Documented Attempt By A Bidder To Unduly Influence The Outcome Of The Bidding In His Favor; (xi) Failure Of The Potential Joint Venture Partners To Enter Into The Joint Venture After The Bid Is Declared Successful; Or (xii) All Other Acts That Tend To Defeat The Purpose Of The Competitive Bidding, Such As Habitually Withdrawing From Bidding, Submitting Late Bids Or Patently Insufficient Bid, For At Least Three (3) Times Within A Year, Except For Valid Reasons. (b) If The Successful Bidder: (i) Fails To Sign The Contract In Accordance With Itb Clause 31; (ii) Fails To Furnish Performance Security In Accordance With Itb Clause 32. 19. Format And Signing Of Bids 19.1. Bidders Shall Submit Their Bids Through Their Duly Authorized Representative Using The Appropriate Forms Provided In Section Ix. Bidding Forms On Or Before The Deadline Specified In The Itb Clause 21 In Two (2) Separate Sealed Bid Envelopes, And Which Shall Be Submitted Simultaneously. The First Shall Contain The Technical Component Of The Bid, Including The Eligibility Requirements Under Itb Clause 12.1, And The Second Shall Contain The Financial Component Of The Bid. 19.2. Forms As Mentioned In Itb Clause 19.1 Must Be Completed Without Any Alterations To Their Format, And No Substitute Form Shall Be Accepted. All Blank Spaces Shall Be Filled In With The Information Requested. 19.3. The Bidder Shall Prepare An Original Of The First And Second Envelopes As Described In Itb Clauses 12 And 13. In Addition, The Bidder Shall Submit Copies Of The First And Second Envelopes. In The Event Of Any Discrepancy Between The Original And The Copies, The Original Shall Prevail. 19.4. The Bid, Except For Unamended Printed Literature, Shall Be Signed, And Each And Every Page Thereof Shall Be Initialed, By The Duly Authorized Representative/s Of The Bidder. 19.5. Any Interlineations, Erasures, Or Overwriting Shall Be Valid Only If They Are Signed Or Initialed By The Duly Authorized Representative/s Of The Bidder. 20. Sealing And Marking Of Bids 20.1. Bidders Shall Enclose Their Original Eligibility And Technical Documents Described In Itb Clause 12, In One Sealed Envelope Marked “original - Technical Component”, And The Original Of Their Financial Component In Another Sealed Envelope Marked “original - Financial Component”, Sealing Them All In An Outer Envelope Marked “original Bid”. 20.2. Each Copy Of The First And Second Envelopes Shall Be Similarly Sealed Duly Marking The Inner Envelopes As “copy No. ___ - Technical Component” And “copy No. ___ – Financial Component” And The Outer Envelope As “copy No. ___”, Respectively. These Envelopes Containing The Original And The Copies Shall Then Be Enclosed In One Single Envelope. 20.3. The Original And The Number Of Copies Of The Bid As Indicated In The Bds Shall Be Typed Or Written In Indelible Ink And Shall Be Signed By The Bidder Or Its Duly Authorized Representative/s. 20.4. All Envelopes Shall: (a) Contain The Name Of The Contract To Be Bid In Capital Letters; (b) Bear The Name And Address Of The Bidder In Capital Letters; (c) Be Addressed To The Procuring Entity’s Bac Identified In Itb Clause 10.1; (d) Bear The Specific Identification Of This Bidding Process Indicated In The Invitation To Bid; And (e) Bear A Warning “do Not Open Before…” The Date And Time For The Opening Of Bids, In Accordance With Itb Clause 21. 20.5. If Bids Are Not Sealed And Marked As Required, The Procuring Entity Will Assume No Responsibility For The Misplacement Or Premature Opening Of The Bid. D. Submission And Opening Of Bids 21. Deadline For Submission Of Bids Bids Must Be Received By The Procuring Entity’s Bac At The Address And On Or Before The Date And Time Indicated In The Bds. 22. Late Bids Any Bid Submitted After The Deadline For Submission And Receipt Of Bids Prescribed By The Procuring Entity, Pursuant To Itb Clause 21, Shall Be Declared “late” And Shall Not Be Accepted By The Procuring Entity. 23. Modification And Withdrawal Of Bids 23.1. The Bidder May Modify Its Bid After It Has Been Submitted; Provided That The Modification Is Received By The Procuring Entity Prior To The Deadline Prescribed For Submission And Receipt Of Bids. The Bidder Shall Not Be Allowed To Retrieve Its Original Bid, But Shall Be Allowed To Submit Another Bid Equally Sealed, Properly Identified, Linked To Its Original Bid Marked As “technical Modification” Or “financial Modification” And Stamped “received” By The Bac. Bid Modifications Received After The Applicable Deadline Shall Not Be Considered And Shall Be Returned To The Bidder Unopened. 23.2. A Bidder May, Through A Letter Of Withdrawal, Withdraw Its Bid After It Has Been Submitted, For Valid And Justifiable Reason; Provided That The Letter Of Withdrawal Is Received By The Procuring Entity Prior To The Deadline Prescribed For Submission And Receipt Of Bids. 23.3. Bids Requested To Be Withdrawn In Accordance With Itb Clause 23.1 Shall Be Returned Unopened To The Bidders. A Bidder May Also Express Its Intention Not To Participate In The Bidding Through A Letter Which Should Reach And Be Stamped By The Bac Before The Deadline For Submission And Receipt Of Bids. A Bidder That Withdraws Its Bid Shall Not Be Permitted To Submit Another Bid, Directly Or Indirectly, For The Same Contract. 23.4. No Bid May Be Modified After The Deadline For Submission Of Bids. No Bid May Be Withdrawn In The Interval Between The Deadline For Submission Of Bids And The Expiration Of The Period Of Bid Validity Specified By The Bidder On The Financial Bid Form. Withdrawal Of A Bid During This Interval Shall Result In The Forfeiture Of The Bidder’s Bid Security, Pursuant To Itb Clause 18.5, And The Imposition Of Administrative, Civil, And Criminal Sanctions As Prescribed By Ra 9184 And Its Irr. 24. Opening And Preliminary Examination Of Bids 24.1. The Bac Shall Open The First Bid Envelopes Of Bidders In Public As Specified In The Bds To Determine Each Bidder’s Compliance With The Documents Prescribed In Itb Clause 12. For This Purpose, The Bac Shall Check The Submitted Documents Of Each Bidder Against A Checklist Of Required Documents To Ascertain If They Are All Present, Using A Non-discretionary “pass/fail” Criterion. If A Bidder Submits The Required Document, It Shall Be Rated “passed” For That Particular Requirement. In This Regard, Bids That Fail To Include Any Requirement Or Are Incomplete Or Patently Insufficient Shall Be Considered As “failed”. Otherwise, The Bac Shall Rate The Said First Bid Envelope As “passed”. 24.2. Unless Otherwise Specified In The Bds, Immediately After Determining Compliance With The Requirements In The First Envelope, The Bac Shall Forthwith Open The Second Bid Envelope Of Each Remaining Eligible Bidder Whose First Bid Envelope Was Rated “passed”. The Second Envelope Of Each Complying Bidder Shall Be Opened Within The Same Day. In Case One Or More Of The Requirements In The Second Envelope Of A Particular Bid Is Missing, Incomplete Or Patently Insufficient, And/or If The Submitted Total Bid Price Exceeds The Abc Unless Otherwise Provided In Itb Clause 13.1(b), The Bac Shall Rate The Bid Concerned As “failed”. Only Bids That Are Determined To Contain All The Bid Requirements For Both Components Shall Be Rated “passed” And Shall Immediately Be Considered For Evaluation And Comparison. 24.3. Letters Of Withdrawal Shall Be Read Out And Recorded During Bid Opening, And The Envelope Containing The Corresponding Withdrawn Bid Shall Be Returned To The Bidder Unopened. If The Withdrawing Bidder’s Representative Is In Attendance, The Original Bid And All Copies Thereof Shall Be Returned To The Representative During The Bid Opening. If The Representative Is Not In Attendance, The Bid Shall Be Returned Unopened By Registered Mail. The Bidder May Withdraw Its Bid Prior To The Deadline For The Submission And Receipt Of Bids, Provided That The Corresponding Letter Of Withdrawal Contains A Valid Authorization Requesting For Such Withdrawal, Subject To Appropriate Administrative Sanctions. 24.4. If A Bidder Has Previously Secured A Certification From The Procuring Entity To The Effect That It Has Previously Submitted The Above-enumerated Class “a” Documents, The Said Certification May Be Submitted In Lieu Of The Requirements Enumerated In Itb Clause 12.1(a), Items (i) To (vi). 24.5. In The Case Of An Eligible Foreign Bidder As Described In Itb Clause 5, The Class “a” Documents Enumerated In Itb Clause 12.1(a) May Be Substituted With The Appropriate Equivalent Documents, If Any, Issued By The Country Of The Foreign Bidder Concerned. 24.6. Each Partner Of A Joint Venture Agreement Shall Likewise Submit The Documents Required In Itb Clauses 12.1(a)(i) And 12.1(a)(ii). Submission Of Documents Required Under Itb Clauses 12.1(a)(iii) To 12.1(a)(vi) By Any Of The Joint Venture Partners Constitutes Compliance. 24.7. A Bidder Determined As “failed” Has Three (3) Calendar Days Upon Written Notice Or, If Present At The Time Of Bid Opening, Upon Verbal Notification Within Which To File A Request For Reconsideration With The Bac: Provided, However, That The Request For Reconsideration Shall Not Be Granted If It Is Established That The Finding Of Failure Is Due To The Fault Of The Bidder Concerned: Provided, Further, That The Bac Shall Decide On The Request For Reconsideration Within Seven (7) Calendar Days From Receipt Thereof. If A Failed Bidder Signifies His Intent To File A Request For Reconsideration, The Bac Shall Keep The Bid Envelopes Of The Said Failed Bidder Unopened And/or Duly Sealed Until Such Time That The Request For Reconsideration Or Protest Has Been Resolved. E. Evaluation And Comparison Of Bids 25. Process To Be Confidential 25.1. Members Of The Bac, Including Its Staff And Personnel, As Well As Its Secretariat And Twg, Are Prohibited From Making Or Accepting Any Kind Of Communication With Any Bidder Regarding The Evaluation Of Their Bids Until The Issuance Of The Notice Of Award, Unless N The Case Of Itb Clause 26. 25.2. Any Effort By A Bidder To Influence The Procuring Entity In The Procuring Entity’s Decision In Respect Of Bid Evaluation, Bid Comparison Or Contract Award Will Result In The Rejection Of The Bidder’s Bid. 26. Clarification Of Bids To Assist In The Evaluation, Comparison And Post-qualification Of The Bids, The Procuring Entity May Ask In Writing Any Bidder For A Clarification Of Its Bid. All Responses To Requests For Clarification Shall Be In Writing. Any Clarification Submitted By A Bidder In Respect To Its Bid And That Is Not In Response To A Request By The Procuring Entity Shall Not Be Considered 27. Detailed Evaluation And Comparison Of Bids 27.1. The Procuring Entity Will Undertake The Detailed Evaluation And Comparison Of Bids Which Have Passed The Opening And Preliminary Examination Of Bids, Pursuant To Itb Clause 24, In Order To Determine The Lowest Calculated Bid. 27.2. In Evaluating The Bids To Get The Lowest Calculated Bid, The Procuring Entity Shall Undertake The Following: (a) The Detailed Evaluation Of The Financial Component Of The Bids, To Establish The Correct Calculated Prices Of The Bids; And (b) The Ranking Of The Total Bid Prices As So Calculated From The Lowest To Highest. The Bid With The Lowest Price Shall Be Identified As The Lowest Calculated Bid. 27.3. The Procuring Entity's Bac Shall Immediately Conduct A Detailed Evaluation Of All Bids Rated “passed,” Using Non-discretionary “pass/fail” Criterion. The Bac Shall Consider The Following In The Evaluation Of Bids: (a) Completeness Of The Bid. Unless The Itb Specifically Allows Partial Bids, Bids Not Addressing Or Providing All Of The Required Items In The Schedule Of Requirements Including, Where Applicable, Bill Of Quantities, Shall Be Considered Non-responsive And, Thus, Automatically Disqualified. In This Regard, Where A Required Item Is Provided, But No Price Is Indicated, The Same Shall Be Considered As Non-responsive, But Specifying A "0" (zero) For The Said Item Would Mean That It Is Being Offered For Free To The Procuring Entity; And (b) Arithmetical Corrections. Consider Computational Errors And Omissions To Enable Proper Comparison Of All Eligible Bids. It May Also Consider Bid Modifications If Expressly Allowed In The Bds. Any Adjustment Shall Be Calculated In Monetary Terms To Determine The Calculated Prices. 27.4. Based On The Detailed Evaluation Of Bids, Those That Comply With The Above-mentioned Requirements Shall Be Ranked In The Ascending Order Of Their Total Calculated Bid Prices, As Evaluated And Corrected For Computational Errors, Discounts And Other Modifications, To Identify The Lowest Calculated Bid. Total Calculated Bid Prices, As Evaluated And Corrected For Computational Errors, Discounts And Other Modifications, Which Exceed The Abc Shall Not Be Considered, Unless Otherwise Indicated In The Bds. 27.5. The Procuring Entity’s Evaluation Of Bids Shall Only Be Based On The Bid Price Quoted In The Financial Bid Form 27.6. Bids Shall Be Evaluated On An Equal Footing To Ensure Fair Competition. For This Purpose, All Bidders Shall Be Required To Include In Their Bids The Cost Of All Taxes, Such As, But Not Limited To, Value Added Tax (vat), Income Tax, Local Taxes, And Other Fiscal Levies And Duties Which Shall Be Itemized In The Bid Form And Reflected In The Detailed Estimates. Such Bids, Including Said Taxes, Shall Be The Basis For Bid Evaluation And Comparison. 28. Post Qualification 28.1. The Procuring Entity Shall Determine To Its Satisfaction Whether The Bidder That Is Evaluated As Having Submitted The Lowest Calculated Bid (lcb) Complies With And Is Responsive To All The Requirements And Conditions Specified In Itb Clauses 5, 12, And 13. 28.2. Within A Non-extendible Period Of Three (3) Calendar Days From Receipt By The Bidder Of The Notice From The Bac That It Submitted The Lcb, The Bidder Shall Submit The Following Documentary Requirements: (a) Tax Clearance Per Executive Order 398, Series Of 2005; (b) Latest Income And Business Tax Returns In The Form Specified In The Bds; (c) Certificate Of Philgeps Registration; And (d) Other Appropriate Licenses And Permits Required By Law And Stated In The Bds. Failure Of The Bidder Declared As Lcb To Duly Submit The Requirements Under This Clause Or A Finding Against The Veracity Of Such, Shall Be Ground For Forfeiture Of The Bid Security And Disqualification Of The Bidder For Award. 28.3. The Determination Shall Be Based Upon An Examination Of The Documentary Evidence Of The Bidder’s Qualifications Submitted Pursuant To Itb Clauses 12 And 13, As Well As Other Information As The Procuring Entity Deems Necessary And Appropriate, Using A Non-discretionary “pass/fail” Criterion. 28.4. If The Bac Determines That The Bidder With The Lowest Calculated Bid Passes All The Criteria For Post-qualification, It Shall Declare The Said Bid As The Lowest Calculated Responsive Bid, And Recommend To The Head Of The Procuring Entity The Award Of Contract To The Said Bidder At Its Submitted Price Or Its Calculated Bid Price, Whichever Is Lower, Subject To Itb Clause 30.3. 28.5. A Negative Determination Shall Result In Rejection Of The Bidder’s Bid, In Which Event The Procuring Entity Shall Proceed To The Next Lowest Calculated Bid To Make A Similar Determination Of That Bidder’s Capabilities To Perform Satisfactorily. If The Second Bidder, However, Fails The Post Qualification, The Procedure For Post Qualification Shall Be Repeated For The Bidder With The Next Lowest Calculated Bid, And So On Until The Lowest Calculated And Responsive Bid Is Determined For Contract Award. 28.6. Within A Period Not Exceeding Seven (7) Calendar Days From The Date Of Receipt Of The Recommendation Of The Bac, The Head Of The Procuring Entity Shall Approve Or Disapprove The Said Recommendation. In The Case Of Government Owned And Government-owned And/or -controlled Corporations (goccs) And Government Financial Institutions (gfis), The Period Provided Herein Shall Be Fifteen (15) Calendar Days. 29. Reservation Clause 29.1. Notwithstanding The Eligibility Or Post-qualification Of A Bidder, The Procuring Entity Concerned Reserves The Right To Review Its Qualifications At Any Stage Of The Procurement Process If It Has Reasonable Grounds To Believe That A Misrepresentation Has Been Made By The Said Bidder, Or That There Has Been A Change In The Bidder’s Capability To Undertake The Project From The Time It Submitted Its Eligibility Requirements. Should Such Review Uncover Any Misrepresentation Made In The Eligibility And Bidding Requirements, Statements Or Documents, Or Any Changes In The Situation Of The Bidder Which Will Affect Its Capability To Undertake The Project So That It Fails The Preset Eligibility Or Bid Evaluation Criteria, The Procuring Entity Shall Consider The Said Bidder As Ineligible And Shall Disqualify It From Submitting A Bid Or From Obtaining An Award Or Contract. 29.2. Based On The Following Grounds, The Procuring Entity Reserves The Right To Reject Any And All Bids, Declare A Failure Of Bidding At Any Time Prior To The Contract Award, Or Not To Award The Contract, Without Thereby Incurring Any Liability, And Make No Assurance That A Contract Shall Be Entered Into As A Result Of The Bidding: (a) If There Is Prima Facie Evidence Of Collusion Between Appropriate Public Officers Or Employees Of The Procuring Entity, Or Between The Bac And Any Of The Bidders, Or If The Collusion Is Between Or Among The Bidders Themselves, Or Between A Bidder And A Third Party, Including Any Act Which Restricts, Suppresses Or Nullifies Or Tends To Restrict, Suppress Or Nullify Competition; (b) If The Procuring Entity’s Bac Is Found To Have Failed In Following The Prescribed Bidding Procedures; Or (c) For Any Justifiable And Reasonable Ground Where The Award Of The Contract Will Not Redound To The Benefit Of The Government As Follows: (i) If The Physical And Economic Conditions Have Significantly Changed So As To Render The Project No Longer Economically, Financially Or Technically Feasible As Determined By The Head Of The Procuring Entity; (ii) If The Project Is No Longer Necessary As Determined By The Head Of The Procuring Entity; And (iii) If The Source Of Funds For The Project Has Been Withheld Or Reduced Through No Fault Of The Procuring Entity. 29.3. In Addition, The Procuring Entity May Likewise Declare A Failure Of Bidding When: (a) No Bids Are Received; (b) All Prospective Bidders Are Declared Ineligible; (c) All Bids Fail To Comply With All The Bid Requirements Or Fail Post-qualification; Or (d) The Bidder With The Lowest Calculated Responsive Bid Refuses, Without Justifiable Cause To Accept The Award Of Contract, And No Award Is Made. F. Award Of Contract 30. Contract Award 30.1. Subject To Itb Clause 28, The Procuring Entity Shall Award The Contract To The Bidder Whose Bid Has Been Determined To Be The Lowest Calculated And Responsive Bid (lcrb). 30.2. Prior To The Expiration Of The Period Of Bid Validity, The Procuring Entity Shall Notify The Successful Bidder In Writing That Its Bid Has Been Accepted, Through A Notice Of Award Received Personally Or Sent By Registered Mail Or Electronically, Receipt Of Which Must Be Confirmed In Writing Within Two (2) Days By The Lcrb And Submitted Personally Or Sent By Registered Mail Or Electronically To The Procuring Entity. 30.3. Notwithstanding The Issuance Of The Notice Of Award, Award Of Contract Shall Be Subject To The Following Conditions: (a) Submission Of The Following Documents Within The Prescribed Period From Receipt By The Bidder Of The Notice That It Has The Lowest Calculated And Responsive Bid: (i) Valid Jva, If Applicable, Within Ten (10) Calendar Days; (ii) Valid Pcab License And Registration For The Type And Cost Of The Contract To Be Bid For Foreign Bidders, Within Thirty (30) Calendar Days, If Allowed Under A Treaty Or International Or Executive Agreement Mentioned In Itb Clause 12.1(a)(iv); (b) Posting Of The Performance Security In Accordance With Itb Clause 32; (c) Signing Of The Contract As Provided In Itb Clause 31; And (d) Approval By Higher Authority, If Required. 31. Signing Of The Contract 31.1. At The Same Time As The Procuring Entity Notifies The Successful Bidder That Its Bid Has Been Accepted, The Procuring Entity Shall Send The Contract Form To The Bidder, Which Contract Has Been Provided In The Bidding Documents, Incorporating Therein All Agreements Between The Parties. 31.2. Within Ten (10) Calendar Days From Receipt Of The Notice Of Award, The Successful Bidder Shall Post The Required Performance Security, Sign And Date The Contract And Return It To The Procuring Entity. 31.3. The Procuring Entity Shall Enter Into Contract With The Successful Bidder Within The Same Ten (10) Calendar Day Period Provided That All The Documentary Requirements Are Complied With. 31.4. The Following Documents Shall Form Part Of The Contract: (a) Contract Agreement; (b) Bidding Documents; (c) Winning Bidder’s Bid, Including The Technical And Financial Proposals, And All Other Documents/statements Submitted; (d) Performance Security; (e) Credit Line In Accordance With Itb Clause 5.5, If Applicable; (f) Notice Of Award Of Contract; And (g) Other Contract Documents That May Be Required By Existing Laws And/or Specified In The Bds. 32. Performance Security 32.1. To Guarantee The Faithful Performance By The Winning Bidder Of Its Obligations Under The Contract, It Shall Post A Performance Security Within A Maximum Period Of Ten (10) Calendar Days From The Receipt Of The Notice Of Award From The Procuring Entity And In No Case Later Than The Signing Of The Contract. 32.2. The Performance Security Shall Be Denominated In Philippine Pesos And Posted In Favor Of The Procuring Entity In An Amount Equal To The Percentage Of The Total Contract Price As Stated In The Bds In Accordance With The Following Schedule: 33. 33.1. Form Of Performance Security Amount Of Performance Security (equal To Percentage Of The Total Contract Price) (a) Cash Or Cashier’s/manager’s Check Issued By A Universal Or Commercial Bank. Ten Percent (10%) (b) Bank Draft/guarantee Or Irrevocable Letter Of Credit Issued By A Universal Or Commercial Bank: Provided, However, That It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank. (c) Surety Bond Callable Upon Demand Issued By A Surety Or Insurance Company Duly Certified By The Insurance Commission As Authorized To Issue Such Security; And/or Thirty Percent (30%) (d) Any Combination Of The Foregoing. Proportionate To Share Of Form With Respect To Total Amount Of Security 33.2. Failure Of The Successful Bidder To Comply With The Above-mentioned Requirement Shall Constitute Sufficient Ground For The Annulment Of The Award And Forfeiture Of The Bid Security, In Which Event The Procuring Entity Shall Initiate And Complete The Post Qualification Of The Second Lowest Calculated Bid. The Procedure Shall Be Repeated Until The Lowest Calculated And Responsive Bid Is Identified And Selected For Contract Award. However If No Bidder Passed Post-qualification, The Bac Shall Declare The Bidding A Failure And Conduct A Re-bidding With Re-advertisement. 34. Notice To Proceed 34.1. Within Three (3) Calendar Days From The Date Of Approval Of The Contract By The Appropriate Government Approving Authority, The Procuring Entity Shall Issue Its Notice To Proceed To The Bidder. 34.2. The Contract Effectivity Date Shall Be Provided In The Notice To Proceed By The Procuring Entity, Which Date Shall Not Be Later Than Seven (7) Calendar Days From The Issuance Of The Notice To Proceed. Section Iii. Bid Data Sheet Bid Data Sheet Itb Clause 1.1 The Procuring Entity Is Lgu- Mapanas, Northern Samar. The Name Of The Contract Is Construction Of Siljagon Multi-purpose Gym Phase 2, Brgy. Siljagon, Mapanas N. Samar The Identification Number Of The Contract Is Pr No-2024-11-103___ 2 The Funding Source Is: 20% Economic Development Fund (edf) For Fy 2025. The Name Of The Project Is: Construction Of Siljagon Multi-purpose Gym Phase 2 Brgy. Siljagon, Mapanas N. Samar 3.1 No Further Instructions. 5.1 No Further Instructions. 5.2 Bidding Is Restricted To Eligible Bidders As Defined In Itb Clause 5.1. 5.4 For This Purpose, Similar Contracts Shall Refer To Bidder’s Annual Turnover From All Works Average Over The Last Three Years Shall Be Equal To 50% Of The Estimated Cost Of The Contract Being Procured. The Bidder Must Have Completed, Within The Past Ten (10) Years From The Submission Of Bids, A Single Contract That Is Similar To This Project, Equivalent To At Least Eighty Percent (80%) Of The Abc. 8.1 “subcontracting Is Not Allowed.” 8.2 “not Applicable”. 9.1 The Procuring Entity Will Hold A Pre-bid Conference For This Project On December 05, 2024 At 10:00 A.m. At Executive Conference 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar. 10.1 The Procuring Entity’s Address Is: The Municipality Of Mapanas, Province Of Northern Samar Ma. Teresa L. Minguez Lgu-bac Chairperson Tel. No. 09778033758 10.3 No Further Instructions. 12.1 Not Applicable 12.1(a)(i) “no Other Acceptable Proof Of Registration Is Recognized.” 12.1(a)(iv) No Further Instructions. 13.1 “no Additional Requirements” 13.1(b) The Abc Is Php2,981,332.95 Any Bid With A Financial Component Exceeding This Amount Shall Not Be Accepted. 14.2 “no Further Instructions.” 15.4 No Further Instruction. 16.1 The Bid Prices Shall Be Quoted In Philippine Pesos. 17.1 Bids Will Be Valid Until 60 Calendar Days After The Bid Submission Deadline Date As Prescribed By The Procuring Entity) 18.1 The Bid Security Shall Be In The Following Amount: 1. The Amount Of 59,626.66 If Bid Security Is In Cash, Cashier’s/manager’s Check, Bank Draft/guarantee Or Irrevocable Letter Of Credit; 2. The Amount Of P149,066.65 If Bid Security Is In Surety Bond; Or 3. Any Combination Of The Foregoing Proportionate To The Share Of Form With Respect To Total Amount Of Security. 18.2 The Bid Security Shall Be Valid Twenty Eight Days Beyond The Validity Period Of The Bid. 20.3 Each Bidder Shall Submit One Original And One Copy Of The First And Second Components Of Its Bid. 21 The Address For Submission Of Bids Is Ma. Teresa L. Minguez Lgu-bac Chairperson Bac Office @ Mpdo, 1st Floor, New Municipal Bldg. Municipality Of Mapanas, Northern Samar The Deadline For Submission Of Bids Is 9:00 A.m. On December 16 , 2024. 22 The Place Of Bid Opening Is Executive Conference Room, 2nd Floor, New Municipal Bldg. Municipality Of Mapanas, Northern Samar. The Date And Time Of Bid Opening Is December 16, 2024 At Exactly 10:00 A.m. 24.2 No Further Instructions. 27.3(b) Bid Modification Is Not Allowed. 27.4 No Further Instructions. 28.2(b) Bidders Have Option To Submit Manually Filed Tax Returns Or Tax Returns Filed Through The Electronic Filing And Payments System (efps). Note: The Latest Income And Business Tax Returns Are Those Within The Last Six Months Preceding The Date Of Bid Submission. 28.2(d) List Licenses And Permits Relevant To The Project And The Corresponding Law Requiring It. 1. Taxpayer’s Identification Number 2. Vat Registration 3. Philippine Contractors Accreditation Board (pcab) License The Requirements Are Applicable Only In A Case Where The Lowest Calculated Bid (lcb) Is Submitted By A Domestic Bidder, And If The Lowest Calculated Bid (lcb) Is Submitted By A Foreign Bidder, This Requirements Are Not Applicable 31.4(g) List Additional Contract Documents Relevant To The Project That May Be Required By Existing Laws And/or The Procuring Entity, Such As Construction Schedule And S-curve, Manpower Schedule, Construction Methods, Equipment Utilization Schedule, Construction Safety And Health Program Approved By The Department Of Labor And Employment, And Pert/cpm. 32.2 The Performance Security Shall Be In The Following Amount: 1. The Amount Of 10% Of Contract If Performance Security Is In Cash, Cashier’s/manager’s Check, Bank Draft/guarantee Or Irrevocable Letter Of Credit; 2. The Amount Of 30% Of Contract If Performance Security Is In Surety Bond; Or 3. Any Combination Of The Foregoing Proportionate To The Share Of Form With Respect To Total Amount Of Security. Section Iv. General Conditions Of Contract Table Of Contents 1. Definitions 41 2. Interpretation 43 3. Governing Language And Law 43 4. Communications 43 5. Possession Of Site 43 6. The Contractor’s Obligations 44 7. Performance Security 45 8. Subcontracting 46 9. Liquidated Damages 46 10. Site Investigation Reports 47 11. The Procuring Entity, Licenses And Permits 47 12. Contractor’s Risk And Warranty Security 47 13. Liability Of The Contractor 49 14. Procuring Entity’s Risk 49 15. Insurance 49 16. Termination For Default Of Contractor 51 17. Termination For Default Of Procuring Entity 51 18. Termination For Other Causes 52 19. Procedures For Termination Of Contracts 53 20. Force Majeure, Release From Performance 56 21. Resolution Of Disputes 56 22. Suspension Of Loan, Credit, Grant, Or Appropriation 57 23. Procuring Entity’s Representative’s Decisions 57 24. Approval Of Drawings And Temporary Works By The Procuring Entity’s Representative 57 25. Acceleration And Delays Ordered By The Procuring Entity’s Representative 58 26. Extension Of The Intended Completion Date 58 27. Right To Vary 58 28. Contractors Right To Claim 59 29. Dayworks 59 30. Early Warning 59 31. Program Of Work 59 32. Management Conferences 60 33. Bill Of Quantities 60 34. Instructions, Inspections And Audits 61 35. Identifying Defects 61 36. Cost Of Repairs 61 37. Correction Of Defects 61 38. Uncorrected Defects 62 39. Advance Payment 62 40. Progress Payments 62 41. Payment Certificates 63 42. Retention 63 43. Variation Orders 64 44. Contract Completion 66 45. Suspension Of Work 66 46. Payment On Termination 67 47. Extension Of Contract Time 67 48. Price Adjustment 68 49. Completion 68 50. Taking Over 69 51. Operating And Maintenance Manuals 69 1. Definitions For Purposes Of This Clause, Boldface Type Is Used To Identify Defined Terms. 1.1. The Arbiter Is The Person Appointed Jointly By The Procuring Entity And The Contractor To Resolve Disputes In The First Instance, As Provided For In Gcc Clause 21. 1.2. Bill Of Quantities Refers To A List Of The Specific Items Of The Work And Their Corresponding Unit Prices, Lump Sums, And/or Provisional Sums. 1.3. The Completion Date Is The Date Of Completion Of The Works As Certified By The Procuring Entity’s Representative, In Accordance With Gcc Clause 49. 1.4. The Contract Is The Contract Between The Procuring Entity And The Contractor To Execute, Complete, And Maintain The Works. 1.5. The Contract Price Is The Price Stated In The Letter Of Acceptance And Thereafter To Be Paid By The Procuring Entity To The Contractor For The Execution Of The Works In Accordance With This Contract. 1.6. Contract Time Extension Is The Allowable Period For The Contractor To Complete The Works In Addition To The Original Completion Date Stated In This Contract. 1.7. The Contractor Is The Juridical Entity Whose Proposal Has Been Accepted By The Procuring Entity And To Whom The Contract To Execute The Work Was Awarded. 1.8. The Contractor’s Bid Is The Signed Offer Or Proposal Submitted By The Contractor To The Procuring Entity In Response To The Bidding Documents. 1.9. Days Are Calendar Days; Months Are Calendar Months. 1.10. Dayworks Are Varied Work Inputs Subject To Payment On A Time Basis For The Contractor’s Employees And Equipment, In Addition To Payments For Associated Materials And Plant. 1.11. A Defect Is Any Part Of The Works Not Completed In Accordance With The Contract. 1.12. The Defects Liability Certificate Is The Certificate Issued By Procuring Entity’s Representative Upon Correction Of Defects By The Contractor. 1.13. The Defects Liability Period Is The One Year Period Between Contract Completion And Final Acceptance Within Which The Contractor Assumes The Responsibility To Undertake The Repair Of Any Damage To The Works At His Own Expense. 1.14. Drawings Are Graphical Presentations Of The Works. They Include All Supplementary Details, Shop Drawings, Calculations, And Other Information Provided Or Approved For The Execution Of This Contract. 1.15. Equipment Refers To All Facilities, Supplies, Appliances, Materials Or Things Required For The Execution And Completion Of The Work Provided By The Contractor And Which Shall Not Form Or Are Not Intended To Form Part Of The Permanent Works. 1.16. The Intended Completion Date Refers To The Date Specified In The Scc When The Contractor Is Expected To Have Completed The Works. The Intended Completion Date May Be Revised Only By The Procuring Entity’s Representative By Issuing An Extension Of Time Or An Acceleration Order. 1.17. Materials Are All Supplies, Including Consumables, Used By The Contractor For Incorporation In The Works. 1.18. The Notice To Proceed Is A Written Notice Issued By The Procuring Entity Or The Procuring Entity’s Representative To The Contractor Requiring The Latter To Begin The Commencement Of The Work Not Later Than A Specified Or Determinable Date. 1.19. Permanent Works All Permanent Structures And All Other Project Features And Facilities Required To Be Constructed And Completed In Accordance With This Contract Which Shall Be Delivered To The Procuring Entity And Which Shall Remain At The Site After The Removal Of All Temporary Works. 1.20. Plant Refers To The Machinery, Apparatus, And The Like Intended To Form An Integral Part Of The Permanent Works. 1.21. The Procuring Entity Is The Party Who Employs The Contractor To Carry Out The Works Stated In The Scc. 1.22. The Procuring Entity’s Representative Refers To The Head Of The Procuring Entity Or His Duly Authorized Representative, Identified In The Scc, Who Shall Be Responsible For Supervising The Execution Of The Works And Administering This Contract. 1.23. The Site Is The Place Provided By The Procuring Entity Where The Works Shall Be Executed And Any Other Place Or Places Which May Be Designated In The Scc, Or Notified To The Contractor By The Procuring Entity’s Representative As Forming Part Of The Site. 1.24. Site Investigation Reports Are Those That Were Included In The Bidding Documents And Are Factual And Interpretative Reports About The Surface And Subsurface Conditions At The Site. 1.25. Slippage Is A Delay In Work Execution Occurring When Actual Accomplishment Falls Below The Target As Measured By The Difference Between The Scheduled And Actual Accomplishment Of The Work By The Contractor As Established From The Work Schedule. This Is Actually Described As A Percentage Of The Whole Works. 1.26. Specifications Means The Description Of Works To Be Done And The Qualities Of Materials To Be Used, The Equipment To Be Installed And The Mode Of Construction. 1.27. The Start Date, As Specified In The Scc, Is The Date When The Contractor Is Obliged To Commence Execution Of The Works. It Does Not Necessarily Coincide With Any Of The Site Possession Dates. 1.28. A Subcontractor Is Any Person Or Organization To Whom A Part Of The Works Has Been Subcontracted By The Contractor, As Allowed By The Procuring Entity, But Not Any Assignee Of Such Person. 1.29. Temporary Works Are Works Designed, Constructed, Installed, And Removed By The Contractor That Are Needed For Construction Or Installation Of The Permanent Works. 1.30. Work(s)refer To The Permanent Works And Temporary Works To Be Executed By The Contractor In Accordance With This Contract, Including (i) The Furnishing Of All Labor, Materials, Equipment And Others Incidental, Necessary Or Convenient To The Complete Execution Of The Works; (ii) The Passing Of Any Tests Before Acceptance By The Procuring Entity’s Representative; (iii) And The Carrying Out Of All Duties And Obligations Of The Contractor Imposed By This Contract As Described In The Scc. 2. Interpretation 2.1. In Interpreting The Conditions Of Contract, Singular Also Means Plural, Male Also Means Female Or Neuter, And The Other Way Around. Headings Have No Significance. Words Have Their Normal Meaning Under The Language Of This Contract Unless Specifically Defined. The Procuring Entity’s Representative Will Provide Instructions Clarifying Queries About The Conditions Of Contract. 2.2. If Sectional Completion Is Specified In The Scc, References In The Conditions Of Contract To The Works, The Completion Date, And The Intended Completion Date Apply To Any Section Of The Works (other Than References To The Completion Date And Intended Completion Date For The Whole Of The Works). 3. Governing Language And Law 3.1. This Contract Has Been Executed In The English Language, Which Shall Be The Binding And Controlling Language For All Matters Relating To The Meaning Or Interpretation Of This Contract. All Correspondence And Other Documents Pertaining To This Contract Which Are Exchanged By The Parties Shall Be Written In English. 3.2. This Contract Shall Be Interpreted In Accordance With The Laws Of The Republic Of The Philippines. 4. Communications Communications Between Parties That Are Referred To In The Conditions Shall Be Effective Only When In Writing. A Notice Shall Be Effective Only When It Is Received By The Concerned Party. 5. Possession Of Site 5.1. On The Date Specified In The Scc, The Procuring Entity Shall Grant The Contractor Possession Of So Much Of The Site As May Be Required To Enable It To Proceed With The Execution Of The Works. If The Contractor Suffers Delay Or Incurs Cost From Failure On The Part Of The Procuring Entity To Give Possession In Accordance With The Terms Of This Clause, The Procuring Entity’s Representative Shall Give The Contractor A Contract Time Extension And Certify Such Sum As Fair To Cover The Cost Incurred, Which Sum Shall Be Paid By Procuring Entity. 5.2. If Possession Of A Portion Is Not Given By The Date Stated In The Scc Clause 5.1, The Procuring Entity Will Be Deemed To Have Delayed The Start Of The Relevant Activities. The Resulting Adjustments In Contact Time To Address Such Delay Shall Be In Accordance With Gcc Clause 47. 5.3. The Contractor Shall Bear All Costs And Charges For Special Or Temporary Right-of-way Required By It In Connection With Access To The Site. The Contractor Shall Also Provide At His Own Cost Any Additional Facilities Outside The Site Required By It For Purposes Of The Works. 5.4. The Contractor Shall Allow The Procuring Entity’s Representative And Any Person Authorized By The Procuring Entity’s Representative Access To The Site And To Any Place Where Work In Connection With This Contract Is Being Carried Out Or Is Intended To Be Carried Out. 6. The Contractor’s Obligations 6.1. The Contractor Shall Carry Out The Works Properly And In Accordance With This Contract. The Contractor Shall Provide All Supervision, Labor, Materials, Plant And Contractor's Equipment, Which May Be Required. All Materials And Plant On Site Shall Be Deemed To Be The Property Of The Procuring Entity. 6.2. The Contractor Shall Commence Execution Of The Works On The Start Date And Shall Carry Out The Works In Accordance With The Program Of Work Submitted By The Contractor, As Updated With The Approval Of The Procuring Entity’s Representative, And Complete Them By The Intended Completion Date. 6.3. The Contractor Shall Be Responsible For The Safety Of All Activities On The Site. 6.4. The Contractor Shall Carry Out All Instructions Of The Procuring Entity’s Representative That Comply With The Applicable Laws Where The Site Is Located. 6.5. The Contractor Shall Employ The Key Personnel Named In The Schedule Of Key Personnel, As Referred To In The Scc, To Carry Out The Supervision Of The Works. The Procuring Entity Will Approve Any Proposed Replacement Of Key Personnel Only If Their Relevant Qualifications And Abilities Are Equal To Or Better Than Those Of The Personnel Listed In The Schedule. 6.6. If The Procuring Entity’s Representative Asks The Contractor To Remove A Member Of The Contractor’s Staff Or Work Force, For Justifiable Cause, The Contractor Shall Ensure That The Person Leaves The Site Within Seven (7) Days And Has No Further Connection With The Work In This Contract. 6.7. During Contract Implementation, The Contractor And His Subcontractors Shall Abide At All Times By All Labor Laws, Including Child Labor Related Enactments, And Other Relevant Rules. 6.8. The Contractor Shall Submit To The Procuring Entity For Consent The Name And Particulars Of The Person Authorized To Receive Instructions On Behalf Of The Contractor. 6.9. The Contractor Shall Cooperate And Share The Site With Other Contractors, Public Authorities, Utilities, And The Procuring Entity Between The Dates Given In The Schedule Of Other Contractors Particularly When They Shall Require Access To The Site. The Contractor Shall Also Provide Facilities And Services For Them During This Period. The Procuring Entity May Modify The Schedule Of Other Contractors, And Shall Notify The Contractor Of Any Such Modification Thereto. 6.10. Should Anything Of Historical Or Other Interest Or Of Significant Value Be Unexpectedly Discovered On The Site, It Shall Be The Property Of The Procuring Entity. The Contractor Shall Notify The Procuring Entity’s Representative Of Such Discoveries And Carry Out The Procuring Entity’s Representative’s Instructions In Dealing With Them. 7. Performance Security 7.1. Within Ten (10) Calendar Days From Receipt Of The Notice Of Award From The Procuring Entity But In No Case Later Than The Signing Of The Contract By Both Parties, The Contractor Shall Furnish The Performance Security In Any The Forms Prescribed In Itb Clause 32.2. 7.2. The Performance Security Posted In Favor Of The Procuring Entity Shall Be Forfeited In The Event It Is Established That The Contractor Is In Default In Any Of Its Obligations Under The Contract. 7.3. The Performance Security Shall Remain Valid Until Issuance By The Procuring Entity Of The Certificate Of Final Acceptance. 7.4. The Performance Security May Be Released By The Procuring Entity And Returned To The Contractor After The Issuance Of The Certificate Of Final Acceptance Subject To The Following Conditions: (a) There Are No Pending Claims Against The Contractor Or The Surety Company Filed By The Procuring Entity; (b) The Contractor Has No Pending Claims For Labor And Materials Filed Against It; And (c) Other Terms Specified In The Scc. 7.5. The Contractor Shall Post An Additional Performance Security Following The Amount And Form Specified In Itb Clause 32.2 To Cover Any Cumulative Increase Of More Than Ten Percent (10%) Over The Original Value Of The Contract As A Result Of Amendments To Order Or Change Orders, Extra Work Orders And Supplemental Agreements, As The Case May Be. The Contractor Shall Cause The Extension Of The Validity Of The Performance Security To Cover Approved Contract Time Extensions. 7.6. In Case Of A Reduction In The Contract Value Or For Partially Completed Works Under The Contract Which Are Usable And Accepted By The Procuring Entity The Use Of Which, In The Judgment Of The Implementing Agency Or The Procuring Entity, Will Not Affect The Structural Integrity Of The Entire Project, The Procuring Entity Shall Allow A Proportional Reduction In The Original Performance Security, Provided That Any Such Reduction Is More Than Ten Percent (10%) And That The Aggregate Of Such Reductions Is Not More Than Fifty Percent (50%) Of The Original Performance Security. 7.7. Unless Otherwise Indicated In The Scc, The Contractor, By Entering Into The Contract With The Procuring Entity, Acknowledges The Right Of The Procuring Entity To Institute Action Pursuant To Act 3688 Against Any Subcontractor Be They An Individual, Firm, Partnership, Corporation, Or Association Supplying The Contractor With Labor, Materials And/or Equipment For The Performance Of This Contract. 8. Subcontracting 8.1. Unless Otherwise Indicated In The Scc, The Contractor Cannot Subcontract Works More Than The Percentage Specified In Itb Clause 8.1. 8.2. Subcontracting Of Any Portion Of The Works Does Not Relieve The Contractor Of Any Liability Or Obligation Under This Contract. The Contractor Will Be Responsible For The Acts, Defaults, And Negligence Of Any Subcontractor, Its Agents, Servants Or Workmen As Fully As If These Were The Contractor’s Own Acts, Defaults, Or Negligence, Or Those Of Its Agents, Servants Or Workmen. 8.3. Subcontractors Disclosed And Identified During The Bidding May Be Changed During The Implementation Of This Contract, Subject To Compliance With The Required Qualifications And The Approval Of The Procuring Entity. 9. Liquidated Damages 9.1. The Contractor Shall Pay Liquidated Damages To The Procuring Entity For Each Day That The Completion Date Is Later Than The Intended Completion Date. The Applicable Liquidated Damages Is At Least One-tenth (1/10) Of A Percent Of The Cost Of The Unperformed Portion For Every Day Of Delay. The Total Amount Of Liquidated Damages Shall Not Exceed Ten Percent (10%) Of The Amount Of The Contract. The Procuring Entity May Deduct Liquidated Damages From Payments Due To The Contractor. Payment Of Liquidated Damages Shall Not Affect The Contractor. Once The Cumulative Amount Of Liquidated Damages Reaches Ten Percent (10%) Of The Amount Of This Contract, The Procuring Entity Shall Rescind This Contract, Without Prejudice To Other Courses Of Action And Remedies Open To It. 9.2. If The Intended Completion Date Is Extended After Liquidated Damages Have Been Paid, The Engineer Of The Procuring Entity Shall Correct Any Overpayment Of Liquidated Damages By The Contractor By Adjusting The Next Payment Certificate. The Contractor Shall Be Paid Interest On The Overpayment, Calculated From The Date Of Payment To The Date Of Repayment, At The Rates Specified In Gcc Clause 40.3. 10. Site Investigation Reports The Contractor, In Preparing The Bid, Shall Rely On Any Site Investigation Reports Referred To In The Scc Supplemented By Any Information Obtained By The Contractor. 11. The Procuring Entity, Licenses And Permits The Procuring Entity Shall, If Requested By The Contractor, Assist Him In Applying For Permits, Licenses Or Approvals, Which Are Required For The Works. 12. Contractor’s Risk And Warranty Security 12.1. The Contractor Shall Assume Full Responsibility For The Works From The Time Project Construction Commenced Up To Final Acceptance By The Procuring Entity And Shall Be Held Responsible For Any Damage Or Destruction Of The Works Except Those Occasioned By Force Majeure. The Contractor Shall Be Fully Responsible For The Safety, Protection, Security, And Convenience Of His Personnel, Third Parties, And The Public At Large, As Well As The Works, Equipment, Installation, And The Like To Be Affected By His Construction Work. 12.2. The Defects Liability Period For Infrastructure Projects Shall Be One Year From Contract Completion Up To Final Acceptance By The Procuring Entity. During This Period, The Contractor Shall Undertake The Repair Works, At His Own Expense, Of Any Damage To The Works On Account Of The Use Of Materials Of Inferior Quality Within Ninety (90) Days From The Time The Head Of The Procuring Entity Has Issued An Order To Undertake Repair. In Case Of Failure Or Refusal To Comply With This Mandate, The Procuring Entity Shall Undertake Such Repair Works And Shall Be Entitled To Full Reimbursement Of Expenses Incurred Therein Upon Demand. 12.3. Unless Otherwise Indicated In The Scc, In Case The Contractor Fails To Comply With The Preceding Paragraph, The Procuring Entity Shall Forfeit Its Performance Security, Subject Its Property (ies) To Attachment Or Garnishment Proceedings, And Perpetually Disqualify It From Participating In Any Public Bidding. All Payables Of The Gop In His Favor Shall Be Offset To Recover The Costs. 12.4. After Final Acceptance Of The Works By The Procuring Entity, The Contractor Shall Be Held Responsible For “structural Defects”, I.e., Major Faults/flaws/deficiencies In One Or More Key Structural Elements Of The Project Which May Lead To Structural Failure Of The Completed Elements Or Structure, Or “structural Failures”, I.e., Where One Or More Key Structural Elements In An Infrastructure Facility Fails Or Collapses, Thereby Rendering The Facility Or Part Thereof Incapable Of Withstanding The Design Loads, And/or Endangering The Safety Of The Users Or The General Public: (a) Contractor – Where Structural Defects/failures Arise Due To Faults Attributable To Improper Construction, Use Of Inferior Quality/substandard Materials, And Any Violation Of The Contract Plans And Specifications, The Contractor Shall Be Held Liable; (b) Consultants – Where Structural Defects/failures Arise Due To Faulty And/or Inadequate Design And Specifications As Well As Construction Supervision, Then The Consultant Who Prepared The Design Or Undertook Construction Supervision For The Project Shall Be Held Liable; (c) Procuring Entity’s Representatives/project Manager/construction Managers And Supervisors – The Project Owner’s Representative(s), Project Manager, Construction Manager, And Supervisor(s) Shall Be Held Liable In Cases Where The Structural Defects/failures Are Due To His/their Willful Intervention In Altering The Designs And Other Specifications; Negligence Or Omission In Not Approving Or Acting On Proposed Changes To Noted Defects Or Deficiencies In The Design And/or Specifications; And The Use Of Substandard Construction Materials In The Project; (d) Third Parties - Third Parties Shall Be Held Liable In Cases Where Structural Defects/failures Are Caused By Work Undertaken By Them Such As Leaking Pipes, Diggings Or Excavations, Underground Cables And Electrical Wires, Underground Tunnel, Mining Shaft And The Like, In Which Case The Applicable Warranty To Such Structure Should Be Levied To Third Parties For Their Construction Or Restoration Works. (e) Users - In Cases Where Structural Defects/failures Are Due To Abuse/misuse By The End User Of The Constructed Facility And/or Non–compliance By A User With The Technical Design Limits And/or Intended Purpose Of The Same, Then The User Concerned Shall Be Held Liable. 12.5. The Warranty Against Structural Defects/failures, Except Those Occasioned On Force Majeure, Shall Cover The Period Specified In The Scc Reckoned From The Date Of Issuance Of The Certificate Of Final Acceptance By The Procuring Entity. 12.6. The Contractor Shall Be Required To Put Up A Warranty Security In The Form Of Cash, Bank Guarantee, Letter Of Credit, Gsis Or Surety Bond Callable On Demand, In Accordance With The Following Schedule: Form Of Warranty Minimum Amount In Percentage (%) Of Total Contract Price (a) Cash Or Letter Of Credit Issued By Universal Or Commercial Bank: Provided, However, That The Letter Of Credit Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank Five Percent (5%) (b) Bank Guarantee Confirmed By Universal Or Commercial Bank: Provided, However, That The Letter Of Credit Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank Ten Percent (10%) (c) Surety Bond Callable Upon Demand Issued By Gsis Or Any Surety Or Insurance Company Duly Certified By The Insurance Commission Thirty Percent (30%) 12.7. The Warranty Security Shall Be Stated In Philippine Pesos And Shall Remain Effective For One Year From The Date Of Issuance Of The Certificate Of Final Acceptance By The Procuring Entity, And Returned Only After The Lapse Of Said One Year Period. 12.8. In Case Of Structural Defects/failure Occurring During The Applicable Warranty Period Provided In Gcc Clause 12.5, The Procuring Entity Shall Undertake The Necessary Restoration Or Reconstruction Works And Shall Be Entitled To Full Reimbursement By The Parties Found To Be Liable For Expenses Incurred Therein Upon Demand, Without Prejudice To The Filing Of Appropriate Administrative, Civil, And/or Criminal Charges Against The Responsible Persons As Well As The Forfeiture Of The Warranty Security Posted In Favor Of The Procuring Entity. 13. Liability Of The Contractor Subject To Additional Provisions, If Any, Set Forth In The Scc, The Contractor’s Liability Under This Contract Shall Be As Provided By The Laws Of The Republic Of The Philippines. 14. Procuring Entity’s Risk 14.1. From The Start Date Until The Certificate Of Final Acceptance Has Been Issued, The Following Are Risks Of The Procuring Entity: (a) The Risk Of Personal Injury, Death, Or Loss Of Or Damage To Property (excluding The Works, Plant, Materials, And Equipment), Which Are Due To: (i) Any Type Of Use Or Occupation Of The Site Authorized By The Procuring Entity After The Official Acceptance Of The Works; Or (ii) Negligence, Breach Of Statutory Duty, Or Interference With Any Legal Right By The Procuring Entity Or By Any Person Employed By Or Contracted To Him Except The Contractor. (b) The Risk Of Damage To The Works, Plant, Materials, And Equipment To The Extent That It Is Due To A Fault Of The Procuring Entity Or In The Procuring Entity’s Design, Or Due To War Or Radioactive Contamination Directly Affecting The Country Where The Works Are To Be Executed. 15. Insurance 15.1. The Contractor Shall, Under His Name And At His Own Expense, Obtain And Maintain, For The Duration Of This Contract, The Following Insurance Coverage: (a) Contractor’s All Risk Insurance; (b) Transportation To The Project Site Of Equipment, Machinery, And Supplies Owned By The Contractor; (c) Personal Injury Or Death Of Contractor’s Employees; And (d) Comprehensive Insurance For Third Party Liability To Contractor’s Direct Or Indirect Act Or Omission Causing Damage To Third Persons. 15.2. The Contractor Shall Provide Evidence To The Procuring Entity’s Representative That The Insurances Required Under This Contract Have Been Effected And Shall, Within A Reasonable Time, Provide Copies Of The Insurance Policies To The Procuring Entity’s Representative. Such Evidence And Such Policies Shall Be Provided To The Procuring Entity’s Through The Procuring Entity’s Representative. 15.3. The Contractor Shall Notify The Insurers Of Changes In The Nature, Extent, Or Program For The Execution Of The Works And Ensure The Adequacy Of The Insurances At All Times In Accordance With The Terms Of This Contract And Shall Produce To The Procuring Entity’s Representative The Insurance Policies In Force Including The Receipts For Payment Of The Current Premiums. The Above Insurance Policies Shall Be Obtained From Any Reputable Insurance Company Approved By The Procuring Entity’s Representative. 15.4. If The Contractor Fails To Obtain And Keep In Force The Insurances Referred To Herein Or Any Other Insurance Which He May Be Required To Obtain Under The Terms Of This Contract, The Procuring Entity May Obtain And Keep In Force Any Such Insurances And Pay Such Premiums As May Be Necessary For The Purpose. From Time To Time, The Procuring Entity May Deduct The Amount It Shall Pay For Said Premiums Including Twenty Five Percent (25%) Therein From Any Monies Due, Or Which May Become Due, To The Contractor, Without Prejudice To The Procuring Entity Exercising Its Right To Impose Other Sanctions Against The Contractor Pursuant To The Provisions Of This Contract. 15.5. In The Event The Contractor Fails To Observe The Above Safeguards, The Procuring Entity May, At The Contractor’s Expense, Take Whatever Measure Is Deemed Necessary For Its Protection And That Of The Contractor’s Personnel And Third Parties, And/or Order The Interruption Of Dangerous Works. In Addition, The Procuring Entity May Refuse To Make The Payments Under Gcc Clause 40 Until The Contractor Complies With This Clause. 15.6. The Contractor Shall Immediately Replace The Insurance Policy Obtained As Required In This Contract, Without Need Of The Procuring Entity’s Demand, With A New Policy Issued By A New Insurance Company Acceptable To The Procuring Entity For Any Of The Following Grounds: (a) The Issuer Of The Insurance Policy To Be Replaced Has: (i) Become Bankrupt; (ii) Been Placed Under Receivership Or Under A Management Committee; (iii) Been Sued For Suspension Of Payment; Or (iv) Been Suspended By The Insurance Commission And Its License To Engage In Business Or Its Authority To Issue Insurance Policies Cancelled; Or (v) Where Reasonable Grounds Exist That The Insurer May Not Be Able, Fully And Promptly, To Fulfill Its Obligation Under The Insurance Policy. 16. Termination For Default Of Contractor 16.1. The Procuring Entity Shall Terminate This Contract For Default When Any Of The Following Conditions Attend Its Implementation: 16.2. Due To The Contractor’s Fault And While The Project Is On-going, It Has Incurred Negative Slippage Of Fifteen Percent (15%) Or More In Accordance With Presidential Decree 1870, Regardless Of Whether Or Not Previous Warnings And Notices Have Been Issued For The Contractor To Improve His Performance; 16.3. Due To Its Own Fault And After This Contract Time Has Expired, The Contractor Incurs Delay In The Completion Of The Work After This Contract Has Expired; Or 16.4. The Contractor: (a) Abandons The Contract Works, Refuses Or Fails To Comply With A Valid Instruction Of The Procuring Entity Or Fails To Proceed Expeditiously And Without Delay Despite A Written Notice By The Procuring Entity; (b) Does Not Actually Have On The Project Site The Minimum Essential Equipment Listed On The Bid Necessary To Prosecute The Works In Accordance With The Approved Program Of Work And Equipment Deployment Schedule As Required For The Project; (c) Does Not Execute The Works In Accordance With This Contract Or Persistently Or Flagrantly Neglects To Carry Out Its Obligations Under This Contract; (d) Neglects Or Refuses To Remove Materials Or To Perform A New Work That Has Been Rejected As Defective Or Unsuitable; Or (e) Sub-lets Any Part Of This Contract Without Approval By The Procuring Entity. 16.5. All Materials On The Site, Plant, Equipment, And Works Shall Be Deemed To Be The Property Of The Procuring Entity If This Contract Is Rescinded Because Of The Contractor’s Default. 17. Termination For Default Of Procuring Entity The Contractor May Terminate This Contract With The Procuring Entity If The Works Are Completely Stopped For A Continuous Period Of At Least Sixty (60) Calendar Days Through No Fault Of Its Own, Due To Any Of The Following Reasons: (a) Failure Of The Procuring Entity To Deliver, Within A Reasonable Time, Supplies, Materials, Right-of-way, Or Other Items It Is Obligated To Furnish Under The Terms Of This Contract; Or (b) The Prosecution Of The Work Is Disrupted By The Adverse Peace And Order Situation, As Certified By The Armed Forces Of The Philippines Provincial Commander And Approved By The Secretary Of National Defense. 18. Termination For Other Causes 18.1. The Procuring Entity May Terminate This Contract, In Whole Or In Part, At Any Time For Its Convenience. The Head Of The Procuring Entity May Terminate This Contract For The Convenience Of The Procuring Entity If He Has Determined The Existence Of Conditions That Make Project Implementation Economically, Financially Or Technically Impractical And/or Unnecessary, Such As, But Not Limited To, Fortuitous Event(s) Or Changes In Law And National Government Policies. 18.2. The Procuring Entity Or The Contractor May Terminate This Contract If The Other Party Causes A Fundamental Breach Of This Contract. 18.3. Fundamental Breaches Of Contract Shall Include, But Shall Not Be Limited To, The Following: (a) The Contractor Stops Work For Twenty Eight (28) Days When No Stoppage Of Work Is Shown On The Current Program Of Work And The Stoppage Has Not Been Authorized By The Procuring Entity’s Representative; (b) The Procuring Entity’s Representative Instructs The Contractor To Delay The Progress Of The Works, And The Instruction Is Not Withdrawn Within Twenty Eight (28) Days; (c) The Procuring Entity Shall Terminate This Contract If The Contractor Is Declared Bankrupt Or Insolvent As Determined With Finality By A Court Of Competent Jurisdiction. In This Event, Termination Will Be Without Compensation To The Contractor, Provided That Such Termination Will Not Prejudice Or Affect Any Right Of Action Or Remedy Which Has Accrued Or Will Accrue Thereafter To The Procuring Entity And/or The Contractor. In The Case Of The Contractor's Insolvency, Any Contractor's Equipment Which The Procuring Entity Instructs In The Notice Is To Be Used Until The Completion Of The Works; (d) A Payment Certified By The Procuring Entity’s Representative Is Not Paid By The Procuring Entity To The Contractor Within Eighty Four (84) Days From The Date Of The Procuring Entity’s Representative’s Certificate; (e) The Procuring Entity’s Representative Gives Notice That Failure To Correct A Particular Defect Is A Fundamental Breach Of Contract And The Contractor Fails To Correct It Within A Reasonable Period Of Time Determined By The Procuring Entity’s Representative; (f) The Contractor Does Not Maintain A Security, Which Is Required; (g) The Contractor Has Delayed The Completion Of The Works By The Number Of Days For Which The Maximum Amount Of Liquidated Damages Can Be Paid, As Defined In The Gcc Clause 9; And (h) In Case It Is Determined Prima Facie By The Procuring Entity That The Contractor Has Engaged, Before Or During The Implementation Of The Contract, In Unlawful Deeds And Behaviors Relative To Contract Acquisition And Implementation, Such As, But Not Limited To, The Following: (i) Corrupt, Fraudulent, Collusive, Coercive, And Obstructive Practices As Defined In Itb Clause 3.1(a), Unless Otherwise Specified In The Scc; (ii) Drawing Up Or Using Forged Documents; (iii) Using Adulterated Materials, Means Or Methods, Or Engaging In Production Contrary To Rules Of Science Or The Trade; And (iv) Any Other Act Analogous To The Foregoing. 18.4. The Funding Source Or The Procuring Entity, As Appropriate, Will Seek To Impose The Maximum Civil, Administrative And/or Criminal Penalties Available Under The Applicable Law On Individuals And Organizations Deemed To Be Involved With Corrupt, Fraudulent, Or Coercive Practices. 18.5. When Persons From Either Party To This Contract Gives Notice Of A Fundamental Breach To The Procuring Entity’s Representative In Order To Terminate The Existing Contract For A Cause Other Than Those Listed Under Gcc Clause 18.3, The Procuring Entity’s Representative Shall Decide Whether The Breach Is Fundamental Or Not. 18.6. If This Contract Is Terminated, The Contractor Shall Stop Work Immediately, Make The Site Safe And Secure, And Leave The Site As Soon As Reasonably Possible. 19. Procedures For Termination Of Contracts 19.1. The Following Provisions Shall Govern The Procedures For The Termination Of This Contract: (a) Upon Receipt Of A Written Report Of Acts Or Causes Which May Constitute Ground(s) For Termination As Aforementioned, Or Upon Its Own Initiative, The Procuring Entity Shall, Within A Period Of Seven (7) Calendar Days, Verify The Existence Of Such Ground(s) And Cause The Execution Of A Verified Report, With All Relevant Evidence Attached; (b) Upon Recommendation By The Procuring Entity, The Head Of The Procuring Entity Shall Terminate This Contract Only By A Written Notice To The Contractor Conveying The Termination Of This Contract. The Notice Shall State: (i) That This Contract Is Being Terminated For Any Of The Ground(s) Afore-mentioned, And A Statement Of The Acts That Constitute The Ground(s) Constituting The Same; (ii) The Extent Of Termination, Whether In Whole Or In Part; (iii) An Instruction To The Contractor To Show Cause As To Why This Contract Should Not Be Terminated; And (iv) Special Instructions Of The Procuring Entity, If Any. The Notice To Terminate Shall Be Accompanied By A Copy Of The Verified Report; (c) Within A Period Of Seven (7) Calendar Days From Receipt Of The Notice Of Termination, The Contractor Shall Submit To The Head Of The Procuring Entity A Verified Position Paper Stating Why The Contract Should Not Be Terminated. If The Contractor Fails To Show Cause After The Lapse Of The Seven (7) Day Period, Either By Inaction Or By Default, The Head Of The Procuring Entity Shall Issue An Order Terminating The Contract; (d) The Procuring Entity May, At Anytime Before Receipt Of The Bidder’s Verified Position Paper Described In Item (c) Above Withdraw The Notice To Terminate If It Is Determined That Certain Items Or Works Subject Of The Notice Had Been Completed, Delivered, Or Performed Before The Contractor’s Receipt Of The Notice; (e) Within A Non-extendible Period Of Ten (10) Calendar Days From Receipt Of The Verified Position Paper, The Head Of The Procuring Entity Shall Decide Whether Or Not To Terminate This Contract. It Shall Serve A Written Notice To The Contractor Of Its Decision And, Unless Otherwise Provided In The Said Notice, This Contract Is Deemed Terminated From Receipt Of The Contractor Of The Notice Of Decision. The Termination Shall Only Be Based On The Ground(s) Stated In The Notice To Terminate; And (f) The Head Of The Procuring Entity May Create A Contract Termination Review Committee (ctrc) To Assist Him In The Discharge Of This Function. All Decisions Recommended By The Ctrc Shall Be Subject To The Approval Of The Head Of The Procuring Entity. 19.2. Pursuant To Section 69(f) Of Ra 9184 And Without Prejudice To The Imposition Of Additional Administrative Sanctions As The Internal Rules Of The Agency May Provide And/or Further Criminal Prosecution As Provided By Applicable Laws, The Procuring Entity Shall Impose On Contractors After The Termination Of The Contract The Penalty Of Suspension For One (1) Year For The First Offense, Suspension For Two (2) Years For The Second Offense From Participating In The Public Bidding Process, For Violations Committed During The Contract Implementation Stage, Which Include But Not Limited To The Following: (a) Failure Of The Contractor, Due Solely To His Fault Or Negligence, To Mobilize And Start Work Or Performance Within The Specified Period In The Notice To Proceed (“ntp”); (b) Failure By The Contractor To Fully And Faithfully Comply With Its Contractual Obligations Without Valid Cause, Or Failure By The Contractor To Comply With Any Written Lawful Instruction Of The Procuring Entity Or Its Representative(s) Pursuant To The Implementation Of The Contract. For The Procurement Of Infrastructure Projects Or Consultancy Contracts, Lawful Instructions Include But Are Not Limited To The Following: (i) Employment Of Competent Technical Personnel, Competent Engineers And/or Work Supervisors; (ii) Provision Of Warning Signs And Barricades In Accordance With Approved Plans And Specifications And Contract Provisions; (iii) Stockpiling In Proper Places Of All Materials And Removal From The Project Site Of Waste And Excess Materials, Including Broken Pavement And Excavated Debris In Accordance With Approved Plans And Specifications And Contract Provisions; (iv) Deployment Of Committed Equipment, Facilities, Support Staff And Manpower; And (v) Renewal Of The Effectivity Dates Of The Performance Security After Its Expiration During The Course Of Contract Implementation. (c) Assignment And Subcontracting Of The Contract Or Any Part Thereof Or Substitution Of Key Personnel Named In The Proposal Without Prior Written Approval By The Procuring Entity. (d) Poor Performance By The Contractor Or Unsatisfactory Quality And/or Progress Of Work Arising From His Fault Or Negligence As Reflected In The Constructor's Performance Evaluation System (“cpes”) Rating Sheet. In The Absence Of The Cpes Rating Sheet, The Existing Performance Monitoring System Of The Procuring Entity Shall Be Applied. Any Of The Following Acts By The Contractor Shall Be Construed As Poor Performance: (i) Negative Slippage Of 15% And Above Within The Critical Path Of The Project Due Entirely To The Fault Or Negligence Of The Contractor; And (ii) Quality Of Materials And Workmanship Not Complying With The Approved Specifications Arising From The Contractor's Fault Or Negligence. (e) Willful Or Deliberate Abandonment Or Non-performance Of The Project Or Contract By The Contractor Resulting To Substantial Breach Thereof Without Lawful And/or Just Cause. In Addition To The Penalty Of Suspension, The Performance Security Posted By The Contractor Shall Also Be Forfeited. 20. Force Majeure, Release From Performance 20.1. For Purposes Of This Contract The Terms “force Majeure” And “fortuitous Event” May Be Used Interchangeably. In This Regard, A Fortuitous Event Or Force Majeure Shall Be Interpreted To Mean An Event Which The Contractor Could Not Have Foreseen, Or Which Though Foreseen, Was Inevitable. It Shall Not Include Ordinary Unfavorable Weather Conditions; And Any Other Cause The Effects Of Which Could Have Been Avoided With The Exercise Of Reasonable Diligence By The Contractor. 20.2. If This Contract Is Discontinued By An Outbreak Of War Or By Any Other Event Entirely Outside The Control Of Either The Procuring Entity Or The Contractor, The Procuring Entity’s Representative Shall Certify That This Contract Has Been Discontinued. The Contractor Shall Make The Site Safe And Stop Work As Quickly As Possible After Receiving This Certificate And Shall Be Paid For All Works Carried Out Before Receiving It And For Any Work Carried Out Afterwards To Which A Commitment Was Made. 20.3. If The Event Continues For A Period Of Eighty Four (84) Days, Either Party May Then Give Notice Of Termination, Which Shall Take Effect Twenty Eight (28) Days After The Giving Of The Notice. 20.4. After Termination, The Contractor Shall Be Entitled To Payment Of The Unpaid Balance Of The Value Of The Works Executed And Of The Materials And Plant Reasonably Delivered To The Site, Adjusted By The Following: (a) Any Sum To Which The Contractor Is Entitled Under Gcc Clause 28; (b) The Cost Of His Suspension And Demobilization; (c) Any Sum To Which The Procuring Entity Is Entitled. 20.5. The Net Balance Due Shall Be Paid Or Repaid Within A Reasonable Time Period From The Time Of The Notice Of Termination. 21. Resolution Of Disputes 21.1. If Any Dispute Or Difference Of Any Kind Whatsoever Shall Arise Between The Parties In Connection With The Implementation Of The Contract Covered By The Act And This Irr, The Parties Shall Make Every Effort To Resolve Amicably Such Dispute Or Difference By Mutual Consultation. 21.2. If The Contractor Believes That A Decision Taken By The Procuring Entity’s Representative Was Either Outside The Authority Given To The Procuring Entity’s Representative By This Contract Or That The Decision Was Wrongly Taken, The Decision Shall Be Referred To The Arbiter Indicated In The Scc Within Fourteen (14) Days Of The Notification Of The Procuring Entity’s Representative’s Decision. 21.3. Any And All Disputes Arising From The Implementation Of This Contract Covered By The R.a. 9184 And Its Irr Shall Be Submitted To Arbitration In The Philippines According To The Provisions Of Republic Act No. 876, Otherwise Known As The “ Arbitration Law” And Republic Act 9285, Otherwise Known As The “alternative Dispute Resolution Act Of 2004”: Provided, However, That, Disputes That Are Within The Competence Of The Construction Industry Arbitration Commission To Resolve Shall Be Referred Thereto. The Process Of Arbitration Shall Be Incorporated As A Provision In This Contract That Will Be Executed Pursuant To The Provisions Of The Act And Its Irr: Provided, Further, That, By Mutual Agreement, The Parties May Agree In Writing To Resort To Other Alternative Modes Of Dispute Resolution. 22. Suspension Of Loan, Credit, Grant, Or Appropriation In The Event That The Funding Source Suspends The Loan, Credit, Grant, Or Appropriation To The Procuring Entity, From Which Part Of The Payments To The Contractor Are Being Made: (a) The Procuring Entity Is Obligated To Notify The Contractor Of Such Suspension Within Seven (7) Days Of Having Received The Suspension Notice. (b) If The Contractor Has Not Received Sums Due It For Work Already Done Within Forty Five (45) Days From The Time The Contractor’s Claim For Payment Has Been Certified By The Procuring Entity’s Representative, The Contractor May Immediately Issue A Suspension Of Work Notice In Accordance With Gcc Clause 45.2. 23. Procuring Entity’s Representative’s Decisions 23.1. Except Where Otherwise Specifically Stated, The Procuring Entity’s Representative Will Decide Contractual Matters Between The Procuring Entity And The Contractor In The Role Representing The Procuring Entity. 23.2. The Procuring Entity’s Representative May Delegate Any Of His Duties And Responsibilities To Other People, Except To The Arbiter, After Notifying The Contractor, And May Cancel Any Delegation After Notifying The Contractor. 24. Approval Of Drawings And Temporary Works By The Procuring Entity’s Representative 24.1. All Drawings Prepared By The Contractor For The Execution Of The Temporary Works, Are Subject To Prior Approval By The Procuring Entity’s Representative Before Its Use. 24.2. The Contractor Shall Be Responsible For Design Of Temporary Works. 24.3. The Procuring Entity’s Representative’s Approval Shall Not Alter The Contractor’s Responsibility For Design Of The Temporary Works. 24.4. The Contractor Shall Obtain Approval Of Third Parties To The Design Of The Temporary Works, When Required By The Procuring Entity. 25. Acceleration And Delays Ordered By The Procuring Entity’s Representative 25.1. When The Procuring Entity Wants The Contractor To Finish Before The Intended Completion Date, The Procuring Entity’s Representative Will Obtain Priced Proposals For Achieving The Necessary Acceleration From The Contractor. If The Procuring Entity Accepts These Proposals, The Intended Completion Date Will Be Adjusted Accordingly And Confirmed By Both The Procuring Entity And The Contractor. 25.2. If The Contractor’s Financial Proposals For An Acceleration Are Accepted By The Procuring Entity, They Are Incorporated In The Contract Price And Treated As A Variation. 26. Extension Of The Intended Completion Date 26.1. The Procuring Entity’s Representative Shall Extend The Intended Completion Date If A Variation Is Issued Which Makes It Impossible For The Intended Completion Date To Be Achieved By The Contractor Without Taking Steps To Accelerate The Remaining Work, Which Would Cause The Contractor To Incur Additional Costs. No Payment Shall Be Made For Any Event Which May Warrant The Extension Of The Intended Completion Date. 26.2. The Procuring Entity’s Representative Shall Decide Whether And By How Much To Extend The Intended Completion Date Within Twenty One (21) Days Of The Contractor Asking The Procuring Entity’s Representative For A Decision Thereto After Fully Submitting All Supporting Information. If The Contractor Has Failed To Give Early Warning Of A Delay Or Has Failed To Cooperate In Dealing With A Delay, The Delay By This Failure Shall Not Be Considered In Assessing The New Intended Completion Date. 27. Right To Vary 27.1. The Procuring Entity’s Representative With The Prior Approval Of The Procuring Entity May Instruct Variations, Up To A Maximum Cumulative Amount Of Ten Percent (10%) Of The Original Contract Cost. 27.2. Variations Shall Be Valued As Follows: (a) At A Lump Sum Price Agreed Between The Parties; (b) Where Appropriate, At Rates In This Contract; (c) In The Absence Of Appropriate Rates, The Rates In This Contract Shall Be Used As The Basis For Valuation; Or Failing Which (d) At Appropriate New Rates, Equal To Or Lower Than Current Industry Rates And To Be Agreed Upon By Both Parties And Approved By The Head Of The Procuring Entity. 28. Contractor's Right To Claim If The Contractor Incurs Cost As A Result Of Any Of The Events Under Gcc Clause 13, The Contractor Shall Be Entitled To The Amount Of Such Cost. If As A Result Of Any Of The Said Events, It Is Necessary To Change The Works, This Shall Be Dealt With As A Variation. 29. Dayworks 29.1. Subject To Gcc Clause 43 On Variation Order, And If Applicable As Indicated In The Scc, The Day Works Rates In The Contractor’s Bid Shall Be Used For Small Additional Amounts Of Work Only When The Procuring Entity’s Representative Has Given Written Instructions In Advance For Additional Work To Be Paid For In That Way. 29.2. All Work To Be Paid For As Day Works Shall Be Recorded By The Contractor On Forms Approved By The Procuring Entity’s Representative. Each Completed Form Shall Be Verified And Signed By The Procuring Entity’s Representative Within Two Days Of The Work Being Done. 29.3. The Contractor Shall Be Paid For Day Works Subject To Obtaining Signed Dayworks Forms. 30. Early Warning 30.1. The Contractor Shall Warn The Procuring Entity’s Representative At The Earliest Opportunity Of Specific Likely Future Events Or Circumstances That May Adversely Affect The Quality Of The Work, Increase The Contract Price, Or Delay The Execution Of The Works. The Procuring Entity’s Representative May Require The Contractor To Provide An Estimate Of The Expected Effect Of The Future Event Or Circumstance On The Contract Price And Completion Date. The Estimate Shall Be Provided By The Contractor As Soon As Reasonably Possible. 30.2. The Contractor Shall Cooperate With The Procuring Entity’s Representative In Making And Considering Proposals For How The Effect Of Such An Event Or Circumstance Can Be Avoided Or Reduced By Anyone Involved In The Work And In Carrying Out Any Resulting Instruction Of The Procuring Entity’s Representative. 31. Program Of Work 31.1. Within The Time Stated In The Scc, The Contractor Shall Submit To The Procuring Entity’s Representative For Approval A Program Of Work Showing The General Methods, Arrangements, Order, And Timing For All The Activities In The Works. 31.2. An Update Of The Program Of Work Shall The Show The Actual Progress Achieved On Each Activity And The Effect Of The Progress Achieved On The Timing Of The Remaining Work, Including Any Changes To The Sequence Of The Activities. 31.3. The Contractor Shall Submit To The Procuring Entity’s Representative For Approval An Updated Program Of Work At Intervals No Longer Than The Period Stated In The Scc. If The Contractor Does Not Submit An Updated Program Of Work Within This Period, The Procuring Entity’s Representative May Withhold The Amount Stated In The Scc From The Next Payment Certificate And Continue To Withhold This Amount Until The Next Payment After The Date On Which The Overdue Program Of Work Has Been Submitted. 31.4. The Procuring Entity’s Representative’s Approval Of The Program Of Work Shall Not Alter The Contractor’s Obligations. The Contractor May Revise The Program Of Work And Submit It To The Procuring Entity’s Representative Again At Any Time. A Revised Program Of Work Shall Show The Effect Of Any Approved Variations. 31.5. When The Program Of Work Is Updated, The Contractor Shall Provide The Procuring Entity’s Representative With An Updated Cash Flow Forecast. The Cash Flow Forecast Shall Include Different Currencies, As Defined In The Contract, Converted As Necessary Using The Contract Exchange Rates. 31.6. All Variations Shall Be Included In Updated Program Of Work Produced By The Contractor. 32. Management Conferences 32.1. Either The Procuring Entity’s Representative Or The Contractor May Require The Other To Attend A Management Conference. The Management Conference Shall Review The Plans For Remaining Work And Deal With Matters Raised In Accordance With The Early Warning Procedure. 32.2. The Procuring Entity’s Representative Shall Record The Business Of Management Conferences And Provide Copies Of The Record To Those Attending The Conference And To The Procuring Entity . The Responsibility Of The Parties For Actions To Be Taken Shall Be Decided By The Procuring Entity’s Representative Either At The Management Conference Or After The Management Conference And Stated In Writing To All Who Attended The Conference. 33. Bill Of Quantities 33.1. The Bill Of Quantities Shall Contain Items Of Work For The Construction, Installation, Testing, And Commissioning Of Work To Be Done By The Contractor. 33.2. The Bill Of Quantities Is Used To Calculate The Contract Price. The Contractor Is Paid For The Quantity Of The Work Done At The Rate In The Bill Of Quantities For Each Item. 33.3. If The Final Quantity Of Any Work Done Differs From The Quantity In The Bill Of Quantities For The Particular Item And Is Not More Than Twenty Five Percent (25%) Of The Original Quantity, Provided The Aggregate Changes For All Items Do Not Exceed Ten Percent (10%) Of The Contract Price, The Procuring Entity’s Representative Shall Make The Necessary Adjustments To Allow For The Changes Subject To Applicable Laws, Rules, And Regulations. 33.4. If Requested By The Procuring Entity’s Representative, The Contractor Shall Provide The Procuring Entity’s Representative With A Detailed Cost Breakdown Of Any Rate In The Bill Of Quantities. 34. Instructions, Inspections And Audits 34.1. The Procuring Entity’s Personnel Shall At All Reasonable Times During Construction Of The Work Be Entitled To Examine, Inspect, Measure And Test The Materials And Workmanship, And To Check The Progress Of The Construction. 34.2. If The Procuring Entity’s Representative Instructs The Contractor To Carry Out A Test Not Specified In The Specification To Check Whether Any Work Has A Defect And The Test Shows That It Does, The Contractor Shall Pay For The Test And Any Samples. If There Is No Defect, The Test Shall Be A Compensation Event. 34.3. The Contractor Shall Permit The Funding Source Named In The Scc To Inspect The Contractor’s Accounts And Records Relating To The Performance Of The Contractor And To Have Them Audited By Auditors Appointed By The Funding Source, If So Required By The Funding Source. 35. Identifying Defects The Procuring Entity’s Representative Shall Check The Contractor’s Work And Notify The Contractor Of Any Defects That Are Found. Such Checking Shall Not Affect The Contractor’s Responsibilities. The Procuring Entity’s Representative May Instruct The Contractor To Search Uncover Defects And Test Any Work That The Procuring Entity’s Representative Considers Below Standards And Defective. 36. Cost Of Repairs Loss Or Damage To The Works Or Materials To Be Incorporated In The Works Between The Start Date And The End Of The Defects Liability Periods Shall Be Remedied By The Contractor At The Contractor’s Cost If The Loss Or Damage Arises From The Contractor’s Acts Or Omissions. 37. Correction Of Defects 37.1. The Procuring Entity’s Representative Shall Give Notice To The Contractor Of Any Defects Before The End Of The Defects Liability Period, Which Isone (1) Year From Project Completion Up To Final Acceptance By The Procuring Entity’s. 37.2. Every Time Notice Of A Defect Is Given, The Contractor Shall Correct The Notified Defect Within The Length Of Time Specified In The Procuring Entity’s Representative’s Notice. 37.3. The Contractor Shall Correct The Defects Which He Notices Himself Before The End Of The Defects Liability Period. 37.4. The Procuring Entity Shall Certify That All Defects Have Been Corrected. If The Procuring Entity Considers That Correction Of A Defect Is Not Essential, He Can Request The Contractor To Submit A Quotation For The Corresponding Reduction In The Contract Price. If The Procuring Entity Accepts The Quotation, The Corresponding Change In The Scc Is A Variation. 38. Uncorrected Defects 38.1. The Procuring Entity Shall Give The Contractor At Least Fourteen (14) Days Notice Of His Intention To Use A Third Party To Correct A Defect. If The Contractor Does Not Correct The Defect Himself Within The Period, The Procuring Entity May Have The Defect Corrected By The Third Party. The Cost Of The Correction Will Be Deducted From The Contract Price. 38.2. The Use Of A Third Party To Correct Defects That Are Uncorrected By The Contractor Will In No Way Relieve The Contractor Of Its Liabilities And Warranties Under The Contract. 39. Advance Payment 39.1. The Procuring Entity Shall, Upon A Written Request Of The Contractor Which Shall Be Submitted As A Contract Document, Make An Advance Payment To The Contractor In An Amount Not Exceeding Fifteen Percent (15%) Of The Total Contract Price, To Be Made In Lump Sum Or, At The Most Two, Installments According To A Schedule Specified In The Scc. 39.2. The Advance Payment Shall Be Made Only Upon The Submission To And Acceptance By The Procuring Entity Of An Irrevocable Standby Letter Of Credit Of Equivalent Value From A Commercial Bank, A Bank Guarantee Or A Surety Bond Callable Upon Demand, Issued By A Surety Or Insurance Company Duly Licensed By The Insurance Commission And Confirmed By The Procuring Entity. 39.3. The Advance Payment Shall Be Repaid By The Contractor By An Amount Equal To The Percentage Of The Total Contract Price Used For The Advance Payment. 39.4. The Contractor May Reduce His Standby Letter Of Credit Or Guarantee Instrument By The Amounts Refunded By The Monthly Certificates In The Advance Payment. 39.5. The Procuring Entity Will Provide An Advance Payment On The Contract Price As Stipulated In The Conditions Of Contract, Subject To The Maximum Amount Stated In Scc Clause 39.1. 40. Progress Payments 40.1. The Contractor May Submit A Request For Payment For Work Accomplished. Such Request For Payment Shall Be Verified And Certified By The Procuring Entity’s Representative/project Engineer. Except As Otherwise Stipulated In The Scc, Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Not Be Included For Payment. 40.2. The Procuring Entity Shall Deduct The Following From The Certified Gross Amounts To Be Paid To The Contractor As Progress Payment: (a) Cumulative Value Of The Work Previously Certified And Paid For. (b) Portion Of The Advance Payment To Be Recouped For The Month. (c) Retention Money In Accordance With The Condition Of Contract. (d) Amount To Cover Third Party Liabilities. (e) Amount To Cover Uncorrected Discovered Defects In The Works. 40.3. Payments Shall Be Adjusted By Deducting There From The Amounts For Advance Payments And Retention. The Procuring Entity Shall Pay The Contractor The Amounts Certified By The Procuring Entity’s Representative Within Twenty Eight (28) Days From The Date Each Certificate Was Issued. No Payment Of Interest For Delayed Payments And Adjustments Shall Be Made By The Procuring Entity. 40.4. The First Progress Payment May Be Paid By The Procuring Entity To The Contractor Provided That At Least Twenty Percent (20%) Of The Work Has Been Accomplished As Certified By The Procuring Entity’s Representative. 40.5. Items Of The Works For Which A Price Of “0” (zero) Has Been Entered Will Not Be Paid For By The Procuring Entity And Shall Be Deemed Covered By Other Rates And Prices In The Contract. 41. Payment Certificates 41.1. The Contractor Shall Submit To The Procuring Entity’s Representative Monthly Statements Of The Estimated Value Of The Work Executed Less The Cumulative Amount Certified Previously. 41.2. The Procuring Entity’s Representative Shall Check The Contractor’s Monthly Statement And Certify The Amount To Be Paid To The Contractor. 41.3. The Value Of Work Executed Shall: (a) Be Determined By The Procuring Entity’s Representative; (b) Comprise The Value Of The Quantities Of The Items In The Bill Of Quantities Completed; And (c) Include The Valuations Of Approved Variations. 41.4. The Procuring Entity’s Representative May Exclude Any Item Certified In A Previous Certificate Or Reduce The Proportion Of Any Item Previously Certified In Any Certificate In The Light Of Later Information. 42. Retention 42.1. The Procuring Entity Shall Retain From Each Payment Due To The Contractor An Amount Equal To A Percentage Thereof Using The Rate As Specified In Itb Sub-clause 42.2. 42.2. Progress Payments Are Subject To Retention Of Ten Percent (10%), Referred To As The “retention Money.” Such Retention Shall Be Based On The Total Amount Due To The Contractor Prior To Any Deduction And Shall Be Retained From Every Progress Payment Until Fifty Percent (50%) Of The Value Of Works, As Determined By The Procuring Entity, Are Completed. If, After Fifty Percent (50%) Completion, The Work Is Satisfactorily Done And On Schedule, No Additional Retention Shall Be Made; Otherwise, The Ten Percent (10%) Retention Shall Again Be Imposed Using The Rate Specified Therefore. 42.3. The Total “retention Money” Shall Be Due For Release Upon Final Acceptance Of The Works. The Contractor May, However, Request The Substitution Of The Retention Money For Each Progress Billing With Irrevocable Standby Letters Of Credit From A Commercial Bank, Bank Guarantees Or Surety Bonds Callable On Demand, Of Amounts Equivalent To The Retention Money Substituted For And Acceptable To The Procuring Entity, Provided That The Project Is On Schedule And Is Satisfactorily Undertaken. Otherwise, The Ten (10%) Percent Retention Shall Be Made. Said Irrevocable Standby Letters Of Credit, Bank Guarantees And/or Surety Bonds, To Be Posted In Favor Of The Government Shall Be Valid For A Duration To Be Determined By The Concerned Implementing Office/agency Or Procuring Entity And Will Answer For The Purpose For Which The Ten (10%) Percent Retention Is Intended, I.e., To Cover Uncorrected Discovered Defects And Third Party Liabilities. 42.4. On Completion Of The Whole Works, The Contractor May Substitute Retention Money With An “on Demand” Bank Guarantee In A Form Acceptable To The Procuring Entity. 43. Variation Orders 43.1. Variation Orders May Be Issued By The Procuring Entity To Cover Any Increase/decrease In Quantities, Including The Introduction Of New Work Items That Are Not Included In The Original Contract Or Reclassification Of Work Items That Are Either Due To Change Of Plans, Design Or Alignment To Suit Actual Field Conditions Resulting In Disparity Between The Preconstruction Plans Used For Purposes Of Bidding And The “as Staked Plans” Or Construction Drawings Prepared After A Joint Survey By The Contractor And The Procuring Entity After Award Of The Contract, Provided That The Cumulative Amount Of The Variation Order Does Not Exceed Ten Percent (10%) Of The Original Project Cost. The Addition/deletion Of Works Should Be Within The General Scope Of The Project As Bid And Awarded. The Scope Of Works Shall Not Be Reduced So As To Accommodate A Positive Variation Order. A Variation Order May Either Be In The Form Of A Change Order Or Extra Work Order. 43.2. A Change Order May Be Issued By The Procuring Entity To Cover Any Increase/decrease In Quantities Of Original Work Items In The Contract. 43.3. An Extra Work Order May Be Issued By The Procuring Entity To Cover The Introduction Of New Work Necessary For The Completion, Improvement Or Protection Of The Project Which Were Not Included As Items Of Work In The Original Contract, Such As, Where There Are Subsurface Or Latent Physical Conditions At The Site Differing Materially From Those Indicated In The Contract, Or Where There Are Duly Unknown Physical Conditions At The Site Of An Unusual Nature Differing Materially From Those Ordinarily Encountered And Generally Recognized As Inherent In The Work Or Character Provided For In The Contract. 43.4. Any Cumulative Variation Order Beyond Ten Percent (10%) Shall Be Subject Of Another Contract To Be Bid Out If The Works Are Separable From The Original Contract. In Exceptional Cases Where It Is Urgently Necessary To Complete The Original Scope Of Work, The Head Of The Procuring Entity May Authorize A Positive Variation Order Go Beyond Ten Percent (10%) But Not More Than Twenty Percent (20%) Of The Original Contract Price, Subject To The Guidelines To Be Determined By The Gppb: Provided, However, That Appropriate Sanctions Shall Be Imposed On The Designer, Consultant Or Official Responsible For The Original Detailed Engineering Design Which Failed To Consider The Variation Order Beyond Ten Percent (10%). 43.5. In Claiming For Any Variation Order, The Contractor Shall, Within Seven (7) Calendar Days After Such Work Has Been Commenced Or After The Circumstances Leading To Such Condition(s) Leading To The Extra Cost, And Within Twenty-eight (28) Calendar Days Deliver A Written Communication Giving Full And Detailed Particulars Of Any Extra Cost In Order That It May Be Investigated At That Time. Failure To Provide Either Of Such Notices In The Time Stipulated Shall Constitute A Waiver By The Contractor For Any Claim. The Preparation And Submission Of Variation Orders Are As Follows: (a) If The Procuring Entity’s Representative/project Engineer Believes That A Change Order Or Extra Work Order Should Be Issued, He Shall Prepare The Proposed Order Accompanied With The Notices Submitted By The Contractor, The Plans Therefore, His Computations As To The Quantities Of The Additional Works Involved Per Item Indicating The Specific Stations Where Such Works Are Needed, The Date Of His Inspections And Investigations Thereon, And The Log Book Thereof, And A Detailed Estimate Of The Unit Cost Of Such Items Of Work, Together With His Justifications For The Need Of Such Change Order Or Extra Work Order, And Shall Submit The Same To The Head Of The Procuring Entity For Approval. (b) The Head Of The Procuring Entity Or His Duly Authorized Representative, Upon Receipt Of The Proposed Change Order Or Extra Work Order Shall Immediately Instruct The Technical Staff Of The Procuring Entity’s To Conduct An On-the-spot Investigation To Verify The Need For The Work To Be Prosecuted. A Report Of Such Verification Shall Be Submitted Directly To The Head Of The Procuring Entity Or His Duly Authorized Representative. (c) The, Head Of The Procuring Entity Or His Duly Authorized Representative, After Being Satisfied That Such Change Order Or Extra Work Order Is Justified And Necessary, Shall Review The Estimated Quantities And Prices And Forward The Proposal With The Supporting Documentation To The Head Of Procuring Entity For Consideration. (d) If, After Review Of The Plans, Quantities And Estimated Unit Cost Of The Items Of Work Involved, The Proper Office Of The Procuring Entity Empowered To Review And Evaluate Change Orders Or Extra Work Orders Recommends Approval Thereof, Head Of The Procuring Entity Or His Duly Authorized Representative, Believing The Change Order Or Extra Work Order To Be In Order, Shall Approve The Same. (e) The Timeframe For The Processing Of Variation Orders From The Preparation Up To The Approval By The Head Of The Procuring Entity Concerned Shall Not Exceed Thirty (30) Calendar Days. 44. Contract Completion Once The Project Reaches An Accomplishment Of Ninety Five (95%) Of The Total Contract Amount, The Procuring Entity May Create An Inspectorate Team To Make Preliminary Inspection And Submit A Punch-list To The Contractor In Preparation For The Final Turnover Of The Project. Said Punch-list Will Contain, Among Others, The Remaining Works, Work Deficiencies For Necessary Corrections, And The Specific Duration/time To Fully Complete The Project Considering The Approved Remaining Contract Time. This, However, Shall Not Preclude The Claim Of The Procuring Entity For Liquidated Damages. 45. Suspension Of Work 45.1. The Procuring Entity Shall Have The Authority To Suspend The Work Wholly Or Partly By Written Order For Such Period As May Be Deemed Necessary, Due To Force Majeure Or Any Fortuitous Events Or For Failure On The Part Of The Contractor To Correct Bad Conditions Which Are Unsafe For Workers Or For The General Public, To Carry Out Valid Orders Given By The Procuring Entity Or To Perform Any Provisions Of The Contract, Or Due To Adjustment Of Plans To Suit Field Conditions As Found Necessary During Construction. The Contractor Shall Immediately Comply With Such Order To Suspend The Work Wholly Or Partly. 45.2. The Contractor Or Its Duly Authorized Representative Shall Have The Right To Suspend Work Operation On Any Or All Projects/activities Along The Critical Path Of Activities After Fifteen (15) Calendar Days From Date Of Receipt Of Written Notice From The Contractor To The District Engineer/regional Director/consultant Or Equivalent Official, As The Case May Be, Due To The Following: (a) There Exist Right-of-way Problems Which Prohibit The Contractor From Performing Work In Accordance With The Approved Construction Schedule. (b) Requisite Construction Plans Which Must Be Owner-furnished Are Not Issued To The Contractor Precluding Any Work Called For By Such Plans. (c) Peace And Order Conditions Make It Extremely Dangerous, If Not Possible, To Work. However, This Condition Must Be Certified In Writing By The Philippine National Police (pnp) Station Which Has Responsibility Over The Affected Area And Confirmed By The Department Of Interior And Local Government (dilg) Regional Director. (d) There Is Failure On The Part Of The Procuring Entity To Deliver Government-furnished Materials And Equipment As Stipulated In The Contract. (e) Delay In The Payment Of Contractor’s Claim For Progress Billing Beyond Forty-five (45) Calendar Days From The Time The Contractor’s Claim Has Been Certified To By The Procuring Entity’s Authorized Representative That The Documents Are Complete Unless There Are Justifiable Reasons Thereof Which Shall Be Communicated In Writing To The Contractor. 45.3. In Case Of Total Suspension, Or Suspension Of Activities Along The Critical Path, Which Is Not Due To Any Fault Of The Contractor, The Elapsed Time Between The Effective Order Of Suspending Operation And The Order To Resume Work Shall Be Allowed The Contractor By Adjusting The Contract Time Accordingly. 46. Payment On Termination 46.1. If The Contract Is Terminated Because Of A Fundamental Breach Of Contract By The Contractor, The Procuring Entity’s Representative Shall Issue A Certificate For The Value Of The Work Done And Materials Ordered Less Advance Payments Received Up To The Date Of The Issue Of The Certificate And Less The Percentage To Apply To The Value Of The Work Not Completed, As Indicated In The Scc. Additional Liquidated Damages Shall Not Apply. If The Total Amount Due To The Procuring Entity Exceeds Any Payment Due To The Contractor, The Difference Shall Be A Debt Payable To The Procuring Entity. 46.2. If The Contract Is Terminated For The Procuring Entity’s Convenience Or Because Of A Fundamental Breach Of Contract By The Procuring Entity, The Procuring Entity’s Representative Shall Issue A Certificate For The Value Of The Work Done, Materials Ordered, The Reasonable Cost Of Removal Of Equipment, Repatriation Of The Contractor’s Personnel Employed Solely On The Works, And The Contractor’s Costs Of Protecting And Securing The Works, And Less Advance Payments Received Up To The Date Of The Certificate. 46.3. The Net Balance Due Shall Be Paid Or Repaid Within Twenty Eight (28) Days From The Notice Of Termination. 46.4. If The Contractor Has Terminated The Contract Under Gcc Clauses 17 Or 18, The Procuring Entity Shall Promptly Return The Performance Security To The Contractor. 47. Extension Of Contract Time 47.1. Should The Amount Of Additional Work Of Any Kind Or Other Special Circumstances Of Any Kind Whatsoever Occur Such As To Fairly Entitle The Contractor To An Extension Of Contract Time, The Procuring Entity Shall Determine The Amount Of Such Extension; Provided That The Procuring Entity Is Not Bound To Take Into Account Any Claim For An Extension Of Time Unless The Contractor Has, Prior To The Expiration Of The Contract Time And Within Thirty (30) Calendar Days After Such Work Has Been Commenced Or After The Circumstances Leading To Such Claim Have Arisen, Delivered To The Procuring Entity Notices In Order That It Could Have Investigated Them At That Time. Failure To Provide Such Notice Shall Constitute A Waiver By The Contractor Of Any Claim. Upon Receipt Of Full And Detailed Particulars, The Procuring Entity Shall Examine The Facts And Extent Of The Delay And Shall Extend The Contract Time Completing The Contract Work When, In The Procuring Entity’s Opinion, The Findings Of Facts Justify An Extension. 47.2. No Extension Of Contract Time Shall Be Granted The Contractor Due To (a) Ordinary Unfavorable Weather Conditions And (b) Inexcusable Failure Or Negligence Of Contractor To Provide The Required Equipment, Supplies Or Materials. 47.3. Extension Of Contract Time May Be Granted Only When The Affected Activities Fall Within The Critical Path Of The Pert/cpm Network. 47.4. No Extension Of Contract Time Shall Be Granted When The Reason Given To Support The Request For Extension Was Already Considered In The Determination Of The Original Contract Time During The Conduct Of Detailed Engineering And In The Preparation Of The Contract Documents As Agreed Upon By The Parties Before Contract Perfection. 47.5. Extension Of Contract Time Shall Be Granted For Rainy/unworkable Days Considered Unfavorable For The Prosecution Of The Works At The Site, Based On The Actual Conditions Obtained At The Site, In Excess Of The Number Of Rainy/unworkable Days Pre-determined By The Procuring Entity In Relation To The Original Contract Time During The Conduct Of Detailed Engineering And In The Preparation Of The Contract Documents As Agreed Upon By The Parties Before Contract Perfection, And/or For Equivalent Period Of Delay Due To Major Calamities Such As Exceptionally Destructive Typhoons, Floods And Earthquakes, And Epidemics, And For Causes Such As Non-delivery On Time Of Materials, Working Drawings, Or Written Information To Be Furnished By The Procuring Entity, Non-acquisition Of Permit To Enter Private Properties Within The Right-of-way Resulting In Complete Paralyzation Of Construction Activities, And Other Meritorious Causes As Determined By The Procuring Entity’s Representative And Approved By The Head Of The Procuring Entity. Shortage Of Construction Materials, General Labor Strikes, And Peace And Order Problems That Disrupt Construction Operations Through No Fault Of The Contractor May Be Considered As Additional Grounds For Extension Of Contract Time Provided They Are Publicly Felt And Certified By Appropriate Government Agencies Such As Dti, Dole, Dilg, And Dnd, Among Others. The Written Consent Of Bondsmen Must Be Attached To Any Request Of The Contractor For Extension Of Contract Time And Submitted To The Procuring Entity For Consideration And The Validity Of The Performance Security Shall Be Correspondingly Extended. 48. Price Adjustment Except For Extraordinary Circumstances As Determined By Neda And Approved By The Gppb, No Price Adjustment Shall Be Allowed. Nevertheless, In Cases Where The Cost Of The Awarded Contract Is Affected By Any Applicable New Laws, Ordinances, Regulations, Or Other Acts Of The Gop, Promulgated After The Date Of Bid Opening, A Contract Price Adjustment Shall Be Made Or Appropriate Relief Shall Be Applied On A No Loss-no Gain Basis. 49. Completion The Contractor Shall Request The Procuring Entity’s Representative To Issue A Certificate Of Completion Of The Works, And The Procuring Entity’s Representative Will Do So Upon Deciding That The Work Is Completed. 50. Taking Over The Procuring Entity Shall Take Over The Site And The Works Within Seven (7) Days From The Date The Procuring Entity’s Representative Issues A Certificate Of Completion. 51. Operating And Maintenance Manuals 51.1. If “as Built” Drawings And/or Operating And Maintenance Manuals Are Required, The Contractor Shall Supply Them By The Dates Stated In The Scc. 51.2. If The Contractor Does Not Supply The Drawings And/or Manuals By The Dates Stated In The Scc, Or They Do Not Receive The Procuring Entity’s Representative’s Approval, The Procuring Entity’s Representative Shall Withhold The Amount Stated In The Scc From Payments Due To The Contractor. Section V. Special Conditions Of Contract Gcc Clause 1.16 The Intended Completion Date Is 120 Cd From Ntp. 1.21 The Procuring Entity Is Lgu- Mapanas, Northern Samar. 1.22 The Procuring Entity’s Representative Is Atty. Ronn Michael L. Tejano Municipal Mayor Municipality Of Mapanas Province Of Northern Samar 1.23 The Site Is Located At Mapanas, Northern Samar. 1.27 The Start Date Is: Upon Receipt Of Notice To Proceed. 1.30 The Works Consist Of: Item No. Scope Of Work Quantity Unit Construction Of Siljagon Multi-purpose Gym Phase 2, Brgy. Siljagon, Mapanas Northern Samar B.3 Permits & Clearance 1.00 Lot B.5 Project Billboard/signboard 1.00 Lot B.7 Construction Safety And Healthy 1.00 Lot B.9 Mobilization And Demobilization 1.00 Lot 903 Formworks And Falsework 66.36 Sq.m 1047 Metal Structures 1,218.00 In.m 1013 Corrugated Metal Roofing, Gauge 24 618.28 Sq.m 1046 Masonry Works 138.60 Sq.m 2.2 Note: The Items To Follow 5.1 The Procuring Entity Shall Give Possession Of All Parts Of The Site To The Contractor Upon The Issuance Of Notice To Proceed. 6.5 The Contractor Shall Employ The Following Key Personnel: Key Personnel Number Civil Engineer 1 Construction Foreman 1 Labor Workers 3 7.4(c) “no Further Instructions”. 7.7 No Further Instructions. 8.1 No Further Instructions. 10 The Site Investigation Reports Are: None 12.3 No Further Instructions. 12.5 In Case Of Semi-permanent Structures, Such As Buildings Of Types 1, 2, And 3 As Classified Under The National Building Code Of The Philippines, Concrete/asphalt Roads, Concrete River Control, Drainage, Irrigation Lined Canals, River Landing, Deep Wells, Rock Causeway, Pedestrian Overpass, And Other Similar Semi-permanent Structures: Five (5) Years. 13 “no Additional Provision.” 18.3(h)(i) No Further Instructions. 21.2 The Arbiter Is: Construction Industry Arbitration Commission 29.1 No Day Works Are Applicable To The Contract. 31.1 The Contractor Shall Submit The Program Of Work To The Procuring Entity’s Representative Within 15days Of Delivery Of The Letter Of Acceptance. 31.3 The Period Between Program Of Work Updates Is 15days. The Amount To Be Withheld For Late Submission Of An Updated Program Of Work Is P 1,000.00. 34.3 The Funding Source Is Coming From Nia 39.1 The Amount Of The Advance Payment Is 15% Of The Contract Price (lump Sum) And Shall Be Release Once Upon Presentation Of The Following Documents As Required: 1. Letter Request For Advance Payment From The Contractor 2. Bank Guarantee For Advance Payment 40.1 Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Be Included For Payment. 51.1 The Date By Which Operating And Maintenance Manuals Are Required Is Not Applicable. The Date By Which “as Built” Drawings Are Required Is 20 Days Upon Completion Of The Subproject. 51.2 The Amount To Be Withheld For Failing To Produce “as Built” Drawings And/or Operating And Maintenance Manuals By The Date Required Is P1,000.00. Section Vi. Specifications Project Name: Construction Of Siljagon Multi-purpose Gym Phase 2 Location : Brgy. Siljagon, Mapanas, Northern Samar Item No. Description Qty. Unit. B.5 Project Billboard/signboard 1.00 Lot A. Material A. Tarpaulin (4’x8’) 1.00 Pc B. Plywood Marine (1/4”x1.2m X 2.44m) 1.00 Pc C. Coco Lumber, 2” X 3” X 12’ 42.00 Bd.ft. D. Common Nails Assorted 1.00 Kg B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description (1 Gang =1- Foreman, 1-carpenter, 1-laborer 1.00 E. Labor Requirement Foreman 1 1.00 Skilled Carpenter 1 1.00 Unskilled 1 1.00 B.9 Mobilization And Demobilization 1.00 Lot A. Material A. Safety Helmet 2.00 Pc B. Safety Shoes 2.00 Pc C. Safety Vest 2.00 Pc D. Working Gloves 2.00 Pc E. Face Mask (surgical/cloth) 1.00 Box F. Eye Googles 2.00 Pc G. Sanitizing Solution 2.00 Lit H. Ethyl Alcohol 2.00 Lit I. Disinfectant Spray 2.00 Can J. Liquid Hand Soap 2.00 Lit Environmental Mitigating Cost A. Plywood Ordinary (1/4”x1.2m X 2.44m) 1.00 Pc B. Coco Lumber, 2” X 2” X 12’ 12.00 Pcs C. Qde White Enamel 2.00 L D. Qde Red 1.00 Pint E. Qde Green 1.00 Pint F. Qde Blue 1.00 Pint G. Paint Brush, 2” 2.00 Pc H. Lettering Brush 1.00 Pc I. Cwn 2” 1.00 Kg J. Cwn ½” 1.00 Kg K. Trapal, 12 X 12 1.00 Unit B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description E. Labor Requirement Safety Officer 1.00 Health Personnel (full Time First Aide) 1.00 Sanitation Aide 1.00 B.9 Mobilzation And Demobilization 1.00 Lot A. Material B. Freight And Handling C. Name And Capacity Of Equipment Cargo/service Truck (2-5 Mt) D. Labor Derivation (subsidiary Work Description E. Labor Requirement 1047 Metal Structures 1,218.00 In.m A. Material A. Lc 200x75x25x3.2 203.00 Pcs 11,449.20 Kgs B. Sag Rods, Rsb, Plain, 12mmǿ 39.00 Pcs 207.79 Kgs C. Welding Rod 256.00 Kg D. Paint Red Lead 12.00 Gal E. Paint Brush, 2” 12.00 Pc B. Freight And Handling C. Name And Capacity Of Equipment Welding Machine, Electric Driven/ Dc Output 1.00 Cutting Outfit 1.00 D. Labor Derivation (subsidiary Work Description Truss Fabrication And Installation (including Purlins) Fabrication And Install: 1-foreman, 1-welder, 3-laborers 1,218.00 Capability: 18 In.m./day/gang E. Labor Requirement Foreman 1 1.00 Skilled Welder 1 2.00 Unskilled 3 2.00 1013 Corrugated Metal Roofing, Gauge 24 618.28 Sq.m. A. Material Roofing: 618.28 Sq.m. A. 0.6mm Thk Pre-painted Long Span (ribbed Type) G.i Roofing 619.00 In.m. B. J Bolt ¼ X 2 ½ ’’, With Nut And Bonded Washer 3,714.00 Pc C. Touchup Paint 6.00 L D. Paint Brush, 2” 5.00 Pc B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description Roofing Sheets Installation Install: 1 Gang= 1-foreman, 1-carpenter, 3-laborers Capability: 20 Sq.m (doors)/day/gang Jamb Installation Install: 1 Gang= 1-foreman, 1-skilled, 1-laborer Capability: 4 Sets (jamb)/day/gang Window Installation Install: 1 Gang= 1-foreman, 1-skilled, 1-laborer 1.92 Capability: 2.88 Sq.m (window)/day/gang E. Labor Requirement Foreman 1 1.00 Skilled Carpenter 1 1.00 Unskilled 1 1.00 1002 Plumbing Works 1.00 Lot A. Material Cold Water Line A. Pprc Pipe,20mm Dia. X 4m, Pn 16 1.00 Pc B. Pp-r Tee, 20mm Dia. 1.00 Pc C. Pp-r Elbow, 20mm Dia. 2.00 Pc D. Tefflon Tape 1.00 Roll Fixture E. Wall Faucet, 1/2” X 4”, Stainless Steel 1.00 Pc F. Gate Valve 20mm Dia 1.00 Pc B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description Plumbing Installation: Install: 1gang=1-foreman,1-plumber, 1-laborer Capability: 8 Pcs Pipes /day/gang Fixture Installation: Install: 1gang=1-foreman,1-plumber, 1-laborer Capability: 8 Fixtures /day/gang E. Labor Requirement Foreman 1 1.00 Skilled Plumber 1 1.00 Unskilled 1 1.00 1032 Painting, Varnishing And Other Related Works 40.32 Sq.m. A. Material Concrete/masonry Walls/ Ceiling 40.32 Sq.m. A. Skimcoat, 20kg 1.00 Bag B. Acrylic Solvent Based Paint 2.00 Gal C. Paint Enamel, Semi Gloss 2.00 Gal D. Sandpaper 3.00 Pc E. Paint Brush, 2” 1.00 Pc F. Paint Roller (152mm) 1.00 Pc B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description Plumbing Installation: Install: 1gang=1-foreman,1-painter, 1-laborer Capability: 30 Sq.m. (roller)/day/gang E. Labor Requirement Foreman 1 1.00 Skilled Painter 1 2.00 Unskilled 1 2.00 1100 Conduits, Boxes And Fittings 1.00 Ls A. Material Conduits & Fittings A. Pvc Conduit Pipe (3m X 20mm D), Orange 4.00 Pc B. Pvc Conduit Elbow 90 Deg, (20mm D) 4.00 Pc C. Electrical Rigid Steel Conduit (25.4mm D) Pc D. Elbow 90 Deg (rigid Steel) (25mm D) Pc E. Service Entrance Cap (25.4mm D) Pc F. Solvent Cement,400cc 1.00 Can Boxes A. Octagonal Junction Box Type Gauge #16 Pc B. Utility Box Gauge #16 (50mm X 101mm X 53mm) 1.00 Pc B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description Conduit Installation Install: 1 Gang = 1-foreman, 1- Electrician, 1-laborer 12.00 Capability: 28m/day/gang E. Labor Requirement Foreman 1 1.00 Skilled Electrician 1 1.00 Unskilled 1 1.00 1101 Wires And Wiring Devices 1.00 Ls A. Material Wires A. Electric Wires Thwn/thhn 3.5 Mm2 20.00 M B. Electric Wires Thwn/thhn 5.5 Mm2 M C. Electric Wires Thwn/thhn 14 Mm2 M Wiring Devices D. Polarized 3-prongs (acu Outlet) 1.00 Set E. Two-gang Switch Set F. Three Gang Switch Set G. One Gang Convenience Outlet Set H. Duplex Conveniece Outlet Set I. Polarized 3-prongs (acu Outlet Set J. Electrical Tape 3/4 X 20 Yds 1.00 Pc B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description Wirings Install: 1 Gang =1-foreman, 1-electrician, 3-laborers 20.00 Capability: 144m/day/gang E. Labor Requirement Foreman 1 1.00 Skilled Electrician 1 1.00 Unskilled 1 1.00 Section Vii. Drawings Bill Of Quantities Item No. Scope Of Work Quantity Unit Unit Cost Total Amount 1.) Construction Of Siljagon Multi-purpose Gym Phase 2, Brgy. Siljagon, Mapanas, N. Samar B.5 Permits & Clearances 1.00 Lot B.5 Project Billboard/signboard 1.00 Lot 5,409.36 5,409.36 B.7 Construction Safety And Health 1.00 Lot 24,643.00 24,643.00 B.9 Mobilization And Demobilization 1.00 Lot 12,528.00 12,528.00 903 Formworks And Falseworks 1.00 Lot 2,134.55 141,648.64 1047 Metal Structures 1,218.00 Lot 1,126.61 1,372,213.09 1013 Corrugated Metal Roofing, Gauge 24 618.28 Sq.m. 815.66 504,306.60 1046 Masonry Works 138.60 Ls 1,574.15 218,177.28 Total 2,278,925.97 Total Cost Of All Line Item Includes Cost Of Contractor’s Profit, Taxes And Ocm. Attached Detailed Cost Estimates Section Ix. Bidding Forms Table Of Contents Bid Form 79 Form Of Contract Agreement 81 Omnibus Sworn Statement 83 Bid Form Date: Iaeb No: To: Lgu-mapanas Northern Samar Address: Mapanas Northern Samar We, The Undersigned, Declare That: We Have Examined And Have No Reservation To The Bidding Documents, Including Addenda, For The Contract Construction Of Siljagon Multi-purpose Gym Phase 2 , Barangay Siljagon , Mapanas N. Samar (a) We Offer To Execute The Works For This Contract In Accordance With The Bid And Bid Data Sheet, General And Special Conditions Of Contract Accompanying This Bid; The Total Price Of Our Bid, Excluding Any Discounts Offered In Item (d) Below Is: [insert Information]; The Discounts Offered And The Methodology For Their Application Are: [insert Information]; (b) Our Bid Shall Be Valid For A Period Of 120 Days From The Date Fixed For The Bid Submission Deadline In Accordance With The Bidding Documents, And It Shall Remain Binding Upon Us And May Be Accepted At Any Time Before The Expiration Of That Period; (c) If Our Bid Is Accepted, We Commit To Obtain A Performance Security In The Amount Of [insert Percentage Amount] Percent Of The Contract Price For The Due Performance Of The Contract; (d) Our Firm, Including Any Subcontractors Or Suppliers For Any Part Of The Contract, Have Nationalities From The Following Eligible Countries: [insert Information]; (e) We Are Not Participating, As Bidders, In More Than One Bid In This Bidding Process, Other Than Alternative Offers In Accordance With The Bidding Documents; (f) Our Firm, Its Affiliates Or Subsidiaries, Including Any Subcontractors Or Suppliers For Any Part Of The Contract, Has Not Been Declared Ineligible By The Funding Source; (g) We Understand That This Bid, Together With Your Written Acceptance Thereof Included In Your Notification Of Award, Shall Constitute A Binding Contract Between Us, Until A Formal Contract Is Prepared And Executed; And (h) We Understand That You Are Not Bound To Accept The Lowest Evaluated Bid Or Any Other Bid That You May Receive. Name: In The Capacity Of: Signed: Duly Authorized To Sign The Bid For And On Behalf Of: Date: ___________ Form Of Contract Agreement This Agreement, Made This [insert Date] Day Of [insert Month], [insert Year] Between [name And Address Of Procuring Entity](hereinafter Called The “entity”) And [name And Address Of Contractor] (hereinafter Called The “contractor”). Whereas, The Entity Is Desirous That The Contractor Execute [name And Identification Number Of Contract] (hereinafter Called “the Works”) And The Entity Has Accepted The Bid For [insert The Amount In Specified Currency In Numbers And Words] By The Contractor For The Execution And Completion Of Such Works And The Remedying Of Any Defects Therein. Now This Agreement Witnesseth As Follows: 1. In This Agreement, Words And Expressions Shall Have The Same Meanings As Are Respectively Assigned To Them In The Conditions Of Contract Hereinafter Referred To. 2. The Following Documents Shall Be Attached, Deemed To Form, And Be Read And Construed As Part Of This Agreement, To Wit: (a) General And Special Conditions Of Contract; (b) Drawings/plans; (c) Specifications; (d) Invitation To Apply For Eligibility And To Bid; (e) Instructions To Bidders; (f) Bid Data Sheet; (g) Addenda And/or Supplemental/bid Bulletins, If Any; (h) Bid Form, Including All The Documents/statements Contained In The Bidder’s Bidding Envelopes, As Annexes; (i) Eligibility Requirements, Documents And/or Statements; (j) Performance Security; (k) Credit Line Issued By A Licensed Bank, If Any; (l) Notice Of Award Of Contract And The Bidder’s Conforme Thereto; (m) Other Contract Documents That May Be Required By Existing Laws And/or The Entity. 3. In Consideration Of The Payments To Be Made By The Entity To The Contractor As Hereinafter Mentioned, The Contractor Hereby Covenants With The Entity To Execute And Complete The Works And Remedy Any Defects Therein In Conformity With The Provisions Of This Contract In All Respects. 4. The Entity Hereby Covenants To Pay The Contractor In Consideration Of The Execution And Completion Of The Works And The Remedying Of Defects Wherein, The Contract Price Or Such Other Sum As May Become Payable Under The Provisions Of This Contract At The Times And In The Manner Prescribed By This Contract. In Witness Whereof The Parties Thereto Have Caused This Agreement To Be Executed The Day And Year First Before Written. Signed, Sealed, Delivered By The (for The Entity) Signed, Sealed, Delivered By The (for The Contractor). Binding Signature Of Procuring Entity ________________________________________________ Binding Signature Of Contractor _____________________________________________ [addendum Showing The Corrections, If Any, Made During The Bid Evaluation Should Be Attached With This Agreement] Omnibus Sworn Statement Republic Of The Philippines ) City/municipality Of ______ ) S.s. Affidavit I, [name Of Affiant], Of Legal Age, [civil Status], [nationality], And Residing At [address Of Affiant], After Having Been Duly Sworn In Accordance With Law, Do Hereby Depose And State That: 1. Select One, Delete The Other: If A Sole Proprietorship: I Am The Sole Proprietor Of [name Of Bidder] With Office Address At [address Of Bidder]; If A Partnership, Corporation, Cooperative, Or Joint Venture: I Am The Duly Authorized And Designated Representative Of [name Of Bidder] With Office Address At [address Of Bidder]; 2. Select One, Delete The Other: If A Sole Proprietorship: As The Owner And Sole Proprietor Of [name Of Bidder], I Have Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary To Represent It In The Bidding For [name Of The Project] Of The [name Of The Procuring Entity]; If A Partnership, Corporation, Cooperative, Or Joint Venture: I Am Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary And/or To Represent The [name Of Bidder] In The Bidding As Shown In The Attached [state Title Of Attached Document Showing Proof Of Authorization (e.g., Duly Notarized Secretary’s Certificate Issued By The Corporation Or The Members Of The Joint Venture)]; 3. [name Of Bidder] Is Not “blacklisted” Or Barred From Bidding By The Government Of The Philippines Or Any Of Its Agencies, Offices, Corporations, Or Local Government Units, Foreign Government/foreign Or International Financing Institution Whose Blacklisting Rules Have Been Recognized By The Government Procurement Policy Board; 4. Each Of The Documents Submitted In Satisfaction Of The Bidding Requirements Is An Authentic Copy Of The Original, Complete, And All Statements And Information Provided Therein Are True And Correct; 5. [name Of Bidder]is Authorizing The Head Of The Procuring Entity Or Its Duly Authorized Representative(s) To Verify All The Documents Submitted; 6. Select One, Delete The Rest: If A Sole Proprietorship: I Am Not Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; If A Partnership Or Cooperative: None Of The Officers And Members Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; If A Corporation Or Joint Venture: None Of The Officers, Directors, And Controlling Stockholders Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; 7. [name Of Bidder] Complies With Existing Labor Laws And Standards; And 8. [name Of Bidder] Is Aware Of And Has Undertaken The Following Responsibilities As A Bidder: A) Carefully Examine All Of The Bidding Documents; B) Acknowledge All Conditions, Local Or Otherwise, Affecting The Implementation Of The Contract; C) Made An Estimate Of The Facilities Available And Needed For The Contract To Be Bid, If Any; And D) Inquire Or Secure Supplemental/bid Bulletin(s) Issued For The [name Of The Project]. In Witness Whereof, I Have Hereunto Set My Hand This __ Day Of ___, 20__ At ____________, Philippines. _____________________________________ Bidder’s Representative/authorized Signatory [jurat] * This Form Will Not Apply For Wb Funded Projects.
Closing Date16 Dec 2024
Tender AmountPHP 2.9 Million (USD 50.4 K)
Municipality Of Mapanas, Northern Samar Tender
Civil And Construction...+1Civil Works Others
Philippines
Details: Description Bidding Documents Procurement Of Infrastructure Projects Name Of Project: Rehabilatation/improvement Of Longcop St. Barangay E. Loadenio, Mapanas Northern Samar Contract Reference No. 2024-11-104 Table Of Contents Section I. Invitation To Bid 3 Section Ii. Instructions To Bidders 7 Section Iii. Bid Data Sheet 35 Section Iv. General Conditions Of Contract 38 Section V. Special Conditions Of Contract 70 Section Vi. Specifications 72 Section Vii. Drawings 75 Section Viii. Bill Of Quantities Error! Bookmark Not Defined. Section Ix. Bidding Forms 77 Section X. Foreign-assisted Projects Error! Bookmark Not Defined. Section I. Invitation To Bid Bid Notice Abstract Invitation To Bid (itb) Republic Of The Philippines Province Of Northern Samar Municipality Of Mapanas Invitation To Bid For Project: Rehabilatation / Improvement Of Longcop St. Barangay E. Loadenio, Mapanas, Northern Samar The Lgu- Mapanas, Northern Samar, Through The Economic Development Fund Of Fy 2025 Intends To Apply The Sum Of One Million Four Hundred Ninety Two Thousand Six Hundred Sixty Eight Pesos 52/100 Only (p1,492,668.52) Being The Approved Budget For The Contract (abc) To Payments Under The Contract For: Rehabilitation / Improvement Of Longcop St. Barangay E. Laodenio, Mapanas, Northern Samar Bids Received In Excess Of The Abc Shall Be Automatically Rejected At Bid Opening. 1. The Lgu- Mapanas, Northern Samar Now Invites Bids For The Following Description Of Works To Be Procured: Item No. Scope Of Work Quantity Unit Rehabilitation / Improvement Of Longcop St. Barangay E. Laodenio, Mapanas, Northern Samar Part B Other General Requirements B.5 Projects Billboard/sign Board 1.00 Each B.7(2) Occupational Safety And Health Program 1.00 L.s B.9 Mobilization/demobilization 1.00 L.s Part C Earthworks 101(3)a.2 Removal Existing Pcc Pavement, 0.2m Thk (pcc Reblocking At Intermittent 410.00 Sq.m 102(2)b Surplus Common Excavation 123.00 Cu.m 105(1) Subgrade Preparation (common Materials) 492.00 Sq.m Part D Subbase And Base Course 200(1) Aggregate Subbase Course 89.30 Cu.m 201(1) Aggregate Base Course 98.40 Cu.m Part E Surface Courses 311(1)a.2 Pcc Pavement (plain) Convention Method, 200mm Thk 410.00 Sq.m Completion Of The Works Is Required 60 Calendar Days. Bidders Should Have Completed, Within Ten (10) Years From The Date Of Submission And Receipt Of Bids, A Contract Similar To The Project. The Description Of An Eligible Bidder Is Contained In The Bidding Documents, Particularly, In Section Ii. Instructions To Bidders. Section Ii. Instructions To Bidders. 2. Bidding Will Be Conducted Through Open Competitive Bidding Procedures Using Non-discretionary Pass/fail Criterion As Specified In The Implementing Rules And Regulations (irr) Of Republic Act 9184 (ra 9184), Otherwise Known As The “government Procurement Reform Act”. Bidding Is Restricted To Filipino Citizens/sole Proprietorships, Partnerships, Or Organizations With At Least Seventy Five Percent (75%) Interest Or Outstanding Capital Stock Belonging To Citizens Of The Philippines. 4. Interested Bidders May Obtain Further Information From Lgu- Bac Mapanas, Northern Samar And Inspect The Bidding Documents At The Address Given Below From November 26, 2024-december 13, 2024, 8:00 A.m. To 5:00 Pm. A Complete Set Of Bidding Documents May Be Purchased By Interested Bidders From The Address Below And Upon Payment Of A Nonrefundable Fee For The Bidding Documents In The Amount Of P5,000.00. It May Also Be Downloaded Free Of Charge From The Website Of The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity, Provided That Bidders Shall Pay The Fee For The Bidding Documents Not Later That The Submission Of Their Bids. 5. The Lgu- Mapana, Northern Samar Will Hold A Pre-bid Conference On December 5, 2024 At 10:00 A.m. At Executive Conference, 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar, Which Shall Be Open Only To All Interested Parties Who Have Purchased The Bidding Documents. 6. Bids Must Be Delivered To The Address Below On Or Before 9:00 A.m. Of December 16, 2024 At Bac Office, @ Municipal Planning & Development Office (mpdo), Mapanas, Northern Samar. All Bids Must Be Accompanied By A Bid Security In Any Of The Acceptable Forms And In The Amount Stated In Itb Clause 18. Bids Will Be Opened In The Presence Of The Bidders’ Authorized Representatives Who Choose To Attend At The Address Below. Late Bids Shall Not Be Accepted. The Bidder May Request That The Bid Documents Be Sent To Them By Mail Or Courier, And For This, The Bidder Shall Pay The Amount In Philippine Peso To Cover The Cost Of Mail Or Courier Delivery. The Fee For Obtaining A Copy Of The Bid Documents And The Cost Of Mail Or Courier Shall Be Paid By The Bidder Thru S Cashier’s Check Or Manager’s Check Issued In Favor Of The Municipality Of Mapanas. 7. The Lgu- Mapanas, Northern Samar Reserves The Right To Accept Or Reject Any Bid, To Annul The Bidding Process, And To Reject All Bids At Any Time Prior To Contract Award, Without Thereby Incurring Any Liability To The Affected Bidder Or Bidders. 8. For Further Information, Please Refer To: Reno C. Salazar Bac Secretary Mapanas, Northern Samar Mobile # 09459852914 Ma. Teresa L. Minguez Bac Chairperson Mapanas, Northern Samar Mobile # 09778033758 Section Ii. Instructions To Bidders 1. The Bids Must Be Delivered On Or Before December 16, 2024 At 9:00 A.m And Failure To Submit The Bid Proposal May Ground For Disqualification Of The Bid. 2. Bids Received In Excess Of The Abc Shall Be Automatically Rejected At Bid Opening. 1. The Lgu- Mapanas, Northern Samar Now Invites Bids For The Following Description Of Works To Be Procured: Item No. Scope Of Work Quantity Unit Rehabilitation / Improvement Of Longcop St. Barangay E. Laodenio, Mapanas, Northern Samar Part B Other General Requirements B.5 Projects Billboard/sign Board 1.00 Each B.7(2) Occupational Safety And Health Program 1.00 L.s B.9 Mobilization/demobilization 1.00 L.s Part C Earthworks 101(3)a.2 Removal Existing Pcc Pavement, 0.2m Thk (pcc Reblocking At Intermittent 410.00 Sq.m 102(2)b Surplus Common Excavation 123.00 Cu.m 105(1) Subgrade Preparation (common Materials) 492.00 Sq.m Part D Subbase And Base Course 200(1) Aggregate Subbase Course 89.30 Cu.m 201(1) Aggregate Base Course 98.40 Cu.m Part E Surface Courses 311(1)a.2 Pcc Pavement (plain) Convention Method, 200mm Thk 410.00 Sq.m Completion Of The Works Is Required 120 Calendar Days. Bidders Should Have Completed, Within Ten (10) Years From The Date Of Submission And Receipt Of Bids, A Contract Similar To The Project. The Description Of An Eligible Bidder Is Contained In The Bidding Documents, Particularly, In Section Ii. Instructions To Bidders. 2. Bidding Will Be Conducted Through Open Competitive Bidding Procedures Using Non-discretionary Pass/fail Criterion As Specified In The Implementing Rules And Regulations (irr) Of Republic Act 9184 (ra 9184), Otherwise Known As The “government Procurement Reform Act”. Bidding Is Restricted To Filipino Citizens/sole Proprietorships, Partnerships, Or Organizations With At Least Seventy Five Percent (75%) Interest Or Outstanding Capital Stock Belonging To Citizens Of The Philippines. 3. Interested Bidders May Obtain Further Information From Lgu- Bac Mapanas, Northern Samar And Inspect The Bidding Documents At The Address Given Below From November 26, 2024-december 13, 2024, 8:00 A.m. To 5:00 Pm. A Complete Set Of Bidding Documents May Be Purchased By Interested Bidders From The Address Below And Upon Payment Of A Nonrefundable Fee For The Bidding Documents In The Amount Of P5,000.00. It May Also Be Downloaded Free Of Charge From The Website Of The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity, Provided That Bidders Shall Pay The Fee For The Bidding Documents Not Later That The Submission Of Their Bids. 4. The Lgu- Mapanas, Northern Samar Will Hold A Pre-bid Conference On December 5, 2024 At 10:00 A.m. At Executive Conference, 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar, Which Shall Be Open Only To All Interested Parties Who Have Purchased The Bidding Documents. 5. Bids Must Be Delivered To The Address Below On Or Before 9:00 A.m. Of December 16, 2024 At Bac Office, @ Municipal Planning & Development Office (mpdo), Mapanas, Northern Samar. All Bids Must Be Accompanied By A Bid Security In Any Of The Acceptable Forms And In The Amount Stated In Itb Clause 18. Bids Will Be Opened In The Presence Of The Bidders’ Authorized Representatives Who Choose To Attend At The Address Below. Late Bids Shall Not Be Accepted. The Bidder May Request That The Bid Documents Be Sent To Them By Mail Or Courier, And For This, The Bidder Shall Pay The Amount In Philippine Peso To Cover The Cost Of Mail Or Courier Delivery. The Fee For Obtaining A Copy Of The Bid Documents And The Cost Of Mail Or Courier Shall Be Paid By The Bidder Thru S Cashier’s Check Or Manager’s Check Issued In Favor Of The Municipality Of Mapanas. 6. The Lgu- Mapanas, Northern Samar Reserves The Right To Accept Or Reject Any Bid, To Annul The Bidding Process, And To Reject All Bids At Any Time Prior To Contract Award, Without Thereby Incurring Any Liability To The Affected Bidder Or Bidders. 7. For Further Information, Please Refer To: Reno C. Salazar Bac Secretary Mapanas, Northern Samar Mobile # 09459852914 Ma. Teresa L. Minguez Bac Chairperson Mapanas N. Samar Mobile # 09778033758 Table Of Contents A. General 11 1. Scope Of Bid 11 2. Source Of Funds 11 3. Corrupt, Fraudulent, Collusive, And Coercive Practices 11 4. Conflict Of Interest 12 5. Eligible Bidders 14 6. Bidder’s Responsibilities 15 7. Origin Of Goods And Services 17 8. Subcontracts 17 B. Contents Of Bidding Documents 17 9. Pre-bid Conference 17 10. Clarification And Amendment Of Bidding Documents 18 C. Preparation Of Bids 18 11. Language Of Bids 18 12. Documents Comprising The Bid: Eligibility And Technical Components 18 13. Documents Comprising The Bid: Financial Component 21 14. Alternative Bids 21 15. Bid Prices 22 16. Bid Currencies 22 17. Bid Validity 23 18. Bid Security 23 19. Format And Signing Of Bids 25 20. Sealing And Marking Of Bids 26 D. Submission And Opening Of Bids 26 21. Deadline For Submission Of Bids 26 22. Late Bids 26 23. Modification And Withdrawal Of Bids 27 24. Opening And Preliminary Examination Of Bids 27 E. Evaluation And Comparison Of Bids 28 25. Process To Be Confidential 28 26. Clarification Of Bids 29 27. Detailed Evaluation And Comparison Of Bids 29 28. Post Qualification 30 29. Reservation Clause 31 F. Award Of Contract 32 30. Contract Award 32 31. Signing Of The Contract 33 32. Performance Security 33 33. Notice To Proceed 34 A. General 1. Scope Of Bid 1.1. The Procuring Entity As Defined In The Bds, Invites Bids For The Construction Of Works, As Described In Section Vi. Specifications. The Name And Identification Number Of The Contract Is Provided In The Bds. 1.2. The Successful Bidder Will Be Expected To Complete The Works By The Intended Completion Date Specified In Scc Clause 1.16. 2. Source Of Funds The Procuring Entity Has A Budget Or Has Applied For Or Received Funds From The Funding Source Named In The Bds, And In The Amount Indicated In The Bds. It Intends To Apply Part Of The Funds Received For The Project, As Defined In The Bds, To Cover Eligible Payments Under The Contract For The Works. 3. Corrupt, Fraudulent, Collusive, And Coercive Practices 3.1. Unless Otherwise Specified In The Bds, The Procuring Entity, As Well As Bidders And Contractors, Shall Observe The Highest Standard Of Ethics During The Procurement And Execution Of The Contract. In Pursuance Of This Policy, The Funding Source: (a) Defines, For Purposes Of This Provision, The Terms Set Forth Below As Follows: (i) "corrupt Practice" Means Behavior On The Part Of Officials In The Public Or Private Sectors By Which They Improperly And Unlawfully Enrich Themselves, Others, Or Induce Others To Do So, By Misusing The Position In Which They Are Placed, And Includes The Offering, Giving, Receiving, Or Soliciting Of Anything Of Value To Influence The Action Of Any Such Official In The Procurement Process Or In Contract Execution; Entering, On Behalf Of The Procuring Entity, Into Any Contract Or Transaction Manifestly And Grossly Disadvantageous To The Same, Whether Or Not The Public Officer Profited Or Will Profit Thereby, And Similar Acts As Provided In Republic Act 3019; (ii) "fraudulent Practice" Means A Misrepresentation Of Facts In Order To Influence A Procurement Process Or The Execution Of A Contract To The Detriment Of The Procuring Entity, And Includes Collusive Practices Among Bidders (prior To Or After Bid Submission) Designed To Establish Bid Prices At Artificial, Non-competitive Levels And To Deprive The Procuring Entity Of The Benefits Of Free And Open Competition; (iii) “collusive Practices” Means A Scheme Or Arrangement Between Two Or More Bidders, With Or Without The Knowledge Of The Procuring Entity, Designed To Establish Bid Prices At Artificial, Non-competitive Levels; And (iv) “coercive Practices” Means Harming Or Threatening To Harm, Directly Or Indirectly, Persons, Or Their Property To Influence Their Participation In A Procurement Process, Or Affect The Execution Of A Contract; (v) “obstructive Practice” Is (aa) Deliberately Destroying, Falsifying, Altering Or Concealing Of Evidence Material To An Administrative Proceedings Or Investigation Or Making False Statements To Investigators In Order To Materially Impede An Administrative Proceedings Or Investigation Of The Procuring Entity Or Any Foreign Government/foreign Or International Financing Institution Into Allegations Of A Corrupt, Fraudulent, Coercive Or Collusive Practice; And/or Threatening, Harassing Or Intimidating Any Party To Prevent It From Disclosing Its Knowledge Of Matters Relevant To The Administrative Proceedings Or Investigation Or From Pursuing Such Proceedings Or Investigation; Or (bb) Acts Intended To Materially Impede The Exercise Of The Inspection And Audit Rights Of The Procuring Entity Or Any Foreign Government/foreign Or International Financing Institution Herein. (b) Will Reject A Proposal For Award If It Determines That The Bidder Recommended For Award Has Engaged In Corrupt Or Fraudulent Practices In Competing For The Contract; And (c) Will Declare A Firm Ineligible, Either Indefinitely Or For A Stated Period Of Time, To Be Awarded Contract Funded By The Funding Source If It At Any Time Determines That The Firm Has Engaged In Corrupt Or Fraudulent Practices In Competing Or, Or In Executing, A Contract Funded By The Funding Source. 3.2. Further, The Procuring Entity Will Seek To Impose The Maximum Civil, Administrative, And/or Criminal Penalties Available Under The Applicable Laws On Individuals And Organizations Deemed To Be Involved In Any Of The Practices Mentioned In Itb Clause 3.1(a). 3.3. Furthermore, The Funding Source And The Procuring Entity Reserve The Right To Inspect And Audit Records And Accounts Of A Contractor In The Bidding For And Performance Of A Contract Themselves Or Through Independent Auditors As Reflected In The Gcc Clause 34. 4. Conflict Of Interest 4.1. All Bidders Found To Have Conflicting Interests Shall Be Disqualified To Participate In The Procurement At Hand, Without Prejudice To The Imposition Of Appropriate Administrative, Civil, And Criminal Sanctions. A Bidder May Be Considered To Have Conflicting Interests With Another Bidder In Any Of The Events Described In Paragraphs (a) Through (c) And A General Conflict Of Interest In Any Of The Circumstances Set Out In Paragraphs (d) Through (g) Below: (a) A Bidder Has Controlling Shareholders In Common With Another Bidder; (b) A Bidder Receives Or Has Received Any Direct Or Indirect Subsidy From Any Other Bidder; (c) A Bidder Has The Same Legal Representative As That Of Another Bidder For Purposes Of This Bid; (d) A Bidder Has A Relationship, Directly Or Through Third Parties, That Puts Them In A Position To Have Access To Information About Or Influence On The Bid Of Another Bidder Or Influence The Decisions Of The Procuring Entity Regarding This Bidding Process. This Will Include A Firm Or An Organization Who Lends, Or Temporarily Seconds, Its Personnel To Firms Or Organizations Which Are Engaged In Consulting Services For The Preparation Related To Procurement For Or Implementation Of The Project If The Personnel Would Be Involved In Any Capacity On The Same Project; (e) A Bidder Submits More Than One Bid In This Bidding Process. However, This Does Not Limit The Participation Of Subcontractors In More Than One Bid; (f) A Bidder Who Participated As A Consultant In The Preparation Of The Design Or Technical Specifications Of The Goods And Related Services That Are The Subject Of The Bid; Or (g) A Bidder Who Lends, Or Temporary Seconds, Its Personnel To Firms Or Organizations Which Are Engaged In Consulting Services For The Preparation Related To Procurement For Or Implementation Of The Project, If The Personnel Would Be Involved In Any Capacity On The Same Project. 4.2. In Accordance With Section 47 Of The Irr Of Ra 9184, All Bidding Documents Shall Be Accompanied By A Sworn Affidavit Of The Bidder That It Is Not Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), Members Of The Technical Working Group (twg), Members Of The Bac Secretariat, The Head Of The Project Management Office (pmo) Or The End-user Unit, And The Project Consultants, By Consanguinity Or Affinity Up To The Third Civil Degree. On The Part Of The Bidder, This Clause Shall Apply To The Following Persons: (a) If The Bidder Is An Individual Or A Sole Proprietorship, To The Bidder Himself; (b) If The Bidder Is A Partnership, To All Its Officers And Members; (c) If The Bidder Is A Corporation, To All Its Officers, Directors, And Controlling Stockholders; And (d) If The Bidder Is A Joint Venture (jv), The Provisions Of Items (a), (b), Or (c) Of This Clause Shall Correspondingly Apply To Each Of The Members Of The Said Jv, As May Be Appropriate. Relationship Of The Nature Described Above Or Failure To Comply With This Clause Will Result In The Automatic Disqualification Of A Bidder. 5. Eligible Bidders 5.1. Unless Otherwise Indicated In The Bds, The Following Persons Shall Be Eligible To Participate In This Bidding: (a) Duly Licensed Filipino Citizens/sole Proprietorships; (b) Partnerships Duly Organized Under The Laws Of The Philippines And Of Which At Least Seventy Five Percent (75%) Of The Interest Belongs To Citizens Of The Philippines; (c) Corporations Duly Organized Under The Laws Of The Philippines, And Of Which At Least Seventy Five Percent (75%) Of The Outstanding Capital Stock Belongs To Citizens Of The Philippines; (d) Cooperatives Duly Organized Under The Laws Of The Philippines, And Of Which At Least Seventy Five Percent (75%) Of The Interest Belongs To Citizens Of The Philippines; And (e) Persons/entities Forming Themselves Into A Jv, I.e., A Group Of Two (2) Or More Persons/entities That Intend To Be Jointly And Severally Responsible Or Liable For A Particular Contract: Provided, However, That, In Accordance With Letter Of Instructions No. 630, Filipino Ownership Or Interest Of The Joint Venture Concerned Shall Be At Least Seventy Five Percent (75%): Provided, Further, That Joint Ventures In Which Filipino Ownership Or Interest Is Less Than Seventy Five Percent (75%) May Be Eligible Where The Structures To Be Built Require The Application Of Techniques And/or Technologies Which Are Not Adequately Possessed By A Person/entity Meeting The Seventy Five Percent (75%) Filipino Ownership Requirement: Provided, Finally, That In The Latter Case, Filipino Ownership Or Interest Shall Not Be Less Than Twenty Five Percent (25%). For This Purpose Filipino Ownership Or Interest Shall Be Based On The Contributions Of Each Of The Members Of The Joint Venture As Specified In Their Jva. 5.2. The Procuring Entity May Also Invite Foreign Bidders When Provided For Under Any Treaty Or International Or Executive Agreement As Specified In The Bds. 5.3. Government Corporate Entities May Be Eligible To Participate Only If They Can Establish That They (a) Are Legally And Financially Autonomous, (b) Operate Under Commercial Law, And (c) Are Not Dependent Agencies Of The Gop Or The Procuring Entity. 5.4. (a) Unless Otherwise Provided In The Bds, The Bidder Must Have Completed, Within Ten (10) Years From The Submission Of Bids, A Single Contract That Is Similar To This Project, Equivalent To At Least Fifty Percent (50%) Of The Abc Adjusted To Current Prices Using The National Statistics Office Consumer Price Index. (b) For Foreign-funded Procurement, The Procuring Entity And The Foreign Government/foreign Or International Financing Institution May Agree On Another Track Record Requirement, As Specified In The Bds. For This Purpose, Contracts Similar To The Project Shall Be Those Described In Thebds, And Completed Within The Period Stated In The Invitation To Bid And Itb Clause 12.1(a)(iii). 5.5. The Bidder Must Submit A Computation Of Its Net Financial Contracting Capacity (nfcc) Or A Commitment From A Universal Or Commercial Bank To Extend A Credit Line In Its Favor If Awarded The Contract For This Project (clc). The Nfcc, Computed Using The Following Formula, Must Be At Least Equal To The Abc To Be Bid: Nfcc = [(current Assets Minus Current Liabilities) (k)] Minus The Value Of All Outstanding Or Uncompleted Portions Of The Projects Under Ongoing Contracts, Including Awarded Contracts Yet To Be Started Coinciding With The Contract For This Project. Where: K = 10 For A Contract Duration Of One Year Or Less, 15 For A Contract Duration Of More Than One Year Up To Two Years, And 20 For A Contract Duration Of More Than Two Years. The Clc Must Be At Least Equal To Ten Percent (10%) Of The Abc For This Project. If Issued By A Foreign Bank, It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank. In The Case Of Local Government Units (lgus), The Bidder May Also Submit Clc From Other Banks Certified By The Bangko Sentral Ng Pilipinas (bsp) As Authorized To Issue Such Financial Instrument. 6. Bidder’s Responsibilities 6.1. The Bidder Or Its Duly Authorized Representative Shall Submit A Sworn Statement In The Form Prescribed In Section Ix. Bidding Forms As Required In Itb Clause 12.1(b)(iii). 6.2. The Bidder Is Responsible For The Following: (a) Having Taken Steps To Carefully Examine All Of The Bidding Documents; (b) Having Acknowledged All Conditions, Local Or Otherwise, Affecting The Implementation Of The Contract; (c) Having Made An Estimate Of The Facilities Available And Needed For The Contract To Be Bid, If Any; (d) Having Complied With Its Responsibility To Inquire Or Secure Supplemental/bid Bulletin/s As Provided Under Itb Clause 10.3. (e) Ensuring That It Is Not “blacklisted” Or Barred From Bidding By The Gop Or Any Of Its Agencies, Offices, Corporations, Or Lgus, Including Foreign Government/foreign Or International Financing Institution Whose Blacklisting Rules Have Been Recognized By The Gppb; (f) Ensuring That Each Of The Documents Submitted In Satisfaction Of The Bidding Requirements Is An Authentic Copy Of The Original, Complete, And All Statements And Information Provided Therein Are True And Correct; (g) Authorizing The Head Of The Procuring Entity Or Its Duly Authorized Representative/s To Verify All The Documents Submitted; (h) Ensuring That The Signatory Is The Duly Authorized Representative Of The Bidder, And Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary And/or To Represent The Bidder In The Bidding, With The Duly Notarized Secretary’s Certificate Attesting To Such Fact, If The Bidder Is A Corporation, Partnership, Cooperative, Or Joint Venture; (i) Complying With The Disclosure Provision Under Section 47 Of The Act In Relation To Other Provisions Of Republic Act 3019; And (j) Complying With Existing Labor Laws And Standards, If Applicable. Failure To Observe Any Of The Above Responsibilities Shall Be At The Risk Of The Bidder Concerned. 6.3. The Bidder, By The Act Of Submitting Its Bid, Shall Be Deemed To Have Inspected The Site, Determined The General Characteristics Of The Contract Works And The Conditions For This Project And Examine All Instructions, Forms, Terms, And Project Requirements In The Bidding Documents. 6.4. It Shall Be The Sole Responsibility Of The Prospective Bidder To Determine And To Satisfy Itself By Such Means As It Considers Necessary Or Desirable As To All Matters Pertaining To This Project, Including: (a) The Location And The Nature Of The Contract, Project, Or Work; (b) Climatic Conditions; (c) Transportation Facilities; (c) Nature And Condition Of The Terrain, Geological Conditions At The Site Communication Facilities, Requirements, Location And Availability Of Construction Aggregates And Other Materials, Labor, Water, Electric Power And Access Roads; And (d) Other Factors That May Affect The Cost, Duration And Execution Or Implementation Of The Contract, Project, Or Work. 6.5. The Procuring Entity Shall Not Assume Any Responsibility Regarding Erroneous Interpretations Or Conclusions By The Prospective Or Eligible Bidder Out Of The Data Furnished By The Procuring Entity. 6.6. Before Submitting Their Bids, The Bidders Are Deemed To Have Become Familiar With All Existing Laws, Decrees, Ordinances, Acts And Regulations Of The Philippines Which May Affect The Contract In Any Way. 6.7. The Bidder Shall Bear All Costs Associated With The Preparation And Submission Of His Bid, And The Procuring Entity Will In No Case Be Responsible Or Liable For Those Costs, Regardless Of The Conduct Or Outcome Of The Bidding Process. 6.8. Bidders Should Note That The Procuring Entity Will Only Accept Bids Only From Those That Have Paid The Nonrefundable Fee For The Bidding Documents At The Office Indicated In The Invitation To Bid. 7. Origin Of Goods And Services There Is No Restriction On The Origin Of Goods, Or Contracting Of Works Or Services Other Than Those Prohibited By A Decision Of The United Nations Security Council Taken Under Chapter Vii Of The Charter Of The United Nations. 8. Subcontracts 8.1. Unless Otherwise Specified In The Bds, The Bidder May Subcontract Portions Of The Works To An Extent As May Be Approved By The Procuring Entity And Stated In The Bds. However, Subcontracting Of Any Portion Shall Not Relieve The Bidder From Any Liability Or Obligation That May Arise From The Contract For This Project. 8.2. Subcontractors Must Submit The Documentary Requirements Under Itb Clause 12 And Comply With The Eligibility Criteria Specified In The Bds. In The Event That Any Subcontractor Is Found By The Procuring Entity To Be Ineligible, The Subcontracting Of Such Portion Of The Works Shall Be Disallowed. 8.3. The Bidder May Identify The Subcontractor To Whom A Portion Of The Works Will Be Subcontracted At Any Stage Of The Bidding Process Or During Contract Implementation. If The Bidder Opts To Disclose The Name Of The Subcontractor During Bid Submission, The Bidder Shall Include The Required Documents As Part Of The Technical Component Of Its Bid. B. Contents Of Bidding Documents 9. Pre-bid Conference 9.1. (a) If So Specified In The Bds, A Pre-bid Conference Shall Be Held At The Venue And On The Date Indicated Therein, To Clarify And Address The Bidders’ Questions On The Technical And Financial Components Of This Project. (b) The Pre-bid Conference Shall Be Held At Least Twelve (12) Calendar Days Before The Deadline For The Submission Of And Receipt Of Bids. If The Procuring Entity Determines That, By Reason Of The Method, Nature, Or Complexity Of The Contract To Be Bid, Or When International Participation Will Be More Advantageous To The Gop, A Longer Period For The Preparation Of Bids Is Necessary, The Pre-bid Conference Shall Be Held At Least Thirty (30) Calendar Days Before The Deadline For The Submission And Receipt Of Bids, As Specified In The Bds. 9.2. Bidders Are Encouraged To Attend The Pre-bid Conference To Ensure That They Fully Understand The Procuring Entity’s Requirements. Non-attendance Of The Bidder Will In No Way Prejudice Its Bid; However, The Bidder Is Expected To Know The Changes And/or Amendments To The Bidding Documents As Recorded In The Minutes Of The Pre-bid Conference And The Supplemental/bid Bulletin. 9.3. Any Statement Made At The Pre-bid Conference Shall Not Modify The Terms Of The Bidding Documents Unless Such Statement Is Specifically Identified In Writing As An Amendment Thereto And Issued As A Supplemental/bid Bulletin. 10. Clarification And Amendment Of Bidding Documents 10.1. Bidders Who Have Purchased The Bidding Documents May Request For Clarification(s) On Any Part Of The Bidding Documents Or For An Interpretation. Such A Request Must Be In Writing And Submitted To The Procuring Entity At The Address Indicated In The Bds At Least Ten (10) Calendar Days Before The Deadline Set For The Submission And Receipt Of Bids. 10.2. Supplemental/bid Bulletins May Be Issued Upon The Procuring Entity’s Initiative For Purposes Of Clarifying Or Modifying Any Provision Of The Bidding Documents Not Later Than Seven (7) Calendar Days Before The Deadline For The Submission And Receipt Of Bids. Any Modification To The Bidding Documents Shall Be Identified As An Amendment. 10.3. Any Supplemental/bid Bulletin Issued By The Bac Shall Also Be Posted On The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity Concerned, If Available. Unless, Otherwise Provided In The Bds, It Shall Be The Responsibility Of All Bidders Who Secure The Bidding Documents To Inquire And Secure Supplemental/bid Bulletins That May Be Issued By The Bac. However, Bidders Who Have Submitted Bids Before The Issuance Of The Supplemental/bid Bulletin Must Be Informed And Allowed To Modify Or Withdraw Their Bids In Accordance With Itb Clause 23. C. Preparation Of Bids 11. Language Of Bids The Bid, As Well As All Correspondence And Documents Relating To The Bid Exchanged By The Bidder And The Procuring Entity, Shall Be Written In English. Supporting Documents And Printed Literature Furnished By The Bidder May Be In Another Language Provided They Are Accompanied By An Accurate Translation In English Certified By The Appropriate Embassy Or Consulate In The Philippines, In Which Case The English Translation Shall Govern, For Purposes Of Interpretation Of The Bid. 12. Documents Comprising The Bid: Eligibility And Technical Components 12.1. Unless Otherwise Indicated In The Bds, The First Envelope Shall Contain The Following Eligibility And Technical Documents: (a) Eligibility Documents – Class "a" Documents: (i) Registration Certificate From The Securities And Exchange Commission (sec), Department Of Trade And Industry (dti) For Sole Proprietorship, Or Cooperative Development Authority (cda) For Cooperatives, Or Any Proof Of Such Registration As Stated In The Bds; (ii) Mayor’s Permit Issued By The City Or Municipality Where The Principal Place Of Business Of The Prospective Bidder Is Located; (iii) Statement Of All Its Ongoing And Completed Government And Private Contracts Within Ten (10) Years From The Submission Of Bids, Including Contracts Awarded But Not Yet Started, If Any. The Statement Shall Include, For Each Contract, The Following: (iii.1) Name Of The Contract; (iii.2) Date Of The Contract; (iii.3) Contract Duration; (iii.4) Owner’s Name And Address; (iii.5) Nature Of Work; (iii.6) Contractor’s Role (whether Sole Contractor, Subcontractor, Or Partner In A Jv) And Percentage Of Participation; (iii.7) Total Contract Value At Award; (iii.8) Date Of Completion Or Estimated Completion Time; (iii.9) Total Contract Value At Completion, If Applicable; (iii.10) Percentages Of Planned And Actual Accomplishments, If Applicable; (iii.11) Value Of Outstanding Works, If Applicable; (iii.12) The Statement Shall Be Supported By The Notices Of Award And/or Notices To Proceed Issued By The Owners; And (iii.13) The Statement Shall Be Supported By The Constructors Performance Evaluation System (cpes) Rating Sheets, And/or Certificates Of Completion And Owner’s Acceptance, If Applicable; (iv) Unless Otherwise Provided In The Bds, Valid Philippine Contractors Accreditation Board (pcab) License And Registration For The Type And Cost Of The Contract For This Project; (v) Audited Financial Statements, Showing, Among Others, The Prospective Total And Current Assets And Liabilities, Stamped “received” By The Bir Or Its Duly Accredited And Authorized Institutions, For The Preceding Calendar Year Which Should Not Be Earlier Than Two (2) Years From The Date Of Bid Submission; (vi) Nfcc Computation Or Clc In Accordance With Itb Clause 5.5; And Class "b" Document: (vii) If Applicable, Valid Joint Venture Agreement (jva) Or, In Lieu Thereof, Duly Notarized Statements From All The Potential Joint Venture Partners Stating That They Will Enter Into And Abide By The Provisions Of The Jva In The Instance That The Bid Is Successful Shall Be Included In The Bid. (b) Technical Documents – (i) Bid Security As Prescribed In Itb Clause 18. If The Bidder Opts To Submit The Bid Security In The Form Of: (i.1) A Bank Draft/guarantee Or An Irrevocable Letter Of Credit Issued By A Foreign Bank, It Shall Be Accompanied By A Confirmation From A Universal Or Commercial Bank; Or (i.2) A Surety Bond Accompanied By A Certification Coming From An Authorized Insurance Commission That A Surety Or Insurance Company Is Authorized To Issue Such Instrument; (ii) Project Requirements, Which Shall Include The Following: (ii.1) Organizational Chart For The Contract To Be Bid; (ii.2) List Of Contractor’s Personnel (viz, Project Manager, Project Engineers, Materials Engineers, And Foremen), To Be Assigned To The Contract To Be Bid, With Their Complete Qualification And Experience Data; And (ii.3) List Of Contractor’s Equipment Units, Which Are Owned, Leased, And/or Under Purchase Agreements, Supported By Certification Of Availability Of Equipment From The Equipment Lessor/vendor For The Duration Of The Project; And (iii) Sworn Statement In Accordance With Section 25.2(b)(iv) Of The Irr Of Ra 9184 And Using The Form Prescribed In Section Ix. Bidding Forms. 13. Documents Comprising The Bid: Financial Component 13.1. Unless Otherwise Stated In The Bds, The Financial Component Of The Bid Shall Contain The Following: (a) Financial Bid Form In Accordance With The Form Prescribed In Section Ix. Bidding Forms; And (b) Any Other Document Related To The Financial Component Of The Bid As Stated In The Bds. 13.2. (a) Unless Indicated In The Bds, All Bids That Exceed The Abc Shall Not Be Accepted. (b) Unless Otherwise Indicated In The Bds, For Foreign-funded Procurement, A Ceiling May Be Applied To Bid Prices Provided The Following Conditions Are Met: (i) Bidding Documents Are Obtainable Free Of Charge On A Freely Accessible Website. If Payment Of Bidding Documents Is Required By The Procuring Entity, Payment Could Be Made Upon The Submission Of Bids. (ii) The Procuring Entity Has Procedures In Place To Ensure That The Abc Is Based On Recent Estimates Made By The Engineer Or The Responsible Unit Of The Procuring Entity And That The Estimates Are Based On Adequate Detailed Engineering (in The Case Of Works) And Reflect The Quality, Supervision And Risk And Inflationary Factors, As Well As Prevailing Market Prices, Associated With The Types Of Works Or Goods To Be Procured. (iii) The Procuring Entity Has Trained Cost Estimators On Estimating Prices And Analyzing Bid Variances. In The Case Of Infrastructure Projects, The Procuring Entity Must Also Have Trained Quantity Surveyors. (iv) The Procuring Entity Has Established A System To Monitor And Report Bid Prices Relative To Abc And Engineer’s/procuring Entity’s Estimate. (v) The Procuring Entity Has Established A Monitoring And Evaluation System For Contract Implementation To Provide A Feedback On Actual Total Costs Of Goods And Works. 14. Alternative Bids 14.1. Alternative Bids Shall Be Rejected. For This Purpose, Alternative Bid Is An Offer Made By A Bidder In Addition Or As A Substitute To Its Original Bid Which May Be Included As Part Of Its Original Bid Or Submitted Separately Therewith For Purposes Of Bidding. A Bid With Options Is Considered An Alternative Bid Regardless Of Whether Said Bid Proposal Is Contained In A Single Envelope Or Submitted In Two (2) Or More Separate Bid Envelopes. 14.2. Bidders Shall Submit Offers That Comply With The Requirements Of The Bidding Documents, Including The Basic Technical Design As Indicated In The Drawings And Specifications. Unless There Is A Value Engineering Clause In The Bds, Alternative Bids Shall Not Be Accepted. 14.3. Each Bidder Shall Submit Only One Bid, Either Individually Or As A Partner In A Jv. A Bidder Who Submits Or Participates In More Than One Bid (other Than As A Subcontractor If A Subcontractor Is Permitted To Participate In More Than One Bid) Will Cause All The Proposals With The Bidder’s Participation To Be Disqualified. This Shall Be Without Prejudice To Any Applicable Criminal, Civil And Administrative Penalties That May Be Imposed Upon The Persons And Entities Concerned. 15. Bid Prices 15.1. The Contract Shall Be For The Whole Works, As Described In Itb Clause 1.1, Based On The Priced Bill Of Quantities Submitted By The Bidder. 15.2. The Bidder Shall Fill In Rates And Prices For All Items Of The Works Described In The Bill Of Quantities. Bids Not Addressing Or Providing All Of The Required Items In The Bidding Documents Including, Where Applicable, Bill Of Quantities, Shall Be Considered Non-responsive And, Thus, Automatically Disqualified. In This Regard, Where A Required Item Is Provided, But No Price Is Indicated, The Same Shall Be Considered As Non-responsive, But Specifying A "0" (zero) For The Said Item Would Mean That It Is Being Offered For Free To The Government. 15.3. All Duties, Taxes, And Other Levies Payable By The Contractor Under The Contract, Or For Any Other Cause, Prior To The Deadline For Submission Of Bids, Shall Be Included In The Rates, Prices, And Total Bid Price Submitted By The Bidder. 15.4. All Bid Prices For The Given Scope Of Work In The Contract As Awarded Shall Be Considered As Fixed Prices, And Therefore Not Subject To Price Escalation During Contract Implementation, Except Under Extraordinary Circumstances As Specified In Gcc Clause 48. Price Escalation May Be Allowed In Extraordinary Circumstances As May Be Determined By The National Economic And Development Authority In Accordance With The Civil Code Of The Philippines, And Upon The Recommendation Of The Procuring Entity. Furthermore, In Cases Where The Cost Of The Awarded Contract Is Affected By Any Applicable New Laws, Ordinances, Regulations, Or Other Acts Of The Gop, Promulgated After The Date Of Bid Opening, A Contract Price Adjustment Shall Be Made Or Appropriate Relief Shall Be Applied On A No Loss-no Gain Basis. 16. Bid Currencies 16.1. All Bid Prices Shall Be Quoted In Philippine Pesos Unless Otherwise Provided In The Bds. However, For Purposes Of Bid Evaluation, Bids Denominated In Foreign Currencies Shall Be Converted To Philippine Currency Based On The Exchange Rate Prevailing On The Day Of The Bid Opening. 16.2. If So Allowed In Accordance With Itb Clause 16.1, The Procuring Entity For Purposes Of Bid Evaluation And Comparing The Bid Prices Will Convert The Amounts In Various Currencies In Which The Bid Price Is Expressed To Philippine Pesos At The Exchange Rate As Published In The Bsp Reference Rate Bulletin On The Day Of The Bid Opening. 16.3. Unless Otherwise Specified In The Bds, Payment Of The Contract Price Shall Be Made In Philippine Pesos. 17. Bid Validity 17.1. Bids Shall Remain Valid For The Period Specified In The Bds Which Shall Not Exceed One Hundred Twenty (120) Calendar Days From The Date Of The Opening Of Bids. 17.2. In Exceptional Circumstances, Prior To The Expiration Of The Bid Validity Period, The Procuring Entity May Request Bidders To Extend The Period Of Validity Of Their Bids. The Request And The Responses Shall Be Made In Writing. The Bid Security Described In Itb Clause 18 Should Also Be Extended Corresponding To The Extension Of The Bid Validity Period At The Least. A Bidder May Refuse The Request Without Forfeiting Its Bid Security, But His Bid Shall No Longer Be Considered For Further Evaluation And Award. A Bidder Granting The Request Shall Not Be Required Or Permitted To Modify Its Bid. 18. Bid Security 18.1. The Bid Security In The Amount Stated In The Bds Shall Be Equal To The Percentage Of The Abc In Accordance With The Following Schedule: Form Of Bid Security Amount Of Bid Security (equal To Percentage Of The Abc) (a) Cash Or Cashier’s/manager’s Check Issued By A Universal Or Commercial Bank. Two Percent (2%) (b) Bank Draft/guarantee Or Irrevocable Letter Of Credit Issued By A Universal Or Commercial Bank: Provided, However, That It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank. (c) Surety Bond Callable Upon Demand Issued By A Surety Or Insurance Company Duly Certified By The Insurance Commission As Authorized To Issue Such Security; And/or Five Percent (5%) (d) Any Combination Of The Foregoing. Proportionate To Share Of Form With Respect To Total Amount Of Security For Biddings Conducted By Local Government Units, The Bidder May Also Submit Bid Securities In The Form Of Cashier’s/manager’s Check, Bank Draft/guarantee, Or Irrevocable Letter Of Credit From Other Banks Certified By The Bsp As Authorized To Issue Such Financial Statement. 18.2. The Bid Security Should Be Valid For The Period Specified In The Bds. Any Bid Not Accompanied By An Acceptable Bid Security Shall Be Rejected By The Procuring Entity As Non-responsive. 18.3. No Bid Securities Shall Be Returned To Bidders After The Opening Of Bids And Before Contract Signing, Except To Those That Failed Or Declared As Post-disqualified, Upon Submission Of A Written Waiver Of Their Right To File A Motion For Reconsideration And/or Protest. Without Prejudice On Its Forfeiture, Bid Securities Shall Be Returned Only After The Bidder With The Lowest Calculated Responsive Bid Has Signed The Contract And Furnished The Performance Security, But In No Case Later Than The Expiration Of The Bid Security Validity Period Indicated In Itb Clause 18.2. 18.4. Upon Signing And Execution Of The Contract, Pursuant To Itb Clause 31, And The Posting Of The Performance Security, Pursuant To Itb Clause 32, The Successful Bidder’s Bid Security Will Be Discharged, But In No Case Later Than The Bid Security Validity Period As Indicated In Itb Clause 18.2. 18.5. The Bid Security May Be Forfeited: (a) If A Bidder: (i) Withdraws Its Bid During The Period Of Bid Validity Specified In Itb Clause 17; (ii) Does Not Accept The Correction Of Errors Pursuant To Itb Clause 27.3(b); (iii) Fails To Submit The Requirements Within The Prescribed Period, Or A Finding Against Their Veracity, As Stated In Itb Clause 28.2; (iv) Submission Of Eligibility Requirements Containing False Information Or Falsified Documents; (v) Submission Of Bids That Contain False Information Or Falsified Documents, Or The Concealment Of Such Information In The Bids In Order To Influence The Outcome Of Eligibility Screening Or Any Other Stage Of The Public Bidding; (vi) Allowing The Use Of One’s Name, Or Using The Name Of Another For Purposes Of Public Bidding; (vii) Withdrawal Of A Bid, Or Refusal To Accept An Award, Or Enter Into Contract With The Government Without Justifiable Cause, After The Bidder Had Been Adjudged As Having Submitted The Lowest Calculated And Responsive Bid; (viii) Refusal Or Failure To Post The Required Performance Security Within The Prescribed Time; (ix) Refusal To Clarify Or Validate In Writing Its Bid During Post-qualification Within A Period Of Seven (7) Calendar Days From Receipt Of The Request For Clarification; (x) Any Documented Attempt By A Bidder To Unduly Influence The Outcome Of The Bidding In His Favor; (xi) Failure Of The Potential Joint Venture Partners To Enter Into The Joint Venture After The Bid Is Declared Successful; Or (xii) All Other Acts That Tend To Defeat The Purpose Of The Competitive Bidding, Such As Habitually Withdrawing From Bidding, Submitting Late Bids Or Patently Insufficient Bid, For At Least Three (3) Times Within A Year, Except For Valid Reasons. (b) If The Successful Bidder: (i) Fails To Sign The Contract In Accordance With Itb Clause 31; (ii) Fails To Furnish Performance Security In Accordance With Itb Clause 32. 19. Format And Signing Of Bids 19.1. Bidders Shall Submit Their Bids Through Their Duly Authorized Representative Using The Appropriate Forms Provided In Section Ix. Bidding Forms On Or Before The Deadline Specified In The Itb Clause 21 In Two (2) Separate Sealed Bid Envelopes, And Which Shall Be Submitted Simultaneously. The First Shall Contain The Technical Component Of The Bid, Including The Eligibility Requirements Under Itb Clause 12.1, And The Second Shall Contain The Financial Component Of The Bid. 19.2. Forms As Mentioned In Itb Clause 19.1 Must Be Completed Without Any Alterations To Their Format, And No Substitute Form Shall Be Accepted. All Blank Spaces Shall Be Filled In With The Information Requested. 19.3. The Bidder Shall Prepare An Original Of The First And Second Envelopes As Described In Itb Clauses 12 And 13. In Addition, The Bidder Shall Submit Copies Of The First And Second Envelopes. In The Event Of Any Discrepancy Between The Original And The Copies, The Original Shall Prevail. 19.4. The Bid, Except For Unamended Printed Literature, Shall Be Signed, And Each And Every Page Thereof Shall Be Initialed, By The Duly Authorized Representative/s Of The Bidder. 19.5. Any Interlineations, Erasures, Or Overwriting Shall Be Valid Only If They Are Signed Or Initialed By The Duly Authorized Representative/s Of The Bidder. 20. Sealing And Marking Of Bids 20.1. Bidders Shall Enclose Their Original Eligibility And Technical Documents Described In Itb Clause 12, In One Sealed Envelope Marked “original - Technical Component”, And The Original Of Their Financial Component In Another Sealed Envelope Marked “original - Financial Component”, Sealing Them All In An Outer Envelope Marked “original Bid”. 20.2. Each Copy Of The First And Second Envelopes Shall Be Similarly Sealed Duly Marking The Inner Envelopes As “copy No. ___ - Technical Component” And “copy No. ___ – Financial Component” And The Outer Envelope As “copy No. ___”, Respectively. These Envelopes Containing The Original And The Copies Shall Then Be Enclosed In One Single Envelope. 20.3. The Original And The Number Of Copies Of The Bid As Indicated In The Bds Shall Be Typed Or Written In Indelible Ink And Shall Be Signed By The Bidder Or Its Duly Authorized Representative/s. 20.4. All Envelopes Shall: (a) Contain The Name Of The Contract To Be Bid In Capital Letters; (b) Bear The Name And Address Of The Bidder In Capital Letters; (c) Be Addressed To The Procuring Entity’s Bac Identified In Itb Clause 10.1; (d) Bear The Specific Identification Of This Bidding Process Indicated In The Invitation To Bid; And (e) Bear A Warning “do Not Open Before…” The Date And Time For The Opening Of Bids, In Accordance With Itb Clause 21. 20.5. If Bids Are Not Sealed And Marked As Required, The Procuring Entity Will Assume No Responsibility For The Misplacement Or Premature Opening Of The Bid. D. Submission And Opening Of Bids 21. Deadline For Submission Of Bids Bids Must Be Received By The Procuring Entity’s Bac At The Address And On Or Before The Date And Time Indicated In The Bds. 22. Late Bids Any Bid Submitted After The Deadline For Submission And Receipt Of Bids Prescribed By The Procuring Entity, Pursuant To Itb Clause 21, Shall Be Declared “late” And Shall Not Be Accepted By The Procuring Entity. 23. Modification And Withdrawal Of Bids 23.1. The Bidder May Modify Its Bid After It Has Been Submitted; Provided That The Modification Is Received By The Procuring Entity Prior To The Deadline Prescribed For Submission And Receipt Of Bids. The Bidder Shall Not Be Allowed To Retrieve Its Original Bid, But Shall Be Allowed To Submit Another Bid Equally Sealed, Properly Identified, Linked To Its Original Bid Marked As “technical Modification” Or “financial Modification” And Stamped “received” By The Bac. Bid Modifications Received After The Applicable Deadline Shall Not Be Considered And Shall Be Returned To The Bidder Unopened. 23.2. A Bidder May, Through A Letter Of Withdrawal, Withdraw Its Bid After It Has Been Submitted, For Valid And Justifiable Reason; Provided That The Letter Of Withdrawal Is Received By The Procuring Entity Prior To The Deadline Prescribed For Submission And Receipt Of Bids. 23.3. Bids Requested To Be Withdrawn In Accordance With Itb Clause 23.1 Shall Be Returned Unopened To The Bidders. A Bidder May Also Express Its Intention Not To Participate In The Bidding Through A Letter Which Should Reach And Be Stamped By The Bac Before The Deadline For Submission And Receipt Of Bids. A Bidder That Withdraws Its Bid Shall Not Be Permitted To Submit Another Bid, Directly Or Indirectly, For The Same Contract. 23.4. No Bid May Be Modified After The Deadline For Submission Of Bids. No Bid May Be Withdrawn In The Interval Between The Deadline For Submission Of Bids And The Expiration Of The Period Of Bid Validity Specified By The Bidder On The Financial Bid Form. Withdrawal Of A Bid During This Interval Shall Result In The Forfeiture Of The Bidder’s Bid Security, Pursuant To Itb Clause 18.5, And The Imposition Of Administrative, Civil, And Criminal Sanctions As Prescribed By Ra 9184 And Its Irr. 24. Opening And Preliminary Examination Of Bids 24.1. The Bac Shall Open The First Bid Envelopes Of Bidders In Public As Specified In The Bds To Determine Each Bidder’s Compliance With The Documents Prescribed In Itb Clause 12. For This Purpose, The Bac Shall Check The Submitted Documents Of Each Bidder Against A Checklist Of Required Documents To Ascertain If They Are All Present, Using A Non-discretionary “pass/fail” Criterion. If A Bidder Submits The Required Document, It Shall Be Rated “passed” For That Particular Requirement. In This Regard, Bids That Fail To Include Any Requirement Or Are Incomplete Or Patently Insufficient Shall Be Considered As “failed”. Otherwise, The Bac Shall Rate The Said First Bid Envelope As “passed”. 24.2. Unless Otherwise Specified In The Bds, Immediately After Determining Compliance With The Requirements In The First Envelope, The Bac Shall Forthwith Open The Second Bid Envelope Of Each Remaining Eligible Bidder Whose First Bid Envelope Was Rated “passed”. The Second Envelope Of Each Complying Bidder Shall Be Opened Within The Same Day. In Case One Or More Of The Requirements In The Second Envelope Of A Particular Bid Is Missing, Incomplete Or Patently Insufficient, And/or If The Submitted Total Bid Price Exceeds The Abc Unless Otherwise Provided In Itb Clause 13.1(b), The Bac Shall Rate The Bid Concerned As “failed”. Only Bids That Are Determined To Contain All The Bid Requirements For Both Components Shall Be Rated “passed” And Shall Immediately Be Considered For Evaluation And Comparison. 24.3. Letters Of Withdrawal Shall Be Read Out And Recorded During Bid Opening, And The Envelope Containing The Corresponding Withdrawn Bid Shall Be Returned To The Bidder Unopened. If The Withdrawing Bidder’s Representative Is In Attendance, The Original Bid And All Copies Thereof Shall Be Returned To The Representative During The Bid Opening. If The Representative Is Not In Attendance, The Bid Shall Be Returned Unopened By Registered Mail. The Bidder May Withdraw Its Bid Prior To The Deadline For The Submission And Receipt Of Bids, Provided That The Corresponding Letter Of Withdrawal Contains A Valid Authorization Requesting For Such Withdrawal, Subject To Appropriate Administrative Sanctions. 24.4. If A Bidder Has Previously Secured A Certification From The Procuring Entity To The Effect That It Has Previously Submitted The Above-enumerated Class “a” Documents, The Said Certification May Be Submitted In Lieu Of The Requirements Enumerated In Itb Clause 12.1(a), Items (i) To (vi). 24.5. In The Case Of An Eligible Foreign Bidder As Described In Itb Clause 5, The Class “a” Documents Enumerated In Itb Clause 12.1(a) May Be Substituted With The Appropriate Equivalent Documents, If Any, Issued By The Country Of The Foreign Bidder Concerned. 24.6. Each Partner Of A Joint Venture Agreement Shall Likewise Submit The Documents Required In Itb Clauses 12.1(a)(i) And 12.1(a)(ii). Submission Of Documents Required Under Itb Clauses 12.1(a)(iii) To 12.1(a)(vi) By Any Of The Joint Venture Partners Constitutes Compliance. 24.7. A Bidder Determined As “failed” Has Three (3) Calendar Days Upon Written Notice Or, If Present At The Time Of Bid Opening, Upon Verbal Notification Within Which To File A Request For Reconsideration With The Bac: Provided, However, That The Request For Reconsideration Shall Not Be Granted If It Is Established That The Finding Of Failure Is Due To The Fault Of The Bidder Concerned: Provided, Further, That The Bac Shall Decide On The Request For Reconsideration Within Seven (7) Calendar Days From Receipt Thereof. If A Failed Bidder Signifies His Intent To File A Request For Reconsideration, The Bac Shall Keep The Bid Envelopes Of The Said Failed Bidder Unopened And/or Duly Sealed Until Such Time That The Request For Reconsideration Or Protest Has Been Resolved. E. Evaluation And Comparison Of Bids 25. Process To Be Confidential 25.1. Members Of The Bac, Including Its Staff And Personnel, As Well As Its Secretariat And Twg, Are Prohibited From Making Or Accepting Any Kind Of Communication With Any Bidder Regarding The Evaluation Of Their Bids Until The Issuance Of The Notice Of Award, Unless N The Case Of Itb Clause 26. 25.2. Any Effort By A Bidder To Influence The Procuring Entity In The Procuring Entity’s Decision In Respect Of Bid Evaluation, Bid Comparison Or Contract Award Will Result In The Rejection Of The Bidder’s Bid. 26. Clarification Of Bids To Assist In The Evaluation, Comparison And Post-qualification Of The Bids, The Procuring Entity May Ask In Writing Any Bidder For A Clarification Of Its Bid. All Responses To Requests For Clarification Shall Be In Writing. Any Clarification Submitted By A Bidder In Respect To Its Bid And That Is Not In Response To A Request By The Procuring Entity Shall Not Be Considered 27. Detailed Evaluation And Comparison Of Bids 27.1. The Procuring Entity Will Undertake The Detailed Evaluation And Comparison Of Bids Which Have Passed The Opening And Preliminary Examination Of Bids, Pursuant To Itb Clause 24, In Order To Determine The Lowest Calculated Bid. 27.2. In Evaluating The Bids To Get The Lowest Calculated Bid, The Procuring Entity Shall Undertake The Following: (a) The Detailed Evaluation Of The Financial Component Of The Bids, To Establish The Correct Calculated Prices Of The Bids; And (b) The Ranking Of The Total Bid Prices As So Calculated From The Lowest To Highest. The Bid With The Lowest Price Shall Be Identified As The Lowest Calculated Bid. 27.3. The Procuring Entity's Bac Shall Immediately Conduct A Detailed Evaluation Of All Bids Rated “passed,” Using Non-discretionary “pass/fail” Criterion. The Bac Shall Consider The Following In The Evaluation Of Bids: (a) Completeness Of The Bid. Unless The Itb Specifically Allows Partial Bids, Bids Not Addressing Or Providing All Of The Required Items In The Schedule Of Requirements Including, Where Applicable, Bill Of Quantities, Shall Be Considered Non-responsive And, Thus, Automatically Disqualified. In This Regard, Where A Required Item Is Provided, But No Price Is Indicated, The Same Shall Be Considered As Non-responsive, But Specifying A "0" (zero) For The Said Item Would Mean That It Is Being Offered For Free To The Procuring Entity; And (b) Arithmetical Corrections. Consider Computational Errors And Omissions To Enable Proper Comparison Of All Eligible Bids. It May Also Consider Bid Modifications If Expressly Allowed In The Bds. Any Adjustment Shall Be Calculated In Monetary Terms To Determine The Calculated Prices. 27.4. Based On The Detailed Evaluation Of Bids, Those That Comply With The Above-mentioned Requirements Shall Be Ranked In The Ascending Order Of Their Total Calculated Bid Prices, As Evaluated And Corrected For Computational Errors, Discounts And Other Modifications, To Identify The Lowest Calculated Bid. Total Calculated Bid Prices, As Evaluated And Corrected For Computational Errors, Discounts And Other Modifications, Which Exceed The Abc Shall Not Be Considered, Unless Otherwise Indicated In The Bds. 27.5. The Procuring Entity’s Evaluation Of Bids Shall Only Be Based On The Bid Price Quoted In The Financial Bid Form 27.6. Bids Shall Be Evaluated On An Equal Footing To Ensure Fair Competition. For This Purpose, All Bidders Shall Be Required To Include In Their Bids The Cost Of All Taxes, Such As, But Not Limited To, Value Added Tax (vat), Income Tax, Local Taxes, And Other Fiscal Levies And Duties Which Shall Be Itemized In The Bid Form And Reflected In The Detailed Estimates. Such Bids, Including Said Taxes, Shall Be The Basis For Bid Evaluation And Comparison. 28. Post Qualification 28.1. The Procuring Entity Shall Determine To Its Satisfaction Whether The Bidder That Is Evaluated As Having Submitted The Lowest Calculated Bid (lcb) Complies With And Is Responsive To All The Requirements And Conditions Specified In Itb Clauses 5, 12, And 13. 28.2. Within A Non-extendible Period Of Three (3) Calendar Days From Receipt By The Bidder Of The Notice From The Bac That It Submitted The Lcb, The Bidder Shall Submit The Following Documentary Requirements: (a) Tax Clearance Per Executive Order 398, Series Of 2005; (b) Latest Income And Business Tax Returns In The Form Specified In The Bds; (c) Certificate Of Philgeps Registration; And (d) Other Appropriate Licenses And Permits Required By Law And Stated In The Bds. Failure Of The Bidder Declared As Lcb To Duly Submit The Requirements Under This Clause Or A Finding Against The Veracity Of Such, Shall Be Ground For Forfeiture Of The Bid Security And Disqualification Of The Bidder For Award. 28.3. The Determination Shall Be Based Upon An Examination Of The Documentary Evidence Of The Bidder’s Qualifications Submitted Pursuant To Itb Clauses 12 And 13, As Well As Other Information As The Procuring Entity Deems Necessary And Appropriate, Using A Non-discretionary “pass/fail” Criterion. 28.4. If The Bac Determines That The Bidder With The Lowest Calculated Bid Passes All The Criteria For Post-qualification, It Shall Declare The Said Bid As The Lowest Calculated Responsive Bid, And Recommend To The Head Of The Procuring Entity The Award Of Contract To The Said Bidder At Its Submitted Price Or Its Calculated Bid Price, Whichever Is Lower, Subject To Itb Clause 30.3. 28.5. A Negative Determination Shall Result In Rejection Of The Bidder’s Bid, In Which Event The Procuring Entity Shall Proceed To The Next Lowest Calculated Bid To Make A Similar Determination Of That Bidder’s Capabilities To Perform Satisfactorily. If The Second Bidder, However, Fails The Post Qualification, The Procedure For Post Qualification Shall Be Repeated For The Bidder With The Next Lowest Calculated Bid, And So On Until The Lowest Calculated And Responsive Bid Is Determined For Contract Award. 28.6. Within A Period Not Exceeding Seven (7) Calendar Days From The Date Of Receipt Of The Recommendation Of The Bac, The Head Of The Procuring Entity Shall Approve Or Disapprove The Said Recommendation. In The Case Of Government Owned And Government-owned And/or -controlled Corporations (goccs) And Government Financial Institutions (gfis), The Period Provided Herein Shall Be Fifteen (15) Calendar Days. 29. Reservation Clause 29.1. Notwithstanding The Eligibility Or Post-qualification Of A Bidder, The Procuring Entity Concerned Reserves The Right To Review Its Qualifications At Any Stage Of The Procurement Process If It Has Reasonable Grounds To Believe That A Misrepresentation Has Been Made By The Said Bidder, Or That There Has Been A Change In The Bidder’s Capability To Undertake The Project From The Time It Submitted Its Eligibility Requirements. Should Such Review Uncover Any Misrepresentation Made In The Eligibility And Bidding Requirements, Statements Or Documents, Or Any Changes In The Situation Of The Bidder Which Will Affect Its Capability To Undertake The Project So That It Fails The Preset Eligibility Or Bid Evaluation Criteria, The Procuring Entity Shall Consider The Said Bidder As Ineligible And Shall Disqualify It From Submitting A Bid Or From Obtaining An Award Or Contract. 29.2. Based On The Following Grounds, The Procuring Entity Reserves The Right To Reject Any And All Bids, Declare A Failure Of Bidding At Any Time Prior To The Contract Award, Or Not To Award The Contract, Without Thereby Incurring Any Liability, And Make No Assurance That A Contract Shall Be Entered Into As A Result Of The Bidding: (a) If There Is Prima Facie Evidence Of Collusion Between Appropriate Public Officers Or Employees Of The Procuring Entity, Or Between The Bac And Any Of The Bidders, Or If The Collusion Is Between Or Among The Bidders Themselves, Or Between A Bidder And A Third Party, Including Any Act Which Restricts, Suppresses Or Nullifies Or Tends To Restrict, Suppress Or Nullify Competition; (b) If The Procuring Entity’s Bac Is Found To Have Failed In Following The Prescribed Bidding Procedures; Or (c) For Any Justifiable And Reasonable Ground Where The Award Of The Contract Will Not Redound To The Benefit Of The Government As Follows: (i) If The Physical And Economic Conditions Have Significantly Changed So As To Render The Project No Longer Economically, Financially Or Technically Feasible As Determined By The Head Of The Procuring Entity; (ii) If The Project Is No Longer Necessary As Determined By The Head Of The Procuring Entity; And (iii) If The Source Of Funds For The Project Has Been Withheld Or Reduced Through No Fault Of The Procuring Entity. 29.3. In Addition, The Procuring Entity May Likewise Declare A Failure Of Bidding When: (a) No Bids Are Received; (b) All Prospective Bidders Are Declared Ineligible; (c) All Bids Fail To Comply With All The Bid Requirements Or Fail Post-qualification; Or (d) The Bidder With The Lowest Calculated Responsive Bid Refuses, Without Justifiable Cause To Accept The Award Of Contract, And No Award Is Made. F. Award Of Contract 30. Contract Award 30.1. Subject To Itb Clause 28, The Procuring Entity Shall Award The Contract To The Bidder Whose Bid Has Been Determined To Be The Lowest Calculated And Responsive Bid (lcrb). 30.2. Prior To The Expiration Of The Period Of Bid Validity, The Procuring Entity Shall Notify The Successful Bidder In Writing That Its Bid Has Been Accepted, Through A Notice Of Award Received Personally Or Sent By Registered Mail Or Electronically, Receipt Of Which Must Be Confirmed In Writing Within Two (2) Days By The Lcrb And Submitted Personally Or Sent By Registered Mail Or Electronically To The Procuring Entity. 30.3. Notwithstanding The Issuance Of The Notice Of Award, Award Of Contract Shall Be Subject To The Following Conditions: (a) Submission Of The Following Documents Within The Prescribed Period From Receipt By The Bidder Of The Notice That It Has The Lowest Calculated And Responsive Bid: (i) Valid Jva, If Applicable, Within Ten (10) Calendar Days; (ii) Valid Pcab License And Registration For The Type And Cost Of The Contract To Be Bid For Foreign Bidders, Within Thirty (30) Calendar Days, If Allowed Under A Treaty Or International Or Executive Agreement Mentioned In Itb Clause 12.1(a)(iv); (b) Posting Of The Performance Security In Accordance With Itb Clause 32; (c) Signing Of The Contract As Provided In Itb Clause 31; And (d) Approval By Higher Authority, If Required. 31. Signing Of The Contract 31.1. At The Same Time As The Procuring Entity Notifies The Successful Bidder That Its Bid Has Been Accepted, The Procuring Entity Shall Send The Contract Form To The Bidder, Which Contract Has Been Provided In The Bidding Documents, Incorporating Therein All Agreements Between The Parties. 31.2. Within Ten (10) Calendar Days From Receipt Of The Notice Of Award, The Successful Bidder Shall Post The Required Performance Security, Sign And Date The Contract And Return It To The Procuring Entity. 31.3. The Procuring Entity Shall Enter Into Contract With The Successful Bidder Within The Same Ten (10) Calendar Day Period Provided That All The Documentary Requirements Are Complied With. 31.4. The Following Documents Shall Form Part Of The Contract: (a) Contract Agreement; (b) Bidding Documents; (c) Winning Bidder’s Bid, Including The Technical And Financial Proposals, And All Other Documents/statements Submitted; (d) Performance Security; (e) Credit Line In Accordance With Itb Clause 5.5, If Applicable; (f) Notice Of Award Of Contract; And (g) Other Contract Documents That May Be Required By Existing Laws And/or Specified In The Bds. 32. Performance Security 32.1. To Guarantee The Faithful Performance By The Winning Bidder Of Its Obligations Under The Contract, It Shall Post A Performance Security Within A Maximum Period Of Ten (10) Calendar Days From The Receipt Of The Notice Of Award From The Procuring Entity And In No Case Later Than The Signing Of The Contract. 32.2. The Performance Security Shall Be Denominated In Philippine Pesos And Posted In Favor Of The Procuring Entity In An Amount Equal To The Percentage Of The Total Contract Price As Stated In The Bds In Accordance With The Following Schedule: 33. 33.1. Form Of Performance Security Amount Of Performance Security (equal To Percentage Of The Total Contract Price) (a) Cash Or Cashier’s/manager’s Check Issued By A Universal Or Commercial Bank. Ten Percent (10%) (b) Bank Draft/guarantee Or Irrevocable Letter Of Credit Issued By A Universal Or Commercial Bank: Provided, However, That It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank. (c) Surety Bond Callable Upon Demand Issued By A Surety Or Insurance Company Duly Certified By The Insurance Commission As Authorized To Issue Such Security; And/or Thirty Percent (30%) (d) Any Combination Of The Foregoing. Proportionate To Share Of Form With Respect To Total Amount Of Security 33.2. Failure Of The Successful Bidder To Comply With The Above-mentioned Requirement Shall Constitute Sufficient Ground For The Annulment Of The Award And Forfeiture Of The Bid Security, In Which Event The Procuring Entity Shall Initiate And Complete The Post Qualification Of The Second Lowest Calculated Bid. The Procedure Shall Be Repeated Until The Lowest Calculated And Responsive Bid Is Identified And Selected For Contract Award. However If No Bidder Passed Post-qualification, The Bac Shall Declare The Bidding A Failure And Conduct A Re-bidding With Re-advertisement. 34. Notice To Proceed 34.1. Within Three (3) Calendar Days From The Date Of Approval Of The Contract By The Appropriate Government Approving Authority, The Procuring Entity Shall Issue Its Notice To Proceed To The Bidder. 34.2. The Contract Effectivity Date Shall Be Provided In The Notice To Proceed By The Procuring Entity, Which Date Shall Not Be Later Than Seven (7) Calendar Days From The Issuance Of The Notice To Proceed. Section Iii. Bid Data Sheet Bid Data Sheet Itb Clause 1.1 The Procuring Entity Is Lgu- Mapanas, Northern Samar. The Name Of The Contract Is Rehabilitation / Improvement Of Longcop St. Barangay E. Laodenio, Mapanas N. Samar The Identification Number Of The Contract Is Pr No-2024-11-104__ 2 The Funding Source Is: 20% Economic Development Fund (edf) For Fy 2025. The Name Of The Project Is: Rehabilitation / Improvement Of Longcop St. Barangay E. Laodenio, Mapanas N. Samar 3.1 No Further Instructions. 5.1 No Further Instructions. 5.2 Bidding Is Restricted To Eligible Bidders As Defined In Itb Clause 5.1. 5.4 For This Purpose, Similar Contracts Shall Refer To Bidder’s Annual Turnover From All Works Average Over The Last Three Years Shall Be Equal To 50% Of The Estimated Cost Of The Contract Being Procured. The Bidder Must Have Completed, Within The Past Ten (10) Years From The Submission Of Bids, A Single Contract That Is Similar To This Project, Equivalent To At Least Eighty Percent (80%) Of The Abc. 8.1 “subcontracting Is Not Allowed.” 8.2 “not Applicable”. 9.1 The Procuring Entity Will Hold A Pre-bid Conference For This Project On December 05, 2024 At 10:00 A.m. At Executive Conference 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar. 10.1 The Procuring Entity’s Address Is: The Municipality Of Mapanas, Province Of Northern Samar Ma. Teresa L. Minguez Lgu-bac Chairperson Tel. No. 09778033758 10.3 No Further Instructions. 12.1 Not Applicable 12.1(a)(i) “no Other Acceptable Proof Of Registration Is Recognized.” 12.1(a)(iv) No Further Instructions. 13.1 “no Additional Requirements” 13.1(b) The Abc Is Php 1,492,688.53 Any Bid With A Financial Component Exceeding This Amount Shall Not Be Accepted. 14.2 “no Further Instructions.” 15.4 No Further Instruction. 16.1 The Bid Prices Shall Be Quoted In Philippine Pesos. 17.1 Bids Will Be Valid Until 120 Calendar Days After The Bid Submission Deadline Date As Prescribed By The Procuring Entity) 18.1 The Bid Security Shall Be In The Following Amount: 1. The Amount Of 29, 853. 77 If Bid Security Is In Cash, Cashier’s/manager’s Check, Bank Draft/guarantee Or Irrevocable Letter Of Credit; 2. The Amount Of 74,634.43 If Bid Security Is In Su Rety Bond; Or 3. Any Combination Of The Foregoing Proportionate To The Share Of Form With Respect To Total Amount Of Security. 18.2 The Bid Security Shall Be Valid Twenty Eight Days Beyond The Validity Period Of The Bid. 20.3 Each Bidder Shall Submit One Original And One Copy Of The First And Second Components Of Its Bid. 21 The Address For Submission Of Bids Is Ma. Teresa L. Minguez Lgu-bac Chairperson Bac Office @ Mpdo, 1st Floor, New Municipal Bldg. Municipality Of Mapanas, Northern Samar The Deadline For Submission Of Bids Is 9:00 A.m. On December 16 , 2024. 22 The Place Of Bid Opening Is Executive Conference Room, 2nd Floor, New Municipal Bldg. Municipality Of Mapanas, Northern Samar. The Date And Time Of Bid Opening Is December 16, 2024 At Exactly 10:00 A.m. 24.2 No Further Instructions. 27.3(b) Bid Modification Is Not Allowed. 27.4 No Further Instructions. 28.2(b) Bidders Have Option To Submit Manually Filed Tax Returns Or Tax Returns Filed Through The Electronic Filing And Payments System (efps). Note: The Latest Income And Business Tax Returns Are Those Within The Last Six Months Preceding The Date Of Bid Submission. 28.2(d) List Licenses And Permits Relevant To The Project And The Corresponding Law Requiring It. 1. Taxpayer’s Identification Number 2. Vat Registration 3. Philippine Contractors Accreditation Board (pcab) License The Requirements Are Applicable Only In A Case Where The Lowest Calculated Bid (lcb) Is Submitted By A Domestic Bidder, And If The Lowest Calculated Bid (lcb) Is Submitted By A Foreign Bidder, This Requirements Are Not Applicable 31.4(g) List Additional Contract Documents Relevant To The Project That May Be Required By Existing Laws And/or The Procuring Entity, Such As Construction Schedule And S-curve, Manpower Schedule, Construction Methods, Equipment Utilization Schedule, Construction Safety And Health Program Approved By The Department Of Labor And Employment, And Pert/cpm. 32.2 The Performance Security Shall Be In The Following Amount: 1. The Amount Of 10% Of Contract If Performance Security Is In Cash, Cashier’s/manager’s Check, Bank Draft/guarantee Or Irrevocable Letter Of Credit; 2. The Amount Of 30% Of Contract If Performance Security Is In Surety Bond; Or 3. Any Combination Of The Foregoing Proportionate To The Share Of Form With Respect To Total Amount Of Security. Section Iv. General Conditions Of Contract Table Of Contents 1. Definitions 41 2. Interpretation 43 3. Governing Language And Law 43 4. Communications 43 5. Possession Of Site 43 6. The Contractor’s Obligations 44 7. Performance Security 45 8. Subcontracting 46 9. Liquidated Damages 46 10. Site Investigation Reports 47 11. The Procuring Entity, Licenses And Permits 47 12. Contractor’s Risk And Warranty Security 47 13. Liability Of The Contractor 49 14. Procuring Entity’s Risk 49 15. Insurance 49 16. Termination For Default Of Contractor 51 17. Termination For Default Of Procuring Entity 51 18. Termination For Other Causes 52 19. Procedures For Termination Of Contracts 53 20. Force Majeure, Release From Performance 56 21. Resolution Of Disputes 56 22. Suspension Of Loan, Credit, Grant, Or Appropriation 57 23. Procuring Entity’s Representative’s Decisions 57 24. Approval Of Drawings And Temporary Works By The Procuring Entity’s Representative 57 25. Acceleration And Delays Ordered By The Procuring Entity’s Representative 58 26. Extension Of The Intended Completion Date 58 27. Right To Vary 58 28. Contractors Right To Claim 59 29. Dayworks 59 30. Early Warning 59 31. Program Of Work 59 32. Management Conferences 60 33. Bill Of Quantities 60 34. Instructions, Inspections And Audits 61 35. Identifying Defects 61 36. Cost Of Repairs 61 37. Correction Of Defects 61 38. Uncorrected Defects 62 39. Advance Payment 62 40. Progress Payments 62 41. Payment Certificates 63 42. Retention 63 43. Variation Orders 64 44. Contract Completion 66 45. Suspension Of Work 66 46. Payment On Termination 67 47. Extension Of Contract Time 67 48. Price Adjustment 68 49. Completion 68 50. Taking Over 69 51. Operating And Maintenance Manuals 69 1. Definitions For Purposes Of This Clause, Boldface Type Is Used To Identify Defined Terms. 1.1. The Arbiter Is The Person Appointed Jointly By The Procuring Entity And The Contractor To Resolve Disputes In The First Instance, As Provided For In Gcc Clause 21. 1.2. Bill Of Quantities Refers To A List Of The Specific Items Of The Work And Their Corresponding Unit Prices, Lump Sums, And/or Provisional Sums. 1.3. The Completion Date Is The Date Of Completion Of The Works As Certified By The Procuring Entity’s Representative, In Accordance With Gcc Clause 49. 1.4. The Contract Is The Contract Between The Procuring Entity And The Contractor To Execute, Complete, And Maintain The Works. 1.5. The Contract Price Is The Price Stated In The Letter Of Acceptance And Thereafter To Be Paid By The Procuring Entity To The Contractor For The Execution Of The Works In Accordance With This Contract. 1.6. Contract Time Extension Is The Allowable Period For The Contractor To Complete The Works In Addition To The Original Completion Date Stated In This Contract. 1.7. The Contractor Is The Juridical Entity Whose Proposal Has Been Accepted By The Procuring Entity And To Whom The Contract To Execute The Work Was Awarded. 1.8. The Contractor’s Bid Is The Signed Offer Or Proposal Submitted By The Contractor To The Procuring Entity In Response To The Bidding Documents. 1.9. Days Are Calendar Days; Months Are Calendar Months. 1.10. Dayworks Are Varied Work Inputs Subject To Payment On A Time Basis For The Contractor’s Employees And Equipment, In Addition To Payments For Associated Materials And Plant. 1.11. A Defect Is Any Part Of The Works Not Completed In Accordance With The Contract. 1.12. The Defects Liability Certificate Is The Certificate Issued By Procuring Entity’s Representative Upon Correction Of Defects By The Contractor. 1.13. The Defects Liability Period Is The One Year Period Between Contract Completion And Final Acceptance Within Which The Contractor Assumes The Responsibility To Undertake The Repair Of Any Damage To The Works At His Own Expense. 1.14. Drawings Are Graphical Presentations Of The Works. They Include All Supplementary Details, Shop Drawings, Calculations, And Other Information Provided Or Approved For The Execution Of This Contract. 1.15. Equipment Refers To All Facilities, Supplies, Appliances, Materials Or Things Required For The Execution And Completion Of The Work Provided By The Contractor And Which Shall Not Form Or Are Not Intended To Form Part Of The Permanent Works. 1.16. The Intended Completion Date Refers To The Date Specified In The Scc When The Contractor Is Expected To Have Completed The Works. The Intended Completion Date May Be Revised Only By The Procuring Entity’s Representative By Issuing An Extension Of Time Or An Acceleration Order. 1.17. Materials Are All Supplies, Including Consumables, Used By The Contractor For Incorporation In The Works. 1.18. The Notice To Proceed Is A Written Notice Issued By The Procuring Entity Or The Procuring Entity’s Representative To The Contractor Requiring The Latter To Begin The Commencement Of The Work Not Later Than A Specified Or Determinable Date. 1.19. Permanent Works All Permanent Structures And All Other Project Features And Facilities Required To Be Constructed And Completed In Accordance With This Contract Which Shall Be Delivered To The Procuring Entity And Which Shall Remain At The Site After The Removal Of All Temporary Works. 1.20. Plant Refers To The Machinery, Apparatus, And The Like Intended To Form An Integral Part Of The Permanent Works. 1.21. The Procuring Entity Is The Party Who Employs The Contractor To Carry Out The Works Stated In The Scc. 1.22. The Procuring Entity’s Representative Refers To The Head Of The Procuring Entity Or His Duly Authorized Representative, Identified In The Scc, Who Shall Be Responsible For Supervising The Execution Of The Works And Administering This Contract. 1.23. The Site Is The Place Provided By The Procuring Entity Where The Works Shall Be Executed And Any Other Place Or Places Which May Be Designated In The Scc, Or Notified To The Contractor By The Procuring Entity’s Representative As Forming Part Of The Site. 1.24. Site Investigation Reports Are Those That Were Included In The Bidding Documents And Are Factual And Interpretative Reports About The Surface And Subsurface Conditions At The Site. 1.25. Slippage Is A Delay In Work Execution Occurring When Actual Accomplishment Falls Below The Target As Measured By The Difference Between The Scheduled And Actual Accomplishment Of The Work By The Contractor As Established From The Work Schedule. This Is Actually Described As A Percentage Of The Whole Works. 1.26. Specifications Means The Description Of Works To Be Done And The Qualities Of Materials To Be Used, The Equipment To Be Installed And The Mode Of Construction. 1.27. The Start Date, As Specified In The Scc, Is The Date When The Contractor Is Obliged To Commence Execution Of The Works. It Does Not Necessarily Coincide With Any Of The Site Possession Dates. 1.28. A Subcontractor Is Any Person Or Organization To Whom A Part Of The Works Has Been Subcontracted By The Contractor, As Allowed By The Procuring Entity, But Not Any Assignee Of Such Person. 1.29. Temporary Works Are Works Designed, Constructed, Installed, And Removed By The Contractor That Are Needed For Construction Or Installation Of The Permanent Works. 1.30. Work(s)refer To The Permanent Works And Temporary Works To Be Executed By The Contractor In Accordance With This Contract, Including (i) The Furnishing Of All Labor, Materials, Equipment And Others Incidental, Necessary Or Convenient To The Complete Execution Of The Works; (ii) The Passing Of Any Tests Before Acceptance By The Procuring Entity’s Representative; (iii) And The Carrying Out Of All Duties And Obligations Of The Contractor Imposed By This Contract As Described In The Scc. 2. Interpretation 2.1. In Interpreting The Conditions Of Contract, Singular Also Means Plural, Male Also Means Female Or Neuter, And The Other Way Around. Headings Have No Significance. Words Have Their Normal Meaning Under The Language Of This Contract Unless Specifically Defined. The Procuring Entity’s Representative Will Provide Instructions Clarifying Queries About The Conditions Of Contract. 2.2. If Sectional Completion Is Specified In The Scc, References In The Conditions Of Contract To The Works, The Completion Date, And The Intended Completion Date Apply To Any Section Of The Works (other Than References To The Completion Date And Intended Completion Date For The Whole Of The Works). 3. Governing Language And Law 3.1. This Contract Has Been Executed In The English Language, Which Shall Be The Binding And Controlling Language For All Matters Relating To The Meaning Or Interpretation Of This Contract. All Correspondence And Other Documents Pertaining To This Contract Which Are Exchanged By The Parties Shall Be Written In English. 3.2. This Contract Shall Be Interpreted In Accordance With The Laws Of The Republic Of The Philippines. 4. Communications Communications Between Parties That Are Referred To In The Conditions Shall Be Effective Only When In Writing. A Notice Shall Be Effective Only When It Is Received By The Concerned Party. 5. Possession Of Site 5.1. On The Date Specified In The Scc, The Procuring Entity Shall Grant The Contractor Possession Of So Much Of The Site As May Be Required To Enable It To Proceed With The Execution Of The Works. If The Contractor Suffers Delay Or Incurs Cost From Failure On The Part Of The Procuring Entity To Give Possession In Accordance With The Terms Of This Clause, The Procuring Entity’s Representative Shall Give The Contractor A Contract Time Extension And Certify Such Sum As Fair To Cover The Cost Incurred, Which Sum Shall Be Paid By Procuring Entity. 5.2. If Possession Of A Portion Is Not Given By The Date Stated In The Scc Clause 5.1, The Procuring Entity Will Be Deemed To Have Delayed The Start Of The Relevant Activities. The Resulting Adjustments In Contact Time To Address Such Delay Shall Be In Accordance With Gcc Clause 47. 5.3. The Contractor Shall Bear All Costs And Charges For Special Or Temporary Right-of-way Required By It In Connection With Access To The Site. The Contractor Shall Also Provide At His Own Cost Any Additional Facilities Outside The Site Required By It For Purposes Of The Works. 5.4. The Contractor Shall Allow The Procuring Entity’s Representative And Any Person Authorized By The Procuring Entity’s Representative Access To The Site And To Any Place Where Work In Connection With This Contract Is Being Carried Out Or Is Intended To Be Carried Out. 6. The Contractor’s Obligations 6.1. The Contractor Shall Carry Out The Works Properly And In Accordance With This Contract. The Contractor Shall Provide All Supervision, Labor, Materials, Plant And Contractor's Equipment, Which May Be Required. All Materials And Plant On Site Shall Be Deemed To Be The Property Of The Procuring Entity. 6.2. The Contractor Shall Commence Execution Of The Works On The Start Date And Shall Carry Out The Works In Accordance With The Program Of Work Submitted By The Contractor, As Updated With The Approval Of The Procuring Entity’s Representative, And Complete Them By The Intended Completion Date. 6.3. The Contractor Shall Be Responsible For The Safety Of All Activities On The Site. 6.4. The Contractor Shall Carry Out All Instructions Of The Procuring Entity’s Representative That Comply With The Applicable Laws Where The Site Is Located. 6.5. The Contractor Shall Employ The Key Personnel Named In The Schedule Of Key Personnel, As Referred To In The Scc, To Carry Out The Supervision Of The Works. The Procuring Entity Will Approve Any Proposed Replacement Of Key Personnel Only If Their Relevant Qualifications And Abilities Are Equal To Or Better Than Those Of The Personnel Listed In The Schedule. 6.6. If The Procuring Entity’s Representative Asks The Contractor To Remove A Member Of The Contractor’s Staff Or Work Force, For Justifiable Cause, The Contractor Shall Ensure That The Person Leaves The Site Within Seven (7) Days And Has No Further Connection With The Work In This Contract. 6.7. During Contract Implementation, The Contractor And His Subcontractors Shall Abide At All Times By All Labor Laws, Including Child Labor Related Enactments, And Other Relevant Rules. 6.8. The Contractor Shall Submit To The Procuring Entity For Consent The Name And Particulars Of The Person Authorized To Receive Instructions On Behalf Of The Contractor. 6.9. The Contractor Shall Cooperate And Share The Site With Other Contractors, Public Authorities, Utilities, And The Procuring Entity Between The Dates Given In The Schedule Of Other Contractors Particularly When They Shall Require Access To The Site. The Contractor Shall Also Provide Facilities And Services For Them During This Period. The Procuring Entity May Modify The Schedule Of Other Contractors, And Shall Notify The Contractor Of Any Such Modification Thereto. 6.10. Should Anything Of Historical Or Other Interest Or Of Significant Value Be Unexpectedly Discovered On The Site, It Shall Be The Property Of The Procuring Entity. The Contractor Shall Notify The Procuring Entity’s Representative Of Such Discoveries And Carry Out The Procuring Entity’s Representative’s Instructions In Dealing With Them. 7. Performance Security 7.1. Within Ten (10) Calendar Days From Receipt Of The Notice Of Award From The Procuring Entity But In No Case Later Than The Signing Of The Contract By Both Parties, The Contractor Shall Furnish The Performance Security In Any The Forms Prescribed In Itb Clause 32.2. 7.2. The Performance Security Posted In Favor Of The Procuring Entity Shall Be Forfeited In The Event It Is Established That The Contractor Is In Default In Any Of Its Obligations Under The Contract. 7.3. The Performance Security Shall Remain Valid Until Issuance By The Procuring Entity Of The Certificate Of Final Acceptance. 7.4. The Performance Security May Be Released By The Procuring Entity And Returned To The Contractor After The Issuance Of The Certificate Of Final Acceptance Subject To The Following Conditions: (a) There Are No Pending Claims Against The Contractor Or The Surety Company Filed By The Procuring Entity; (b) The Contractor Has No Pending Claims For Labor And Materials Filed Against It; And (c) Other Terms Specified In The Scc. 7.5. The Contractor Shall Post An Additional Performance Security Following The Amount And Form Specified In Itb Clause 32.2 To Cover Any Cumulative Increase Of More Than Ten Percent (10%) Over The Original Value Of The Contract As A Result Of Amendments To Order Or Change Orders, Extra Work Orders And Supplemental Agreements, As The Case May Be. The Contractor Shall Cause The Extension Of The Validity Of The Performance Security To Cover Approved Contract Time Extensions. 7.6. In Case Of A Reduction In The Contract Value Or For Partially Completed Works Under The Contract Which Are Usable And Accepted By The Procuring Entity The Use Of Which, In The Judgment Of The Implementing Agency Or The Procuring Entity, Will Not Affect The Structural Integrity Of The Entire Project, The Procuring Entity Shall Allow A Proportional Reduction In The Original Performance Security, Provided That Any Such Reduction Is More Than Ten Percent (10%) And That The Aggregate Of Such Reductions Is Not More Than Fifty Percent (50%) Of The Original Performance Security. 7.7. Unless Otherwise Indicated In The Scc, The Contractor, By Entering Into The Contract With The Procuring Entity, Acknowledges The Right Of The Procuring Entity To Institute Action Pursuant To Act 3688 Against Any Subcontractor Be They An Individual, Firm, Partnership, Corporation, Or Association Supplying The Contractor With Labor, Materials And/or Equipment For The Performance Of This Contract. 8. Subcontracting 8.1. Unless Otherwise Indicated In The Scc, The Contractor Cannot Subcontract Works More Than The Percentage Specified In Itb Clause 8.1. 8.2. Subcontracting Of Any Portion Of The Works Does Not Relieve The Contractor Of Any Liability Or Obligation Under This Contract. The Contractor Will Be Responsible For The Acts, Defaults, And Negligence Of Any Subcontractor, Its Agents, Servants Or Workmen As Fully As If These Were The Contractor’s Own Acts, Defaults, Or Negligence, Or Those Of Its Agents, Servants Or Workmen. 8.3. Subcontractors Disclosed And Identified During The Bidding May Be Changed During The Implementation Of This Contract, Subject To Compliance With The Required Qualifications And The Approval Of The Procuring Entity. 9. Liquidated Damages 9.1. The Contractor Shall Pay Liquidated Damages To The Procuring Entity For Each Day That The Completion Date Is Later Than The Intended Completion Date. The Applicable Liquidated Damages Is At Least One-tenth (1/10) Of A Percent Of The Cost Of The Unperformed Portion For Every Day Of Delay. The Total Amount Of Liquidated Damages Shall Not Exceed Ten Percent (10%) Of The Amount Of The Contract. The Procuring Entity May Deduct Liquidated Damages From Payments Due To The Contractor. Payment Of Liquidated Damages Shall Not Affect The Contractor. Once The Cumulative Amount Of Liquidated Damages Reaches Ten Percent (10%) Of The Amount Of This Contract, The Procuring Entity Shall Rescind This Contract, Without Prejudice To Other Courses Of Action And Remedies Open To It. 9.2. If The Intended Completion Date Is Extended After Liquidated Damages Have Been Paid, The Engineer Of The Procuring Entity Shall Correct Any Overpayment Of Liquidated Damages By The Contractor By Adjusting The Next Payment Certificate. The Contractor Shall Be Paid Interest On The Overpayment, Calculated From The Date Of Payment To The Date Of Repayment, At The Rates Specified In Gcc Clause 40.3. 10. Site Investigation Reports The Contractor, In Preparing The Bid, Shall Rely On Any Site Investigation Reports Referred To In The Scc Supplemented By Any Information Obtained By The Contractor. 11. The Procuring Entity, Licenses And Permits The Procuring Entity Shall, If Requested By The Contractor, Assist Him In Applying For Permits, Licenses Or Approvals, Which Are Required For The Works. 12. Contractor’s Risk And Warranty Security 12.1. The Contractor Shall Assume Full Responsibility For The Works From The Time Project Construction Commenced Up To Final Acceptance By The Procuring Entity And Shall Be Held Responsible For Any Damage Or Destruction Of The Works Except Those Occasioned By Force Majeure. The Contractor Shall Be Fully Responsible For The Safety, Protection, Security, And Convenience Of His Personnel, Third Parties, And The Public At Large, As Well As The Works, Equipment, Installation, And The Like To Be Affected By His Construction Work. 12.2. The Defects Liability Period For Infrastructure Projects Shall Be One Year From Contract Completion Up To Final Acceptance By The Procuring Entity. During This Period, The Contractor Shall Undertake The Repair Works, At His Own Expense, Of Any Damage To The Works On Account Of The Use Of Materials Of Inferior Quality Within Ninety (90) Days From The Time The Head Of The Procuring Entity Has Issued An Order To Undertake Repair. In Case Of Failure Or Refusal To Comply With This Mandate, The Procuring Entity Shall Undertake Such Repair Works And Shall Be Entitled To Full Reimbursement Of Expenses Incurred Therein Upon Demand. 12.3. Unless Otherwise Indicated In The Scc, In Case The Contractor Fails To Comply With The Preceding Paragraph, The Procuring Entity Shall Forfeit Its Performance Security, Subject Its Property (ies) To Attachment Or Garnishment Proceedings, And Perpetually Disqualify It From Participating In Any Public Bidding. All Payables Of The Gop In His Favor Shall Be Offset To Recover The Costs. 12.4. After Final Acceptance Of The Works By The Procuring Entity, The Contractor Shall Be Held Responsible For “structural Defects”, I.e., Major Faults/flaws/deficiencies In One Or More Key Structural Elements Of The Project Which May Lead To Structural Failure Of The Completed Elements Or Structure, Or “structural Failures”, I.e., Where One Or More Key Structural Elements In An Infrastructure Facility Fails Or Collapses, Thereby Rendering The Facility Or Part Thereof Incapable Of Withstanding The Design Loads, And/or Endangering The Safety Of The Users Or The General Public: (a) Contractor – Where Structural Defects/failures Arise Due To Faults Attributable To Improper Construction, Use Of Inferior Quality/substandard Materials, And Any Violation Of The Contract Plans And Specifications, The Contractor Shall Be Held Liable; (b) Consultants – Where Structural Defects/failures Arise Due To Faulty And/or Inadequate Design And Specifications As Well As Construction Supervision, Then The Consultant Who Prepared The Design Or Undertook Construction Supervision For The Project Shall Be Held Liable; (c) Procuring Entity’s Representatives/project Manager/construction Managers And Supervisors – The Project Owner’s Representative(s), Project Manager, Construction Manager, And Supervisor(s) Shall Be Held Liable In Cases Where The Structural Defects/failures Are Due To His/their Willful Intervention In Altering The Designs And Other Specifications; Negligence Or Omission In Not Approving Or Acting On Proposed Changes To Noted Defects Or Deficiencies In The Design And/or Specifications; And The Use Of Substandard Construction Materials In The Project; (d) Third Parties - Third Parties Shall Be Held Liable In Cases Where Structural Defects/failures Are Caused By Work Undertaken By Them Such As Leaking Pipes, Diggings Or Excavations, Underground Cables And Electrical Wires, Underground Tunnel, Mining Shaft And The Like, In Which Case The Applicable Warranty To Such Structure Should Be Levied To Third Parties For Their Construction Or Restoration Works. (e) Users - In Cases Where Structural Defects/failures Are Due To Abuse/misuse By The End User Of The Constructed Facility And/or Non–compliance By A User With The Technical Design Limits And/or Intended Purpose Of The Same, Then The User Concerned Shall Be Held Liable. 12.5. The Warranty Against Structural Defects/failures, Except Those Occasioned On Force Majeure, Shall Cover The Period Specified In The Scc Reckoned From The Date Of Issuance Of The Certificate Of Final Acceptance By The Procuring Entity. 12.6. The Contractor Shall Be Required To Put Up A Warranty Security In The Form Of Cash, Bank Guarantee, Letter Of Credit, Gsis Or Surety Bond Callable On Demand, In Accordance With The Following Schedule: Form Of Warranty Minimum Amount In Percentage (%) Of Total Contract Price (a) Cash Or Letter Of Credit Issued By Universal Or Commercial Bank: Provided, However, That The Letter Of Credit Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank Five Percent (5%) (b) Bank Guarantee Confirmed By Universal Or Commercial Bank: Provided, However, That The Letter Of Credit Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank Ten Percent (10%) (c) Surety Bond Callable Upon Demand Issued By Gsis Or Any Surety Or Insurance Company Duly Certified By The Insurance Commission Thirty Percent (30%) 12.7. The Warranty Security Shall Be Stated In Philippine Pesos And Shall Remain Effective For One Year From The Date Of Issuance Of The Certificate Of Final Acceptance By The Procuring Entity, And Returned Only After The Lapse Of Said One Year Period. 12.8. In Case Of Structural Defects/failure Occurring During The Applicable Warranty Period Provided In Gcc Clause 12.5, The Procuring Entity Shall Undertake The Necessary Restoration Or Reconstruction Works And Shall Be Entitled To Full Reimbursement By The Parties Found To Be Liable For Expenses Incurred Therein Upon Demand, Without Prejudice To The Filing Of Appropriate Administrative, Civil, And/or Criminal Charges Against The Responsible Persons As Well As The Forfeiture Of The Warranty Security Posted In Favor Of The Procuring Entity. 13. Liability Of The Contractor Subject To Additional Provisions, If Any, Set Forth In The Scc, The Contractor’s Liability Under This Contract Shall Be As Provided By The Laws Of The Republic Of The Philippines. 14. Procuring Entity’s Risk 14.1. From The Start Date Until The Certificate Of Final Acceptance Has Been Issued, The Following Are Risks Of The Procuring Entity: (a) The Risk Of Personal Injury, Death, Or Loss Of Or Damage To Property (excluding The Works, Plant, Materials, And Equipment), Which Are Due To: (i) Any Type Of Use Or Occupation Of The Site Authorized By The Procuring Entity After The Official Acceptance Of The Works; Or (ii) Negligence, Breach Of Statutory Duty, Or Interference With Any Legal Right By The Procuring Entity Or By Any Person Employed By Or Contracted To Him Except The Contractor. (b) The Risk Of Damage To The Works, Plant, Materials, And Equipment To The Extent That It Is Due To A Fault Of The Procuring Entity Or In The Procuring Entity’s Design, Or Due To War Or Radioactive Contamination Directly Affecting The Country Where The Works Are To Be Executed. 15. Insurance 15.1. The Contractor Shall, Under His Name And At His Own Expense, Obtain And Maintain, For The Duration Of This Contract, The Following Insurance Coverage: (a) Contractor’s All Risk Insurance; (b) Transportation To The Project Site Of Equipment, Machinery, And Supplies Owned By The Contractor; (c) Personal Injury Or Death Of Contractor’s Employees; And (d) Comprehensive Insurance For Third Party Liability To Contractor’s Direct Or Indirect Act Or Omission Causing Damage To Third Persons. 15.2. The Contractor Shall Provide Evidence To The Procuring Entity’s Representative That The Insurances Required Under This Contract Have Been Effected And Shall, Within A Reasonable Time, Provide Copies Of The Insurance Policies To The Procuring Entity’s Representative. Such Evidence And Such Policies Shall Be Provided To The Procuring Entity’s Through The Procuring Entity’s Representative. 15.3. The Contractor Shall Notify The Insurers Of Changes In The Nature, Extent, Or Program For The Execution Of The Works And Ensure The Adequacy Of The Insurances At All Times In Accordance With The Terms Of This Contract And Shall Produce To The Procuring Entity’s Representative The Insurance Policies In Force Including The Receipts For Payment Of The Current Premiums. The Above Insurance Policies Shall Be Obtained From Any Reputable Insurance Company Approved By The Procuring Entity’s Representative. 15.4. If The Contractor Fails To Obtain And Keep In Force The Insurances Referred To Herein Or Any Other Insurance Which He May Be Required To Obtain Under The Terms Of This Contract, The Procuring Entity May Obtain And Keep In Force Any Such Insurances And Pay Such Premiums As May Be Necessary For The Purpose. From Time To Time, The Procuring Entity May Deduct The Amount It Shall Pay For Said Premiums Including Twenty Five Percent (25%) Therein From Any Monies Due, Or Which May Become Due, To The Contractor, Without Prejudice To The Procuring Entity Exercising Its Right To Impose Other Sanctions Against The Contractor Pursuant To The Provisions Of This Contract. 15.5. In The Event The Contractor Fails To Observe The Above Safeguards, The Procuring Entity May, At The Contractor’s Expense, Take Whatever Measure Is Deemed Necessary For Its Protection And That Of The Contractor’s Personnel And Third Parties, And/or Order The Interruption Of Dangerous Works. In Addition, The Procuring Entity May Refuse To Make The Payments Under Gcc Clause 40 Until The Contractor Complies With This Clause. 15.6. The Contractor Shall Immediately Replace The Insurance Policy Obtained As Required In This Contract, Without Need Of The Procuring Entity’s Demand, With A New Policy Issued By A New Insurance Company Acceptable To The Procuring Entity For Any Of The Following Grounds: (a) The Issuer Of The Insurance Policy To Be Replaced Has: (i) Become Bankrupt; (ii) Been Placed Under Receivership Or Under A Management Committee; (iii) Been Sued For Suspension Of Payment; Or (iv) Been Suspended By The Insurance Commission And Its License To Engage In Business Or Its Authority To Issue Insurance Policies Cancelled; Or (v) Where Reasonable Grounds Exist That The Insurer May Not Be Able, Fully And Promptly, To Fulfill Its Obligation Under The Insurance Policy. 16. Termination For Default Of Contractor 16.1. The Procuring Entity Shall Terminate This Contract For Default When Any Of The Following Conditions Attend Its Implementation: 16.2. Due To The Contractor’s Fault And While The Project Is On-going, It Has Incurred Negative Slippage Of Fifteen Percent (15%) Or More In Accordance With Presidential Decree 1870, Regardless Of Whether Or Not Previous Warnings And Notices Have Been Issued For The Contractor To Improve His Performance; 16.3. Due To Its Own Fault And After This Contract Time Has Expired, The Contractor Incurs Delay In The Completion Of The Work After This Contract Has Expired; Or 16.4. The Contractor: (a) Abandons The Contract Works, Refuses Or Fails To Comply With A Valid Instruction Of The Procuring Entity Or Fails To Proceed Expeditiously And Without Delay Despite A Written Notice By The Procuring Entity; (b) Does Not Actually Have On The Project Site The Minimum Essential Equipment Listed On The Bid Necessary To Prosecute The Works In Accordance With The Approved Program Of Work And Equipment Deployment Schedule As Required For The Project; (c) Does Not Execute The Works In Accordance With This Contract Or Persistently Or Flagrantly Neglects To Carry Out Its Obligations Under This Contract; (d) Neglects Or Refuses To Remove Materials Or To Perform A New Work That Has Been Rejected As Defective Or Unsuitable; Or (e) Sub-lets Any Part Of This Contract Without Approval By The Procuring Entity. 16.5. All Materials On The Site, Plant, Equipment, And Works Shall Be Deemed To Be The Property Of The Procuring Entity If This Contract Is Rescinded Because Of The Contractor’s Default. 17. Termination For Default Of Procuring Entity The Contractor May Terminate This Contract With The Procuring Entity If The Works Are Completely Stopped For A Continuous Period Of At Least Sixty (60) Calendar Days Through No Fault Of Its Own, Due To Any Of The Following Reasons: (a) Failure Of The Procuring Entity To Deliver, Within A Reasonable Time, Supplies, Materials, Right-of-way, Or Other Items It Is Obligated To Furnish Under The Terms Of This Contract; Or (b) The Prosecution Of The Work Is Disrupted By The Adverse Peace And Order Situation, As Certified By The Armed Forces Of The Philippines Provincial Commander And Approved By The Secretary Of National Defense. 18. Termination For Other Causes 18.1. The Procuring Entity May Terminate This Contract, In Whole Or In Part, At Any Time For Its Convenience. The Head Of The Procuring Entity May Terminate This Contract For The Convenience Of The Procuring Entity If He Has Determined The Existence Of Conditions That Make Project Implementation Economically, Financially Or Technically Impractical And/or Unnecessary, Such As, But Not Limited To, Fortuitous Event(s) Or Changes In Law And National Government Policies. 18.2. The Procuring Entity Or The Contractor May Terminate This Contract If The Other Party Causes A Fundamental Breach Of This Contract. 18.3. Fundamental Breaches Of Contract Shall Include, But Shall Not Be Limited To, The Following: (a) The Contractor Stops Work For Twenty Eight (28) Days When No Stoppage Of Work Is Shown On The Current Program Of Work And The Stoppage Has Not Been Authorized By The Procuring Entity’s Representative; (b) The Procuring Entity’s Representative Instructs The Contractor To Delay The Progress Of The Works, And The Instruction Is Not Withdrawn Within Twenty Eight (28) Days; (c) The Procuring Entity Shall Terminate This Contract If The Contractor Is Declared Bankrupt Or Insolvent As Determined With Finality By A Court Of Competent Jurisdiction. In This Event, Termination Will Be Without Compensation To The Contractor, Provided That Such Termination Will Not Prejudice Or Affect Any Right Of Action Or Remedy Which Has Accrued Or Will Accrue Thereafter To The Procuring Entity And/or The Contractor. In The Case Of The Contractor's Insolvency, Any Contractor's Equipment Which The Procuring Entity Instructs In The Notice Is To Be Used Until The Completion Of The Works; (d) A Payment Certified By The Procuring Entity’s Representative Is Not Paid By The Procuring Entity To The Contractor Within Eighty Four (84) Days From The Date Of The Procuring Entity’s Representative’s Certificate; (e) The Procuring Entity’s Representative Gives Notice That Failure To Correct A Particular Defect Is A Fundamental Breach Of Contract And The Contractor Fails To Correct It Within A Reasonable Period Of Time Determined By The Procuring Entity’s Representative; (f) The Contractor Does Not Maintain A Security, Which Is Required; (g) The Contractor Has Delayed The Completion Of The Works By The Number Of Days For Which The Maximum Amount Of Liquidated Damages Can Be Paid, As Defined In The Gcc Clause 9; And (h) In Case It Is Determined Prima Facie By The Procuring Entity That The Contractor Has Engaged, Before Or During The Implementation Of The Contract, In Unlawful Deeds And Behaviors Relative To Contract Acquisition And Implementation, Such As, But Not Limited To, The Following: (i) Corrupt, Fraudulent, Collusive, Coercive, And Obstructive Practices As Defined In Itb Clause 3.1(a), Unless Otherwise Specified In The Scc; (ii) Drawing Up Or Using Forged Documents; (iii) Using Adulterated Materials, Means Or Methods, Or Engaging In Production Contrary To Rules Of Science Or The Trade; And (iv) Any Other Act Analogous To The Foregoing. 18.4. The Funding Source Or The Procuring Entity, As Appropriate, Will Seek To Impose The Maximum Civil, Administrative And/or Criminal Penalties Available Under The Applicable Law On Individuals And Organizations Deemed To Be Involved With Corrupt, Fraudulent, Or Coercive Practices. 18.5. When Persons From Either Party To This Contract Gives Notice Of A Fundamental Breach To The Procuring Entity’s Representative In Order To Terminate The Existing Contract For A Cause Other Than Those Listed Under Gcc Clause 18.3, The Procuring Entity’s Representative Shall Decide Whether The Breach Is Fundamental Or Not. 18.6. If This Contract Is Terminated, The Contractor Shall Stop Work Immediately, Make The Site Safe And Secure, And Leave The Site As Soon As Reasonably Possible. 19. Procedures For Termination Of Contracts 19.1. The Following Provisions Shall Govern The Procedures For The Termination Of This Contract: (a) Upon Receipt Of A Written Report Of Acts Or Causes Which May Constitute Ground(s) For Termination As Aforementioned, Or Upon Its Own Initiative, The Procuring Entity Shall, Within A Period Of Seven (7) Calendar Days, Verify The Existence Of Such Ground(s) And Cause The Execution Of A Verified Report, With All Relevant Evidence Attached; (b) Upon Recommendation By The Procuring Entity, The Head Of The Procuring Entity Shall Terminate This Contract Only By A Written Notice To The Contractor Conveying The Termination Of This Contract. The Notice Shall State: (i) That This Contract Is Being Terminated For Any Of The Ground(s) Afore-mentioned, And A Statement Of The Acts That Constitute The Ground(s) Constituting The Same; (ii) The Extent Of Termination, Whether In Whole Or In Part; (iii) An Instruction To The Contractor To Show Cause As To Why This Contract Should Not Be Terminated; And (iv) Special Instructions Of The Procuring Entity, If Any. The Notice To Terminate Shall Be Accompanied By A Copy Of The Verified Report; (c) Within A Period Of Seven (7) Calendar Days From Receipt Of The Notice Of Termination, The Contractor Shall Submit To The Head Of The Procuring Entity A Verified Position Paper Stating Why The Contract Should Not Be Terminated. If The Contractor Fails To Show Cause After The Lapse Of The Seven (7) Day Period, Either By Inaction Or By Default, The Head Of The Procuring Entity Shall Issue An Order Terminating The Contract; (d) The Procuring Entity May, At Anytime Before Receipt Of The Bidder’s Verified Position Paper Described In Item (c) Above Withdraw The Notice To Terminate If It Is Determined That Certain Items Or Works Subject Of The Notice Had Been Completed, Delivered, Or Performed Before The Contractor’s Receipt Of The Notice; (e) Within A Non-extendible Period Of Ten (10) Calendar Days From Receipt Of The Verified Position Paper, The Head Of The Procuring Entity Shall Decide Whether Or Not To Terminate This Contract. It Shall Serve A Written Notice To The Contractor Of Its Decision And, Unless Otherwise Provided In The Said Notice, This Contract Is Deemed Terminated From Receipt Of The Contractor Of The Notice Of Decision. The Termination Shall Only Be Based On The Ground(s) Stated In The Notice To Terminate; And (f) The Head Of The Procuring Entity May Create A Contract Termination Review Committee (ctrc) To Assist Him In The Discharge Of This Function. All Decisions Recommended By The Ctrc Shall Be Subject To The Approval Of The Head Of The Procuring Entity. 19.2. Pursuant To Section 69(f) Of Ra 9184 And Without Prejudice To The Imposition Of Additional Administrative Sanctions As The Internal Rules Of The Agency May Provide And/or Further Criminal Prosecution As Provided By Applicable Laws, The Procuring Entity Shall Impose On Contractors After The Termination Of The Contract The Penalty Of Suspension For One (1) Year For The First Offense, Suspension For Two (2) Years For The Second Offense From Participating In The Public Bidding Process, For Violations Committed During The Contract Implementation Stage, Which Include But Not Limited To The Following: (a) Failure Of The Contractor, Due Solely To His Fault Or Negligence, To Mobilize And Start Work Or Performance Within The Specified Period In The Notice To Proceed (“ntp”); (b) Failure By The Contractor To Fully And Faithfully Comply With Its Contractual Obligations Without Valid Cause, Or Failure By The Contractor To Comply With Any Written Lawful Instruction Of The Procuring Entity Or Its Representative(s) Pursuant To The Implementation Of The Contract. For The Procurement Of Infrastructure Projects Or Consultancy Contracts, Lawful Instructions Include But Are Not Limited To The Following: (i) Employment Of Competent Technical Personnel, Competent Engineers And/or Work Supervisors; (ii) Provision Of Warning Signs And Barricades In Accordance With Approved Plans And Specifications And Contract Provisions; (iii) Stockpiling In Proper Places Of All Materials And Removal From The Project Site Of Waste And Excess Materials, Including Broken Pavement And Excavated Debris In Accordance With Approved Plans And Specifications And Contract Provisions; (iv) Deployment Of Committed Equipment, Facilities, Support Staff And Manpower; And (v) Renewal Of The Effectivity Dates Of The Performance Security After Its Expiration During The Course Of Contract Implementation. (c) Assignment And Subcontracting Of The Contract Or Any Part Thereof Or Substitution Of Key Personnel Named In The Proposal Without Prior Written Approval By The Procuring Entity. (d) Poor Performance By The Contractor Or Unsatisfactory Quality And/or Progress Of Work Arising From His Fault Or Negligence As Reflected In The Constructor's Performance Evaluation System (“cpes”) Rating Sheet. In The Absence Of The Cpes Rating Sheet, The Existing Performance Monitoring System Of The Procuring Entity Shall Be Applied. Any Of The Following Acts By The Contractor Shall Be Construed As Poor Performance: (i) Negative Slippage Of 15% And Above Within The Critical Path Of The Project Due Entirely To The Fault Or Negligence Of The Contractor; And (ii) Quality Of Materials And Workmanship Not Complying With The Approved Specifications Arising From The Contractor's Fault Or Negligence. (e) Willful Or Deliberate Abandonment Or Non-performance Of The Project Or Contract By The Contractor Resulting To Substantial Breach Thereof Without Lawful And/or Just Cause. In Addition To The Penalty Of Suspension, The Performance Security Posted By The Contractor Shall Also Be Forfeited. 20. Force Majeure, Release From Performance 20.1. For Purposes Of This Contract The Terms “force Majeure” And “fortuitous Event” May Be Used Interchangeably. In This Regard, A Fortuitous Event Or Force Majeure Shall Be Interpreted To Mean An Event Which The Contractor Could Not Have Foreseen, Or Which Though Foreseen, Was Inevitable. It Shall Not Include Ordinary Unfavorable Weather Conditions; And Any Other Cause The Effects Of Which Could Have Been Avoided With The Exercise Of Reasonable Diligence By The Contractor. 20.2. If This Contract Is Discontinued By An Outbreak Of War Or By Any Other Event Entirely Outside The Control Of Either The Procuring Entity Or The Contractor, The Procuring Entity’s Representative Shall Certify That This Contract Has Been Discontinued. The Contractor Shall Make The Site Safe And Stop Work As Quickly As Possible After Receiving This Certificate And Shall Be Paid For All Works Carried Out Before Receiving It And For Any Work Carried Out Afterwards To Which A Commitment Was Made. 20.3. If The Event Continues For A Period Of Eighty Four (84) Days, Either Party May Then Give Notice Of Termination, Which Shall Take Effect Twenty Eight (28) Days After The Giving Of The Notice. 20.4. After Termination, The Contractor Shall Be Entitled To Payment Of The Unpaid Balance Of The Value Of The Works Executed And Of The Materials And Plant Reasonably Delivered To The Site, Adjusted By The Following: (a) Any Sum To Which The Contractor Is Entitled Under Gcc Clause 28; (b) The Cost Of His Suspension And Demobilization; (c) Any Sum To Which The Procuring Entity Is Entitled. 20.5. The Net Balance Due Shall Be Paid Or Repaid Within A Reasonable Time Period From The Time Of The Notice Of Termination. 21. Resolution Of Disputes 21.1. If Any Dispute Or Difference Of Any Kind Whatsoever Shall Arise Between The Parties In Connection With The Implementation Of The Contract Covered By The Act And This Irr, The Parties Shall Make Every Effort To Resolve Amicably Such Dispute Or Difference By Mutual Consultation. 21.2. If The Contractor Believes That A Decision Taken By The Procuring Entity’s Representative Was Either Outside The Authority Given To The Procuring Entity’s Representative By This Contract Or That The Decision Was Wrongly Taken, The Decision Shall Be Referred To The Arbiter Indicated In The Scc Within Fourteen (14) Days Of The Notification Of The Procuring Entity’s Representative’s Decision. 21.3. Any And All Disputes Arising From The Implementation Of This Contract Covered By The R.a. 9184 And Its Irr Shall Be Submitted To Arbitration In The Philippines According To The Provisions Of Republic Act No. 876, Otherwise Known As The “ Arbitration Law” And Republic Act 9285, Otherwise Known As The “alternative Dispute Resolution Act Of 2004”: Provided, However, That, Disputes That Are Within The Competence Of The Construction Industry Arbitration Commission To Resolve Shall Be Referred Thereto. The Process Of Arbitration Shall Be Incorporated As A Provision In This Contract That Will Be Executed Pursuant To The Provisions Of The Act And Its Irr: Provided, Further, That, By Mutual Agreement, The Parties May Agree In Writing To Resort To Other Alternative Modes Of Dispute Resolution. 22. Suspension Of Loan, Credit, Grant, Or Appropriation In The Event That The Funding Source Suspends The Loan, Credit, Grant, Or Appropriation To The Procuring Entity, From Which Part Of The Payments To The Contractor Are Being Made: (a) The Procuring Entity Is Obligated To Notify The Contractor Of Such Suspension Within Seven (7) Days Of Having Received The Suspension Notice. (b) If The Contractor Has Not Received Sums Due It For Work Already Done Within Forty Five (45) Days From The Time The Contractor’s Claim For Payment Has Been Certified By The Procuring Entity’s Representative, The Contractor May Immediately Issue A Suspension Of Work Notice In Accordance With Gcc Clause 45.2. 23. Procuring Entity’s Representative’s Decisions 23.1. Except Where Otherwise Specifically Stated, The Procuring Entity’s Representative Will Decide Contractual Matters Between The Procuring Entity And The Contractor In The Role Representing The Procuring Entity. 23.2. The Procuring Entity’s Representative May Delegate Any Of His Duties And Responsibilities To Other People, Except To The Arbiter, After Notifying The Contractor, And May Cancel Any Delegation After Notifying The Contractor. 24. Approval Of Drawings And Temporary Works By The Procuring Entity’s Representative 24.1. All Drawings Prepared By The Contractor For The Execution Of The Temporary Works, Are Subject To Prior Approval By The Procuring Entity’s Representative Before Its Use. 24.2. The Contractor Shall Be Responsible For Design Of Temporary Works. 24.3. The Procuring Entity’s Representative’s Approval Shall Not Alter The Contractor’s Responsibility For Design Of The Temporary Works. 24.4. The Contractor Shall Obtain Approval Of Third Parties To The Design Of The Temporary Works, When Required By The Procuring Entity. 25. Acceleration And Delays Ordered By The Procuring Entity’s Representative 25.1. When The Procuring Entity Wants The Contractor To Finish Before The Intended Completion Date, The Procuring Entity’s Representative Will Obtain Priced Proposals For Achieving The Necessary Acceleration From The Contractor. If The Procuring Entity Accepts These Proposals, The Intended Completion Date Will Be Adjusted Accordingly And Confirmed By Both The Procuring Entity And The Contractor. 25.2. If The Contractor’s Financial Proposals For An Acceleration Are Accepted By The Procuring Entity, They Are Incorporated In The Contract Price And Treated As A Variation. 26. Extension Of The Intended Completion Date 26.1. The Procuring Entity’s Representative Shall Extend The Intended Completion Date If A Variation Is Issued Which Makes It Impossible For The Intended Completion Date To Be Achieved By The Contractor Without Taking Steps To Accelerate The Remaining Work, Which Would Cause The Contractor To Incur Additional Costs. No Payment Shall Be Made For Any Event Which May Warrant The Extension Of The Intended Completion Date. 26.2. The Procuring Entity’s Representative Shall Decide Whether And By How Much To Extend The Intended Completion Date Within Twenty One (21) Days Of The Contractor Asking The Procuring Entity’s Representative For A Decision Thereto After Fully Submitting All Supporting Information. If The Contractor Has Failed To Give Early Warning Of A Delay Or Has Failed To Cooperate In Dealing With A Delay, The Delay By This Failure Shall Not Be Considered In Assessing The New Intended Completion Date. 27. Right To Vary 27.1. The Procuring Entity’s Representative With The Prior Approval Of The Procuring Entity May Instruct Variations, Up To A Maximum Cumulative Amount Of Ten Percent (10%) Of The Original Contract Cost. 27.2. Variations Shall Be Valued As Follows: (a) At A Lump Sum Price Agreed Between The Parties; (b) Where Appropriate, At Rates In This Contract; (c) In The Absence Of Appropriate Rates, The Rates In This Contract Shall Be Used As The Basis For Valuation; Or Failing Which (d) At Appropriate New Rates, Equal To Or Lower Than Current Industry Rates And To Be Agreed Upon By Both Parties And Approved By The Head Of The Procuring Entity. 28. Contractor's Right To Claim If The Contractor Incurs Cost As A Result Of Any Of The Events Under Gcc Clause 13, The Contractor Shall Be Entitled To The Amount Of Such Cost. If As A Result Of Any Of The Said Events, It Is Necessary To Change The Works, This Shall Be Dealt With As A Variation. 29. Dayworks 29.1. Subject To Gcc Clause 43 On Variation Order, And If Applicable As Indicated In The Scc, The Day Works Rates In The Contractor’s Bid Shall Be Used For Small Additional Amounts Of Work Only When The Procuring Entity’s Representative Has Given Written Instructions In Advance For Additional Work To Be Paid For In That Way. 29.2. All Work To Be Paid For As Day Works Shall Be Recorded By The Contractor On Forms Approved By The Procuring Entity’s Representative. Each Completed Form Shall Be Verified And Signed By The Procuring Entity’s Representative Within Two Days Of The Work Being Done. 29.3. The Contractor Shall Be Paid For Day Works Subject To Obtaining Signed Dayworks Forms. 30. Early Warning 30.1. The Contractor Shall Warn The Procuring Entity’s Representative At The Earliest Opportunity Of Specific Likely Future Events Or Circumstances That May Adversely Affect The Quality Of The Work, Increase The Contract Price, Or Delay The Execution Of The Works. The Procuring Entity’s Representative May Require The Contractor To Provide An Estimate Of The Expected Effect Of The Future Event Or Circumstance On The Contract Price And Completion Date. The Estimate Shall Be Provided By The Contractor As Soon As Reasonably Possible. 30.2. The Contractor Shall Cooperate With The Procuring Entity’s Representative In Making And Considering Proposals For How The Effect Of Such An Event Or Circumstance Can Be Avoided Or Reduced By Anyone Involved In The Work And In Carrying Out Any Resulting Instruction Of The Procuring Entity’s Representative. 31. Program Of Work 31.1. Within The Time Stated In The Scc, The Contractor Shall Submit To The Procuring Entity’s Representative For Approval A Program Of Work Showing The General Methods, Arrangements, Order, And Timing For All The Activities In The Works. 31.2. An Update Of The Program Of Work Shall The Show The Actual Progress Achieved On Each Activity And The Effect Of The Progress Achieved On The Timing Of The Remaining Work, Including Any Changes To The Sequence Of The Activities. 31.3. The Contractor Shall Submit To The Procuring Entity’s Representative For Approval An Updated Program Of Work At Intervals No Longer Than The Period Stated In The Scc. If The Contractor Does Not Submit An Updated Program Of Work Within This Period, The Procuring Entity’s Representative May Withhold The Amount Stated In The Scc From The Next Payment Certificate And Continue To Withhold This Amount Until The Next Payment After The Date On Which The Overdue Program Of Work Has Been Submitted. 31.4. The Procuring Entity’s Representative’s Approval Of The Program Of Work Shall Not Alter The Contractor’s Obligations. The Contractor May Revise The Program Of Work And Submit It To The Procuring Entity’s Representative Again At Any Time. A Revised Program Of Work Shall Show The Effect Of Any Approved Variations. 31.5. When The Program Of Work Is Updated, The Contractor Shall Provide The Procuring Entity’s Representative With An Updated Cash Flow Forecast. The Cash Flow Forecast Shall Include Different Currencies, As Defined In The Contract, Converted As Necessary Using The Contract Exchange Rates. 31.6. All Variations Shall Be Included In Updated Program Of Work Produced By The Contractor. 32. Management Conferences 32.1. Either The Procuring Entity’s Representative Or The Contractor May Require The Other To Attend A Management Conference. The Management Conference Shall Review The Plans For Remaining Work And Deal With Matters Raised In Accordance With The Early Warning Procedure. 32.2. The Procuring Entity’s Representative Shall Record The Business Of Management Conferences And Provide Copies Of The Record To Those Attending The Conference And To The Procuring Entity . The Responsibility Of The Parties For Actions To Be Taken Shall Be Decided By The Procuring Entity’s Representative Either At The Management Conference Or After The Management Conference And Stated In Writing To All Who Attended The Conference. 33. Bill Of Quantities 33.1. The Bill Of Quantities Shall Contain Items Of Work For The Construction, Installation, Testing, And Commissioning Of Work To Be Done By The Contractor. 33.2. The Bill Of Quantities Is Used To Calculate The Contract Price. The Contractor Is Paid For The Quantity Of The Work Done At The Rate In The Bill Of Quantities For Each Item. 33.3. If The Final Quantity Of Any Work Done Differs From The Quantity In The Bill Of Quantities For The Particular Item And Is Not More Than Twenty Five Percent (25%) Of The Original Quantity, Provided The Aggregate Changes For All Items Do Not Exceed Ten Percent (10%) Of The Contract Price, The Procuring Entity’s Representative Shall Make The Necessary Adjustments To Allow For The Changes Subject To Applicable Laws, Rules, And Regulations. 33.4. If Requested By The Procuring Entity’s Representative, The Contractor Shall Provide The Procuring Entity’s Representative With A Detailed Cost Breakdown Of Any Rate In The Bill Of Quantities. 34. Instructions, Inspections And Audits 34.1. The Procuring Entity’s Personnel Shall At All Reasonable Times During Construction Of The Work Be Entitled To Examine, Inspect, Measure And Test The Materials And Workmanship, And To Check The Progress Of The Construction. 34.2. If The Procuring Entity’s Representative Instructs The Contractor To Carry Out A Test Not Specified In The Specification To Check Whether Any Work Has A Defect And The Test Shows That It Does, The Contractor Shall Pay For The Test And Any Samples. If There Is No Defect, The Test Shall Be A Compensation Event. 34.3. The Contractor Shall Permit The Funding Source Named In The Scc To Inspect The Contractor’s Accounts And Records Relating To The Performance Of The Contractor And To Have Them Audited By Auditors Appointed By The Funding Source, If So Required By The Funding Source. 35. Identifying Defects The Procuring Entity’s Representative Shall Check The Contractor’s Work And Notify The Contractor Of Any Defects That Are Found. Such Checking Shall Not Affect The Contractor’s Responsibilities. The Procuring Entity’s Representative May Instruct The Contractor To Search Uncover Defects And Test Any Work That The Procuring Entity’s Representative Considers Below Standards And Defective. 36. Cost Of Repairs Loss Or Damage To The Works Or Materials To Be Incorporated In The Works Between The Start Date And The End Of The Defects Liability Periods Shall Be Remedied By The Contractor At The Contractor’s Cost If The Loss Or Damage Arises From The Contractor’s Acts Or Omissions. 37. Correction Of Defects 37.1. The Procuring Entity’s Representative Shall Give Notice To The Contractor Of Any Defects Before The End Of The Defects Liability Period, Which Isone (1) Year From Project Completion Up To Final Acceptance By The Procuring Entity’s. 37.2. Every Time Notice Of A Defect Is Given, The Contractor Shall Correct The Notified Defect Within The Length Of Time Specified In The Procuring Entity’s Representative’s Notice. 37.3. The Contractor Shall Correct The Defects Which He Notices Himself Before The End Of The Defects Liability Period. 37.4. The Procuring Entity Shall Certify That All Defects Have Been Corrected. If The Procuring Entity Considers That Correction Of A Defect Is Not Essential, He Can Request The Contractor To Submit A Quotation For The Corresponding Reduction In The Contract Price. If The Procuring Entity Accepts The Quotation, The Corresponding Change In The Scc Is A Variation. 38. Uncorrected Defects 38.1. The Procuring Entity Shall Give The Contractor At Least Fourteen (14) Days Notice Of His Intention To Use A Third Party To Correct A Defect. If The Contractor Does Not Correct The Defect Himself Within The Period, The Procuring Entity May Have The Defect Corrected By The Third Party. The Cost Of The Correction Will Be Deducted From The Contract Price. 38.2. The Use Of A Third Party To Correct Defects That Are Uncorrected By The Contractor Will In No Way Relieve The Contractor Of Its Liabilities And Warranties Under The Contract. 39. Advance Payment 39.1. The Procuring Entity Shall, Upon A Written Request Of The Contractor Which Shall Be Submitted As A Contract Document, Make An Advance Payment To The Contractor In An Amount Not Exceeding Fifteen Percent (15%) Of The Total Contract Price, To Be Made In Lump Sum Or, At The Most Two, Installments According To A Schedule Specified In The Scc. 39.2. The Advance Payment Shall Be Made Only Upon The Submission To And Acceptance By The Procuring Entity Of An Irrevocable Standby Letter Of Credit Of Equivalent Value From A Commercial Bank, A Bank Guarantee Or A Surety Bond Callable Upon Demand, Issued By A Surety Or Insurance Company Duly Licensed By The Insurance Commission And Confirmed By The Procuring Entity. 39.3. The Advance Payment Shall Be Repaid By The Contractor By An Amount Equal To The Percentage Of The Total Contract Price Used For The Advance Payment. 39.4. The Contractor May Reduce His Standby Letter Of Credit Or Guarantee Instrument By The Amounts Refunded By The Monthly Certificates In The Advance Payment. 39.5. The Procuring Entity Will Provide An Advance Payment On The Contract Price As Stipulated In The Conditions Of Contract, Subject To The Maximum Amount Stated In Scc Clause 39.1. 40. Progress Payments 40.1. The Contractor May Submit A Request For Payment For Work Accomplished. Such Request For Payment Shall Be Verified And Certified By The Procuring Entity’s Representative/project Engineer. Except As Otherwise Stipulated In The Scc, Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Not Be Included For Payment. 40.2. The Procuring Entity Shall Deduct The Following From The Certified Gross Amounts To Be Paid To The Contractor As Progress Payment: (a) Cumulative Value Of The Work Previously Certified And Paid For. (b) Portion Of The Advance Payment To Be Recouped For The Month. (c) Retention Money In Accordance With The Condition Of Contract. (d) Amount To Cover Third Party Liabilities. (e) Amount To Cover Uncorrected Discovered Defects In The Works. 40.3. Payments Shall Be Adjusted By Deducting There From The Amounts For Advance Payments And Retention. The Procuring Entity Shall Pay The Contractor The Amounts Certified By The Procuring Entity’s Representative Within Twenty Eight (28) Days From The Date Each Certificate Was Issued. No Payment Of Interest For Delayed Payments And Adjustments Shall Be Made By The Procuring Entity. 40.4. The First Progress Payment May Be Paid By The Procuring Entity To The Contractor Provided That At Least Twenty Percent (20%) Of The Work Has Been Accomplished As Certified By The Procuring Entity’s Representative. 40.5. Items Of The Works For Which A Price Of “0” (zero) Has Been Entered Will Not Be Paid For By The Procuring Entity And Shall Be Deemed Covered By Other Rates And Prices In The Contract. 41. Payment Certificates 41.1. The Contractor Shall Submit To The Procuring Entity’s Representative Monthly Statements Of The Estimated Value Of The Work Executed Less The Cumulative Amount Certified Previously. 41.2. The Procuring Entity’s Representative Shall Check The Contractor’s Monthly Statement And Certify The Amount To Be Paid To The Contractor. 41.3. The Value Of Work Executed Shall: (a) Be Determined By The Procuring Entity’s Representative; (b) Comprise The Value Of The Quantities Of The Items In The Bill Of Quantities Completed; And (c) Include The Valuations Of Approved Variations. 41.4. The Procuring Entity’s Representative May Exclude Any Item Certified In A Previous Certificate Or Reduce The Proportion Of Any Item Previously Certified In Any Certificate In The Light Of Later Information. 42. Retention 42.1. The Procuring Entity Shall Retain From Each Payment Due To The Contractor An Amount Equal To A Percentage Thereof Using The Rate As Specified In Itb Sub-clause 42.2. 42.2. Progress Payments Are Subject To Retention Of Ten Percent (10%), Referred To As The “retention Money.” Such Retention Shall Be Based On The Total Amount Due To The Contractor Prior To Any Deduction And Shall Be Retained From Every Progress Payment Until Fifty Percent (50%) Of The Value Of Works, As Determined By The Procuring Entity, Are Completed. If, After Fifty Percent (50%) Completion, The Work Is Satisfactorily Done And On Schedule, No Additional Retention Shall Be Made; Otherwise, The Ten Percent (10%) Retention Shall Again Be Imposed Using The Rate Specified Therefore. 42.3. The Total “retention Money” Shall Be Due For Release Upon Final Acceptance Of The Works. The Contractor May, However, Request The Substitution Of The Retention Money For Each Progress Billing With Irrevocable Standby Letters Of Credit From A Commercial Bank, Bank Guarantees Or Surety Bonds Callable On Demand, Of Amounts Equivalent To The Retention Money Substituted For And Acceptable To The Procuring Entity, Provided That The Project Is On Schedule And Is Satisfactorily Undertaken. Otherwise, The Ten (10%) Percent Retention Shall Be Made. Said Irrevocable Standby Letters Of Credit, Bank Guarantees And/or Surety Bonds, To Be Posted In Favor Of The Government Shall Be Valid For A Duration To Be Determined By The Concerned Implementing Office/agency Or Procuring Entity And Will Answer For The Purpose For Which The Ten (10%) Percent Retention Is Intended, I.e., To Cover Uncorrected Discovered Defects And Third Party Liabilities. 42.4. On Completion Of The Whole Works, The Contractor May Substitute Retention Money With An “on Demand” Bank Guarantee In A Form Acceptable To The Procuring Entity. 43. Variation Orders 43.1. Variation Orders May Be Issued By The Procuring Entity To Cover Any Increase/decrease In Quantities, Including The Introduction Of New Work Items That Are Not Included In The Original Contract Or Reclassification Of Work Items That Are Either Due To Change Of Plans, Design Or Alignment To Suit Actual Field Conditions Resulting In Disparity Between The Preconstruction Plans Used For Purposes Of Bidding And The “as Staked Plans” Or Construction Drawings Prepared After A Joint Survey By The Contractor And The Procuring Entity After Award Of The Contract, Provided That The Cumulative Amount Of The Variation Order Does Not Exceed Ten Percent (10%) Of The Original Project Cost. The Addition/deletion Of Works Should Be Within The General Scope Of The Project As Bid And Awarded. The Scope Of Works Shall Not Be Reduced So As To Accommodate A Positive Variation Order. A Variation Order May Either Be In The Form Of A Change Order Or Extra Work Order. 43.2. A Change Order May Be Issued By The Procuring Entity To Cover Any Increase/decrease In Quantities Of Original Work Items In The Contract. 43.3. An Extra Work Order May Be Issued By The Procuring Entity To Cover The Introduction Of New Work Necessary For The Completion, Improvement Or Protection Of The Project Which Were Not Included As Items Of Work In The Original Contract, Such As, Where There Are Subsurface Or Latent Physical Conditions At The Site Differing Materially From Those Indicated In The Contract, Or Where There Are Duly Unknown Physical Conditions At The Site Of An Unusual Nature Differing Materially From Those Ordinarily Encountered And Generally Recognized As Inherent In The Work Or Character Provided For In The Contract. 43.4. Any Cumulative Variation Order Beyond Ten Percent (10%) Shall Be Subject Of Another Contract To Be Bid Out If The Works Are Separable From The Original Contract. In Exceptional Cases Where It Is Urgently Necessary To Complete The Original Scope Of Work, The Head Of The Procuring Entity May Authorize A Positive Variation Order Go Beyond Ten Percent (10%) But Not More Than Twenty Percent (20%) Of The Original Contract Price, Subject To The Guidelines To Be Determined By The Gppb: Provided, However, That Appropriate Sanctions Shall Be Imposed On The Designer, Consultant Or Official Responsible For The Original Detailed Engineering Design Which Failed To Consider The Variation Order Beyond Ten Percent (10%). 43.5. In Claiming For Any Variation Order, The Contractor Shall, Within Seven (7) Calendar Days After Such Work Has Been Commenced Or After The Circumstances Leading To Such Condition(s) Leading To The Extra Cost, And Within Twenty-eight (28) Calendar Days Deliver A Written Communication Giving Full And Detailed Particulars Of Any Extra Cost In Order That It May Be Investigated At That Time. Failure To Provide Either Of Such Notices In The Time Stipulated Shall Constitute A Waiver By The Contractor For Any Claim. The Preparation And Submission Of Variation Orders Are As Follows: (a) If The Procuring Entity’s Representative/project Engineer Believes That A Change Order Or Extra Work Order Should Be Issued, He Shall Prepare The Proposed Order Accompanied With The Notices Submitted By The Contractor, The Plans Therefore, His Computations As To The Quantities Of The Additional Works Involved Per Item Indicating The Specific Stations Where Such Works Are Needed, The Date Of His Inspections And Investigations Thereon, And The Log Book Thereof, And A Detailed Estimate Of The Unit Cost Of Such Items Of Work, Together With His Justifications For The Need Of Such Change Order Or Extra Work Order, And Shall Submit The Same To The Head Of The Procuring Entity For Approval. (b) The Head Of The Procuring Entity Or His Duly Authorized Representative, Upon Receipt Of The Proposed Change Order Or Extra Work Order Shall Immediately Instruct The Technical Staff Of The Procuring Entity’s To Conduct An On-the-spot Investigation To Verify The Need For The Work To Be Prosecuted. A Report Of Such Verification Shall Be Submitted Directly To The Head Of The Procuring Entity Or His Duly Authorized Representative. (c) The, Head Of The Procuring Entity Or His Duly Authorized Representative, After Being Satisfied That Such Change Order Or Extra Work Order Is Justified And Necessary, Shall Review The Estimated Quantities And Prices And Forward The Proposal With The Supporting Documentation To The Head Of Procuring Entity For Consideration. (d) If, After Review Of The Plans, Quantities And Estimated Unit Cost Of The Items Of Work Involved, The Proper Office Of The Procuring Entity Empowered To Review And Evaluate Change Orders Or Extra Work Orders Recommends Approval Thereof, Head Of The Procuring Entity Or His Duly Authorized Representative, Believing The Change Order Or Extra Work Order To Be In Order, Shall Approve The Same. (e) The Timeframe For The Processing Of Variation Orders From The Preparation Up To The Approval By The Head Of The Procuring Entity Concerned Shall Not Exceed Thirty (30) Calendar Days. 44. Contract Completion Once The Project Reaches An Accomplishment Of Ninety Five (95%) Of The Total Contract Amount, The Procuring Entity May Create An Inspectorate Team To Make Preliminary Inspection And Submit A Punch-list To The Contractor In Preparation For The Final Turnover Of The Project. Said Punch-list Will Contain, Among Others, The Remaining Works, Work Deficiencies For Necessary Corrections, And The Specific Duration/time To Fully Complete The Project Considering The Approved Remaining Contract Time. This, However, Shall Not Preclude The Claim Of The Procuring Entity For Liquidated Damages. 45. Suspension Of Work 45.1. The Procuring Entity Shall Have The Authority To Suspend The Work Wholly Or Partly By Written Order For Such Period As May Be Deemed Necessary, Due To Force Majeure Or Any Fortuitous Events Or For Failure On The Part Of The Contractor To Correct Bad Conditions Which Are Unsafe For Workers Or For The General Public, To Carry Out Valid Orders Given By The Procuring Entity Or To Perform Any Provisions Of The Contract, Or Due To Adjustment Of Plans To Suit Field Conditions As Found Necessary During Construction. The Contractor Shall Immediately Comply With Such Order To Suspend The Work Wholly Or Partly. 45.2. The Contractor Or Its Duly Authorized Representative Shall Have The Right To Suspend Work Operation On Any Or All Projects/activities Along The Critical Path Of Activities After Fifteen (15) Calendar Days From Date Of Receipt Of Written Notice From The Contractor To The District Engineer/regional Director/consultant Or Equivalent Official, As The Case May Be, Due To The Following: (a) There Exist Right-of-way Problems Which Prohibit The Contractor From Performing Work In Accordance With The Approved Construction Schedule. (b) Requisite Construction Plans Which Must Be Owner-furnished Are Not Issued To The Contractor Precluding Any Work Called For By Such Plans. (c) Peace And Order Conditions Make It Extremely Dangerous, If Not Possible, To Work. However, This Condition Must Be Certified In Writing By The Philippine National Police (pnp) Station Which Has Responsibility Over The Affected Area And Confirmed By The Department Of Interior And Local Government (dilg) Regional Director. (d) There Is Failure On The Part Of The Procuring Entity To Deliver Government-furnished Materials And Equipment As Stipulated In The Contract. (e) Delay In The Payment Of Contractor’s Claim For Progress Billing Beyond Forty-five (45) Calendar Days From The Time The Contractor’s Claim Has Been Certified To By The Procuring Entity’s Authorized Representative That The Documents Are Complete Unless There Are Justifiable Reasons Thereof Which Shall Be Communicated In Writing To The Contractor. 45.3. In Case Of Total Suspension, Or Suspension Of Activities Along The Critical Path, Which Is Not Due To Any Fault Of The Contractor, The Elapsed Time Between The Effective Order Of Suspending Operation And The Order To Resume Work Shall Be Allowed The Contractor By Adjusting The Contract Time Accordingly. 46. Payment On Termination 46.1. If The Contract Is Terminated Because Of A Fundamental Breach Of Contract By The Contractor, The Procuring Entity’s Representative Shall Issue A Certificate For The Value Of The Work Done And Materials Ordered Less Advance Payments Received Up To The Date Of The Issue Of The Certificate And Less The Percentage To Apply To The Value Of The Work Not Completed, As Indicated In The Scc. Additional Liquidated Damages Shall Not Apply. If The Total Amount Due To The Procuring Entity Exceeds Any Payment Due To The Contractor, The Difference Shall Be A Debt Payable To The Procuring Entity. 46.2. If The Contract Is Terminated For The Procuring Entity’s Convenience Or Because Of A Fundamental Breach Of Contract By The Procuring Entity, The Procuring Entity’s Representative Shall Issue A Certificate For The Value Of The Work Done, Materials Ordered, The Reasonable Cost Of Removal Of Equipment, Repatriation Of The Contractor’s Personnel Employed Solely On The Works, And The Contractor’s Costs Of Protecting And Securing The Works, And Less Advance Payments Received Up To The Date Of The Certificate. 46.3. The Net Balance Due Shall Be Paid Or Repaid Within Twenty Eight (28) Days From The Notice Of Termination. 46.4. If The Contractor Has Terminated The Contract Under Gcc Clauses 17 Or 18, The Procuring Entity Shall Promptly Return The Performance Security To The Contractor. 47. Extension Of Contract Time 47.1. Should The Amount Of Additional Work Of Any Kind Or Other Special Circumstances Of Any Kind Whatsoever Occur Such As To Fairly Entitle The Contractor To An Extension Of Contract Time, The Procuring Entity Shall Determine The Amount Of Such Extension; Provided That The Procuring Entity Is Not Bound To Take Into Account Any Claim For An Extension Of Time Unless The Contractor Has, Prior To The Expiration Of The Contract Time And Within Thirty (30) Calendar Days After Such Work Has Been Commenced Or After The Circumstances Leading To Such Claim Have Arisen, Delivered To The Procuring Entity Notices In Order That It Could Have Investigated Them At That Time. Failure To Provide Such Notice Shall Constitute A Waiver By The Contractor Of Any Claim. Upon Receipt Of Full And Detailed Particulars, The Procuring Entity Shall Examine The Facts And Extent Of The Delay And Shall Extend The Contract Time Completing The Contract Work When, In The Procuring Entity’s Opinion, The Findings Of Facts Justify An Extension. 47.2. No Extension Of Contract Time Shall Be Granted The Contractor Due To (a) Ordinary Unfavorable Weather Conditions And (b) Inexcusable Failure Or Negligence Of Contractor To Provide The Required Equipment, Supplies Or Materials. 47.3. Extension Of Contract Time May Be Granted Only When The Affected Activities Fall Within The Critical Path Of The Pert/cpm Network. 47.4. No Extension Of Contract Time Shall Be Granted When The Reason Given To Support The Request For Extension Was Already Considered In The Determination Of The Original Contract Time During The Conduct Of Detailed Engineering And In The Preparation Of The Contract Documents As Agreed Upon By The Parties Before Contract Perfection. 47.5. Extension Of Contract Time Shall Be Granted For Rainy/unworkable Days Considered Unfavorable For The Prosecution Of The Works At The Site, Based On The Actual Conditions Obtained At The Site, In Excess Of The Number Of Rainy/unworkable Days Pre-determined By The Procuring Entity In Relation To The Original Contract Time During The Conduct Of Detailed Engineering And In The Preparation Of The Contract Documents As Agreed Upon By The Parties Before Contract Perfection, And/or For Equivalent Period Of Delay Due To Major Calamities Such As Exceptionally Destructive Typhoons, Floods And Earthquakes, And Epidemics, And For Causes Such As Non-delivery On Time Of Materials, Working Drawings, Or Written Information To Be Furnished By The Procuring Entity, Non-acquisition Of Permit To Enter Private Properties Within The Right-of-way Resulting In Complete Paralyzation Of Construction Activities, And Other Meritorious Causes As Determined By The Procuring Entity’s Representative And Approved By The Head Of The Procuring Entity. Shortage Of Construction Materials, General Labor Strikes, And Peace And Order Problems That Disrupt Construction Operations Through No Fault Of The Contractor May Be Considered As Additional Grounds For Extension Of Contract Time Provided They Are Publicly Felt And Certified By Appropriate Government Agencies Such As Dti, Dole, Dilg, And Dnd, Among Others. The Written Consent Of Bondsmen Must Be Attached To Any Request Of The Contractor For Extension Of Contract Time And Submitted To The Procuring Entity For Consideration And The Validity Of The Performance Security Shall Be Correspondingly Extended. 48. Price Adjustment Except For Extraordinary Circumstances As Determined By Neda And Approved By The Gppb, No Price Adjustment Shall Be Allowed. Nevertheless, In Cases Where The Cost Of The Awarded Contract Is Affected By Any Applicable New Laws, Ordinances, Regulations, Or Other Acts Of The Gop, Promulgated After The Date Of Bid Opening, A Contract Price Adjustment Shall Be Made Or Appropriate Relief Shall Be Applied On A No Loss-no Gain Basis. 49. Completion The Contractor Shall Request The Procuring Entity’s Representative To Issue A Certificate Of Completion Of The Works, And The Procuring Entity’s Representative Will Do So Upon Deciding That The Work Is Completed. 50. Taking Over The Procuring Entity Shall Take Over The Site And The Works Within Seven (7) Days From The Date The Procuring Entity’s Representative Issues A Certificate Of Completion. 51. Operating And Maintenance Manuals 51.1. If “as Built” Drawings And/or Operating And Maintenance Manuals Are Required, The Contractor Shall Supply Them By The Dates Stated In The Scc. 51.2. If The Contractor Does Not Supply The Drawings And/or Manuals By The Dates Stated In The Scc, Or They Do Not Receive The Procuring Entity’s Representative’s Approval, The Procuring Entity’s Representative Shall Withhold The Amount Stated In The Scc From Payments Due To The Contractor. Section V. Special Conditions Of Contract Gcc Clause 1.16 The Intended Completion Date Is 60 Cd From Ntp. 1.21 The Procuring Entity Is Lgu- Mapanas, Northern Samar. 1.22 The Procuring Entity’s Representative Is Atty. Ronn Michael L. Tejano Municipal Mayor Municipality Of Mapanas Province Of Northern Samar 1.23 The Site Is Located At Mapanas, Northern Samar. 1.27 The Start Date Is: Upon Receipt Of Notice To Proceed. 1.30 The Works Consist Of: Item No. Scope Of Work Quantity Unit Rehabilitation / Improvement Of Longcop St. Barangay E. Laodenio, Mapanas, Northern Samar Part B Other General Requirements B.5 Projects Billboard/sign Board 1.00 Each B.7(2) Occupational Safety And Health Program 1.00 L.s B.9 Mobilization/demobilization 1.00 L.s Part C Earthworks 101(3)a.2 Removal Existing Pcc Pavement, 0.2m Thk (pcc Reblocking At Intermittent 410.00 Sq.m 102(2)b Surplus Common Excavation 123.00 Cu.m 105(1) Subgrade Preparation (common Materials) 492.00 Sq.m Part D Subbase And Base Course 200(1) Aggregate Subbase Course 89.30 Cu.m 201(1) Aggregate Base Course 98.40 Cu.m Part E Surface Courses 311(1)a.2 Pcc Pavement (plain) Convention Method, 200mm Thk 410.00 Sq.m 2.2 Note: The Items To Follow 5.1 The Procuring Entity Shall Give Possession Of All Parts Of The Site To The Contractor Upon The Issuance Of Notice To Proceed. 6.5 The Contractor Shall Employ The Following Key Personnel: Key Personnel Number Civil Engineer 1 Construction Foreman 1 Labor Workers 3 7.4(c) “no Further Instructions”. 7.7 No Further Instructions. 8.1 No Further Instructions. 10 The Site Investigation Reports Are: None 12.3 No Further Instructions. 12.5 In Case Of Semi-permanent Structures, Such As Buildings Of Types 1, 2, And 3 As Classified Under The National Building Code Of The Philippines, Concrete/asphalt Roads, Concrete River Control, Drainage, Irrigation Lined Canals, River Landing, Deep Wells, Rock Causeway, Pedestrian Overpass, And Other Similar Semi-permanent Structures: Five (5) Years. 13 “no Additional Provision.” 18.3(h)(i) No Further Instructions. 21.2 The Arbiter Is: Construction Industry Arbitration Commission 29.1 No Day Works Are Applicable To The Contract. 31.1 The Contractor Shall Submit The Program Of Work To The Procuring Entity’s Representative Within 15days Of Delivery Of The Letter Of Acceptance. 31.3 The Period Between Program Of Work Updates Is 15days. The Amount To Be Withheld For Late Submission Of An Updated Program Of Work Is P 1,000.00. 34.3 The Funding Source Is Coming From Nia 39.1 The Amount Of The Advance Payment Is 15% Of The Contract Price (lump Sum) And Shall Be Release Once Upon Presentation Of The Following Documents As Required: 1. Letter Request For Advance Payment From The Contractor 2. Bank Guarantee For Advance Payment 40.1 Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Be Included For Payment. 51.1 The Date By Which Operating And Maintenance Manuals Are Required Is Not Applicable. The Date By Which “as Built” Drawings Are Required Is 20 Days Upon Completion Of The Subproject. 51.2 The Amount To Be Withheld For Failing To Produce “as Built” Drawings And/or Operating And Maintenance Manuals By The Date Required Is P1,000.00. Section Vi. Specifications Project Name: Construction Of Siljagon Multi-purpose Gym Phase 2 Location : Brgy. Siljagon, Mapanas, Northern Samar Item No. Description Qty. Unit. B.5 Project Billboard/signboard Labor A.1 A. Construction Foreman 1 4.00 B. Skilled Laborer 1 4.00 C. Unskilled Laborer 2 4.00 Materials A. Tarpaulin (8’x8”) 1.00 Pc A.2 B. Coco Lumber 84.00 Bd.ft C. Plywood Marine (o0.0125m X 1.2m 2.44m) 2.00 Pc D. Assorted Common Wire Nail 0.05 Kg B.7(2) Occupational Safety And Health Program Labor A.1 A. Safety Practirioner/officer (part Time) 1 8.00 B. Health Personnel (full Time) 1 30.00 Equipment A. Safety Shoes 24.00 Man-day B.1 B. Safety Helmet 24.00 Man-day C. Safety/working Gloves 24.00 Man-day D. Safety Vest 24.00 Man-day E. Rubber Boots 23.00 Man-day F. Rain Coats (30% Of The Duration) Optional 8.00 Man-day B.9 Mobilization/demobilization Equipment B.1 A. Dump Truck (12 Cu.yd) 2 16.00 B. Payloader (1.5 Cu.m), Lx80-2c 1 16.00 C. Bulldozer, D6h Series Ii Psd/dd 1 16.00 D. Backhoe W/ Breaker (0.80 Cu.m 1 16.00 101(3)a.2 Removal Of Existing Pcc Pavement, 0.2m Thk, Pccp (reblocking Of Intermittent Section Labor A.1 A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 Equipment A. Backhoe With Breaker (0.80 Cu.m) 1.00 1 B.1 B. Payloader (1.50), Lx80 – 2c 1.00 1 C. Dump Truck (12 Cu Yd) 0.50 1 D. Concrete Saw (7.5 Hp), 14” Blade Dia 0.50 1 Minor Tools (10% Of Labor Cost) Materials F.1 A. Concrete Saw (diamond Blade 14” Dia) 0.00015 Pc 102(2)b Surplus Common Excavation Labor A.1 A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 Equipment A. Bulldozer, D6h Series Ii Psd/dd 1.00 1 B.1 B. Payloader (1.5 Cu.m) 1.00 1 C. Payloader (1.5 Cu.m) 0.30 1 D. Dump Truck, (12 Cy. Yd) 1.00 3 E. Backhoe (0.80 Cu.m) 1.00 1 105(1) Subgrade Preparation (common Materials) Labor A.1 A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 Equipment A. Motorized Road Grader, G710a 1.00 1 B.1 B. Vibratory Roller (10 M.t,) Sd100dc 1.00 1 C. Water Truck/pump (16000 L) 0.25 1 200(1) Aggregate Subbase Course A.1 A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 Equipment A. Motorized Road Grader, G710a 1.00 1 B.1 B. Vibratory Roller (10 M.t,) Sd100dc 1.00 1 C. Water Truck/pump (16000 L) 0.25 1 Materials B.2 A. Aggregate Subbase Course 1.15 Cu.m (w/ 15% Shrinkage Factor) 201(1) Aggregate Base Course A.1 A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 Equipment A. Motorized Road Grader, G710a 1.00 1 B.1 B. Vibratory Roller (10 M.t,) Sd100dc 1.00 1 C. Water Truck/pump (16000 L) 0.25 1 Materials B.2 A. Aggregate Subbase Course 1.15 Cu.m (w/ 15% Shrinkage Factor) 311(1)a.2 Pcc Pavement (plain) – Conventional Method, 200mm Thk A.1 A. Construction Foreman 1.00 1 B. Skilled Laborer 1.00 4 C. Skilled Labore 1.00 12 Equipment A. Transit Mixer 1.00 B.1 B. Concrete Vibrator 1.00 C. Concrete Batch Plant (30 Cu.m) 1.00 D. Payloader (1.50 Cu.m)lx80-2c 1.00 E. Concrete Screeder (5.5hp) 1.00 F. Water Truck/pump 1.00 G. Concrete Saw Blade 14’ (7.5hp) 1.00 H. Bar Cutter, Single Phase 0.10 I. Joint Sealer Machine 0.25 Minor Tools (5% Of Labor) Materials A. Reinforcing Steel Bar 0.39 Kg B. Curing Compound 0.29 Lit C. Asphalt Sealant 0.12 Lit D. Steel Form 0.46 L.m E. Sand 0.1100 Cu.m F. Gravel 0.20 Cu.m G. Portland Cement 1.90 Bag H. Concrete Saw (diamond 0.00015 Pc I. Joint Sealer Machine 0.0086 L.m Minor Tools (5% Of Labor) 0.0056 Lit Section Vii. Drawings Bill Of Quantities Item No. Scope Of Work Quantity Unit Unit Cost Total Amount Rehabilitation / Improvement Of Longcop St. Barangay E. Laodenio, Mapanas, Northern Samar Part B Other General Requirements B.5 Projects Billboard/sign Board 1.00 Each 10, 959.69 10, 959.69 B.7(2) Occupational Safety And Health Program 1.00 L.s 25, 530.73 25, 530.73 B.9 Mobilization/demobilization 1.00 L.s 11, 556.91 11, 556.91 Part C Earthworks 101(3)a.2 Removal Existing Pcc Pavement, 0.2m Thk (pcc Reblocking At Intermittent 410.00 Sq.m 238.30 97, 703.00 102(2)b Surplus Common Excavation 123.00 Cu.m 204.24 25, 121.52 105(1) Subgrade Preparation (common Materials) 492.00 Sq.m 21.14 10, 400.88 Part D Subbase And Base Course 200(1) Aggregate Subbase Course 89.30 Cu.m 1, 632.8 145, 771.53 201(1) Aggregate Base Course 98.40 Cu.m 2, 843.65 279, 815.16 Part E Surface Courses 311(1)a.2 Pcc Pavement (plain) – Conventional Method 200m, Thk 410.00 Sq.m 2, 160.51 885, 809.10 Total 1, 492,668.52 Total Cost Of All Line Item Includes Cost Of Contractor’s Profit, Taxes And Ocm. Attached Detailed Cost Estimates Section Ix. Bidding Forms Table Of Contents Bid Form 79 Form Of Contract Agreement 81 Omnibus Sworn Statement 83 Bid Form Date: Iaeb No: To: Lgu-mapanas Northern Samar Address: Mapanas Northern Samar We, The Undersigned, Declare That: We Have Examined And Have No Reservation To The Bidding Documents, Including Addenda, For The Contract Rehabilitation / Improvement , Mapanas Of Longcop St Barangay E. Laodenio Mapanas N. Samar (a) We Offer To Execute The Works For This Contract In Accordance With The Bid And Bid Data Sheet, General And Special Conditions Of Contract Accompanying This Bid; The Total Price Of Our Bid, Excluding Any Discounts Offered In Item (d) Below Is: [insert Information]; The Discounts Offered And The Methodology For Their Application Are: [insert Information]; (b) Our Bid Shall Be Valid For A Period Of 120 Days From The Date Fixed For The Bid Submission Deadline In Accordance With The Bidding Documents, And It Shall Remain Binding Upon Us And May Be Accepted At Any Time Before The Expiration Of That Period; (c) If Our Bid Is Accepted, We Commit To Obtain A Performance Security In The Amount Of [insert Percentage Amount] Percent Of The Contract Price For The Due Performance Of The Contract; (d) Our Firm, Including Any Subcontractors Or Suppliers For Any Part Of The Contract, Have Nationalities From The Following Eligible Countries: [insert Information]; (e) We Are Not Participating, As Bidders, In More Than One Bid In This Bidding Process, Other Than Alternative Offers In Accordance With The Bidding Documents; (f) Our Firm, Its Affiliates Or Subsidiaries, Including Any Subcontractors Or Suppliers For Any Part Of The Contract, Has Not Been Declared Ineligible By The Funding Source; (g) We Understand That This Bid, Together With Your Written Acceptance Thereof Included In Your Notification Of Award, Shall Constitute A Binding Contract Between Us, Until A Formal Contract Is Prepared And Executed; And (h) We Understand That You Are Not Bound To Accept The Lowest Evaluated Bid Or Any Other Bid That You May Receive. Name: In The Capacity Of: Signed: Duly Authorized To Sign The Bid For And On Behalf Of: Date: ___________ Form Of Contract Agreement This Agreement, Made This [insert Date] Day Of [insert Month], [insert Year] Between [name And Address Of Procuring Entity](hereinafter Called The “entity”) And [name And Address Of Contractor] (hereinafter Called The “contractor”). Whereas, The Entity Is Desirous That The Contractor Execute [name And Identification Number Of Contract] (hereinafter Called “the Works”) And The Entity Has Accepted The Bid For [insert The Amount In Specified Currency In Numbers And Words] By The Contractor For The Execution And Completion Of Such Works And The Remedying Of Any Defects Therein. Now This Agreement Witnesseth As Follows: 1. In This Agreement, Words And Expressions Shall Have The Same Meanings As Are Respectively Assigned To Them In The Conditions Of Contract Hereinafter Referred To. 2. The Following Documents Shall Be Attached, Deemed To Form, And Be Read And Construed As Part Of This Agreement, To Wit: (a) General And Special Conditions Of Contract; (b) Drawings/plans; (c) Specifications; (d) Invitation To Apply For Eligibility And To Bid; (e) Instructions To Bidders; (f) Bid Data Sheet; (g) Addenda And/or Supplemental/bid Bulletins, If Any; (h) Bid Form, Including All The Documents/statements Contained In The Bidder’s Bidding Envelopes, As Annexes; (i) Eligibility Requirements, Documents And/or Statements; (j) Performance Security; (k) Credit Line Issued By A Licensed Bank, If Any; (l) Notice Of Award Of Contract And The Bidder’s Conforme Thereto; (m) Other Contract Documents That May Be Required By Existing Laws And/or The Entity. 3. In Consideration Of The Payments To Be Made By The Entity To The Contractor As Hereinafter Mentioned, The Contractor Hereby Covenants With The Entity To Execute And Complete The Works And Remedy Any Defects Therein In Conformity With The Provisions Of This Contract In All Respects. 4. The Entity Hereby Covenants To Pay The Contractor In Consideration Of The Execution And Completion Of The Works And The Remedying Of Defects Wherein, The Contract Price Or Such Other Sum As May Become Payable Under The Provisions Of This Contract At The Times And In The Manner Prescribed By This Contract. In Witness Whereof The Parties Thereto Have Caused This Agreement To Be Executed The Day And Year First Before Written. Signed, Sealed, Delivered By The (for The Entity) Signed, Sealed, Delivered By The (for The Contractor). Binding Signature Of Procuring Entity ________________________________________________ Binding Signature Of Contractor _____________________________________________ [addendum Showing The Corrections, If Any, Made During The Bid Evaluation Should Be Attached With This Agreement] Omnibus Sworn Statement Republic Of The Philippines ) City/municipality Of ______ ) S.s. Affidavit I, [name Of Affiant], Of Legal Age, [civil Status], [nationality], And Residing At [address Of Affiant], After Having Been Duly Sworn In Accordance With Law, Do Hereby Depose And State That: 1. Select One, Delete The Other: If A Sole Proprietorship: I Am The Sole Proprietor Of [name Of Bidder] With Office Address At [address Of Bidder]; If A Partnership, Corporation, Cooperative, Or Joint Venture: I Am The Duly Authorized And Designated Representative Of [name Of Bidder] With Office Address At [address Of Bidder]; 2. Select One, Delete The Other: If A Sole Proprietorship: As The Owner And Sole Proprietor Of [name Of Bidder], I Have Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary To Represent It In The Bidding For [name Of The Project] Of The [name Of The Procuring Entity]; If A Partnership, Corporation, Cooperative, Or Joint Venture: I Am Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary And/or To Represent The [name Of Bidder] In The Bidding As Shown In The Attached [state Title Of Attached Document Showing Proof Of Authorization (e.g., Duly Notarized Secretary’s Certificate Issued By The Corporation Or The Members Of The Joint Venture)]; 3. [name Of Bidder] Is Not “blacklisted” Or Barred From Bidding By The Government Of The Philippines Or Any Of Its Agencies, Offices, Corporations, Or Local Government Units, Foreign Government/foreign Or International Financing Institution Whose Blacklisting Rules Have Been Recognized By The Government Procurement Policy Board; 4. Each Of The Documents Submitted In Satisfaction Of The Bidding Requirements Is An Authentic Copy Of The Original, Complete, And All Statements And Information Provided Therein Are True And Correct; 5. [name Of Bidder]is Authorizing The Head Of The Procuring Entity Or Its Duly Authorized Representative(s) To Verify All The Documents Submitted; 6. Select One, Delete The Rest: If A Sole Proprietorship: I Am Not Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; If A Partnership Or Cooperative: None Of The Officers And Members Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; If A Corporation Or Joint Venture: None Of The Officers, Directors, And Controlling Stockholders Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; 7. [name Of Bidder] Complies With Existing Labor Laws And Standards; And 8. [name Of Bidder] Is Aware Of And Has Undertaken The Following Responsibilities As A Bidder: A) Carefully Examine All Of The Bidding Documents; B) Acknowledge All Conditions, Local Or Otherwise, Affecting The Implementation Of The Contract; C) Made An Estimate Of The Facilities Available And Needed For The Contract To Be Bid, If Any; And D) Inquire Or Secure Supplemental/bid Bulletin(s) Issued For The [name Of The Project]. In Witness Whereof, I Have Hereunto Set My Hand This __ Day Of ___, 20__ At ____________, Philippines. _____________________________________ Bidder’s Representative/authorized Signatory [jurat] * This Form Will Not Apply For Wb Funded Projects.
Closing Date16 Dec 2024
Tender AmountPHP 1.4 Million (USD 25.2 K)
Municipality Of Mapanas, Northern Samar Tender
Civil And Construction...+1Civil Works Others
Philippines
Details: Description Bidding Documents Procurement Of Infrastructure Projects Name Of Project: Rehabilitation/improvement Of Aquino St. And San Miguel Barangay Santa Potenciana, Mapanas Northern Samar Contract Reference No. 2024-11-107 Table Of Contents Section I. Invitation To Bid 3 Section Ii. Instructions To Bidders 7 Section Iii. Bid Data Sheet 35 Section Iv. General Conditions Of Contract 38 Section V. Special Conditions Of Contract 70 Section Vi. Specifications 72 Section Vii. Drawings 75 Section Viii. Bill Of Quantities Error! Bookmark Not Defined. Section Ix. Bidding Forms 77 Section X. Foreign-assisted Projects Error! Bookmark Not Defined. Section I. Invitation To Bid Bid Notice Abstract Invitation To Bid (itb) Republic Of The Philippines Province Of Northern Samar Municipality Of Mapanas Invitation To Bid For Project: Rehabilitation/improvement Of Aquino St. And San Miguel, Brgy. Santa Potenciana, Mapanas, Northern Samar The Lgu- Mapanas, Northern Samar, Through The Economic Development Fund Of Fy 2025 Intends To Apply The Sum Of One Million Nine Hundred Eighty Five Thousand One Hundred Seventy Two Pesos 32/100 Only (1,985,172.32) Being The Approved Budget For The Contract (abc) To Payments Under The Contract For : Rehabilitation/improvement Of Aquino St. And San Miguel, Brgy. Santa Potenciana, Mapanas, Northern Samar Bids Received In Excess Of The Abc Shall Be Automatically Rejected At Bid Opening. 1. The Lgu- Mapanas, Northern Samar Now Invites Bids For The Following Description Of Works To Be Procured: Item No. Scope Of Work Quantity Unit Rehabilitation/improvement Of Aquino St. And San Miguel, Brgy. Santa Potenciana, Mapanas, Northern Samar B.5 Project Billboard/signboard 1.00 Each B.7 (2) Occupational Safety And Health Program 1.00 L.s. B.9 Mobilization And Demobiliation 1.00 L.s. 101 (3)a.2 Removal Of Existing Pcc Pavement, 0.2m Thk, Pccp (for Reblocking At Intermittent Section) 539.00 Sq.m. 102 (2)b Surplus Common Excavation 162.00 Cu.m. 105 (1) Subgrade Preparation (common Material) 648.00 Sq.m. 200 (1) Aggregate Subbase Course 115.20 Cu.m. 201 (1) Aggregate Base Course 140.40 Cu.m. 311 (1)a.2 Pcc Pavement (plain)-conventional Method, 200mm Thk. 540.00 Sq.m. Completion Of The Works Is Required 75 Calendar Days. Bidders Should Have Completed, Within Ten (10) Years From The Date Of Submission And Receipt Of Bids, A Contract Similar To The Project. The Description Of An Eligible Bidder Is Contained In The Bidding Documents, Particularly, In Section Ii. Instructions To Bidders. Section Ii. Instructions To Bidders. 2. Bidding Will Be Conducted Through Open Competitive Bidding Procedures Using Non-discretionary Pass/fail Criterion As Specified In The Implementing Rules And Regulations (irr) Of Republic Act 9184 (ra 9184), Otherwise Known As The “government Procurement Reform Act”. Bidding Is Restricted To Filipino Citizens/sole Proprietorships, Partnerships, Or Organizations With At Least Seventy Five Percent (75%) Interest Or Outstanding Capital Stock Belonging To Citizens Of The Philippines. 4. Interested Bidders May Obtain Further Information From Lgu- Bac Mapanas, Northern Samar And Inspect The Bidding Documents At The Address Given Below From December 05, 2024-december 16, 2024, 8:00 A.m. To 5:00 Pm. A Complete Set Of Bidding Documents May Be Purchased By Interested Bidders From The Address Below And Upon Payment Of A Nonrefundable Fee For The Bidding Documents In The Amount Of P5,000.00. It May Also Be Downloaded Free Of Charge From The Website Of The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity, Provided That Bidders Shall Pay The Fee For The Bidding Documents Not Later That The Submission Of Their Bids. 5. The Lgu- Mapana, Northern Samar Will Hold A Pre-bid Conference On December 5, 2024 At 10:00 A.m. At Executive Conference, 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar, Which Shall Be Open Only To All Interested Parties Who Have Purchased The Bidding Documents. 6. Bids Must Be Delivered To The Address Below On Or Before 9:00 A.m. Of December 16, 2024 At Bac Office, @ Municipal Planning & Development Office (mpdo), Mapanas, Northern Samar. All Bids Must Be Accompanied By A Bid Security In Any Of The Acceptable Forms And In The Amount Stated In Itb Clause 18. Bids Will Be Opened In The Presence Of The Bidders’ Authorized Representatives Who Choose To Attend At The Address Below. Late Bids Shall Not Be Accepted. The Bidder May Request That The Bid Documents Be Sent To Them By Mail Or Courier, And For This, The Bidder Shall Pay The Amount In Philippine Peso To Cover The Cost Of Mail Or Courier Delivery. The Fee For Obtaining A Copy Of The Bid Documents And The Cost Of Mail Or Courier Shall Be Paid By The Bidder Thru S Cashier’s Check Or Manager’s Check Issued In Favor Of The Municipality Of Mapanas. 7. The Lgu- Mapanas, Northern Samar Reserves The Right To Accept Or Reject Any Bid, To Annul The Bidding Process, And To Reject All Bids At Any Time Prior To Contract Award, Without Thereby Incurring Any Liability To The Affected Bidder Or Bidders. 8. For Further Information, Please Refer To: Reno C. Salazar Bac Secretary Mapanas, Northern Samar Mobile # 09459852914 Ma. Teresa L. Minguez Bac Chairperson Mapanas, Northern Samar Mobile # 09778033758 Section Ii. Instructions To Bidders 1. The Bids Must Be Delivered On Or Before December 16, 2024 At 9:00 A.m And Failure To Submit The Bid Proposal May Ground For Disqualification Of The Bid. 2. Bids Received In Excess Of The Abc Shall Be Automatically Rejected At Bid Opening. 1. The Lgu- Mapanas, Northern Samar Now Invites Bids For The Following Description Of Works To Be Procured: Item No. Scope Of Work Quantity Unit Rehabilitation/improvement Of Aquino St. And San Miguel, Brgy. Santa Potenciana, Mapanas, Northern Samar B.5 Project Billboard/signboard 1.00 Each B.7 (2) Occupational Safety And Health Program 1.00 L.s. B.9 Mobilization And Demobiliation 1.00 L.s. 101 (3)a.2 Removal Of Existing Pcc Pavement, 0.2m Thk, Pccp (for Reblocking At Intermittent Section) 539.00 Sq.m. 102 (2)b Surplus Common Excavation 162.00 Cu.m. 105 (1) Subgrade Preparation (common Material) 648.00 Sq.m. 200 (1) Aggregate Subbase Course 115.20 Cu.m. 201 (1) Aggregate Base Course 140.40 Cu.m. 311 (1)a.2 Pcc Pavement (plain)-conventional Method, 200mm Thk. 540.00 Sq.m. Completion Of The Works Is Required 75 Calendar Days. Bidders Should Have Completed, Within Ten (10) Years From The Date Of Submission And Receipt Of Bids, A Contract Similar To The Project. The Description Of An Eligible Bidder Is Contained In The Bidding Documents, Particularly, In Section Ii. Instructions To Bidders. 2. Bidding Will Be Conducted Through Open Competitive Bidding Procedures Using Non-discretionary Pass/fail Criterion As Specified In The Implementing Rules And Regulations (irr) Of Republic Act 9184 (ra 9184), Otherwise Known As The “government Procurement Reform Act”. Bidding Is Restricted To Filipino Citizens/sole Proprietorships, Partnerships, Or Organizations With At Least Seventy Five Percent (75%) Interest Or Outstanding Capital Stock Belonging To Citizens Of The Philippines. 3. Interested Bidders May Obtain Further Information From Lgu- Bac Mapanas, Northern Samar And Inspect The Bidding Documents At The Address Given Below From November 26, 2024-december 13, 2024, 8:00 A.m. To 5:00 Pm. A Complete Set Of Bidding Documents May Be Purchased By Interested Bidders From The Address Below And Upon Payment Of A Nonrefundable Fee For The Bidding Documents In The Amount Of P5,000.00. It May Also Be Downloaded Free Of Charge From The Website Of The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity, Provided That Bidders Shall Pay The Fee For The Bidding Documents Not Later That The Submission Of Their Bids. 4. The Lgu- Mapanas, Northern Samar Will Hold A Pre-bid Conference On December 5, 2024 At 10:00 A.m. At Executive Conference, 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar, Which Shall Be Open Only To All Interested Parties Who Have Purchased The Bidding Documents. 5. Bids Must Be Delivered To The Address Below On Or Before 9:00 A.m. Of December 16, 2024 At Bac Office, @ Municipal Planning & Development Office (mpdo), Mapanas, Northern Samar. All Bids Must Be Accompanied By A Bid Security In Any Of The Acceptable Forms And In The Amount Stated In Itb Clause 18. Bids Will Be Opened In The Presence Of The Bidders’ Authorized Representatives Who Choose To Attend At The Address Below. Late Bids Shall Not Be Accepted. The Bidder May Request That The Bid Documents Be Sent To Them By Mail Or Courier, And For This, The Bidder Shall Pay The Amount In Philippine Peso To Cover The Cost Of Mail Or Courier Delivery. The Fee For Obtaining A Copy Of The Bid Documents And The Cost Of Mail Or Courier Shall Be Paid By The Bidder Thru S Cashier’s Check Or Manager’s Check Issued In Favor Of The Municipality Of Mapanas. 6. The Lgu- Mapanas, Northern Samar Reserves The Right To Accept Or Reject Any Bid, To Annul The Bidding Process, And To Reject All Bids At Any Time Prior To Contract Award, Without Thereby Incurring Any Liability To The Affected Bidder Or Bidders. 7. For Further Information, Please Refer To: Reno C. Salazar Bac Secretary Mapanas, Northern Samar Mobile # 09459852914 Ma. Teresa L. Minguez Bac Chairperson Mapanas N. Samar Mobile # 09778033758 Table Of Contents A. General 11 1. Scope Of Bid 11 2. Source Of Funds 11 3. Corrupt, Fraudulent, Collusive, And Coercive Practices 11 4. Conflict Of Interest 12 5. Eligible Bidders 14 6. Bidder’s Responsibilities 15 7. Origin Of Goods And Services 17 8. Subcontracts 17 B. Contents Of Bidding Documents 17 9. Pre-bid Conference 17 10. Clarification And Amendment Of Bidding Documents 18 C. Preparation Of Bids 18 11. Language Of Bids 18 12. Documents Comprising The Bid: Eligibility And Technical Components 18 13. Documents Comprising The Bid: Financial Component 21 14. Alternative Bids 21 15. Bid Prices 22 16. Bid Currencies 22 17. Bid Validity 23 18. Bid Security 23 19. Format And Signing Of Bids 25 20. Sealing And Marking Of Bids 26 D. Submission And Opening Of Bids 26 21. Deadline For Submission Of Bids 26 22. Late Bids 26 23. Modification And Withdrawal Of Bids 27 24. Opening And Preliminary Examination Of Bids 27 E. Evaluation And Comparison Of Bids 28 25. Process To Be Confidential 28 26. Clarification Of Bids 29 27. Detailed Evaluation And Comparison Of Bids 29 28. Post Qualification 30 29. Reservation Clause 31 F. Award Of Contract 32 30. Contract Award 32 31. Signing Of The Contract 33 32. Performance Security 33 33. Notice To Proceed 34 A. General 1. Scope Of Bid 1.1. The Procuring Entity As Defined In The Bds, Invites Bids For The Construction Of Works, As Described In Section Vi. Specifications. The Name And Identification Number Of The Contract Is Provided In The Bds. 1.2. The Successful Bidder Will Be Expected To Complete The Works By The Intended Completion Date Specified In Scc Clause 1.16. 2. Source Of Funds The Procuring Entity Has A Budget Or Has Applied For Or Received Funds From The Funding Source Named In The Bds, And In The Amount Indicated In The Bds. It Intends To Apply Part Of The Funds Received For The Project, As Defined In The Bds, To Cover Eligible Payments Under The Contract For The Works. 3. Corrupt, Fraudulent, Collusive, And Coercive Practices 3.1. Unless Otherwise Specified In The Bds, The Procuring Entity, As Well As Bidders And Contractors, Shall Observe The Highest Standard Of Ethics During The Procurement And Execution Of The Contract. In Pursuance Of This Policy, The Funding Source: (a) Defines, For Purposes Of This Provision, The Terms Set Forth Below As Follows: (i) "corrupt Practice" Means Behavior On The Part Of Officials In The Public Or Private Sectors By Which They Improperly And Unlawfully Enrich Themselves, Others, Or Induce Others To Do So, By Misusing The Position In Which They Are Placed, And Includes The Offering, Giving, Receiving, Or Soliciting Of Anything Of Value To Influence The Action Of Any Such Official In The Procurement Process Or In Contract Execution; Entering, On Behalf Of The Procuring Entity, Into Any Contract Or Transaction Manifestly And Grossly Disadvantageous To The Same, Whether Or Not The Public Officer Profited Or Will Profit Thereby, And Similar Acts As Provided In Republic Act 3019; (ii) "fraudulent Practice" Means A Misrepresentation Of Facts In Order To Influence A Procurement Process Or The Execution Of A Contract To The Detriment Of The Procuring Entity, And Includes Collusive Practices Among Bidders (prior To Or After Bid Submission) Designed To Establish Bid Prices At Artificial, Non-competitive Levels And To Deprive The Procuring Entity Of The Benefits Of Free And Open Competition; (iii) “collusive Practices” Means A Scheme Or Arrangement Between Two Or More Bidders, With Or Without The Knowledge Of The Procuring Entity, Designed To Establish Bid Prices At Artificial, Non-competitive Levels; And (iv) “coercive Practices” Means Harming Or Threatening To Harm, Directly Or Indirectly, Persons, Or Their Property To Influence Their Participation In A Procurement Process, Or Affect The Execution Of A Contract; (v) “obstructive Practice” Is (aa) Deliberately Destroying, Falsifying, Altering Or Concealing Of Evidence Material To An Administrative Proceedings Or Investigation Or Making False Statements To Investigators In Order To Materially Impede An Administrative Proceedings Or Investigation Of The Procuring Entity Or Any Foreign Government/foreign Or International Financing Institution Into Allegations Of A Corrupt, Fraudulent, Coercive Or Collusive Practice; And/or Threatening, Harassing Or Intimidating Any Party To Prevent It From Disclosing Its Knowledge Of Matters Relevant To The Administrative Proceedings Or Investigation Or From Pursuing Such Proceedings Or Investigation; Or (bb) Acts Intended To Materially Impede The Exercise Of The Inspection And Audit Rights Of The Procuring Entity Or Any Foreign Government/foreign Or International Financing Institution Herein. (b) Will Reject A Proposal For Award If It Determines That The Bidder Recommended For Award Has Engaged In Corrupt Or Fraudulent Practices In Competing For The Contract; And (c) Will Declare A Firm Ineligible, Either Indefinitely Or For A Stated Period Of Time, To Be Awarded Contract Funded By The Funding Source If It At Any Time Determines That The Firm Has Engaged In Corrupt Or Fraudulent Practices In Competing Or, Or In Executing, A Contract Funded By The Funding Source. 3.2. Further, The Procuring Entity Will Seek To Impose The Maximum Civil, Administrative, And/or Criminal Penalties Available Under The Applicable Laws On Individuals And Organizations Deemed To Be Involved In Any Of The Practices Mentioned In Itb Clause 3.1(a). 3.3. Furthermore, The Funding Source And The Procuring Entity Reserve The Right To Inspect And Audit Records And Accounts Of A Contractor In The Bidding For And Performance Of A Contract Themselves Or Through Independent Auditors As Reflected In The Gcc Clause 34. 4. Conflict Of Interest 4.1. All Bidders Found To Have Conflicting Interests Shall Be Disqualified To Participate In The Procurement At Hand, Without Prejudice To The Imposition Of Appropriate Administrative, Civil, And Criminal Sanctions. A Bidder May Be Considered To Have Conflicting Interests With Another Bidder In Any Of The Events Described In Paragraphs (a) Through (c) And A General Conflict Of Interest In Any Of The Circumstances Set Out In Paragraphs (d) Through (g) Below: (a) A Bidder Has Controlling Shareholders In Common With Another Bidder; (b) A Bidder Receives Or Has Received Any Direct Or Indirect Subsidy From Any Other Bidder; (c) A Bidder Has The Same Legal Representative As That Of Another Bidder For Purposes Of This Bid; (d) A Bidder Has A Relationship, Directly Or Through Third Parties, That Puts Them In A Position To Have Access To Information About Or Influence On The Bid Of Another Bidder Or Influence The Decisions Of The Procuring Entity Regarding This Bidding Process. This Will Include A Firm Or An Organization Who Lends, Or Temporarily Seconds, Its Personnel To Firms Or Organizations Which Are Engaged In Consulting Services For The Preparation Related To Procurement For Or Implementation Of The Project If The Personnel Would Be Involved In Any Capacity On The Same Project; (e) A Bidder Submits More Than One Bid In This Bidding Process. However, This Does Not Limit The Participation Of Subcontractors In More Than One Bid; (f) A Bidder Who Participated As A Consultant In The Preparation Of The Design Or Technical Specifications Of The Goods And Related Services That Are The Subject Of The Bid; Or (g) A Bidder Who Lends, Or Temporary Seconds, Its Personnel To Firms Or Organizations Which Are Engaged In Consulting Services For The Preparation Related To Procurement For Or Implementation Of The Project, If The Personnel Would Be Involved In Any Capacity On The Same Project. 4.2. In Accordance With Section 47 Of The Irr Of Ra 9184, All Bidding Documents Shall Be Accompanied By A Sworn Affidavit Of The Bidder That It Is Not Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), Members Of The Technical Working Group (twg), Members Of The Bac Secretariat, The Head Of The Project Management Office (pmo) Or The End-user Unit, And The Project Consultants, By Consanguinity Or Affinity Up To The Third Civil Degree. On The Part Of The Bidder, This Clause Shall Apply To The Following Persons: (a) If The Bidder Is An Individual Or A Sole Proprietorship, To The Bidder Himself; (b) If The Bidder Is A Partnership, To All Its Officers And Members; (c) If The Bidder Is A Corporation, To All Its Officers, Directors, And Controlling Stockholders; And (d) If The Bidder Is A Joint Venture (jv), The Provisions Of Items (a), (b), Or (c) Of This Clause Shall Correspondingly Apply To Each Of The Members Of The Said Jv, As May Be Appropriate. Relationship Of The Nature Described Above Or Failure To Comply With This Clause Will Result In The Automatic Disqualification Of A Bidder. 5. Eligible Bidders 5.1. Unless Otherwise Indicated In The Bds, The Following Persons Shall Be Eligible To Participate In This Bidding: (a) Duly Licensed Filipino Citizens/sole Proprietorships; (b) Partnerships Duly Organized Under The Laws Of The Philippines And Of Which At Least Seventy Five Percent (75%) Of The Interest Belongs To Citizens Of The Philippines; (c) Corporations Duly Organized Under The Laws Of The Philippines, And Of Which At Least Seventy Five Percent (75%) Of The Outstanding Capital Stock Belongs To Citizens Of The Philippines; (d) Cooperatives Duly Organized Under The Laws Of The Philippines, And Of Which At Least Seventy Five Percent (75%) Of The Interest Belongs To Citizens Of The Philippines; And (e) Persons/entities Forming Themselves Into A Jv, I.e., A Group Of Two (2) Or More Persons/entities That Intend To Be Jointly And Severally Responsible Or Liable For A Particular Contract: Provided, However, That, In Accordance With Letter Of Instructions No. 630, Filipino Ownership Or Interest Of The Joint Venture Concerned Shall Be At Least Seventy Five Percent (75%): Provided, Further, That Joint Ventures In Which Filipino Ownership Or Interest Is Less Than Seventy Five Percent (75%) May Be Eligible Where The Structures To Be Built Require The Application Of Techniques And/or Technologies Which Are Not Adequately Possessed By A Person/entity Meeting The Seventy Five Percent (75%) Filipino Ownership Requirement: Provided, Finally, That In The Latter Case, Filipino Ownership Or Interest Shall Not Be Less Than Twenty Five Percent (25%). For This Purpose Filipino Ownership Or Interest Shall Be Based On The Contributions Of Each Of The Members Of The Joint Venture As Specified In Their Jva. 5.2. The Procuring Entity May Also Invite Foreign Bidders When Provided For Under Any Treaty Or International Or Executive Agreement As Specified In The Bds. 5.3. Government Corporate Entities May Be Eligible To Participate Only If They Can Establish That They (a) Are Legally And Financially Autonomous, (b) Operate Under Commercial Law, And (c) Are Not Dependent Agencies Of The Gop Or The Procuring Entity. 5.4. (a) Unless Otherwise Provided In The Bds, The Bidder Must Have Completed, Within Ten (10) Years From The Submission Of Bids, A Single Contract That Is Similar To This Project, Equivalent To At Least Fifty Percent (50%) Of The Abc Adjusted To Current Prices Using The National Statistics Office Consumer Price Index. (b) For Foreign-funded Procurement, The Procuring Entity And The Foreign Government/foreign Or International Financing Institution May Agree On Another Track Record Requirement, As Specified In The Bds. For This Purpose, Contracts Similar To The Project Shall Be Those Described In Thebds, And Completed Within The Period Stated In The Invitation To Bid And Itb Clause 12.1(a)(iii). 5.5. The Bidder Must Submit A Computation Of Its Net Financial Contracting Capacity (nfcc) Or A Commitment From A Universal Or Commercial Bank To Extend A Credit Line In Its Favor If Awarded The Contract For This Project (clc). The Nfcc, Computed Using The Following Formula, Must Be At Least Equal To The Abc To Be Bid: Nfcc = [(current Assets Minus Current Liabilities) (k)] Minus The Value Of All Outstanding Or Uncompleted Portions Of The Projects Under Ongoing Contracts, Including Awarded Contracts Yet To Be Started Coinciding With The Contract For This Project. Where: K = 10 For A Contract Duration Of One Year Or Less, 15 For A Contract Duration Of More Than One Year Up To Two Years, And 20 For A Contract Duration Of More Than Two Years. The Clc Must Be At Least Equal To Ten Percent (10%) Of The Abc For This Project. If Issued By A Foreign Bank, It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank. In The Case Of Local Government Units (lgus), The Bidder May Also Submit Clc From Other Banks Certified By The Bangko Sentral Ng Pilipinas (bsp) As Authorized To Issue Such Financial Instrument. 6. Bidder’s Responsibilities 6.1. The Bidder Or Its Duly Authorized Representative Shall Submit A Sworn Statement In The Form Prescribed In Section Ix. Bidding Forms As Required In Itb Clause 12.1(b)(iii). 6.2. The Bidder Is Responsible For The Following: (a) Having Taken Steps To Carefully Examine All Of The Bidding Documents; (b) Having Acknowledged All Conditions, Local Or Otherwise, Affecting The Implementation Of The Contract; (c) Having Made An Estimate Of The Facilities Available And Needed For The Contract To Be Bid, If Any; (d) Having Complied With Its Responsibility To Inquire Or Secure Supplemental/bid Bulletin/s As Provided Under Itb Clause 10.3. (e) Ensuring That It Is Not “blacklisted” Or Barred From Bidding By The Gop Or Any Of Its Agencies, Offices, Corporations, Or Lgus, Including Foreign Government/foreign Or International Financing Institution Whose Blacklisting Rules Have Been Recognized By The Gppb; (f) Ensuring That Each Of The Documents Submitted In Satisfaction Of The Bidding Requirements Is An Authentic Copy Of The Original, Complete, And All Statements And Information Provided Therein Are True And Correct; (g) Authorizing The Head Of The Procuring Entity Or Its Duly Authorized Representative/s To Verify All The Documents Submitted; (h) Ensuring That The Signatory Is The Duly Authorized Representative Of The Bidder, And Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary And/or To Represent The Bidder In The Bidding, With The Duly Notarized Secretary’s Certificate Attesting To Such Fact, If The Bidder Is A Corporation, Partnership, Cooperative, Or Joint Venture; (i) Complying With The Disclosure Provision Under Section 47 Of The Act In Relation To Other Provisions Of Republic Act 3019; And (j) Complying With Existing Labor Laws And Standards, If Applicable. Failure To Observe Any Of The Above Responsibilities Shall Be At The Risk Of The Bidder Concerned. 6.3. The Bidder, By The Act Of Submitting Its Bid, Shall Be Deemed To Have Inspected The Site, Determined The General Characteristics Of The Contract Works And The Conditions For This Project And Examine All Instructions, Forms, Terms, And Project Requirements In The Bidding Documents. 6.4. It Shall Be The Sole Responsibility Of The Prospective Bidder To Determine And To Satisfy Itself By Such Means As It Considers Necessary Or Desirable As To All Matters Pertaining To This Project, Including: (a) The Location And The Nature Of The Contract, Project, Or Work; (b) Climatic Conditions; (c) Transportation Facilities; (c) Nature And Condition Of The Terrain, Geological Conditions At The Site Communication Facilities, Requirements, Location And Availability Of Construction Aggregates And Other Materials, Labor, Water, Electric Power And Access Roads; And (d) Other Factors That May Affect The Cost, Duration And Execution Or Implementation Of The Contract, Project, Or Work. 6.5. The Procuring Entity Shall Not Assume Any Responsibility Regarding Erroneous Interpretations Or Conclusions By The Prospective Or Eligible Bidder Out Of The Data Furnished By The Procuring Entity. 6.6. Before Submitting Their Bids, The Bidders Are Deemed To Have Become Familiar With All Existing Laws, Decrees, Ordinances, Acts And Regulations Of The Philippines Which May Affect The Contract In Any Way. 6.7. The Bidder Shall Bear All Costs Associated With The Preparation And Submission Of His Bid, And The Procuring Entity Will In No Case Be Responsible Or Liable For Those Costs, Regardless Of The Conduct Or Outcome Of The Bidding Process. 6.8. Bidders Should Note That The Procuring Entity Will Only Accept Bids Only From Those That Have Paid The Nonrefundable Fee For The Bidding Documents At The Office Indicated In The Invitation To Bid. 7. Origin Of Goods And Services There Is No Restriction On The Origin Of Goods, Or Contracting Of Works Or Services Other Than Those Prohibited By A Decision Of The United Nations Security Council Taken Under Chapter Vii Of The Charter Of The United Nations. 8. Subcontracts 8.1. Unless Otherwise Specified In The Bds, The Bidder May Subcontract Portions Of The Works To An Extent As May Be Approved By The Procuring Entity And Stated In The Bds. However, Subcontracting Of Any Portion Shall Not Relieve The Bidder From Any Liability Or Obligation That May Arise From The Contract For This Project. 8.2. Subcontractors Must Submit The Documentary Requirements Under Itb Clause 12 And Comply With The Eligibility Criteria Specified In The Bds. In The Event That Any Subcontractor Is Found By The Procuring Entity To Be Ineligible, The Subcontracting Of Such Portion Of The Works Shall Be Disallowed. 8.3. The Bidder May Identify The Subcontractor To Whom A Portion Of The Works Will Be Subcontracted At Any Stage Of The Bidding Process Or During Contract Implementation. If The Bidder Opts To Disclose The Name Of The Subcontractor During Bid Submission, The Bidder Shall Include The Required Documents As Part Of The Technical Component Of Its Bid. B. Contents Of Bidding Documents 9. Pre-bid Conference 9.1. (a) If So Specified In The Bds, A Pre-bid Conference Shall Be Held At The Venue And On The Date Indicated Therein, To Clarify And Address The Bidders’ Questions On The Technical And Financial Components Of This Project. (b) The Pre-bid Conference Shall Be Held At Least Twelve (12) Calendar Days Before The Deadline For The Submission Of And Receipt Of Bids. If The Procuring Entity Determines That, By Reason Of The Method, Nature, Or Complexity Of The Contract To Be Bid, Or When International Participation Will Be More Advantageous To The Gop, A Longer Period For The Preparation Of Bids Is Necessary, The Pre-bid Conference Shall Be Held At Least Thirty (30) Calendar Days Before The Deadline For The Submission And Receipt Of Bids, As Specified In The Bds. 9.2. Bidders Are Encouraged To Attend The Pre-bid Conference To Ensure That They Fully Understand The Procuring Entity’s Requirements. Non-attendance Of The Bidder Will In No Way Prejudice Its Bid; However, The Bidder Is Expected To Know The Changes And/or Amendments To The Bidding Documents As Recorded In The Minutes Of The Pre-bid Conference And The Supplemental/bid Bulletin. 9.3. Any Statement Made At The Pre-bid Conference Shall Not Modify The Terms Of The Bidding Documents Unless Such Statement Is Specifically Identified In Writing As An Amendment Thereto And Issued As A Supplemental/bid Bulletin. 10. Clarification And Amendment Of Bidding Documents 10.1. Bidders Who Have Purchased The Bidding Documents May Request For Clarification(s) On Any Part Of The Bidding Documents Or For An Interpretation. Such A Request Must Be In Writing And Submitted To The Procuring Entity At The Address Indicated In The Bds At Least Ten (10) Calendar Days Before The Deadline Set For The Submission And Receipt Of Bids. 10.2. Supplemental/bid Bulletins May Be Issued Upon The Procuring Entity’s Initiative For Purposes Of Clarifying Or Modifying Any Provision Of The Bidding Documents Not Later Than Seven (7) Calendar Days Before The Deadline For The Submission And Receipt Of Bids. Any Modification To The Bidding Documents Shall Be Identified As An Amendment. 10.3. Any Supplemental/bid Bulletin Issued By The Bac Shall Also Be Posted On The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity Concerned, If Available. Unless, Otherwise Provided In The Bds, It Shall Be The Responsibility Of All Bidders Who Secure The Bidding Documents To Inquire And Secure Supplemental/bid Bulletins That May Be Issued By The Bac. However, Bidders Who Have Submitted Bids Before The Issuance Of The Supplemental/bid Bulletin Must Be Informed And Allowed To Modify Or Withdraw Their Bids In Accordance With Itb Clause 23. C. Preparation Of Bids 11. Language Of Bids The Bid, As Well As All Correspondence And Documents Relating To The Bid Exchanged By The Bidder And The Procuring Entity, Shall Be Written In English. Supporting Documents And Printed Literature Furnished By The Bidder May Be In Another Language Provided They Are Accompanied By An Accurate Translation In English Certified By The Appropriate Embassy Or Consulate In The Philippines, In Which Case The English Translation Shall Govern, For Purposes Of Interpretation Of The Bid. 12. Documents Comprising The Bid: Eligibility And Technical Components 12.1. Unless Otherwise Indicated In The Bds, The First Envelope Shall Contain The Following Eligibility And Technical Documents: (a) Eligibility Documents – Class "a" Documents: (i) Registration Certificate From The Securities And Exchange Commission (sec), Department Of Trade And Industry (dti) For Sole Proprietorship, Or Cooperative Development Authority (cda) For Cooperatives, Or Any Proof Of Such Registration As Stated In The Bds; (ii) Mayor’s Permit Issued By The City Or Municipality Where The Principal Place Of Business Of The Prospective Bidder Is Located; (iii) Statement Of All Its Ongoing And Completed Government And Private Contracts Within Ten (10) Years From The Submission Of Bids, Including Contracts Awarded But Not Yet Started, If Any. The Statement Shall Include, For Each Contract, The Following: (iii.1) Name Of The Contract; (iii.2) Date Of The Contract; (iii.3) Contract Duration; (iii.4) Owner’s Name And Address; (iii.5) Nature Of Work; (iii.6) Contractor’s Role (whether Sole Contractor, Subcontractor, Or Partner In A Jv) And Percentage Of Participation; (iii.7) Total Contract Value At Award; (iii.8) Date Of Completion Or Estimated Completion Time; (iii.9) Total Contract Value At Completion, If Applicable; (iii.10) Percentages Of Planned And Actual Accomplishments, If Applicable; (iii.11) Value Of Outstanding Works, If Applicable; (iii.12) The Statement Shall Be Supported By The Notices Of Award And/or Notices To Proceed Issued By The Owners; And (iii.13) The Statement Shall Be Supported By The Constructors Performance Evaluation System (cpes) Rating Sheets, And/or Certificates Of Completion And Owner’s Acceptance, If Applicable; (iv) Unless Otherwise Provided In The Bds, Valid Philippine Contractors Accreditation Board (pcab) License And Registration For The Type And Cost Of The Contract For This Project; (v) Audited Financial Statements, Showing, Among Others, The Prospective Total And Current Assets And Liabilities, Stamped “received” By The Bir Or Its Duly Accredited And Authorized Institutions, For The Preceding Calendar Year Which Should Not Be Earlier Than Two (2) Years From The Date Of Bid Submission; (vi) Nfcc Computation Or Clc In Accordance With Itb Clause 5.5; And Class "b" Document: (vii) If Applicable, Valid Joint Venture Agreement (jva) Or, In Lieu Thereof, Duly Notarized Statements From All The Potential Joint Venture Partners Stating That They Will Enter Into And Abide By The Provisions Of The Jva In The Instance That The Bid Is Successful Shall Be Included In The Bid. (b) Technical Documents – (i) Bid Security As Prescribed In Itb Clause 18. If The Bidder Opts To Submit The Bid Security In The Form Of: (i.1) A Bank Draft/guarantee Or An Irrevocable Letter Of Credit Issued By A Foreign Bank, It Shall Be Accompanied By A Confirmation From A Universal Or Commercial Bank; Or (i.2) A Surety Bond Accompanied By A Certification Coming From An Authorized Insurance Commission That A Surety Or Insurance Company Is Authorized To Issue Such Instrument; (ii) Project Requirements, Which Shall Include The Following: (ii.1) Organizational Chart For The Contract To Be Bid; (ii.2) List Of Contractor’s Personnel (viz, Project Manager, Project Engineers, Materials Engineers, And Foremen), To Be Assigned To The Contract To Be Bid, With Their Complete Qualification And Experience Data; And (ii.3) List Of Contractor’s Equipment Units, Which Are Owned, Leased, And/or Under Purchase Agreements, Supported By Certification Of Availability Of Equipment From The Equipment Lessor/vendor For The Duration Of The Project; And (iii) Sworn Statement In Accordance With Section 25.2(b)(iv) Of The Irr Of Ra 9184 And Using The Form Prescribed In Section Ix. Bidding Forms. 13. Documents Comprising The Bid: Financial Component 13.1. Unless Otherwise Stated In The Bds, The Financial Component Of The Bid Shall Contain The Following: (a) Financial Bid Form In Accordance With The Form Prescribed In Section Ix. Bidding Forms; And (b) Any Other Document Related To The Financial Component Of The Bid As Stated In The Bds. 13.2. (a) Unless Indicated In The Bds, All Bids That Exceed The Abc Shall Not Be Accepted. (b) Unless Otherwise Indicated In The Bds, For Foreign-funded Procurement, A Ceiling May Be Applied To Bid Prices Provided The Following Conditions Are Met: (i) Bidding Documents Are Obtainable Free Of Charge On A Freely Accessible Website. If Payment Of Bidding Documents Is Required By The Procuring Entity, Payment Could Be Made Upon The Submission Of Bids. (ii) The Procuring Entity Has Procedures In Place To Ensure That The Abc Is Based On Recent Estimates Made By The Engineer Or The Responsible Unit Of The Procuring Entity And That The Estimates Are Based On Adequate Detailed Engineering (in The Case Of Works) And Reflect The Quality, Supervision And Risk And Inflationary Factors, As Well As Prevailing Market Prices, Associated With The Types Of Works Or Goods To Be Procured. (iii) The Procuring Entity Has Trained Cost Estimators On Estimating Prices And Analyzing Bid Variances. In The Case Of Infrastructure Projects, The Procuring Entity Must Also Have Trained Quantity Surveyors. (iv) The Procuring Entity Has Established A System To Monitor And Report Bid Prices Relative To Abc And Engineer’s/procuring Entity’s Estimate. (v) The Procuring Entity Has Established A Monitoring And Evaluation System For Contract Implementation To Provide A Feedback On Actual Total Costs Of Goods And Works. 14. Alternative Bids 14.1. Alternative Bids Shall Be Rejected. For This Purpose, Alternative Bid Is An Offer Made By A Bidder In Addition Or As A Substitute To Its Original Bid Which May Be Included As Part Of Its Original Bid Or Submitted Separately Therewith For Purposes Of Bidding. A Bid With Options Is Considered An Alternative Bid Regardless Of Whether Said Bid Proposal Is Contained In A Single Envelope Or Submitted In Two (2) Or More Separate Bid Envelopes. 14.2. Bidders Shall Submit Offers That Comply With The Requirements Of The Bidding Documents, Including The Basic Technical Design As Indicated In The Drawings And Specifications. Unless There Is A Value Engineering Clause In The Bds, Alternative Bids Shall Not Be Accepted. 14.3. Each Bidder Shall Submit Only One Bid, Either Individually Or As A Partner In A Jv. A Bidder Who Submits Or Participates In More Than One Bid (other Than As A Subcontractor If A Subcontractor Is Permitted To Participate In More Than One Bid) Will Cause All The Proposals With The Bidder’s Participation To Be Disqualified. This Shall Be Without Prejudice To Any Applicable Criminal, Civil And Administrative Penalties That May Be Imposed Upon The Persons And Entities Concerned. 15. Bid Prices 15.1. The Contract Shall Be For The Whole Works, As Described In Itb Clause 1.1, Based On The Priced Bill Of Quantities Submitted By The Bidder. 15.2. The Bidder Shall Fill In Rates And Prices For All Items Of The Works Described In The Bill Of Quantities. Bids Not Addressing Or Providing All Of The Required Items In The Bidding Documents Including, Where Applicable, Bill Of Quantities, Shall Be Considered Non-responsive And, Thus, Automatically Disqualified. In This Regard, Where A Required Item Is Provided, But No Price Is Indicated, The Same Shall Be Considered As Non-responsive, But Specifying A "0" (zero) For The Said Item Would Mean That It Is Being Offered For Free To The Government. 15.3. All Duties, Taxes, And Other Levies Payable By The Contractor Under The Contract, Or For Any Other Cause, Prior To The Deadline For Submission Of Bids, Shall Be Included In The Rates, Prices, And Total Bid Price Submitted By The Bidder. 15.4. All Bid Prices For The Given Scope Of Work In The Contract As Awarded Shall Be Considered As Fixed Prices, And Therefore Not Subject To Price Escalation During Contract Implementation, Except Under Extraordinary Circumstances As Specified In Gcc Clause 48. Price Escalation May Be Allowed In Extraordinary Circumstances As May Be Determined By The National Economic And Development Authority In Accordance With The Civil Code Of The Philippines, And Upon The Recommendation Of The Procuring Entity. Furthermore, In Cases Where The Cost Of The Awarded Contract Is Affected By Any Applicable New Laws, Ordinances, Regulations, Or Other Acts Of The Gop, Promulgated After The Date Of Bid Opening, A Contract Price Adjustment Shall Be Made Or Appropriate Relief Shall Be Applied On A No Loss-no Gain Basis. 16. Bid Currencies 16.1. All Bid Prices Shall Be Quoted In Philippine Pesos Unless Otherwise Provided In The Bds. However, For Purposes Of Bid Evaluation, Bids Denominated In Foreign Currencies Shall Be Converted To Philippine Currency Based On The Exchange Rate Prevailing On The Day Of The Bid Opening. 16.2. If So Allowed In Accordance With Itb Clause 16.1, The Procuring Entity For Purposes Of Bid Evaluation And Comparing The Bid Prices Will Convert The Amounts In Various Currencies In Which The Bid Price Is Expressed To Philippine Pesos At The Exchange Rate As Published In The Bsp Reference Rate Bulletin On The Day Of The Bid Opening. 16.3. Unless Otherwise Specified In The Bds, Payment Of The Contract Price Shall Be Made In Philippine Pesos. 17. Bid Validity 17.1. Bids Shall Remain Valid For The Period Specified In The Bds Which Shall Not Exceed One Hundred Twenty (120) Calendar Days From The Date Of The Opening Of Bids. 17.2. In Exceptional Circumstances, Prior To The Expiration Of The Bid Validity Period, The Procuring Entity May Request Bidders To Extend The Period Of Validity Of Their Bids. The Request And The Responses Shall Be Made In Writing. The Bid Security Described In Itb Clause 18 Should Also Be Extended Corresponding To The Extension Of The Bid Validity Period At The Least. A Bidder May Refuse The Request Without Forfeiting Its Bid Security, But His Bid Shall No Longer Be Considered For Further Evaluation And Award. A Bidder Granting The Request Shall Not Be Required Or Permitted To Modify Its Bid. 18. Bid Security 18.1. The Bid Security In The Amount Stated In The Bds Shall Be Equal To The Percentage Of The Abc In Accordance With The Following Schedule: Form Of Bid Security Amount Of Bid Security (equal To Percentage Of The Abc) (a) Cash Or Cashier’s/manager’s Check Issued By A Universal Or Commercial Bank. Two Percent (2%) (b) Bank Draft/guarantee Or Irrevocable Letter Of Credit Issued By A Universal Or Commercial Bank: Provided, However, That It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank. (c) Surety Bond Callable Upon Demand Issued By A Surety Or Insurance Company Duly Certified By The Insurance Commission As Authorized To Issue Such Security; And/or Five Percent (5%) (d) Any Combination Of The Foregoing. Proportionate To Share Of Form With Respect To Total Amount Of Security For Biddings Conducted By Local Government Units, The Bidder May Also Submit Bid Securities In The Form Of Cashier’s/manager’s Check, Bank Draft/guarantee, Or Irrevocable Letter Of Credit From Other Banks Certified By The Bsp As Authorized To Issue Such Financial Statement. 18.2. The Bid Security Should Be Valid For The Period Specified In The Bds. Any Bid Not Accompanied By An Acceptable Bid Security Shall Be Rejected By The Procuring Entity As Non-responsive. 18.3. No Bid Securities Shall Be Returned To Bidders After The Opening Of Bids And Before Contract Signing, Except To Those That Failed Or Declared As Post-disqualified, Upon Submission Of A Written Waiver Of Their Right To File A Motion For Reconsideration And/or Protest. Without Prejudice On Its Forfeiture, Bid Securities Shall Be Returned Only After The Bidder With The Lowest Calculated Responsive Bid Has Signed The Contract And Furnished The Performance Security, But In No Case Later Than The Expiration Of The Bid Security Validity Period Indicated In Itb Clause 18.2. 18.4. Upon Signing And Execution Of The Contract, Pursuant To Itb Clause 31, And The Posting Of The Performance Security, Pursuant To Itb Clause 32, The Successful Bidder’s Bid Security Will Be Discharged, But In No Case Later Than The Bid Security Validity Period As Indicated In Itb Clause 18.2. 18.5. The Bid Security May Be Forfeited: (a) If A Bidder: (i) Withdraws Its Bid During The Period Of Bid Validity Specified In Itb Clause 17; (ii) Does Not Accept The Correction Of Errors Pursuant To Itb Clause 27.3(b); (iii) Fails To Submit The Requirements Within The Prescribed Period, Or A Finding Against Their Veracity, As Stated In Itb Clause 28.2; (iv) Submission Of Eligibility Requirements Containing False Information Or Falsified Documents; (v) Submission Of Bids That Contain False Information Or Falsified Documents, Or The Concealment Of Such Information In The Bids In Order To Influence The Outcome Of Eligibility Screening Or Any Other Stage Of The Public Bidding; (vi) Allowing The Use Of One’s Name, Or Using The Name Of Another For Purposes Of Public Bidding; (vii) Withdrawal Of A Bid, Or Refusal To Accept An Award, Or Enter Into Contract With The Government Without Justifiable Cause, After The Bidder Had Been Adjudged As Having Submitted The Lowest Calculated And Responsive Bid; (viii) Refusal Or Failure To Post The Required Performance Security Within The Prescribed Time; (ix) Refusal To Clarify Or Validate In Writing Its Bid During Post-qualification Within A Period Of Seven (7) Calendar Days From Receipt Of The Request For Clarification; (x) Any Documented Attempt By A Bidder To Unduly Influence The Outcome Of The Bidding In His Favor; (xi) Failure Of The Potential Joint Venture Partners To Enter Into The Joint Venture After The Bid Is Declared Successful; Or (xii) All Other Acts That Tend To Defeat The Purpose Of The Competitive Bidding, Such As Habitually Withdrawing From Bidding, Submitting Late Bids Or Patently Insufficient Bid, For At Least Three (3) Times Within A Year, Except For Valid Reasons. (b) If The Successful Bidder: (i) Fails To Sign The Contract In Accordance With Itb Clause 31; (ii) Fails To Furnish Performance Security In Accordance With Itb Clause 32. 19. Format And Signing Of Bids 19.1. Bidders Shall Submit Their Bids Through Their Duly Authorized Representative Using The Appropriate Forms Provided In Section Ix. Bidding Forms On Or Before The Deadline Specified In The Itb Clause 21 In Two (2) Separate Sealed Bid Envelopes, And Which Shall Be Submitted Simultaneously. The First Shall Contain The Technical Component Of The Bid, Including The Eligibility Requirements Under Itb Clause 12.1, And The Second Shall Contain The Financial Component Of The Bid. 19.2. Forms As Mentioned In Itb Clause 19.1 Must Be Completed Without Any Alterations To Their Format, And No Substitute Form Shall Be Accepted. All Blank Spaces Shall Be Filled In With The Information Requested. 19.3. The Bidder Shall Prepare An Original Of The First And Second Envelopes As Described In Itb Clauses 12 And 13. In Addition, The Bidder Shall Submit Copies Of The First And Second Envelopes. In The Event Of Any Discrepancy Between The Original And The Copies, The Original Shall Prevail. 19.4. The Bid, Except For Unamended Printed Literature, Shall Be Signed, And Each And Every Page Thereof Shall Be Initialed, By The Duly Authorized Representative/s Of The Bidder. 19.5. Any Interlineations, Erasures, Or Overwriting Shall Be Valid Only If They Are Signed Or Initialed By The Duly Authorized Representative/s Of The Bidder. 20. Sealing And Marking Of Bids 20.1. Bidders Shall Enclose Their Original Eligibility And Technical Documents Described In Itb Clause 12, In One Sealed Envelope Marked “original - Technical Component”, And The Original Of Their Financial Component In Another Sealed Envelope Marked “original - Financial Component”, Sealing Them All In An Outer Envelope Marked “original Bid”. 20.2. Each Copy Of The First And Second Envelopes Shall Be Similarly Sealed Duly Marking The Inner Envelopes As “copy No. ___ - Technical Component” And “copy No. ___ – Financial Component” And The Outer Envelope As “copy No. ___”, Respectively. These Envelopes Containing The Original And The Copies Shall Then Be Enclosed In One Single Envelope. 20.3. The Original And The Number Of Copies Of The Bid As Indicated In The Bds Shall Be Typed Or Written In Indelible Ink And Shall Be Signed By The Bidder Or Its Duly Authorized Representative/s. 20.4. All Envelopes Shall: (a) Contain The Name Of The Contract To Be Bid In Capital Letters; (b) Bear The Name And Address Of The Bidder In Capital Letters; (c) Be Addressed To The Procuring Entity’s Bac Identified In Itb Clause 10.1; (d) Bear The Specific Identification Of This Bidding Process Indicated In The Invitation To Bid; And (e) Bear A Warning “do Not Open Before…” The Date And Time For The Opening Of Bids, In Accordance With Itb Clause 21. 20.5. If Bids Are Not Sealed And Marked As Required, The Procuring Entity Will Assume No Responsibility For The Misplacement Or Premature Opening Of The Bid. D. Submission And Opening Of Bids 21. Deadline For Submission Of Bids Bids Must Be Received By The Procuring Entity’s Bac At The Address And On Or Before The Date And Time Indicated In The Bds. 22. Late Bids Any Bid Submitted After The Deadline For Submission And Receipt Of Bids Prescribed By The Procuring Entity, Pursuant To Itb Clause 21, Shall Be Declared “late” And Shall Not Be Accepted By The Procuring Entity. 23. Modification And Withdrawal Of Bids 23.1. The Bidder May Modify Its Bid After It Has Been Submitted; Provided That The Modification Is Received By The Procuring Entity Prior To The Deadline Prescribed For Submission And Receipt Of Bids. The Bidder Shall Not Be Allowed To Retrieve Its Original Bid, But Shall Be Allowed To Submit Another Bid Equally Sealed, Properly Identified, Linked To Its Original Bid Marked As “technical Modification” Or “financial Modification” And Stamped “received” By The Bac. Bid Modifications Received After The Applicable Deadline Shall Not Be Considered And Shall Be Returned To The Bidder Unopened. 23.2. A Bidder May, Through A Letter Of Withdrawal, Withdraw Its Bid After It Has Been Submitted, For Valid And Justifiable Reason; Provided That The Letter Of Withdrawal Is Received By The Procuring Entity Prior To The Deadline Prescribed For Submission And Receipt Of Bids. 23.3. Bids Requested To Be Withdrawn In Accordance With Itb Clause 23.1 Shall Be Returned Unopened To The Bidders. A Bidder May Also Express Its Intention Not To Participate In The Bidding Through A Letter Which Should Reach And Be Stamped By The Bac Before The Deadline For Submission And Receipt Of Bids. A Bidder That Withdraws Its Bid Shall Not Be Permitted To Submit Another Bid, Directly Or Indirectly, For The Same Contract. 23.4. No Bid May Be Modified After The Deadline For Submission Of Bids. No Bid May Be Withdrawn In The Interval Between The Deadline For Submission Of Bids And The Expiration Of The Period Of Bid Validity Specified By The Bidder On The Financial Bid Form. Withdrawal Of A Bid During This Interval Shall Result In The Forfeiture Of The Bidder’s Bid Security, Pursuant To Itb Clause 18.5, And The Imposition Of Administrative, Civil, And Criminal Sanctions As Prescribed By Ra 9184 And Its Irr. 24. Opening And Preliminary Examination Of Bids 24.1. The Bac Shall Open The First Bid Envelopes Of Bidders In Public As Specified In The Bds To Determine Each Bidder’s Compliance With The Documents Prescribed In Itb Clause 12. For This Purpose, The Bac Shall Check The Submitted Documents Of Each Bidder Against A Checklist Of Required Documents To Ascertain If They Are All Present, Using A Non-discretionary “pass/fail” Criterion. If A Bidder Submits The Required Document, It Shall Be Rated “passed” For That Particular Requirement. In This Regard, Bids That Fail To Include Any Requirement Or Are Incomplete Or Patently Insufficient Shall Be Considered As “failed”. Otherwise, The Bac Shall Rate The Said First Bid Envelope As “passed”. 24.2. Unless Otherwise Specified In The Bds, Immediately After Determining Compliance With The Requirements In The First Envelope, The Bac Shall Forthwith Open The Second Bid Envelope Of Each Remaining Eligible Bidder Whose First Bid Envelope Was Rated “passed”. The Second Envelope Of Each Complying Bidder Shall Be Opened Within The Same Day. In Case One Or More Of The Requirements In The Second Envelope Of A Particular Bid Is Missing, Incomplete Or Patently Insufficient, And/or If The Submitted Total Bid Price Exceeds The Abc Unless Otherwise Provided In Itb Clause 13.1(b), The Bac Shall Rate The Bid Concerned As “failed”. Only Bids That Are Determined To Contain All The Bid Requirements For Both Components Shall Be Rated “passed” And Shall Immediately Be Considered For Evaluation And Comparison. 24.3. Letters Of Withdrawal Shall Be Read Out And Recorded During Bid Opening, And The Envelope Containing The Corresponding Withdrawn Bid Shall Be Returned To The Bidder Unopened. If The Withdrawing Bidder’s Representative Is In Attendance, The Original Bid And All Copies Thereof Shall Be Returned To The Representative During The Bid Opening. If The Representative Is Not In Attendance, The Bid Shall Be Returned Unopened By Registered Mail. The Bidder May Withdraw Its Bid Prior To The Deadline For The Submission And Receipt Of Bids, Provided That The Corresponding Letter Of Withdrawal Contains A Valid Authorization Requesting For Such Withdrawal, Subject To Appropriate Administrative Sanctions. 24.4. If A Bidder Has Previously Secured A Certification From The Procuring Entity To The Effect That It Has Previously Submitted The Above-enumerated Class “a” Documents, The Said Certification May Be Submitted In Lieu Of The Requirements Enumerated In Itb Clause 12.1(a), Items (i) To (vi). 24.5. In The Case Of An Eligible Foreign Bidder As Described In Itb Clause 5, The Class “a” Documents Enumerated In Itb Clause 12.1(a) May Be Substituted With The Appropriate Equivalent Documents, If Any, Issued By The Country Of The Foreign Bidder Concerned. 24.6. Each Partner Of A Joint Venture Agreement Shall Likewise Submit The Documents Required In Itb Clauses 12.1(a)(i) And 12.1(a)(ii). Submission Of Documents Required Under Itb Clauses 12.1(a)(iii) To 12.1(a)(vi) By Any Of The Joint Venture Partners Constitutes Compliance. 24.7. A Bidder Determined As “failed” Has Three (3) Calendar Days Upon Written Notice Or, If Present At The Time Of Bid Opening, Upon Verbal Notification Within Which To File A Request For Reconsideration With The Bac: Provided, However, That The Request For Reconsideration Shall Not Be Granted If It Is Established That The Finding Of Failure Is Due To The Fault Of The Bidder Concerned: Provided, Further, That The Bac Shall Decide On The Request For Reconsideration Within Seven (7) Calendar Days From Receipt Thereof. If A Failed Bidder Signifies His Intent To File A Request For Reconsideration, The Bac Shall Keep The Bid Envelopes Of The Said Failed Bidder Unopened And/or Duly Sealed Until Such Time That The Request For Reconsideration Or Protest Has Been Resolved. E. Evaluation And Comparison Of Bids 25. Process To Be Confidential 25.1. Members Of The Bac, Including Its Staff And Personnel, As Well As Its Secretariat And Twg, Are Prohibited From Making Or Accepting Any Kind Of Communication With Any Bidder Regarding The Evaluation Of Their Bids Until The Issuance Of The Notice Of Award, Unless N The Case Of Itb Clause 26. 25.2. Any Effort By A Bidder To Influence The Procuring Entity In The Procuring Entity’s Decision In Respect Of Bid Evaluation, Bid Comparison Or Contract Award Will Result In The Rejection Of The Bidder’s Bid. 26. Clarification Of Bids To Assist In The Evaluation, Comparison And Post-qualification Of The Bids, The Procuring Entity May Ask In Writing Any Bidder For A Clarification Of Its Bid. All Responses To Requests For Clarification Shall Be In Writing. Any Clarification Submitted By A Bidder In Respect To Its Bid And That Is Not In Response To A Request By The Procuring Entity Shall Not Be Considered 27. Detailed Evaluation And Comparison Of Bids 27.1. The Procuring Entity Will Undertake The Detailed Evaluation And Comparison Of Bids Which Have Passed The Opening And Preliminary Examination Of Bids, Pursuant To Itb Clause 24, In Order To Determine The Lowest Calculated Bid. 27.2. In Evaluating The Bids To Get The Lowest Calculated Bid, The Procuring Entity Shall Undertake The Following: (a) The Detailed Evaluation Of The Financial Component Of The Bids, To Establish The Correct Calculated Prices Of The Bids; And (b) The Ranking Of The Total Bid Prices As So Calculated From The Lowest To Highest. The Bid With The Lowest Price Shall Be Identified As The Lowest Calculated Bid. 27.3. The Procuring Entity's Bac Shall Immediately Conduct A Detailed Evaluation Of All Bids Rated “passed,” Using Non-discretionary “pass/fail” Criterion. The Bac Shall Consider The Following In The Evaluation Of Bids: (a) Completeness Of The Bid. Unless The Itb Specifically Allows Partial Bids, Bids Not Addressing Or Providing All Of The Required Items In The Schedule Of Requirements Including, Where Applicable, Bill Of Quantities, Shall Be Considered Non-responsive And, Thus, Automatically Disqualified. In This Regard, Where A Required Item Is Provided, But No Price Is Indicated, The Same Shall Be Considered As Non-responsive, But Specifying A "0" (zero) For The Said Item Would Mean That It Is Being Offered For Free To The Procuring Entity; And (b) Arithmetical Corrections. Consider Computational Errors And Omissions To Enable Proper Comparison Of All Eligible Bids. It May Also Consider Bid Modifications If Expressly Allowed In The Bds. Any Adjustment Shall Be Calculated In Monetary Terms To Determine The Calculated Prices. 27.4. Based On The Detailed Evaluation Of Bids, Those That Comply With The Above-mentioned Requirements Shall Be Ranked In The Ascending Order Of Their Total Calculated Bid Prices, As Evaluated And Corrected For Computational Errors, Discounts And Other Modifications, To Identify The Lowest Calculated Bid. Total Calculated Bid Prices, As Evaluated And Corrected For Computational Errors, Discounts And Other Modifications, Which Exceed The Abc Shall Not Be Considered, Unless Otherwise Indicated In The Bds. 27.5. The Procuring Entity’s Evaluation Of Bids Shall Only Be Based On The Bid Price Quoted In The Financial Bid Form 27.6. Bids Shall Be Evaluated On An Equal Footing To Ensure Fair Competition. For This Purpose, All Bidders Shall Be Required To Include In Their Bids The Cost Of All Taxes, Such As, But Not Limited To, Value Added Tax (vat), Income Tax, Local Taxes, And Other Fiscal Levies And Duties Which Shall Be Itemized In The Bid Form And Reflected In The Detailed Estimates. Such Bids, Including Said Taxes, Shall Be The Basis For Bid Evaluation And Comparison. 28. Post Qualification 28.1. The Procuring Entity Shall Determine To Its Satisfaction Whether The Bidder That Is Evaluated As Having Submitted The Lowest Calculated Bid (lcb) Complies With And Is Responsive To All The Requirements And Conditions Specified In Itb Clauses 5, 12, And 13. 28.2. Within A Non-extendible Period Of Three (3) Calendar Days From Receipt By The Bidder Of The Notice From The Bac That It Submitted The Lcb, The Bidder Shall Submit The Following Documentary Requirements: (a) Tax Clearance Per Executive Order 398, Series Of 2005; (b) Latest Income And Business Tax Returns In The Form Specified In The Bds; (c) Certificate Of Philgeps Registration; And (d) Other Appropriate Licenses And Permits Required By Law And Stated In The Bds. Failure Of The Bidder Declared As Lcb To Duly Submit The Requirements Under This Clause Or A Finding Against The Veracity Of Such, Shall Be Ground For Forfeiture Of The Bid Security And Disqualification Of The Bidder For Award. 28.3. The Determination Shall Be Based Upon An Examination Of The Documentary Evidence Of The Bidder’s Qualifications Submitted Pursuant To Itb Clauses 12 And 13, As Well As Other Information As The Procuring Entity Deems Necessary And Appropriate, Using A Non-discretionary “pass/fail” Criterion. 28.4. If The Bac Determines That The Bidder With The Lowest Calculated Bid Passes All The Criteria For Post-qualification, It Shall Declare The Said Bid As The Lowest Calculated Responsive Bid, And Recommend To The Head Of The Procuring Entity The Award Of Contract To The Said Bidder At Its Submitted Price Or Its Calculated Bid Price, Whichever Is Lower, Subject To Itb Clause 30.3. 28.5. A Negative Determination Shall Result In Rejection Of The Bidder’s Bid, In Which Event The Procuring Entity Shall Proceed To The Next Lowest Calculated Bid To Make A Similar Determination Of That Bidder’s Capabilities To Perform Satisfactorily. If The Second Bidder, However, Fails The Post Qualification, The Procedure For Post Qualification Shall Be Repeated For The Bidder With The Next Lowest Calculated Bid, And So On Until The Lowest Calculated And Responsive Bid Is Determined For Contract Award. 28.6. Within A Period Not Exceeding Seven (7) Calendar Days From The Date Of Receipt Of The Recommendation Of The Bac, The Head Of The Procuring Entity Shall Approve Or Disapprove The Said Recommendation. In The Case Of Government Owned And Government-owned And/or -controlled Corporations (goccs) And Government Financial Institutions (gfis), The Period Provided Herein Shall Be Fifteen (15) Calendar Days. 29. Reservation Clause 29.1. Notwithstanding The Eligibility Or Post-qualification Of A Bidder, The Procuring Entity Concerned Reserves The Right To Review Its Qualifications At Any Stage Of The Procurement Process If It Has Reasonable Grounds To Believe That A Misrepresentation Has Been Made By The Said Bidder, Or That There Has Been A Change In The Bidder’s Capability To Undertake The Project From The Time It Submitted Its Eligibility Requirements. Should Such Review Uncover Any Misrepresentation Made In The Eligibility And Bidding Requirements, Statements Or Documents, Or Any Changes In The Situation Of The Bidder Which Will Affect Its Capability To Undertake The Project So That It Fails The Preset Eligibility Or Bid Evaluation Criteria, The Procuring Entity Shall Consider The Said Bidder As Ineligible And Shall Disqualify It From Submitting A Bid Or From Obtaining An Award Or Contract. 29.2. Based On The Following Grounds, The Procuring Entity Reserves The Right To Reject Any And All Bids, Declare A Failure Of Bidding At Any Time Prior To The Contract Award, Or Not To Award The Contract, Without Thereby Incurring Any Liability, And Make No Assurance That A Contract Shall Be Entered Into As A Result Of The Bidding: (a) If There Is Prima Facie Evidence Of Collusion Between Appropriate Public Officers Or Employees Of The Procuring Entity, Or Between The Bac And Any Of The Bidders, Or If The Collusion Is Between Or Among The Bidders Themselves, Or Between A Bidder And A Third Party, Including Any Act Which Restricts, Suppresses Or Nullifies Or Tends To Restrict, Suppress Or Nullify Competition; (b) If The Procuring Entity’s Bac Is Found To Have Failed In Following The Prescribed Bidding Procedures; Or (c) For Any Justifiable And Reasonable Ground Where The Award Of The Contract Will Not Redound To The Benefit Of The Government As Follows: (i) If The Physical And Economic Conditions Have Significantly Changed So As To Render The Project No Longer Economically, Financially Or Technically Feasible As Determined By The Head Of The Procuring Entity; (ii) If The Project Is No Longer Necessary As Determined By The Head Of The Procuring Entity; And (iii) If The Source Of Funds For The Project Has Been Withheld Or Reduced Through No Fault Of The Procuring Entity. 29.3. In Addition, The Procuring Entity May Likewise Declare A Failure Of Bidding When: (a) No Bids Are Received; (b) All Prospective Bidders Are Declared Ineligible; (c) All Bids Fail To Comply With All The Bid Requirements Or Fail Post-qualification; Or (d) The Bidder With The Lowest Calculated Responsive Bid Refuses, Without Justifiable Cause To Accept The Award Of Contract, And No Award Is Made. F. Award Of Contract 30. Contract Award 30.1. Subject To Itb Clause 28, The Procuring Entity Shall Award The Contract To The Bidder Whose Bid Has Been Determined To Be The Lowest Calculated And Responsive Bid (lcrb). 30.2. Prior To The Expiration Of The Period Of Bid Validity, The Procuring Entity Shall Notify The Successful Bidder In Writing That Its Bid Has Been Accepted, Through A Notice Of Award Received Personally Or Sent By Registered Mail Or Electronically, Receipt Of Which Must Be Confirmed In Writing Within Two (2) Days By The Lcrb And Submitted Personally Or Sent By Registered Mail Or Electronically To The Procuring Entity. 30.3. Notwithstanding The Issuance Of The Notice Of Award, Award Of Contract Shall Be Subject To The Following Conditions: (a) Submission Of The Following Documents Within The Prescribed Period From Receipt By The Bidder Of The Notice That It Has The Lowest Calculated And Responsive Bid: (i) Valid Jva, If Applicable, Within Ten (10) Calendar Days; (ii) Valid Pcab License And Registration For The Type And Cost Of The Contract To Be Bid For Foreign Bidders, Within Thirty (30) Calendar Days, If Allowed Under A Treaty Or International Or Executive Agreement Mentioned In Itb Clause 12.1(a)(iv); (b) Posting Of The Performance Security In Accordance With Itb Clause 32; (c) Signing Of The Contract As Provided In Itb Clause 31; And (d) Approval By Higher Authority, If Required. 31. Signing Of The Contract 31.1. At The Same Time As The Procuring Entity Notifies The Successful Bidder That Its Bid Has Been Accepted, The Procuring Entity Shall Send The Contract Form To The Bidder, Which Contract Has Been Provided In The Bidding Documents, Incorporating Therein All Agreements Between The Parties. 31.2. Within Ten (10) Calendar Days From Receipt Of The Notice Of Award, The Successful Bidder Shall Post The Required Performance Security, Sign And Date The Contract And Return It To The Procuring Entity. 31.3. The Procuring Entity Shall Enter Into Contract With The Successful Bidder Within The Same Ten (10) Calendar Day Period Provided That All The Documentary Requirements Are Complied With. 31.4. The Following Documents Shall Form Part Of The Contract: (a) Contract Agreement; (b) Bidding Documents; (c) Winning Bidder’s Bid, Including The Technical And Financial Proposals, And All Other Documents/statements Submitted; (d) Performance Security; (e) Credit Line In Accordance With Itb Clause 5.5, If Applicable; (f) Notice Of Award Of Contract; And (g) Other Contract Documents That May Be Required By Existing Laws And/or Specified In The Bds. 32. Performance Security 32.1. To Guarantee The Faithful Performance By The Winning Bidder Of Its Obligations Under The Contract, It Shall Post A Performance Security Within A Maximum Period Of Ten (10) Calendar Days From The Receipt Of The Notice Of Award From The Procuring Entity And In No Case Later Than The Signing Of The Contract. 32.2. The Performance Security Shall Be Denominated In Philippine Pesos And Posted In Favor Of The Procuring Entity In An Amount Equal To The Percentage Of The Total Contract Price As Stated In The Bds In Accordance With The Following Schedule: 33. 33.1. Form Of Performance Security Amount Of Performance Security (equal To Percentage Of The Total Contract Price) (a) Cash Or Cashier’s/manager’s Check Issued By A Universal Or Commercial Bank. Ten Percent (10%) (b) Bank Draft/guarantee Or Irrevocable Letter Of Credit Issued By A Universal Or Commercial Bank: Provided, However, That It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank. (c) Surety Bond Callable Upon Demand Issued By A Surety Or Insurance Company Duly Certified By The Insurance Commission As Authorized To Issue Such Security; And/or Thirty Percent (30%) (d) Any Combination Of The Foregoing. Proportionate To Share Of Form With Respect To Total Amount Of Security 33.2. Failure Of The Successful Bidder To Comply With The Above-mentioned Requirement Shall Constitute Sufficient Ground For The Annulment Of The Award And Forfeiture Of The Bid Security, In Which Event The Procuring Entity Shall Initiate And Complete The Post Qualification Of The Second Lowest Calculated Bid. The Procedure Shall Be Repeated Until The Lowest Calculated And Responsive Bid Is Identified And Selected For Contract Award. However If No Bidder Passed Post-qualification, The Bac Shall Declare The Bidding A Failure And Conduct A Re-bidding With Re-advertisement. 34. Notice To Proceed 34.1. Within Three (3) Calendar Days From The Date Of Approval Of The Contract By The Appropriate Government Approving Authority, The Procuring Entity Shall Issue Its Notice To Proceed To The Bidder. 34.2. The Contract Effectivity Date Shall Be Provided In The Notice To Proceed By The Procuring Entity, Which Date Shall Not Be Later Than Seven (7) Calendar Days From The Issuance Of The Notice To Proceed. Section Iii. Bid Data Sheet Bid Data Sheet Itb Clause 1.1 The Procuring Entity Is Lgu- Mapanas, Northern Samar. The Name Of The Contract Is Rehabilitation/improvement Of Aquino St. And San Miguel, Brgy. Santa Potenciana, Mapanas, Northern Samar The Identification Number Of The Contract Is Pr No-2024-11-107___ 2 The Funding Source Is: 20% Economic Development Fund (edf) For Fy 2023. The Name Of The Project Is: Rehabilitation/improvement Of Aquino St. And San Miguel, Brgy. Santa Potenciana, Mapanas, Northern Samar 3.1 No Further Instructions. 5.1 No Further Instructions. 5.2 Bidding Is Restricted To Eligible Bidders As Defined In Itb Clause 5.1. 5.4 For This Purpose, Similar Contracts Shall Refer To Bidder’s Annual Turnover From All Works Average Over The Last Three Years Shall Be Equal To 50% Of The Estimated Cost Of The Contract Being Procured. The Bidder Must Have Completed, Within The Past Ten (10) Years From The Submission Of Bids, A Single Contract That Is Similar To This Project, Equivalent To At Least Eighty Percent (80%) Of The Abc. 8.1 “subcontracting Is Not Allowed.” 8.2 “not Applicable”. 9.1 The Procuring Entity Will Hold A Pre-bid Conference For This Project On December 05, 2024 At 10:00 A.m. At Executive Conference 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar. 10.1 The Procuring Entity’s Address Is: The Municipality Of Mapanas, Province Of Northern Samar Ma. Teresa L. Minguez Lgu-bac Chairperson Tel. No. 09778033758 10.3 No Further Instructions. 12.1 Not Applicable 12.1(a)(i) “no Other Acceptable Proof Of Registration Is Recognized.” 12.1(a)(iv) No Further Instructions. 13.1 “no Additional Requirements” 13.1(b) The Abc Is Php1,985,172.32 Any Bid With A Financial Component Exceeding This Amount Shall Not Be Accepted. 14.2 “no Further Instructions.” 15.4 No Further Instruction. 16.1 The Bid Prices Shall Be Quoted In Philippine Pesos. 17.1 Bids Will Be Valid Until 75 Calendar Days After The Bid Submission Deadline Date As Prescribed By The Procuring Entity) 18.1 The Bid Security Shall Be In The Following Amount: 1. The Amount Of P39,703.45 If Bid Security Is In Cash, Cashier’s/manager’s Check, Bank Draft/guarantee Or Irrevocable Letter Of Credit; 2. The Amount Of P99,258.62 If Bid Security Is In Surety Bond; Or 3. Any Combination Of The Foregoing Proportionate To The Share Of Form With Respect To Total Amount Of Security. 18.2 The Bid Security Shall Be Valid Twenty Eight Days Beyond The Validity Period Of The Bid. 20.3 Each Bidder Shall Submit One Original And One Copy Of The First And Second Components Of Its Bid. 21 The Address For Submission Of Bids Is Ma. Teresa L. Minguez Lgu-bac Chairperson Bac Office @ Mpdo, 1st Floor, New Municipal Bldg. Municipality Of Mapanas, Northern Samar The Deadline For Submission Of Bids Is 9:00 A.m. On December 16 , 2024. 22 The Place Of Bid Opening Is Executive Conference Room, 2nd Floor, New Municipal Bldg. Municipality Of Mapanas, Northern Samar. The Date And Time Of Bid Opening Is December 16, 2024 At Exactly 10:00 A.m. 24.2 No Further Instructions. 27.3(b) Bid Modification Is Not Allowed. 27.4 No Further Instructions. 28.2(b) Bidders Have Option To Submit Manually Filed Tax Returns Or Tax Returns Filed Through The Electronic Filing And Payments System (efps). Note: The Latest Income And Business Tax Returns Are Those Within The Last Six Months Preceding The Date Of Bid Submission. 28.2(d) List Licenses And Permits Relevant To The Project And The Corresponding Law Requiring It. 1. Taxpayer’s Identification Number 2. Vat Registration 3. Philippine Contractors Accreditation Board (pcab) License The Requirements Are Applicable Only In A Case Where The Lowest Calculated Bid (lcb) Is Submitted By A Domestic Bidder, And If The Lowest Calculated Bid (lcb) Is Submitted By A Foreign Bidder, This Requirements Are Not Applicable 31.4(g) List Additional Contract Documents Relevant To The Project That May Be Required By Existing Laws And/or The Procuring Entity, Such As Construction Schedule And S-curve, Manpower Schedule, Construction Methods, Equipment Utilization Schedule, Construction Safety And Health Program Approved By The Department Of Labor And Employment, And Pert/cpm. 32.2 The Performance Security Shall Be In The Following Amount: 1. The Amount Of 10% Of Contract If Performance Security Is In Cash, Cashier’s/manager’s Check, Bank Draft/guarantee Or Irrevocable Letter Of Credit; 2. The Amount Of 30% Of Contract If Performance Security Is In Surety Bond; Or 3. Any Combination Of The Foregoing Proportionate To The Share Of Form With Respect To Total Amount Of Security. Section Iv. General Conditions Of Contract Table Of Contents 1. Definitions 41 2. Interpretation 43 3. Governing Language And Law 43 4. Communications 43 5. Possession Of Site 43 6. The Contractor’s Obligations 44 7. Performance Security 45 8. Subcontracting 46 9. Liquidated Damages 46 10. Site Investigation Reports 47 11. The Procuring Entity, Licenses And Permits 47 12. Contractor’s Risk And Warranty Security 47 13. Liability Of The Contractor 49 14. Procuring Entity’s Risk 49 15. Insurance 49 16. Termination For Default Of Contractor 51 17. Termination For Default Of Procuring Entity 51 18. Termination For Other Causes 52 19. Procedures For Termination Of Contracts 53 20. Force Majeure, Release From Performance 56 21. Resolution Of Disputes 56 22. Suspension Of Loan, Credit, Grant, Or Appropriation 57 23. Procuring Entity’s Representative’s Decisions 57 24. Approval Of Drawings And Temporary Works By The Procuring Entity’s Representative 57 25. Acceleration And Delays Ordered By The Procuring Entity’s Representative 58 26. Extension Of The Intended Completion Date 58 27. Right To Vary 58 28. Contractors Right To Claim 59 29. Dayworks 59 30. Early Warning 59 31. Program Of Work 59 32. Management Conferences 60 33. Bill Of Quantities 60 34. Instructions, Inspections And Audits 61 35. Identifying Defects 61 36. Cost Of Repairs 61 37. Correction Of Defects 61 38. Uncorrected Defects 62 39. Advance Payment 62 40. Progress Payments 62 41. Payment Certificates 63 42. Retention 63 43. Variation Orders 64 44. Contract Completion 66 45. Suspension Of Work 66 46. Payment On Termination 67 47. Extension Of Contract Time 67 48. Price Adjustment 68 49. Completion 68 50. Taking Over 69 51. Operating And Maintenance Manuals 69 1. Definitions For Purposes Of This Clause, Boldface Type Is Used To Identify Defined Terms. 1.1. The Arbiter Is The Person Appointed Jointly By The Procuring Entity And The Contractor To Resolve Disputes In The First Instance, As Provided For In Gcc Clause 21. 1.2. Bill Of Quantities Refers To A List Of The Specific Items Of The Work And Their Corresponding Unit Prices, Lump Sums, And/or Provisional Sums. 1.3. The Completion Date Is The Date Of Completion Of The Works As Certified By The Procuring Entity’s Representative, In Accordance With Gcc Clause 49. 1.4. The Contract Is The Contract Between The Procuring Entity And The Contractor To Execute, Complete, And Maintain The Works. 1.5. The Contract Price Is The Price Stated In The Letter Of Acceptance And Thereafter To Be Paid By The Procuring Entity To The Contractor For The Execution Of The Works In Accordance With This Contract. 1.6. Contract Time Extension Is The Allowable Period For The Contractor To Complete The Works In Addition To The Original Completion Date Stated In This Contract. 1.7. The Contractor Is The Juridical Entity Whose Proposal Has Been Accepted By The Procuring Entity And To Whom The Contract To Execute The Work Was Awarded. 1.8. The Contractor’s Bid Is The Signed Offer Or Proposal Submitted By The Contractor To The Procuring Entity In Response To The Bidding Documents. 1.9. Days Are Calendar Days; Months Are Calendar Months. 1.10. Dayworks Are Varied Work Inputs Subject To Payment On A Time Basis For The Contractor’s Employees And Equipment, In Addition To Payments For Associated Materials And Plant. 1.11. A Defect Is Any Part Of The Works Not Completed In Accordance With The Contract. 1.12. The Defects Liability Certificate Is The Certificate Issued By Procuring Entity’s Representative Upon Correction Of Defects By The Contractor. 1.13. The Defects Liability Period Is The One Year Period Between Contract Completion And Final Acceptance Within Which The Contractor Assumes The Responsibility To Undertake The Repair Of Any Damage To The Works At His Own Expense. 1.14. Drawings Are Graphical Presentations Of The Works. They Include All Supplementary Details, Shop Drawings, Calculations, And Other Information Provided Or Approved For The Execution Of This Contract. 1.15. Equipment Refers To All Facilities, Supplies, Appliances, Materials Or Things Required For The Execution And Completion Of The Work Provided By The Contractor And Which Shall Not Form Or Are Not Intended To Form Part Of The Permanent Works. 1.16. The Intended Completion Date Refers To The Date Specified In The Scc When The Contractor Is Expected To Have Completed The Works. The Intended Completion Date May Be Revised Only By The Procuring Entity’s Representative By Issuing An Extension Of Time Or An Acceleration Order. 1.17. Materials Are All Supplies, Including Consumables, Used By The Contractor For Incorporation In The Works. 1.18. The Notice To Proceed Is A Written Notice Issued By The Procuring Entity Or The Procuring Entity’s Representative To The Contractor Requiring The Latter To Begin The Commencement Of The Work Not Later Than A Specified Or Determinable Date. 1.19. Permanent Works All Permanent Structures And All Other Project Features And Facilities Required To Be Constructed And Completed In Accordance With This Contract Which Shall Be Delivered To The Procuring Entity And Which Shall Remain At The Site After The Removal Of All Temporary Works. 1.20. Plant Refers To The Machinery, Apparatus, And The Like Intended To Form An Integral Part Of The Permanent Works. 1.21. The Procuring Entity Is The Party Who Employs The Contractor To Carry Out The Works Stated In The Scc. 1.22. The Procuring Entity’s Representative Refers To The Head Of The Procuring Entity Or His Duly Authorized Representative, Identified In The Scc, Who Shall Be Responsible For Supervising The Execution Of The Works And Administering This Contract. 1.23. The Site Is The Place Provided By The Procuring Entity Where The Works Shall Be Executed And Any Other Place Or Places Which May Be Designated In The Scc, Or Notified To The Contractor By The Procuring Entity’s Representative As Forming Part Of The Site. 1.24. Site Investigation Reports Are Those That Were Included In The Bidding Documents And Are Factual And Interpretative Reports About The Surface And Subsurface Conditions At The Site. 1.25. Slippage Is A Delay In Work Execution Occurring When Actual Accomplishment Falls Below The Target As Measured By The Difference Between The Scheduled And Actual Accomplishment Of The Work By The Contractor As Established From The Work Schedule. This Is Actually Described As A Percentage Of The Whole Works. 1.26. Specifications Means The Description Of Works To Be Done And The Qualities Of Materials To Be Used, The Equipment To Be Installed And The Mode Of Construction. 1.27. The Start Date, As Specified In The Scc, Is The Date When The Contractor Is Obliged To Commence Execution Of The Works. It Does Not Necessarily Coincide With Any Of The Site Possession Dates. 1.28. A Subcontractor Is Any Person Or Organization To Whom A Part Of The Works Has Been Subcontracted By The Contractor, As Allowed By The Procuring Entity, But Not Any Assignee Of Such Person. 1.29. Temporary Works Are Works Designed, Constructed, Installed, And Removed By The Contractor That Are Needed For Construction Or Installation Of The Permanent Works. 1.30. Work(s)refer To The Permanent Works And Temporary Works To Be Executed By The Contractor In Accordance With This Contract, Including (i) The Furnishing Of All Labor, Materials, Equipment And Others Incidental, Necessary Or Convenient To The Complete Execution Of The Works; (ii) The Passing Of Any Tests Before Acceptance By The Procuring Entity’s Representative; (iii) And The Carrying Out Of All Duties And Obligations Of The Contractor Imposed By This Contract As Described In The Scc. 2. Interpretation 2.1. In Interpreting The Conditions Of Contract, Singular Also Means Plural, Male Also Means Female Or Neuter, And The Other Way Around. Headings Have No Significance. Words Have Their Normal Meaning Under The Language Of This Contract Unless Specifically Defined. The Procuring Entity’s Representative Will Provide Instructions Clarifying Queries About The Conditions Of Contract. 2.2. If Sectional Completion Is Specified In The Scc, References In The Conditions Of Contract To The Works, The Completion Date, And The Intended Completion Date Apply To Any Section Of The Works (other Than References To The Completion Date And Intended Completion Date For The Whole Of The Works). 3. Governing Language And Law 3.1. This Contract Has Been Executed In The English Language, Which Shall Be The Binding And Controlling Language For All Matters Relating To The Meaning Or Interpretation Of This Contract. All Correspondence And Other Documents Pertaining To This Contract Which Are Exchanged By The Parties Shall Be Written In English. 3.2. This Contract Shall Be Interpreted In Accordance With The Laws Of The Republic Of The Philippines. 4. Communications Communications Between Parties That Are Referred To In The Conditions Shall Be Effective Only When In Writing. A Notice Shall Be Effective Only When It Is Received By The Concerned Party. 5. Possession Of Site 5.1. On The Date Specified In The Scc, The Procuring Entity Shall Grant The Contractor Possession Of So Much Of The Site As May Be Required To Enable It To Proceed With The Execution Of The Works. If The Contractor Suffers Delay Or Incurs Cost From Failure On The Part Of The Procuring Entity To Give Possession In Accordance With The Terms Of This Clause, The Procuring Entity’s Representative Shall Give The Contractor A Contract Time Extension And Certify Such Sum As Fair To Cover The Cost Incurred, Which Sum Shall Be Paid By Procuring Entity. 5.2. If Possession Of A Portion Is Not Given By The Date Stated In The Scc Clause 5.1, The Procuring Entity Will Be Deemed To Have Delayed The Start Of The Relevant Activities. The Resulting Adjustments In Contact Time To Address Such Delay Shall Be In Accordance With Gcc Clause 47. 5.3. The Contractor Shall Bear All Costs And Charges For Special Or Temporary Right-of-way Required By It In Connection With Access To The Site. The Contractor Shall Also Provide At His Own Cost Any Additional Facilities Outside The Site Required By It For Purposes Of The Works. 5.4. The Contractor Shall Allow The Procuring Entity’s Representative And Any Person Authorized By The Procuring Entity’s Representative Access To The Site And To Any Place Where Work In Connection With This Contract Is Being Carried Out Or Is Intended To Be Carried Out. 6. The Contractor’s Obligations 6.1. The Contractor Shall Carry Out The Works Properly And In Accordance With This Contract. The Contractor Shall Provide All Supervision, Labor, Materials, Plant And Contractor's Equipment, Which May Be Required. All Materials And Plant On Site Shall Be Deemed To Be The Property Of The Procuring Entity. 6.2. The Contractor Shall Commence Execution Of The Works On The Start Date And Shall Carry Out The Works In Accordance With The Program Of Work Submitted By The Contractor, As Updated With The Approval Of The Procuring Entity’s Representative, And Complete Them By The Intended Completion Date. 6.3. The Contractor Shall Be Responsible For The Safety Of All Activities On The Site. 6.4. The Contractor Shall Carry Out All Instructions Of The Procuring Entity’s Representative That Comply With The Applicable Laws Where The Site Is Located. 6.5. The Contractor Shall Employ The Key Personnel Named In The Schedule Of Key Personnel, As Referred To In The Scc, To Carry Out The Supervision Of The Works. The Procuring Entity Will Approve Any Proposed Replacement Of Key Personnel Only If Their Relevant Qualifications And Abilities Are Equal To Or Better Than Those Of The Personnel Listed In The Schedule. 6.6. If The Procuring Entity’s Representative Asks The Contractor To Remove A Member Of The Contractor’s Staff Or Work Force, For Justifiable Cause, The Contractor Shall Ensure That The Person Leaves The Site Within Seven (7) Days And Has No Further Connection With The Work In This Contract. 6.7. During Contract Implementation, The Contractor And His Subcontractors Shall Abide At All Times By All Labor Laws, Including Child Labor Related Enactments, And Other Relevant Rules. 6.8. The Contractor Shall Submit To The Procuring Entity For Consent The Name And Particulars Of The Person Authorized To Receive Instructions On Behalf Of The Contractor. 6.9. The Contractor Shall Cooperate And Share The Site With Other Contractors, Public Authorities, Utilities, And The Procuring Entity Between The Dates Given In The Schedule Of Other Contractors Particularly When They Shall Require Access To The Site. The Contractor Shall Also Provide Facilities And Services For Them During This Period. The Procuring Entity May Modify The Schedule Of Other Contractors, And Shall Notify The Contractor Of Any Such Modification Thereto. 6.10. Should Anything Of Historical Or Other Interest Or Of Significant Value Be Unexpectedly Discovered On The Site, It Shall Be The Property Of The Procuring Entity. The Contractor Shall Notify The Procuring Entity’s Representative Of Such Discoveries And Carry Out The Procuring Entity’s Representative’s Instructions In Dealing With Them. 7. Performance Security 7.1. Within Ten (10) Calendar Days From Receipt Of The Notice Of Award From The Procuring Entity But In No Case Later Than The Signing Of The Contract By Both Parties, The Contractor Shall Furnish The Performance Security In Any The Forms Prescribed In Itb Clause 32.2. 7.2. The Performance Security Posted In Favor Of The Procuring Entity Shall Be Forfeited In The Event It Is Established That The Contractor Is In Default In Any Of Its Obligations Under The Contract. 7.3. The Performance Security Shall Remain Valid Until Issuance By The Procuring Entity Of The Certificate Of Final Acceptance. 7.4. The Performance Security May Be Released By The Procuring Entity And Returned To The Contractor After The Issuance Of The Certificate Of Final Acceptance Subject To The Following Conditions: (a) There Are No Pending Claims Against The Contractor Or The Surety Company Filed By The Procuring Entity; (b) The Contractor Has No Pending Claims For Labor And Materials Filed Against It; And (c) Other Terms Specified In The Scc. 7.5. The Contractor Shall Post An Additional Performance Security Following The Amount And Form Specified In Itb Clause 32.2 To Cover Any Cumulative Increase Of More Than Ten Percent (10%) Over The Original Value Of The Contract As A Result Of Amendments To Order Or Change Orders, Extra Work Orders And Supplemental Agreements, As The Case May Be. The Contractor Shall Cause The Extension Of The Validity Of The Performance Security To Cover Approved Contract Time Extensions. 7.6. In Case Of A Reduction In The Contract Value Or For Partially Completed Works Under The Contract Which Are Usable And Accepted By The Procuring Entity The Use Of Which, In The Judgment Of The Implementing Agency Or The Procuring Entity, Will Not Affect The Structural Integrity Of The Entire Project, The Procuring Entity Shall Allow A Proportional Reduction In The Original Performance Security, Provided That Any Such Reduction Is More Than Ten Percent (10%) And That The Aggregate Of Such Reductions Is Not More Than Fifty Percent (50%) Of The Original Performance Security. 7.7. Unless Otherwise Indicated In The Scc, The Contractor, By Entering Into The Contract With The Procuring Entity, Acknowledges The Right Of The Procuring Entity To Institute Action Pursuant To Act 3688 Against Any Subcontractor Be They An Individual, Firm, Partnership, Corporation, Or Association Supplying The Contractor With Labor, Materials And/or Equipment For The Performance Of This Contract. 8. Subcontracting 8.1. Unless Otherwise Indicated In The Scc, The Contractor Cannot Subcontract Works More Than The Percentage Specified In Itb Clause 8.1. 8.2. Subcontracting Of Any Portion Of The Works Does Not Relieve The Contractor Of Any Liability Or Obligation Under This Contract. The Contractor Will Be Responsible For The Acts, Defaults, And Negligence Of Any Subcontractor, Its Agents, Servants Or Workmen As Fully As If These Were The Contractor’s Own Acts, Defaults, Or Negligence, Or Those Of Its Agents, Servants Or Workmen. 8.3. Subcontractors Disclosed And Identified During The Bidding May Be Changed During The Implementation Of This Contract, Subject To Compliance With The Required Qualifications And The Approval Of The Procuring Entity. 9. Liquidated Damages 9.1. The Contractor Shall Pay Liquidated Damages To The Procuring Entity For Each Day That The Completion Date Is Later Than The Intended Completion Date. The Applicable Liquidated Damages Is At Least One-tenth (1/10) Of A Percent Of The Cost Of The Unperformed Portion For Every Day Of Delay. The Total Amount Of Liquidated Damages Shall Not Exceed Ten Percent (10%) Of The Amount Of The Contract. The Procuring Entity May Deduct Liquidated Damages From Payments Due To The Contractor. Payment Of Liquidated Damages Shall Not Affect The Contractor. Once The Cumulative Amount Of Liquidated Damages Reaches Ten Percent (10%) Of The Amount Of This Contract, The Procuring Entity Shall Rescind This Contract, Without Prejudice To Other Courses Of Action And Remedies Open To It. 9.2. If The Intended Completion Date Is Extended After Liquidated Damages Have Been Paid, The Engineer Of The Procuring Entity Shall Correct Any Overpayment Of Liquidated Damages By The Contractor By Adjusting The Next Payment Certificate. The Contractor Shall Be Paid Interest On The Overpayment, Calculated From The Date Of Payment To The Date Of Repayment, At The Rates Specified In Gcc Clause 40.3. 10. Site Investigation Reports The Contractor, In Preparing The Bid, Shall Rely On Any Site Investigation Reports Referred To In The Scc Supplemented By Any Information Obtained By The Contractor. 11. The Procuring Entity, Licenses And Permits The Procuring Entity Shall, If Requested By The Contractor, Assist Him In Applying For Permits, Licenses Or Approvals, Which Are Required For The Works. 12. Contractor’s Risk And Warranty Security 12.1. The Contractor Shall Assume Full Responsibility For The Works From The Time Project Construction Commenced Up To Final Acceptance By The Procuring Entity And Shall Be Held Responsible For Any Damage Or Destruction Of The Works Except Those Occasioned By Force Majeure. The Contractor Shall Be Fully Responsible For The Safety, Protection, Security, And Convenience Of His Personnel, Third Parties, And The Public At Large, As Well As The Works, Equipment, Installation, And The Like To Be Affected By His Construction Work. 12.2. The Defects Liability Period For Infrastructure Projects Shall Be One Year From Contract Completion Up To Final Acceptance By The Procuring Entity. During This Period, The Contractor Shall Undertake The Repair Works, At His Own Expense, Of Any Damage To The Works On Account Of The Use Of Materials Of Inferior Quality Within Ninety (90) Days From The Time The Head Of The Procuring Entity Has Issued An Order To Undertake Repair. In Case Of Failure Or Refusal To Comply With This Mandate, The Procuring Entity Shall Undertake Such Repair Works And Shall Be Entitled To Full Reimbursement Of Expenses Incurred Therein Upon Demand. 12.3. Unless Otherwise Indicated In The Scc, In Case The Contractor Fails To Comply With The Preceding Paragraph, The Procuring Entity Shall Forfeit Its Performance Security, Subject Its Property (ies) To Attachment Or Garnishment Proceedings, And Perpetually Disqualify It From Participating In Any Public Bidding. All Payables Of The Gop In His Favor Shall Be Offset To Recover The Costs. 12.4. After Final Acceptance Of The Works By The Procuring Entity, The Contractor Shall Be Held Responsible For “structural Defects”, I.e., Major Faults/flaws/deficiencies In One Or More Key Structural Elements Of The Project Which May Lead To Structural Failure Of The Completed Elements Or Structure, Or “structural Failures”, I.e., Where One Or More Key Structural Elements In An Infrastructure Facility Fails Or Collapses, Thereby Rendering The Facility Or Part Thereof Incapable Of Withstanding The Design Loads, And/or Endangering The Safety Of The Users Or The General Public: (a) Contractor – Where Structural Defects/failures Arise Due To Faults Attributable To Improper Construction, Use Of Inferior Quality/substandard Materials, And Any Violation Of The Contract Plans And Specifications, The Contractor Shall Be Held Liable; (b) Consultants – Where Structural Defects/failures Arise Due To Faulty And/or Inadequate Design And Specifications As Well As Construction Supervision, Then The Consultant Who Prepared The Design Or Undertook Construction Supervision For The Project Shall Be Held Liable; (c) Procuring Entity’s Representatives/project Manager/construction Managers And Supervisors – The Project Owner’s Representative(s), Project Manager, Construction Manager, And Supervisor(s) Shall Be Held Liable In Cases Where The Structural Defects/failures Are Due To His/their Willful Intervention In Altering The Designs And Other Specifications; Negligence Or Omission In Not Approving Or Acting On Proposed Changes To Noted Defects Or Deficiencies In The Design And/or Specifications; And The Use Of Substandard Construction Materials In The Project; (d) Third Parties - Third Parties Shall Be Held Liable In Cases Where Structural Defects/failures Are Caused By Work Undertaken By Them Such As Leaking Pipes, Diggings Or Excavations, Underground Cables And Electrical Wires, Underground Tunnel, Mining Shaft And The Like, In Which Case The Applicable Warranty To Such Structure Should Be Levied To Third Parties For Their Construction Or Restoration Works. (e) Users - In Cases Where Structural Defects/failures Are Due To Abuse/misuse By The End User Of The Constructed Facility And/or Non–compliance By A User With The Technical Design Limits And/or Intended Purpose Of The Same, Then The User Concerned Shall Be Held Liable. 12.5. The Warranty Against Structural Defects/failures, Except Those Occasioned On Force Majeure, Shall Cover The Period Specified In The Scc Reckoned From The Date Of Issuance Of The Certificate Of Final Acceptance By The Procuring Entity. 12.6. The Contractor Shall Be Required To Put Up A Warranty Security In The Form Of Cash, Bank Guarantee, Letter Of Credit, Gsis Or Surety Bond Callable On Demand, In Accordance With The Following Schedule: Form Of Warranty Minimum Amount In Percentage (%) Of Total Contract Price (a) Cash Or Letter Of Credit Issued By Universal Or Commercial Bank: Provided, However, That The Letter Of Credit Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank Five Percent (5%) (b) Bank Guarantee Confirmed By Universal Or Commercial Bank: Provided, However, That The Letter Of Credit Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank Ten Percent (10%) (c) Surety Bond Callable Upon Demand Issued By Gsis Or Any Surety Or Insurance Company Duly Certified By The Insurance Commission Thirty Percent (30%) 12.7. The Warranty Security Shall Be Stated In Philippine Pesos And Shall Remain Effective For One Year From The Date Of Issuance Of The Certificate Of Final Acceptance By The Procuring Entity, And Returned Only After The Lapse Of Said One Year Period. 12.8. In Case Of Structural Defects/failure Occurring During The Applicable Warranty Period Provided In Gcc Clause 12.5, The Procuring Entity Shall Undertake The Necessary Restoration Or Reconstruction Works And Shall Be Entitled To Full Reimbursement By The Parties Found To Be Liable For Expenses Incurred Therein Upon Demand, Without Prejudice To The Filing Of Appropriate Administrative, Civil, And/or Criminal Charges Against The Responsible Persons As Well As The Forfeiture Of The Warranty Security Posted In Favor Of The Procuring Entity. 13. Liability Of The Contractor Subject To Additional Provisions, If Any, Set Forth In The Scc, The Contractor’s Liability Under This Contract Shall Be As Provided By The Laws Of The Republic Of The Philippines. 14. Procuring Entity’s Risk 14.1. From The Start Date Until The Certificate Of Final Acceptance Has Been Issued, The Following Are Risks Of The Procuring Entity: (a) The Risk Of Personal Injury, Death, Or Loss Of Or Damage To Property (excluding The Works, Plant, Materials, And Equipment), Which Are Due To: (i) Any Type Of Use Or Occupation Of The Site Authorized By The Procuring Entity After The Official Acceptance Of The Works; Or (ii) Negligence, Breach Of Statutory Duty, Or Interference With Any Legal Right By The Procuring Entity Or By Any Person Employed By Or Contracted To Him Except The Contractor. (b) The Risk Of Damage To The Works, Plant, Materials, And Equipment To The Extent That It Is Due To A Fault Of The Procuring Entity Or In The Procuring Entity’s Design, Or Due To War Or Radioactive Contamination Directly Affecting The Country Where The Works Are To Be Executed. 15. Insurance 15.1. The Contractor Shall, Under His Name And At His Own Expense, Obtain And Maintain, For The Duration Of This Contract, The Following Insurance Coverage: (a) Contractor’s All Risk Insurance; (b) Transportation To The Project Site Of Equipment, Machinery, And Supplies Owned By The Contractor; (c) Personal Injury Or Death Of Contractor’s Employees; And (d) Comprehensive Insurance For Third Party Liability To Contractor’s Direct Or Indirect Act Or Omission Causing Damage To Third Persons. 15.2. The Contractor Shall Provide Evidence To The Procuring Entity’s Representative That The Insurances Required Under This Contract Have Been Effected And Shall, Within A Reasonable Time, Provide Copies Of The Insurance Policies To The Procuring Entity’s Representative. Such Evidence And Such Policies Shall Be Provided To The Procuring Entity’s Through The Procuring Entity’s Representative. 15.3. The Contractor Shall Notify The Insurers Of Changes In The Nature, Extent, Or Program For The Execution Of The Works And Ensure The Adequacy Of The Insurances At All Times In Accordance With The Terms Of This Contract And Shall Produce To The Procuring Entity’s Representative The Insurance Policies In Force Including The Receipts For Payment Of The Current Premiums. The Above Insurance Policies Shall Be Obtained From Any Reputable Insurance Company Approved By The Procuring Entity’s Representative. 15.4. If The Contractor Fails To Obtain And Keep In Force The Insurances Referred To Herein Or Any Other Insurance Which He May Be Required To Obtain Under The Terms Of This Contract, The Procuring Entity May Obtain And Keep In Force Any Such Insurances And Pay Such Premiums As May Be Necessary For The Purpose. From Time To Time, The Procuring Entity May Deduct The Amount It Shall Pay For Said Premiums Including Twenty Five Percent (25%) Therein From Any Monies Due, Or Which May Become Due, To The Contractor, Without Prejudice To The Procuring Entity Exercising Its Right To Impose Other Sanctions Against The Contractor Pursuant To The Provisions Of This Contract. 15.5. In The Event The Contractor Fails To Observe The Above Safeguards, The Procuring Entity May, At The Contractor’s Expense, Take Whatever Measure Is Deemed Necessary For Its Protection And That Of The Contractor’s Personnel And Third Parties, And/or Order The Interruption Of Dangerous Works. In Addition, The Procuring Entity May Refuse To Make The Payments Under Gcc Clause 40 Until The Contractor Complies With This Clause. 15.6. The Contractor Shall Immediately Replace The Insurance Policy Obtained As Required In This Contract, Without Need Of The Procuring Entity’s Demand, With A New Policy Issued By A New Insurance Company Acceptable To The Procuring Entity For Any Of The Following Grounds: (a) The Issuer Of The Insurance Policy To Be Replaced Has: (i) Become Bankrupt; (ii) Been Placed Under Receivership Or Under A Management Committee; (iii) Been Sued For Suspension Of Payment; Or (iv) Been Suspended By The Insurance Commission And Its License To Engage In Business Or Its Authority To Issue Insurance Policies Cancelled; Or (v) Where Reasonable Grounds Exist That The Insurer May Not Be Able, Fully And Promptly, To Fulfill Its Obligation Under The Insurance Policy. 16. Termination For Default Of Contractor 16.1. The Procuring Entity Shall Terminate This Contract For Default When Any Of The Following Conditions Attend Its Implementation: 16.2. Due To The Contractor’s Fault And While The Project Is On-going, It Has Incurred Negative Slippage Of Fifteen Percent (15%) Or More In Accordance With Presidential Decree 1870, Regardless Of Whether Or Not Previous Warnings And Notices Have Been Issued For The Contractor To Improve His Performance; 16.3. Due To Its Own Fault And After This Contract Time Has Expired, The Contractor Incurs Delay In The Completion Of The Work After This Contract Has Expired; Or 16.4. The Contractor: (a) Abandons The Contract Works, Refuses Or Fails To Comply With A Valid Instruction Of The Procuring Entity Or Fails To Proceed Expeditiously And Without Delay Despite A Written Notice By The Procuring Entity; (b) Does Not Actually Have On The Project Site The Minimum Essential Equipment Listed On The Bid Necessary To Prosecute The Works In Accordance With The Approved Program Of Work And Equipment Deployment Schedule As Required For The Project; (c) Does Not Execute The Works In Accordance With This Contract Or Persistently Or Flagrantly Neglects To Carry Out Its Obligations Under This Contract; (d) Neglects Or Refuses To Remove Materials Or To Perform A New Work That Has Been Rejected As Defective Or Unsuitable; Or (e) Sub-lets Any Part Of This Contract Without Approval By The Procuring Entity. 16.5. All Materials On The Site, Plant, Equipment, And Works Shall Be Deemed To Be The Property Of The Procuring Entity If This Contract Is Rescinded Because Of The Contractor’s Default. 17. Termination For Default Of Procuring Entity The Contractor May Terminate This Contract With The Procuring Entity If The Works Are Completely Stopped For A Continuous Period Of At Least Sixty (60) Calendar Days Through No Fault Of Its Own, Due To Any Of The Following Reasons: (a) Failure Of The Procuring Entity To Deliver, Within A Reasonable Time, Supplies, Materials, Right-of-way, Or Other Items It Is Obligated To Furnish Under The Terms Of This Contract; Or (b) The Prosecution Of The Work Is Disrupted By The Adverse Peace And Order Situation, As Certified By The Armed Forces Of The Philippines Provincial Commander And Approved By The Secretary Of National Defense. 18. Termination For Other Causes 18.1. The Procuring Entity May Terminate This Contract, In Whole Or In Part, At Any Time For Its Convenience. The Head Of The Procuring Entity May Terminate This Contract For The Convenience Of The Procuring Entity If He Has Determined The Existence Of Conditions That Make Project Implementation Economically, Financially Or Technically Impractical And/or Unnecessary, Such As, But Not Limited To, Fortuitous Event(s) Or Changes In Law And National Government Policies. 18.2. The Procuring Entity Or The Contractor May Terminate This Contract If The Other Party Causes A Fundamental Breach Of This Contract. 18.3. Fundamental Breaches Of Contract Shall Include, But Shall Not Be Limited To, The Following: (a) The Contractor Stops Work For Twenty Eight (28) Days When No Stoppage Of Work Is Shown On The Current Program Of Work And The Stoppage Has Not Been Authorized By The Procuring Entity’s Representative; (b) The Procuring Entity’s Representative Instructs The Contractor To Delay The Progress Of The Works, And The Instruction Is Not Withdrawn Within Twenty Eight (28) Days; (c) The Procuring Entity Shall Terminate This Contract If The Contractor Is Declared Bankrupt Or Insolvent As Determined With Finality By A Court Of Competent Jurisdiction. In This Event, Termination Will Be Without Compensation To The Contractor, Provided That Such Termination Will Not Prejudice Or Affect Any Right Of Action Or Remedy Which Has Accrued Or Will Accrue Thereafter To The Procuring Entity And/or The Contractor. In The Case Of The Contractor's Insolvency, Any Contractor's Equipment Which The Procuring Entity Instructs In The Notice Is To Be Used Until The Completion Of The Works; (d) A Payment Certified By The Procuring Entity’s Representative Is Not Paid By The Procuring Entity To The Contractor Within Eighty Four (84) Days From The Date Of The Procuring Entity’s Representative’s Certificate; (e) The Procuring Entity’s Representative Gives Notice That Failure To Correct A Particular Defect Is A Fundamental Breach Of Contract And The Contractor Fails To Correct It Within A Reasonable Period Of Time Determined By The Procuring Entity’s Representative; (f) The Contractor Does Not Maintain A Security, Which Is Required; (g) The Contractor Has Delayed The Completion Of The Works By The Number Of Days For Which The Maximum Amount Of Liquidated Damages Can Be Paid, As Defined In The Gcc Clause 9; And (h) In Case It Is Determined Prima Facie By The Procuring Entity That The Contractor Has Engaged, Before Or During The Implementation Of The Contract, In Unlawful Deeds And Behaviors Relative To Contract Acquisition And Implementation, Such As, But Not Limited To, The Following: (i) Corrupt, Fraudulent, Collusive, Coercive, And Obstructive Practices As Defined In Itb Clause 3.1(a), Unless Otherwise Specified In The Scc; (ii) Drawing Up Or Using Forged Documents; (iii) Using Adulterated Materials, Means Or Methods, Or Engaging In Production Contrary To Rules Of Science Or The Trade; And (iv) Any Other Act Analogous To The Foregoing. 18.4. The Funding Source Or The Procuring Entity, As Appropriate, Will Seek To Impose The Maximum Civil, Administrative And/or Criminal Penalties Available Under The Applicable Law On Individuals And Organizations Deemed To Be Involved With Corrupt, Fraudulent, Or Coercive Practices. 18.5. When Persons From Either Party To This Contract Gives Notice Of A Fundamental Breach To The Procuring Entity’s Representative In Order To Terminate The Existing Contract For A Cause Other Than Those Listed Under Gcc Clause 18.3, The Procuring Entity’s Representative Shall Decide Whether The Breach Is Fundamental Or Not. 18.6. If This Contract Is Terminated, The Contractor Shall Stop Work Immediately, Make The Site Safe And Secure, And Leave The Site As Soon As Reasonably Possible. 19. Procedures For Termination Of Contracts 19.1. The Following Provisions Shall Govern The Procedures For The Termination Of This Contract: (a) Upon Receipt Of A Written Report Of Acts Or Causes Which May Constitute Ground(s) For Termination As Aforementioned, Or Upon Its Own Initiative, The Procuring Entity Shall, Within A Period Of Seven (7) Calendar Days, Verify The Existence Of Such Ground(s) And Cause The Execution Of A Verified Report, With All Relevant Evidence Attached; (b) Upon Recommendation By The Procuring Entity, The Head Of The Procuring Entity Shall Terminate This Contract Only By A Written Notice To The Contractor Conveying The Termination Of This Contract. The Notice Shall State: (i) That This Contract Is Being Terminated For Any Of The Ground(s) Afore-mentioned, And A Statement Of The Acts That Constitute The Ground(s) Constituting The Same; (ii) The Extent Of Termination, Whether In Whole Or In Part; (iii) An Instruction To The Contractor To Show Cause As To Why This Contract Should Not Be Terminated; And (iv) Special Instructions Of The Procuring Entity, If Any. The Notice To Terminate Shall Be Accompanied By A Copy Of The Verified Report; (c) Within A Period Of Seven (7) Calendar Days From Receipt Of The Notice Of Termination, The Contractor Shall Submit To The Head Of The Procuring Entity A Verified Position Paper Stating Why The Contract Should Not Be Terminated. If The Contractor Fails To Show Cause After The Lapse Of The Seven (7) Day Period, Either By Inaction Or By Default, The Head Of The Procuring Entity Shall Issue An Order Terminating The Contract; (d) The Procuring Entity May, At Anytime Before Receipt Of The Bidder’s Verified Position Paper Described In Item (c) Above Withdraw The Notice To Terminate If It Is Determined That Certain Items Or Works Subject Of The Notice Had Been Completed, Delivered, Or Performed Before The Contractor’s Receipt Of The Notice; (e) Within A Non-extendible Period Of Ten (10) Calendar Days From Receipt Of The Verified Position Paper, The Head Of The Procuring Entity Shall Decide Whether Or Not To Terminate This Contract. It Shall Serve A Written Notice To The Contractor Of Its Decision And, Unless Otherwise Provided In The Said Notice, This Contract Is Deemed Terminated From Receipt Of The Contractor Of The Notice Of Decision. The Termination Shall Only Be Based On The Ground(s) Stated In The Notice To Terminate; And (f) The Head Of The Procuring Entity May Create A Contract Termination Review Committee (ctrc) To Assist Him In The Discharge Of This Function. All Decisions Recommended By The Ctrc Shall Be Subject To The Approval Of The Head Of The Procuring Entity. 19.2. Pursuant To Section 69(f) Of Ra 9184 And Without Prejudice To The Imposition Of Additional Administrative Sanctions As The Internal Rules Of The Agency May Provide And/or Further Criminal Prosecution As Provided By Applicable Laws, The Procuring Entity Shall Impose On Contractors After The Termination Of The Contract The Penalty Of Suspension For One (1) Year For The First Offense, Suspension For Two (2) Years For The Second Offense From Participating In The Public Bidding Process, For Violations Committed During The Contract Implementation Stage, Which Include But Not Limited To The Following: (a) Failure Of The Contractor, Due Solely To His Fault Or Negligence, To Mobilize And Start Work Or Performance Within The Specified Period In The Notice To Proceed (“ntp”); (b) Failure By The Contractor To Fully And Faithfully Comply With Its Contractual Obligations Without Valid Cause, Or Failure By The Contractor To Comply With Any Written Lawful Instruction Of The Procuring Entity Or Its Representative(s) Pursuant To The Implementation Of The Contract. For The Procurement Of Infrastructure Projects Or Consultancy Contracts, Lawful Instructions Include But Are Not Limited To The Following: (i) Employment Of Competent Technical Personnel, Competent Engineers And/or Work Supervisors; (ii) Provision Of Warning Signs And Barricades In Accordance With Approved Plans And Specifications And Contract Provisions; (iii) Stockpiling In Proper Places Of All Materials And Removal From The Project Site Of Waste And Excess Materials, Including Broken Pavement And Excavated Debris In Accordance With Approved Plans And Specifications And Contract Provisions; (iv) Deployment Of Committed Equipment, Facilities, Support Staff And Manpower; And (v) Renewal Of The Effectivity Dates Of The Performance Security After Its Expiration During The Course Of Contract Implementation. (c) Assignment And Subcontracting Of The Contract Or Any Part Thereof Or Substitution Of Key Personnel Named In The Proposal Without Prior Written Approval By The Procuring Entity. (d) Poor Performance By The Contractor Or Unsatisfactory Quality And/or Progress Of Work Arising From His Fault Or Negligence As Reflected In The Constructor's Performance Evaluation System (“cpes”) Rating Sheet. In The Absence Of The Cpes Rating Sheet, The Existing Performance Monitoring System Of The Procuring Entity Shall Be Applied. Any Of The Following Acts By The Contractor Shall Be Construed As Poor Performance: (i) Negative Slippage Of 15% And Above Within The Critical Path Of The Project Due Entirely To The Fault Or Negligence Of The Contractor; And (ii) Quality Of Materials And Workmanship Not Complying With The Approved Specifications Arising From The Contractor's Fault Or Negligence. (e) Willful Or Deliberate Abandonment Or Non-performance Of The Project Or Contract By The Contractor Resulting To Substantial Breach Thereof Without Lawful And/or Just Cause. In Addition To The Penalty Of Suspension, The Performance Security Posted By The Contractor Shall Also Be Forfeited. 20. Force Majeure, Release From Performance 20.1. For Purposes Of This Contract The Terms “force Majeure” And “fortuitous Event” May Be Used Interchangeably. In This Regard, A Fortuitous Event Or Force Majeure Shall Be Interpreted To Mean An Event Which The Contractor Could Not Have Foreseen, Or Which Though Foreseen, Was Inevitable. It Shall Not Include Ordinary Unfavorable Weather Conditions; And Any Other Cause The Effects Of Which Could Have Been Avoided With The Exercise Of Reasonable Diligence By The Contractor. 20.2. If This Contract Is Discontinued By An Outbreak Of War Or By Any Other Event Entirely Outside The Control Of Either The Procuring Entity Or The Contractor, The Procuring Entity’s Representative Shall Certify That This Contract Has Been Discontinued. The Contractor Shall Make The Site Safe And Stop Work As Quickly As Possible After Receiving This Certificate And Shall Be Paid For All Works Carried Out Before Receiving It And For Any Work Carried Out Afterwards To Which A Commitment Was Made. 20.3. If The Event Continues For A Period Of Eighty Four (84) Days, Either Party May Then Give Notice Of Termination, Which Shall Take Effect Twenty Eight (28) Days After The Giving Of The Notice. 20.4. After Termination, The Contractor Shall Be Entitled To Payment Of The Unpaid Balance Of The Value Of The Works Executed And Of The Materials And Plant Reasonably Delivered To The Site, Adjusted By The Following: (a) Any Sum To Which The Contractor Is Entitled Under Gcc Clause 28; (b) The Cost Of His Suspension And Demobilization; (c) Any Sum To Which The Procuring Entity Is Entitled. 20.5. The Net Balance Due Shall Be Paid Or Repaid Within A Reasonable Time Period From The Time Of The Notice Of Termination. 21. Resolution Of Disputes 21.1. If Any Dispute Or Difference Of Any Kind Whatsoever Shall Arise Between The Parties In Connection With The Implementation Of The Contract Covered By The Act And This Irr, The Parties Shall Make Every Effort To Resolve Amicably Such Dispute Or Difference By Mutual Consultation. 21.2. If The Contractor Believes That A Decision Taken By The Procuring Entity’s Representative Was Either Outside The Authority Given To The Procuring Entity’s Representative By This Contract Or That The Decision Was Wrongly Taken, The Decision Shall Be Referred To The Arbiter Indicated In The Scc Within Fourteen (14) Days Of The Notification Of The Procuring Entity’s Representative’s Decision. 21.3. Any And All Disputes Arising From The Implementation Of This Contract Covered By The R.a. 9184 And Its Irr Shall Be Submitted To Arbitration In The Philippines According To The Provisions Of Republic Act No. 876, Otherwise Known As The “ Arbitration Law” And Republic Act 9285, Otherwise Known As The “alternative Dispute Resolution Act Of 2004”: Provided, However, That, Disputes That Are Within The Competence Of The Construction Industry Arbitration Commission To Resolve Shall Be Referred Thereto. The Process Of Arbitration Shall Be Incorporated As A Provision In This Contract That Will Be Executed Pursuant To The Provisions Of The Act And Its Irr: Provided, Further, That, By Mutual Agreement, The Parties May Agree In Writing To Resort To Other Alternative Modes Of Dispute Resolution. 22. Suspension Of Loan, Credit, Grant, Or Appropriation In The Event That The Funding Source Suspends The Loan, Credit, Grant, Or Appropriation To The Procuring Entity, From Which Part Of The Payments To The Contractor Are Being Made: (a) The Procuring Entity Is Obligated To Notify The Contractor Of Such Suspension Within Seven (7) Days Of Having Received The Suspension Notice. (b) If The Contractor Has Not Received Sums Due It For Work Already Done Within Forty Five (45) Days From The Time The Contractor’s Claim For Payment Has Been Certified By The Procuring Entity’s Representative, The Contractor May Immediately Issue A Suspension Of Work Notice In Accordance With Gcc Clause 45.2. 23. Procuring Entity’s Representative’s Decisions 23.1. Except Where Otherwise Specifically Stated, The Procuring Entity’s Representative Will Decide Contractual Matters Between The Procuring Entity And The Contractor In The Role Representing The Procuring Entity. 23.2. The Procuring Entity’s Representative May Delegate Any Of His Duties And Responsibilities To Other People, Except To The Arbiter, After Notifying The Contractor, And May Cancel Any Delegation After Notifying The Contractor. 24. Approval Of Drawings And Temporary Works By The Procuring Entity’s Representative 24.1. All Drawings Prepared By The Contractor For The Execution Of The Temporary Works, Are Subject To Prior Approval By The Procuring Entity’s Representative Before Its Use. 24.2. The Contractor Shall Be Responsible For Design Of Temporary Works. 24.3. The Procuring Entity’s Representative’s Approval Shall Not Alter The Contractor’s Responsibility For Design Of The Temporary Works. 24.4. The Contractor Shall Obtain Approval Of Third Parties To The Design Of The Temporary Works, When Required By The Procuring Entity. 25. Acceleration And Delays Ordered By The Procuring Entity’s Representative 25.1. When The Procuring Entity Wants The Contractor To Finish Before The Intended Completion Date, The Procuring Entity’s Representative Will Obtain Priced Proposals For Achieving The Necessary Acceleration From The Contractor. If The Procuring Entity Accepts These Proposals, The Intended Completion Date Will Be Adjusted Accordingly And Confirmed By Both The Procuring Entity And The Contractor. 25.2. If The Contractor’s Financial Proposals For An Acceleration Are Accepted By The Procuring Entity, They Are Incorporated In The Contract Price And Treated As A Variation. 26. Extension Of The Intended Completion Date 26.1. The Procuring Entity’s Representative Shall Extend The Intended Completion Date If A Variation Is Issued Which Makes It Impossible For The Intended Completion Date To Be Achieved By The Contractor Without Taking Steps To Accelerate The Remaining Work, Which Would Cause The Contractor To Incur Additional Costs. No Payment Shall Be Made For Any Event Which May Warrant The Extension Of The Intended Completion Date. 26.2. The Procuring Entity’s Representative Shall Decide Whether And By How Much To Extend The Intended Completion Date Within Twenty One (21) Days Of The Contractor Asking The Procuring Entity’s Representative For A Decision Thereto After Fully Submitting All Supporting Information. If The Contractor Has Failed To Give Early Warning Of A Delay Or Has Failed To Cooperate In Dealing With A Delay, The Delay By This Failure Shall Not Be Considered In Assessing The New Intended Completion Date. 27. Right To Vary 27.1. The Procuring Entity’s Representative With The Prior Approval Of The Procuring Entity May Instruct Variations, Up To A Maximum Cumulative Amount Of Ten Percent (10%) Of The Original Contract Cost. 27.2. Variations Shall Be Valued As Follows: (a) At A Lump Sum Price Agreed Between The Parties; (b) Where Appropriate, At Rates In This Contract; (c) In The Absence Of Appropriate Rates, The Rates In This Contract Shall Be Used As The Basis For Valuation; Or Failing Which (d) At Appropriate New Rates, Equal To Or Lower Than Current Industry Rates And To Be Agreed Upon By Both Parties And Approved By The Head Of The Procuring Entity. 28. Contractor's Right To Claim If The Contractor Incurs Cost As A Result Of Any Of The Events Under Gcc Clause 13, The Contractor Shall Be Entitled To The Amount Of Such Cost. If As A Result Of Any Of The Said Events, It Is Necessary To Change The Works, This Shall Be Dealt With As A Variation. 29. Dayworks 29.1. Subject To Gcc Clause 43 On Variation Order, And If Applicable As Indicated In The Scc, The Day Works Rates In The Contractor’s Bid Shall Be Used For Small Additional Amounts Of Work Only When The Procuring Entity’s Representative Has Given Written Instructions In Advance For Additional Work To Be Paid For In That Way. 29.2. All Work To Be Paid For As Day Works Shall Be Recorded By The Contractor On Forms Approved By The Procuring Entity’s Representative. Each Completed Form Shall Be Verified And Signed By The Procuring Entity’s Representative Within Two Days Of The Work Being Done. 29.3. The Contractor Shall Be Paid For Day Works Subject To Obtaining Signed Dayworks Forms. 30. Early Warning 30.1. The Contractor Shall Warn The Procuring Entity’s Representative At The Earliest Opportunity Of Specific Likely Future Events Or Circumstances That May Adversely Affect The Quality Of The Work, Increase The Contract Price, Or Delay The Execution Of The Works. The Procuring Entity’s Representative May Require The Contractor To Provide An Estimate Of The Expected Effect Of The Future Event Or Circumstance On The Contract Price And Completion Date. The Estimate Shall Be Provided By The Contractor As Soon As Reasonably Possible. 30.2. The Contractor Shall Cooperate With The Procuring Entity’s Representative In Making And Considering Proposals For How The Effect Of Such An Event Or Circumstance Can Be Avoided Or Reduced By Anyone Involved In The Work And In Carrying Out Any Resulting Instruction Of The Procuring Entity’s Representative. 31. Program Of Work 31.1. Within The Time Stated In The Scc, The Contractor Shall Submit To The Procuring Entity’s Representative For Approval A Program Of Work Showing The General Methods, Arrangements, Order, And Timing For All The Activities In The Works. 31.2. An Update Of The Program Of Work Shall The Show The Actual Progress Achieved On Each Activity And The Effect Of The Progress Achieved On The Timing Of The Remaining Work, Including Any Changes To The Sequence Of The Activities. 31.3. The Contractor Shall Submit To The Procuring Entity’s Representative For Approval An Updated Program Of Work At Intervals No Longer Than The Period Stated In The Scc. If The Contractor Does Not Submit An Updated Program Of Work Within This Period, The Procuring Entity’s Representative May Withhold The Amount Stated In The Scc From The Next Payment Certificate And Continue To Withhold This Amount Until The Next Payment After The Date On Which The Overdue Program Of Work Has Been Submitted. 31.4. The Procuring Entity’s Representative’s Approval Of The Program Of Work Shall Not Alter The Contractor’s Obligations. The Contractor May Revise The Program Of Work And Submit It To The Procuring Entity’s Representative Again At Any Time. A Revised Program Of Work Shall Show The Effect Of Any Approved Variations. 31.5. When The Program Of Work Is Updated, The Contractor Shall Provide The Procuring Entity’s Representative With An Updated Cash Flow Forecast. The Cash Flow Forecast Shall Include Different Currencies, As Defined In The Contract, Converted As Necessary Using The Contract Exchange Rates. 31.6. All Variations Shall Be Included In Updated Program Of Work Produced By The Contractor. 32. Management Conferences 32.1. Either The Procuring Entity’s Representative Or The Contractor May Require The Other To Attend A Management Conference. The Management Conference Shall Review The Plans For Remaining Work And Deal With Matters Raised In Accordance With The Early Warning Procedure. 32.2. The Procuring Entity’s Representative Shall Record The Business Of Management Conferences And Provide Copies Of The Record To Those Attending The Conference And To The Procuring Entity . The Responsibility Of The Parties For Actions To Be Taken Shall Be Decided By The Procuring Entity’s Representative Either At The Management Conference Or After The Management Conference And Stated In Writing To All Who Attended The Conference. 33. Bill Of Quantities 33.1. The Bill Of Quantities Shall Contain Items Of Work For The Construction, Installation, Testing, And Commissioning Of Work To Be Done By The Contractor. 33.2. The Bill Of Quantities Is Used To Calculate The Contract Price. The Contractor Is Paid For The Quantity Of The Work Done At The Rate In The Bill Of Quantities For Each Item. 33.3. If The Final Quantity Of Any Work Done Differs From The Quantity In The Bill Of Quantities For The Particular Item And Is Not More Than Twenty Five Percent (25%) Of The Original Quantity, Provided The Aggregate Changes For All Items Do Not Exceed Ten Percent (10%) Of The Contract Price, The Procuring Entity’s Representative Shall Make The Necessary Adjustments To Allow For The Changes Subject To Applicable Laws, Rules, And Regulations. 33.4. If Requested By The Procuring Entity’s Representative, The Contractor Shall Provide The Procuring Entity’s Representative With A Detailed Cost Breakdown Of Any Rate In The Bill Of Quantities. 34. Instructions, Inspections And Audits 34.1. The Procuring Entity’s Personnel Shall At All Reasonable Times During Construction Of The Work Be Entitled To Examine, Inspect, Measure And Test The Materials And Workmanship, And To Check The Progress Of The Construction. 34.2. If The Procuring Entity’s Representative Instructs The Contractor To Carry Out A Test Not Specified In The Specification To Check Whether Any Work Has A Defect And The Test Shows That It Does, The Contractor Shall Pay For The Test And Any Samples. If There Is No Defect, The Test Shall Be A Compensation Event. 34.3. The Contractor Shall Permit The Funding Source Named In The Scc To Inspect The Contractor’s Accounts And Records Relating To The Performance Of The Contractor And To Have Them Audited By Auditors Appointed By The Funding Source, If So Required By The Funding Source. 35. Identifying Defects The Procuring Entity’s Representative Shall Check The Contractor’s Work And Notify The Contractor Of Any Defects That Are Found. Such Checking Shall Not Affect The Contractor’s Responsibilities. The Procuring Entity’s Representative May Instruct The Contractor To Search Uncover Defects And Test Any Work That The Procuring Entity’s Representative Considers Below Standards And Defective. 36. Cost Of Repairs Loss Or Damage To The Works Or Materials To Be Incorporated In The Works Between The Start Date And The End Of The Defects Liability Periods Shall Be Remedied By The Contractor At The Contractor’s Cost If The Loss Or Damage Arises From The Contractor’s Acts Or Omissions. 37. Correction Of Defects 37.1. The Procuring Entity’s Representative Shall Give Notice To The Contractor Of Any Defects Before The End Of The Defects Liability Period, Which Isone (1) Year From Project Completion Up To Final Acceptance By The Procuring Entity’s. 37.2. Every Time Notice Of A Defect Is Given, The Contractor Shall Correct The Notified Defect Within The Length Of Time Specified In The Procuring Entity’s Representative’s Notice. 37.3. The Contractor Shall Correct The Defects Which He Notices Himself Before The End Of The Defects Liability Period. 37.4. The Procuring Entity Shall Certify That All Defects Have Been Corrected. If The Procuring Entity Considers That Correction Of A Defect Is Not Essential, He Can Request The Contractor To Submit A Quotation For The Corresponding Reduction In The Contract Price. If The Procuring Entity Accepts The Quotation, The Corresponding Change In The Scc Is A Variation. 38. Uncorrected Defects 38.1. The Procuring Entity Shall Give The Contractor At Least Fourteen (14) Days Notice Of His Intention To Use A Third Party To Correct A Defect. If The Contractor Does Not Correct The Defect Himself Within The Period, The Procuring Entity May Have The Defect Corrected By The Third Party. The Cost Of The Correction Will Be Deducted From The Contract Price. 38.2. The Use Of A Third Party To Correct Defects That Are Uncorrected By The Contractor Will In No Way Relieve The Contractor Of Its Liabilities And Warranties Under The Contract. 39. Advance Payment 39.1. The Procuring Entity Shall, Upon A Written Request Of The Contractor Which Shall Be Submitted As A Contract Document, Make An Advance Payment To The Contractor In An Amount Not Exceeding Fifteen Percent (15%) Of The Total Contract Price, To Be Made In Lump Sum Or, At The Most Two, Installments According To A Schedule Specified In The Scc. 39.2. The Advance Payment Shall Be Made Only Upon The Submission To And Acceptance By The Procuring Entity Of An Irrevocable Standby Letter Of Credit Of Equivalent Value From A Commercial Bank, A Bank Guarantee Or A Surety Bond Callable Upon Demand, Issued By A Surety Or Insurance Company Duly Licensed By The Insurance Commission And Confirmed By The Procuring Entity. 39.3. The Advance Payment Shall Be Repaid By The Contractor By An Amount Equal To The Percentage Of The Total Contract Price Used For The Advance Payment. 39.4. The Contractor May Reduce His Standby Letter Of Credit Or Guarantee Instrument By The Amounts Refunded By The Monthly Certificates In The Advance Payment. 39.5. The Procuring Entity Will Provide An Advance Payment On The Contract Price As Stipulated In The Conditions Of Contract, Subject To The Maximum Amount Stated In Scc Clause 39.1. 40. Progress Payments 40.1. The Contractor May Submit A Request For Payment For Work Accomplished. Such Request For Payment Shall Be Verified And Certified By The Procuring Entity’s Representative/project Engineer. Except As Otherwise Stipulated In The Scc, Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Not Be Included For Payment. 40.2. The Procuring Entity Shall Deduct The Following From The Certified Gross Amounts To Be Paid To The Contractor As Progress Payment: (a) Cumulative Value Of The Work Previously Certified And Paid For. (b) Portion Of The Advance Payment To Be Recouped For The Month. (c) Retention Money In Accordance With The Condition Of Contract. (d) Amount To Cover Third Party Liabilities. (e) Amount To Cover Uncorrected Discovered Defects In The Works. 40.3. Payments Shall Be Adjusted By Deducting There From The Amounts For Advance Payments And Retention. The Procuring Entity Shall Pay The Contractor The Amounts Certified By The Procuring Entity’s Representative Within Twenty Eight (28) Days From The Date Each Certificate Was Issued. No Payment Of Interest For Delayed Payments And Adjustments Shall Be Made By The Procuring Entity. 40.4. The First Progress Payment May Be Paid By The Procuring Entity To The Contractor Provided That At Least Twenty Percent (20%) Of The Work Has Been Accomplished As Certified By The Procuring Entity’s Representative. 40.5. Items Of The Works For Which A Price Of “0” (zero) Has Been Entered Will Not Be Paid For By The Procuring Entity And Shall Be Deemed Covered By Other Rates And Prices In The Contract. 41. Payment Certificates 41.1. The Contractor Shall Submit To The Procuring Entity’s Representative Monthly Statements Of The Estimated Value Of The Work Executed Less The Cumulative Amount Certified Previously. 41.2. The Procuring Entity’s Representative Shall Check The Contractor’s Monthly Statement And Certify The Amount To Be Paid To The Contractor. 41.3. The Value Of Work Executed Shall: (a) Be Determined By The Procuring Entity’s Representative; (b) Comprise The Value Of The Quantities Of The Items In The Bill Of Quantities Completed; And (c) Include The Valuations Of Approved Variations. 41.4. The Procuring Entity’s Representative May Exclude Any Item Certified In A Previous Certificate Or Reduce The Proportion Of Any Item Previously Certified In Any Certificate In The Light Of Later Information. 42. Retention 42.1. The Procuring Entity Shall Retain From Each Payment Due To The Contractor An Amount Equal To A Percentage Thereof Using The Rate As Specified In Itb Sub-clause 42.2. 42.2. Progress Payments Are Subject To Retention Of Ten Percent (10%), Referred To As The “retention Money.” Such Retention Shall Be Based On The Total Amount Due To The Contractor Prior To Any Deduction And Shall Be Retained From Every Progress Payment Until Fifty Percent (50%) Of The Value Of Works, As Determined By The Procuring Entity, Are Completed. If, After Fifty Percent (50%) Completion, The Work Is Satisfactorily Done And On Schedule, No Additional Retention Shall Be Made; Otherwise, The Ten Percent (10%) Retention Shall Again Be Imposed Using The Rate Specified Therefore. 42.3. The Total “retention Money” Shall Be Due For Release Upon Final Acceptance Of The Works. The Contractor May, However, Request The Substitution Of The Retention Money For Each Progress Billing With Irrevocable Standby Letters Of Credit From A Commercial Bank, Bank Guarantees Or Surety Bonds Callable On Demand, Of Amounts Equivalent To The Retention Money Substituted For And Acceptable To The Procuring Entity, Provided That The Project Is On Schedule And Is Satisfactorily Undertaken. Otherwise, The Ten (10%) Percent Retention Shall Be Made. Said Irrevocable Standby Letters Of Credit, Bank Guarantees And/or Surety Bonds, To Be Posted In Favor Of The Government Shall Be Valid For A Duration To Be Determined By The Concerned Implementing Office/agency Or Procuring Entity And Will Answer For The Purpose For Which The Ten (10%) Percent Retention Is Intended, I.e., To Cover Uncorrected Discovered Defects And Third Party Liabilities. 42.4. On Completion Of The Whole Works, The Contractor May Substitute Retention Money With An “on Demand” Bank Guarantee In A Form Acceptable To The Procuring Entity. 43. Variation Orders 43.1. Variation Orders May Be Issued By The Procuring Entity To Cover Any Increase/decrease In Quantities, Including The Introduction Of New Work Items That Are Not Included In The Original Contract Or Reclassification Of Work Items That Are Either Due To Change Of Plans, Design Or Alignment To Suit Actual Field Conditions Resulting In Disparity Between The Preconstruction Plans Used For Purposes Of Bidding And The “as Staked Plans” Or Construction Drawings Prepared After A Joint Survey By The Contractor And The Procuring Entity After Award Of The Contract, Provided That The Cumulative Amount Of The Variation Order Does Not Exceed Ten Percent (10%) Of The Original Project Cost. The Addition/deletion Of Works Should Be Within The General Scope Of The Project As Bid And Awarded. The Scope Of Works Shall Not Be Reduced So As To Accommodate A Positive Variation Order. A Variation Order May Either Be In The Form Of A Change Order Or Extra Work Order. 43.2. A Change Order May Be Issued By The Procuring Entity To Cover Any Increase/decrease In Quantities Of Original Work Items In The Contract. 43.3. An Extra Work Order May Be Issued By The Procuring Entity To Cover The Introduction Of New Work Necessary For The Completion, Improvement Or Protection Of The Project Which Were Not Included As Items Of Work In The Original Contract, Such As, Where There Are Subsurface Or Latent Physical Conditions At The Site Differing Materially From Those Indicated In The Contract, Or Where There Are Duly Unknown Physical Conditions At The Site Of An Unusual Nature Differing Materially From Those Ordinarily Encountered And Generally Recognized As Inherent In The Work Or Character Provided For In The Contract. 43.4. Any Cumulative Variation Order Beyond Ten Percent (10%) Shall Be Subject Of Another Contract To Be Bid Out If The Works Are Separable From The Original Contract. In Exceptional Cases Where It Is Urgently Necessary To Complete The Original Scope Of Work, The Head Of The Procuring Entity May Authorize A Positive Variation Order Go Beyond Ten Percent (10%) But Not More Than Twenty Percent (20%) Of The Original Contract Price, Subject To The Guidelines To Be Determined By The Gppb: Provided, However, That Appropriate Sanctions Shall Be Imposed On The Designer, Consultant Or Official Responsible For The Original Detailed Engineering Design Which Failed To Consider The Variation Order Beyond Ten Percent (10%). 43.5. In Claiming For Any Variation Order, The Contractor Shall, Within Seven (7) Calendar Days After Such Work Has Been Commenced Or After The Circumstances Leading To Such Condition(s) Leading To The Extra Cost, And Within Twenty-eight (28) Calendar Days Deliver A Written Communication Giving Full And Detailed Particulars Of Any Extra Cost In Order That It May Be Investigated At That Time. Failure To Provide Either Of Such Notices In The Time Stipulated Shall Constitute A Waiver By The Contractor For Any Claim. The Preparation And Submission Of Variation Orders Are As Follows: (a) If The Procuring Entity’s Representative/project Engineer Believes That A Change Order Or Extra Work Order Should Be Issued, He Shall Prepare The Proposed Order Accompanied With The Notices Submitted By The Contractor, The Plans Therefore, His Computations As To The Quantities Of The Additional Works Involved Per Item Indicating The Specific Stations Where Such Works Are Needed, The Date Of His Inspections And Investigations Thereon, And The Log Book Thereof, And A Detailed Estimate Of The Unit Cost Of Such Items Of Work, Together With His Justifications For The Need Of Such Change Order Or Extra Work Order, And Shall Submit The Same To The Head Of The Procuring Entity For Approval. (b) The Head Of The Procuring Entity Or His Duly Authorized Representative, Upon Receipt Of The Proposed Change Order Or Extra Work Order Shall Immediately Instruct The Technical Staff Of The Procuring Entity’s To Conduct An On-the-spot Investigation To Verify The Need For The Work To Be Prosecuted. A Report Of Such Verification Shall Be Submitted Directly To The Head Of The Procuring Entity Or His Duly Authorized Representative. (c) The, Head Of The Procuring Entity Or His Duly Authorized Representative, After Being Satisfied That Such Change Order Or Extra Work Order Is Justified And Necessary, Shall Review The Estimated Quantities And Prices And Forward The Proposal With The Supporting Documentation To The Head Of Procuring Entity For Consideration. (d) If, After Review Of The Plans, Quantities And Estimated Unit Cost Of The Items Of Work Involved, The Proper Office Of The Procuring Entity Empowered To Review And Evaluate Change Orders Or Extra Work Orders Recommends Approval Thereof, Head Of The Procuring Entity Or His Duly Authorized Representative, Believing The Change Order Or Extra Work Order To Be In Order, Shall Approve The Same. (e) The Timeframe For The Processing Of Variation Orders From The Preparation Up To The Approval By The Head Of The Procuring Entity Concerned Shall Not Exceed Thirty (30) Calendar Days. 44. Contract Completion Once The Project Reaches An Accomplishment Of Ninety Five (95%) Of The Total Contract Amount, The Procuring Entity May Create An Inspectorate Team To Make Preliminary Inspection And Submit A Punch-list To The Contractor In Preparation For The Final Turnover Of The Project. Said Punch-list Will Contain, Among Others, The Remaining Works, Work Deficiencies For Necessary Corrections, And The Specific Duration/time To Fully Complete The Project Considering The Approved Remaining Contract Time. This, However, Shall Not Preclude The Claim Of The Procuring Entity For Liquidated Damages. 45. Suspension Of Work 45.1. The Procuring Entity Shall Have The Authority To Suspend The Work Wholly Or Partly By Written Order For Such Period As May Be Deemed Necessary, Due To Force Majeure Or Any Fortuitous Events Or For Failure On The Part Of The Contractor To Correct Bad Conditions Which Are Unsafe For Workers Or For The General Public, To Carry Out Valid Orders Given By The Procuring Entity Or To Perform Any Provisions Of The Contract, Or Due To Adjustment Of Plans To Suit Field Conditions As Found Necessary During Construction. The Contractor Shall Immediately Comply With Such Order To Suspend The Work Wholly Or Partly. 45.2. The Contractor Or Its Duly Authorized Representative Shall Have The Right To Suspend Work Operation On Any Or All Projects/activities Along The Critical Path Of Activities After Fifteen (15) Calendar Days From Date Of Receipt Of Written Notice From The Contractor To The District Engineer/regional Director/consultant Or Equivalent Official, As The Case May Be, Due To The Following: (a) There Exist Right-of-way Problems Which Prohibit The Contractor From Performing Work In Accordance With The Approved Construction Schedule. (b) Requisite Construction Plans Which Must Be Owner-furnished Are Not Issued To The Contractor Precluding Any Work Called For By Such Plans. (c) Peace And Order Conditions Make It Extremely Dangerous, If Not Possible, To Work. However, This Condition Must Be Certified In Writing By The Philippine National Police (pnp) Station Which Has Responsibility Over The Affected Area And Confirmed By The Department Of Interior And Local Government (dilg) Regional Director. (d) There Is Failure On The Part Of The Procuring Entity To Deliver Government-furnished Materials And Equipment As Stipulated In The Contract. (e) Delay In The Payment Of Contractor’s Claim For Progress Billing Beyond Forty-five (45) Calendar Days From The Time The Contractor’s Claim Has Been Certified To By The Procuring Entity’s Authorized Representative That The Documents Are Complete Unless There Are Justifiable Reasons Thereof Which Shall Be Communicated In Writing To The Contractor. 45.3. In Case Of Total Suspension, Or Suspension Of Activities Along The Critical Path, Which Is Not Due To Any Fault Of The Contractor, The Elapsed Time Between The Effective Order Of Suspending Operation And The Order To Resume Work Shall Be Allowed The Contractor By Adjusting The Contract Time Accordingly. 46. Payment On Termination 46.1. If The Contract Is Terminated Because Of A Fundamental Breach Of Contract By The Contractor, The Procuring Entity’s Representative Shall Issue A Certificate For The Value Of The Work Done And Materials Ordered Less Advance Payments Received Up To The Date Of The Issue Of The Certificate And Less The Percentage To Apply To The Value Of The Work Not Completed, As Indicated In The Scc. Additional Liquidated Damages Shall Not Apply. If The Total Amount Due To The Procuring Entity Exceeds Any Payment Due To The Contractor, The Difference Shall Be A Debt Payable To The Procuring Entity. 46.2. If The Contract Is Terminated For The Procuring Entity’s Convenience Or Because Of A Fundamental Breach Of Contract By The Procuring Entity, The Procuring Entity’s Representative Shall Issue A Certificate For The Value Of The Work Done, Materials Ordered, The Reasonable Cost Of Removal Of Equipment, Repatriation Of The Contractor’s Personnel Employed Solely On The Works, And The Contractor’s Costs Of Protecting And Securing The Works, And Less Advance Payments Received Up To The Date Of The Certificate. 46.3. The Net Balance Due Shall Be Paid Or Repaid Within Twenty Eight (28) Days From The Notice Of Termination. 46.4. If The Contractor Has Terminated The Contract Under Gcc Clauses 17 Or 18, The Procuring Entity Shall Promptly Return The Performance Security To The Contractor. 47. Extension Of Contract Time 47.1. Should The Amount Of Additional Work Of Any Kind Or Other Special Circumstances Of Any Kind Whatsoever Occur Such As To Fairly Entitle The Contractor To An Extension Of Contract Time, The Procuring Entity Shall Determine The Amount Of Such Extension; Provided That The Procuring Entity Is Not Bound To Take Into Account Any Claim For An Extension Of Time Unless The Contractor Has, Prior To The Expiration Of The Contract Time And Within Thirty (30) Calendar Days After Such Work Has Been Commenced Or After The Circumstances Leading To Such Claim Have Arisen, Delivered To The Procuring Entity Notices In Order That It Could Have Investigated Them At That Time. Failure To Provide Such Notice Shall Constitute A Waiver By The Contractor Of Any Claim. Upon Receipt Of Full And Detailed Particulars, The Procuring Entity Shall Examine The Facts And Extent Of The Delay And Shall Extend The Contract Time Completing The Contract Work When, In The Procuring Entity’s Opinion, The Findings Of Facts Justify An Extension. 47.2. No Extension Of Contract Time Shall Be Granted The Contractor Due To (a) Ordinary Unfavorable Weather Conditions And (b) Inexcusable Failure Or Negligence Of Contractor To Provide The Required Equipment, Supplies Or Materials. 47.3. Extension Of Contract Time May Be Granted Only When The Affected Activities Fall Within The Critical Path Of The Pert/cpm Network. 47.4. No Extension Of Contract Time Shall Be Granted When The Reason Given To Support The Request For Extension Was Already Considered In The Determination Of The Original Contract Time During The Conduct Of Detailed Engineering And In The Preparation Of The Contract Documents As Agreed Upon By The Parties Before Contract Perfection. 47.5. Extension Of Contract Time Shall Be Granted For Rainy/unworkable Days Considered Unfavorable For The Prosecution Of The Works At The Site, Based On The Actual Conditions Obtained At The Site, In Excess Of The Number Of Rainy/unworkable Days Pre-determined By The Procuring Entity In Relation To The Original Contract Time During The Conduct Of Detailed Engineering And In The Preparation Of The Contract Documents As Agreed Upon By The Parties Before Contract Perfection, And/or For Equivalent Period Of Delay Due To Major Calamities Such As Exceptionally Destructive Typhoons, Floods And Earthquakes, And Epidemics, And For Causes Such As Non-delivery On Time Of Materials, Working Drawings, Or Written Information To Be Furnished By The Procuring Entity, Non-acquisition Of Permit To Enter Private Properties Within The Right-of-way Resulting In Complete Paralyzation Of Construction Activities, And Other Meritorious Causes As Determined By The Procuring Entity’s Representative And Approved By The Head Of The Procuring Entity. Shortage Of Construction Materials, General Labor Strikes, And Peace And Order Problems That Disrupt Construction Operations Through No Fault Of The Contractor May Be Considered As Additional Grounds For Extension Of Contract Time Provided They Are Publicly Felt And Certified By Appropriate Government Agencies Such As Dti, Dole, Dilg, And Dnd, Among Others. The Written Consent Of Bondsmen Must Be Attached To Any Request Of The Contractor For Extension Of Contract Time And Submitted To The Procuring Entity For Consideration And The Validity Of The Performance Security Shall Be Correspondingly Extended. 48. Price Adjustment Except For Extraordinary Circumstances As Determined By Neda And Approved By The Gppb, No Price Adjustment Shall Be Allowed. Nevertheless, In Cases Where The Cost Of The Awarded Contract Is Affected By Any Applicable New Laws, Ordinances, Regulations, Or Other Acts Of The Gop, Promulgated After The Date Of Bid Opening, A Contract Price Adjustment Shall Be Made Or Appropriate Relief Shall Be Applied On A No Loss-no Gain Basis. 49. Completion The Contractor Shall Request The Procuring Entity’s Representative To Issue A Certificate Of Completion Of The Works, And The Procuring Entity’s Representative Will Do So Upon Deciding That The Work Is Completed. 50. Taking Over The Procuring Entity Shall Take Over The Site And The Works Within Seven (7) Days From The Date The Procuring Entity’s Representative Issues A Certificate Of Completion. 51. Operating And Maintenance Manuals 51.1. If “as Built” Drawings And/or Operating And Maintenance Manuals Are Required, The Contractor Shall Supply Them By The Dates Stated In The Scc. 51.2. If The Contractor Does Not Supply The Drawings And/or Manuals By The Dates Stated In The Scc, Or They Do Not Receive The Procuring Entity’s Representative’s Approval, The Procuring Entity’s Representative Shall Withhold The Amount Stated In The Scc From Payments Due To The Contractor. Section V. Special Conditions Of Contract Gcc Clause 1.16 The Intended Completion Date Is 75 Cd From Ntp. 1.21 The Procuring Entity Is Lgu- Mapanas, Northern Samar. 1.22 The Procuring Entity’s Representative Is Atty. Ronn Michael L. Tejano Municipal Mayor Municipality Of Mapanas Province Of Northern Samar 1.23 The Site Is Located At Mapanas, Northern Samar. 1.27 The Start Date Is: Upon Receipt Of Notice To Proceed. 1.30 Rehabilitation/improvement Of Aquino St. And San Miguel, Brgy. Santa Potenciana, Mapanas, Northern Samar B.5 Project Billboard/signboard 1.00 Each B.7 (2) Occupational Safety And Health Program 1.00 L.s. B.9 Mobilization And Demobiliation 1.00 L.s. 101 (3)a.2 Removal Of Existing Pcc Pavement, 0.2m Thk, Pccp (for Reblocking At Intermittent Section) 539.00 Sq.m. 102 (2)b Surplus Common Excavation 162.00 Cu.m. 105 (1) Subgrade Preparation (common Material) 648.00 Sq.m. 200 (1) Aggregate Subbase Course 115.20 Cu.m. 201 (1) Aggregate Base Course 140.40 Cu.m. 311 (1)a.2 Pcc Pavement (plain)-conventional Method, 200mm Thk. 540.00 Sq.m. 2.2 Note: The Items To Follow 5.1 The Procuring Entity Shall Give Possession Of All Parts Of The Site To The Contractor Upon The Issuance Of Notice To Proceed. 6.5 The Contractor Shall Employ The Following Key Personnel: Key Personnel Number Civil Engineer 1 Construction Foreman 1 Labor Workers 3 7.4(c) “no Further Instructions”. 7.7 No Further Instructions. 8.1 No Further Instructions. 10 The Site Investigation Reports Are: None 12.3 No Further Instructions. 12.5 In Case Of Semi-permanent Structures, Such As Buildings Of Types 1, 2, And 3 As Classified Under The National Building Code Of The Philippines, Concrete/asphalt Roads, Concrete River Control, Drainage, Irrigation Lined Canals, River Landing, Deep Wells, Rock Causeway, Pedestrian Overpass, And Other Similar Semi-permanent Structures: Five (5) Years. 13 “no Additional Provision.” 18.3(h)(i) No Further Instructions. 21.2 The Arbiter Is: Construction Industry Arbitration Commission 29.1 No Day Works Are Applicable To The Contract. 31.1 The Contractor Shall Submit The Program Of Work To The Procuring Entity’s Representative Within 15days Of Delivery Of The Letter Of Acceptance. 31.3 The Period Between Program Of Work Updates Is 15days. The Amount To Be Withheld For Late Submission Of An Updated Program Of Work Is P 1,000.00. 34.3 The Funding Source Is Coming From Nia 39.1 The Amount Of The Advance Payment Is 15% Of The Contract Price (lump Sum) And Shall Be Release Once Upon Presentation Of The Following Documents As Required: 1. Letter Request For Advance Payment From The Contractor 2. Bank Guarantee For Advance Payment 40.1 Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Be Included For Payment. 51.1 The Date By Which Operating And Maintenance Manuals Are Required Is Not Applicable. The Date By Which “as Built” Drawings Are Required Is 20 Days Upon Completion Of The Subproject. 51.2 The Amount To Be Withheld For Failing To Produce “as Built” Drawings And/or Operating And Maintenance Manuals By The Date Required Is P1,000.00. Section Vi. Specifications Project Name: Rehabilitation/improvement Of Aquino St. And San Miguel Location : Brgy. Santa Potenciana, Mapanas, Northern Samar Item No. Description Qty. Unit. B.5 Project Billboard/signboard 1.00 Each A. 1 Labor A. Construction Foreman 4.00 B. Skilled Laborer 4.00 C. Unskilled Laborer 4.00 A.2 Labor Construction Foreman Skilled Laborer Unskilled Laborer Name And Capacity B. 1 Equipment B. 2 Equipment Name And Specification F.1 Materials A. Tarpaulin (8’ X 8”) 1.00 Pc. B. Coco Lumber 84.00 Bd.ft. C. Plywood Marine, (0.0125m X 1.2m X 2.44m) 2.00 Pc. D. Assorted Common Wire Nail 0.50 Kg. F.2 Materials A. A. Tarpaulin (8’ X 8”) B. Coco Lumber C. Plywood Marine, (0.0125m X 1.2m X 2.44m) D. Assorted Common Wire Nail B.7 (2) Occupational Safety And Health Program 1.00 L.s A.1 Labor A. Safety Practitioner/officer (part Time) 9.00 1 B. Health Personnel (full Time) 35.00 1 A.2 Labor A. Safety Practitioner/officer (part Time) B. Health Personnel (full Time) Name And Capacity B.1 Equipment A. Safety Shoes 31.00 Man-day B. Safety Helmet 31.00 Man-day C. Safety/working Gloves 31.00 Man-day D. Safety Vest 31.00 Man-day E. Rubber Boots 31.00 Man-day F. Rain Coats (30% Of The Duration) Optional 10.00 Man-day B.2 Equipment Safety Shoes Safety Helmet Safety/working Gloves Safety Vest Rubber Boots Rain Coats (30% Of The Duration) Optional Name And Specification F.1 Materials F.2 Materials B.9 Mobilization/demobilization 1.00 L.s. A.1 Labor A.2 Labor Name And Capacity B.1 Equipment Dumptruck (12 Cu.yd) 16.00 2 Payloader (1.5 Cu.m.), Lx80-2c 16.00 1 Bulldozer, D6h Series Ii Psds/dd 16.00 1 Backhoe W/ Breaker (0.80 Cu.m.) 16.00 1 B.2 Equipment Name And Specification F.1 Materials F.2 Materials 101 (3)a.2 Removal Of Existing Pcc Pavement, 0.2m Thk, Pccp (for Reblocking At Intermittent Section) 539.00 Sq.m. A.1 A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 A.2 A. Construction Foreman B. Unskilled Laborer Name And Capacity B.1 Equipment A. Backhoe W/ Breaker (0.80 Cu.m.) 1.00 1 B. Payloader (1.50), Lx80-2c 1.00 1 C. Dumptruck (12 Cu.yd.) 0.50 1 D. Concrete Saw (7.5 Hp), 14” Blade Dia 0.50 1 E. Minor Tools (10% Of Labor Cost) B.2 Equipment A. Backhoe W/ Breaker (0.80 Cu.m.) B. Payloader (1.50), Lx80-2c C. Dumptruck (12 Cu.yd.) Minor Tools (10% Of Labor Cost) Name And Specification F.1 Materials Concrete Saw (diamond Blade 14”dia) 0.00015 Pc 102 (2)b Surplus Common Excavation 71.77 Cu.m. A.1 Labor A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 A.2 Labor Construction Foreman Unskilled Laborer Name And Capacity B.1 Equipment A. Bulldozer, D6h Series Ii Psds/dd 1.00 1 B. Payloader (1.5 Cu.m.) 1.00 1 C. Payloader (1.5 Cu.m.) 0.30 1 D. Dump Truck (12 Cu.yd.) 1.00 3 E. Backhoe (0.80 Cu.m.) 1.00 1 B.2 Equipment A. Bulldozer, D6h Series Ii Psds/dd B. Payloader (1.5 Cu.m.) C. Payloader (1.5 Cu.m.) D. Dump Truck (12 Cu.yd.) E. Backhoe (0.80 Cu.m.) Name And Specification F.1 Materials F.2 Materials 105 (1) Subgrade Preparation (common Material) 648.00 Sq.m. A.1 Labor A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 A.2 Labor Construction Foreman Unskilled Laborer Name And Capacity B.1 Equipment A. Motorized Road Grader 1.00 1 B. Vibrator Roller (10 M.t), Sd100dc 1.00 1 C. Water Truck/pump (16000 L) 0.25 1 B.2 Equipment Motorized Road Grader Vibrator Roller (10 M.t), Sd100dc Water Truck/pump (16000 L) Name And Specification F.1 Materials F.2 Materials 200(1) Aggregate Subbase Course 115.20 Cu.m. A.1 Labor Construction Foreman 1.00 1 Unskilled Laborer 1.00 2 A.2 Labor Construction Foreman Unskilled Laborer Name And Capacity B.1 Equipment Motorized Road Grader, G710a 1.00 1 Vibrator Roller (10 M.t), Sd100dc 1.00 1 Water Truck/pump (16000 L) 0.25 1 B.2 Equipment Motorized Road Grader Vibrator Roller (10 M.t), Sd100dc Water Truck/pump (16000 L) Name And Specification F.1 Materials A. Aggregate Subbase Course (w/ 15% Shrinkage Factor) 1.15 Cu.m. F.2 Materials A. Aggregate Subbase Course (w/ 15% Shrinkage Factor) 201 (1) Aggregate Base Course 140.40 Cu.m. A.1 Labor Construction Foreman 1.00 1 Unskilled Laborer 1.00 2 A.2 Labor Construction Foreman Unskilled Laborer Name And Capacity B.1 Equipment Motorized Road Grader, G710a 1.00 1 Vibrator Roller (10 M.t), Sd100dc 1.00 1 Water Truck/pump (16000 L) 0.25 1 B.2 Equipment Motorized Road Grader Vibrator Roller (10 M.t), Sd100dc Water Truck/pump (16000 L) Name And Specification F.1 Materials A. Aggregate Subbase Course (w/ 15% Shrinkage Factor) 1.15 Cu.m. F.2 Materials A. Aggregate Subbase Course (w/ 15% Shrinkage Factor) 311 (1)a.2 Pcc Pavement (plain)- Conventional Method, 200mm Thk. 124.00 Sq.m. A.1 Labor A. Construction Foreman 1.00 1 B. Skilled Laborer 1.00 4 C. Unskilled Laborer 1.00 12 Name And Capacity B.1 Equipment A. Transit Mixer (5-6 Cu.yd) 1.00 4 B. Concrete Vibrator 1.00 2 C. Concrete Batch Plant (30 Cu.m.) 1.00 1 D. Payloader (1.50 Cu.m.), Lx80-2c 1.00 1 E. Concrete Screeder (5.5 Hp) 1.00 1 F. Water Truck/pump (16000l) 1.00 1 G. Concrete Saw, Blade Ǿ 14” (7.5 Hp) 1.00 1 H. Bar Cutter, Single Phase 0.10 1 I. Joint Sealer Machine 0.25 1 Minor Tools (5% Of Labor) Name And Specification F.1 Materials A. Reinforcing Steel Bar, Grade 40 0.39 Kg. B. Curing Compound 0.29 Lit. C. Asphalt Sealant 0.12 Lit. D. Steel Forms (rental) 0.46 L.m. E. Sand 0.1100 Cu.m. F. Gravel 0.20 Cu.m. G. Portland Cement, Type 1 1.90 Bag H. Concrete Saw (diamond Blade 14”) 0.00015 Pc I. Pipe Sleeve, 2” Dia 0.0086 L.m. J. Grease Tar 0.0056 Lit. Section Vii. Drawings Bill Of Quantities Item No. Scope Of Work Quantity Unit Unit Cost Total Amount Rehabilitation/improvement Of Aquino St. And San Miguel, Brgy. Santa Potenciana, Mapanas, Northern Samar B.5 Project Billboard/signboard 1.00 Each 10,959.69 10,959.69 B.7 (2) Occupational Safety And Health Program 1.00 L.s. 29,575.74 29,575.74 B.9 Mobilization And Demobiliation 1.00 L.s. 15,433.55 15,433.55 101 (3)a.2 Removal Of Existing Pcc Pavement, 0.2m Thk, Pccp (for Reblocking At Intermittent Section) 539.00 Sq.m. 238.30 128,443.70 102 (2)b Surplus Common Excavation 162.00 Cu.m. 204.24 33,086.88 105 (1) Subgrade Preparation (common Material) 648.00 Sq.m. 21.14 13,698.72 200 (1) Aggregate Subbase Course 115.20 Cu.m. 1,632.38 188,050.18 201 (1) Aggregate Base Course 140.40 Cu.m. 2,843.65 399,248.46 311 (1)a.2 Pcc Pavement (plain)-conventional Method, 200mm Thk. 540.00 Sq.m. 2,160.51 1,166,675.40 Total 1,985,172.32 Total Cost Of All Line Item Includes Cost Of Contractor’s Profit, Taxes And Ocm. Attached Detailed Cost Estimates Section Ix. Bidding Forms Table Of Contents Bid Form 79 Form Of Contract Agreement 81 Omnibus Sworn Statement 83 Bid Form Date: Iaeb No: To: Lgu-mapanas Northern Samar Address: Mapanas Northern Samar We, The Undersigned, Declare That: We Have Examined And Have No Reservation To The Bidding Documents, Including Addenda, For The Contract Rehabilitation/improvement Of Aquino St. And San Miguel We Offer To Execute The Works For This Contract In Accordance With The Bid And Bid Data Sheet, General And Special Conditions Of Contract Accompanying This Bid; The Total Price Of Our Bid, Excluding Any Discounts Offered In Item (d) Below Is: [insert Information]; The Discounts Offered And The Methodology For Their Application Are: [insert Information]; (a) Our Bid Shall Be Valid For A Period Of 75 Days From The Date Fixed For The Bid Submission Deadline In Accordance With The Bidding Documents, And It Shall Remain Binding Upon Us And May Be Accepted At Any Time Before The Expiration Of That Period; (b) If Our Bid Is Accepted, We Commit To Obtain A Performance Security In The Amount Of [insert Percentage Amount] Percent Of The Contract Price For The Due Performance Of The Contract; (c) Our Firm, Including Any Subcontractors Or Suppliers For Any Part Of The Contract, Have Nationalities From The Following Eligible Countries: [insert Information]; (d) We Are Not Participating, As Bidders, In More Than One Bid In This Bidding Process, Other Than Alternative Offers In Accordance With The Bidding Documents; (e) Our Firm, Its Affiliates Or Subsidiaries, Including Any Subcontractors Or Suppliers For Any Part Of The Contract, Has Not Been Declared Ineligible By The Funding Source; (f) We Understand That This Bid, Together With Your Written Acceptance Thereof Included In Your Notification Of Award, Shall Constitute A Binding Contract Between Us, Until A Formal Contract Is Prepared And Executed; And (g) We Understand That You Are Not Bound To Accept The Lowest Evaluated Bid Or Any Other Bid That You May Receive. Name: In The Capacity Of: Signed: Duly Authorized To Sign The Bid For And On Behalf Of: Date: ___________ Form Of Contract Agreement This Agreement, Made This [insert Date] Day Of [insert Month], [insert Year] Between [name And Address Of Procuring Entity](hereinafter Called The “entity”) And [name And Address Of Contractor] (hereinafter Called The “contractor”). Whereas, The Entity Is Desirous That The Contractor Execute [name And Identification Number Of Contract] (hereinafter Called “the Works”) And The Entity Has Accepted The Bid For [insert The Amount In Specified Currency In Numbers And Words] By The Contractor For The Execution And Completion Of Such Works And The Remedying Of Any Defects Therein. Now This Agreement Witnesseth As Follows: 1. In This Agreement, Words And Expressions Shall Have The Same Meanings As Are Respectively Assigned To Them In The Conditions Of Contract Hereinafter Referred To. 2. The Following Documents Shall Be Attached, Deemed To Form, And Be Read And Construed As Part Of This Agreement, To Wit: (a) General And Special Conditions Of Contract; (b) Drawings/plans; (c) Specifications; (d) Invitation To Apply For Eligibility And To Bid; (e) Instructions To Bidders; (f) Bid Data Sheet; (g) Addenda And/or Supplemental/bid Bulletins, If Any; (h) Bid Form, Including All The Documents/statements Contained In The Bidder’s Bidding Envelopes, As Annexes; (i) Eligibility Requirements, Documents And/or Statements; (j) Performance Security; (k) Credit Line Issued By A Licensed Bank, If Any; (l) Notice Of Award Of Contract And The Bidder’s Conforme Thereto; (m) Other Contract Documents That May Be Required By Existing Laws And/or The Entity. 3. In Consideration Of The Payments To Be Made By The Entity To The Contractor As Hereinafter Mentioned, The Contractor Hereby Covenants With The Entity To Execute And Complete The Works And Remedy Any Defects Therein In Conformity With The Provisions Of This Contract In All Respects. 4. The Entity Hereby Covenants To Pay The Contractor In Consideration Of The Execution And Completion Of The Works And The Remedying Of Defects Wherein, The Contract Price Or Such Other Sum As May Become Payable Under The Provisions Of This Contract At The Times And In The Manner Prescribed By This Contract. In Witness Whereof The Parties Thereto Have Caused This Agreement To Be Executed The Day And Year First Before Written. Signed, Sealed, Delivered By The (for The Entity) Signed, Sealed, Delivered By The (for The Contractor). Binding Signature Of Procuring Entity ________________________________________________ Binding Signature Of Contractor _____________________________________________ [addendum Showing The Corrections, If Any, Made During The Bid Evaluation Should Be Attached With This Agreement] Omnibus Sworn Statement Republic Of The Philippines ) City/municipality Of ______ ) S.s. Affidavit I, [name Of Affiant], Of Legal Age, [civil Status], [nationality], And Residing At [address Of Affiant], After Having Been Duly Sworn In Accordance With Law, Do Hereby Depose And State That: 1. Select One, Delete The Other: If A Sole Proprietorship: I Am The Sole Proprietor Of [name Of Bidder] With Office Address At [address Of Bidder]; If A Partnership, Corporation, Cooperative, Or Joint Venture: I Am The Duly Authorized And Designated Representative Of [name Of Bidder] With Office Address At [address Of Bidder]; 2. Select One, Delete The Other: If A Sole Proprietorship: As The Owner And Sole Proprietor Of [name Of Bidder], I Have Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary To Represent It In The Bidding For [name Of The Project] Of The [name Of The Procuring Entity]; If A Partnership, Corporation, Cooperative, Or Joint Venture: I Am Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary And/or To Represent The [name Of Bidder] In The Bidding As Shown In The Attached [state Title Of Attached Document Showing Proof Of Authorization (e.g., Duly Notarized Secretary’s Certificate Issued By The Corporation Or The Members Of The Joint Venture)]; 3. [name Of Bidder] Is Not “blacklisted” Or Barred From Bidding By The Government Of The Philippines Or Any Of Its Agencies, Offices, Corporations, Or Local Government Units, Foreign Government/foreign Or International Financing Institution Whose Blacklisting Rules Have Been Recognized By The Government Procurement Policy Board; 4. Each Of The Documents Submitted In Satisfaction Of The Bidding Requirements Is An Authentic Copy Of The Original, Complete, And All Statements And Information Provided Therein Are True And Correct; 5. [name Of Bidder]is Authorizing The Head Of The Procuring Entity Or Its Duly Authorized Representative(s) To Verify All The Documents Submitted; 6. Select One, Delete The Rest: If A Sole Proprietorship: I Am Not Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; If A Partnership Or Cooperative: None Of The Officers And Members Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; If A Corporation Or Joint Venture: None Of The Officers, Directors, And Controlling Stockholders Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; 7. [name Of Bidder] Complies With Existing Labor Laws And Standards; And 8. [name Of Bidder] Is Aware Of And Has Undertaken The Following Responsibilities As A Bidder: A) Carefully Examine All Of The Bidding Documents; B) Acknowledge All Conditions, Local Or Otherwise, Affecting The Implementation Of The Contract; C) Made An Estimate Of The Facilities Available And Needed For The Contract To Be Bid, If Any; And D) Inquire Or Secure Supplemental/bid Bulletin(s) Issued For The [name Of The Project]. In Witness Whereof, I Have Hereunto Set My Hand This __ Day Of ___, 20__ At ____________, Philippines. _____________________________________ Bidder’s Representative/authorized Signatory [jurat] * This Form Will Not Apply For Wb Funded Projects.
Closing Date16 Dec 2024
Tender AmountPHP 1.9 Million (USD 33.6 K)
Municipality Of Mapanas, Northern Samar Tender
Civil And Construction...+1Civil Works Others
Philippines
Details: Description Bidding Documents Procurement Of Infrastructure Projects Name Of Project: Completion Of Naparasan-quezon Fmr Barangay Quezon, Mapanas Northern Samar Contract Reference No. 2024-11-105 Table Of Contents Section I. Invitation To Bid 3 Section Ii. Instructions To Bidders 7 Section Iii. Bid Data Sheet 35 Section Iv. General Conditions Of Contract 38 Section V. Special Conditions Of Contract 70 Section Vi. Specifications 72 Section Vii. Drawings 75 Section Viii. Bill Of Quantities Error! Bookmark Not Defined. Section Ix. Bidding Forms 77 Section X. Foreign-assisted Projects Error! Bookmark Not Defined. Section I. Invitation To Bid Bid Notice Abstract Invitation To Bid (itb) Republic Of The Philippines Province Of Northern Samar Municipality Of Mapanas Invitation To Bid For Project: Completion Of Naparasan-quezon Fmr, Brgy. Quezon, Mapanas, Northern Samar The Lgu- Mapanas, Northern Samar, Through The Economic Development Fund Of Fy 2025 Intends To Apply The Sum Of Nine Hundred Eighty Five Thousand Eight Hundred Sixty Three Pesos 77/100 Only (985,863.77) Being The Approved Budget For The Contract (abc) To Payments Under The Contract For : Completion Of Naparasan-quezon Fmr, Brgy. Quezon, Mapanas, Northern Samar Bids Received In Excess Of The Abc Shall Be Automatically Rejected At Bid Opening. 1. The Lgu- Mapanas, Northern Samar Now Invites Bids For The Following Description Of Works To Be Procured: Item No. Scope Of Work Quantity Unit Completion Of Naparasan-quezon Fmr, Brgy. Quezon, Mapanas, Northern Samar B.5 Project Billboard/signboard 1.00 Each B.7 (2) Occupational Safety And Health Program 1.00 L.s. B.9 Mobilization And Demobiliation 1.00 L.s. 102 (2)b Surplus Common Excavation 71.77 Cu.m. 104 (1)a Embankment From Roadway Excavation (common Soil) 71.77 Cu.m. 104 (2)a Embankment From Borrow (common Soil 164.50 Cu.m. 105 (1) Subgrade Preparation (common Material) 186.00 Sq.m. 200 (1) Aggregate Subbase Course 45.11 Cu.m. 201 (1) Aggregate Base Course 42.59 Cu.m. 311 (1)a.2 Pcc Pavement (plain)-conventional Method, 200mm Thk. 124.00 Sq.m. 505 (2)a Grouted Riprap 38.55 Cu.m. 506 (1) Stone Masonry 5.50 Cu.m. Completion Of The Works Is Required 60 Calendar Days. Bidders Should Have Completed, Within Ten (10) Years From The Date Of Submission And Receipt Of Bids, A Contract Similar To The Project. The Description Of An Eligible Bidder Is Contained In The Bidding Documents, Particularly, In Section Ii. Instructions To Bidders. Section Ii. Instructions To Bidders. 2. Bidding Will Be Conducted Through Open Competitive Bidding Procedures Using Non-discretionary Pass/fail Criterion As Specified In The Implementing Rules And Regulations (irr) Of Republic Act 9184 (ra 9184), Otherwise Known As The “government Procurement Reform Act”. Bidding Is Restricted To Filipino Citizens/sole Proprietorships, Partnerships, Or Organizations With At Least Seventy Five Percent (75%) Interest Or Outstanding Capital Stock Belonging To Citizens Of The Philippines. 4. Interested Bidders May Obtain Further Information From Lgu- Bac Mapanas, Northern Samar And Inspect The Bidding Documents At The Address Given Below From December 05, 2024-december 16, 2024, 8:00 A.m. To 5:00 Pm. A Complete Set Of Bidding Documents May Be Purchased By Interested Bidders From The Address Below And Upon Payment Of A Nonrefundable Fee For The Bidding Documents In The Amount Of P1,000.00. It May Also Be Downloaded Free Of Charge From The Website Of The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity, Provided That Bidders Shall Pay The Fee For The Bidding Documents Not Later That The Submission Of Their Bids. 5. The Lgu- Mapana, Northern Samar Will Hold A Pre-bid Conference On December 5, 2024 At 10:00 A.m. At Executive Conference, 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar, Which Shall Be Open Only To All Interested Parties Who Have Purchased The Bidding Documents. 6. Bids Must Be Delivered To The Address Below On Or Before 9:00 A.m. Of December 16, 2024 At Bac Office, @ Municipal Planning & Development Office (mpdo), Mapanas, Northern Samar. All Bids Must Be Accompanied By A Bid Security In Any Of The Acceptable Forms And In The Amount Stated In Itb Clause 18. Bids Will Be Opened In The Presence Of The Bidders’ Authorized Representatives Who Choose To Attend At The Address Below. Late Bids Shall Not Be Accepted. The Bidder May Request That The Bid Documents Be Sent To Them By Mail Or Courier, And For This, The Bidder Shall Pay The Amount In Philippine Peso To Cover The Cost Of Mail Or Courier Delivery. The Fee For Obtaining A Copy Of The Bid Documents And The Cost Of Mail Or Courier Shall Be Paid By The Bidder Thru S Cashier’s Check Or Manager’s Check Issued In Favor Of The Municipality Of Mapanas. 7. The Lgu- Mapanas, Northern Samar Reserves The Right To Accept Or Reject Any Bid, To Annul The Bidding Process, And To Reject All Bids At Any Time Prior To Contract Award, Without Thereby Incurring Any Liability To The Affected Bidder Or Bidders. 8. For Further Information, Please Refer To: Reno C. Salazar Bac Secretary Mapanas, Northern Samar Mobile # 09459852914 Ma. Teresa L. Minguez Bac Chairperson Mapanas, Northern Samar Mobile # 09778033758 Section Ii. Instructions To Bidders 1. The Bids Must Be Delivered On Or Before December 16, 2024 At 9:00 A.m And Failure To Submit The Bid Proposal May Ground For Disqualification Of The Bid. 2. Bids Received In Excess Of The Abc Shall Be Automatically Rejected At Bid Opening. 1. The Lgu- Mapanas, Northern Samar Now Invites Bids For The Following Description Of Works To Be Procured: Item No. Scope Of Work Quantity Unit Completion Of Naparasan-quezon Fmr, Brgy. Quezon, Mapanas, Northern Samar B.5 Project Billboard/signboard 1.00 Each B.7 (2) Occupational Safety And Health Program 1.00 L.s. B.9 Mobilization And Demobiliation 1.00 L.s. 102 (2)b Surplus Common Excavation 71.77 Cu.m. 104 (1)a Embankment From Roadway Excavation (common Soil) 71.77 Cu.m. 104 (2)a Embankment From Borrow (common Soil 164.50 Cu.m. 105 (1) Subgrade Preparation (common Material) 186.00 Sq.m. 200 (1) Aggregate Subbase Course 45.11 Cu.m. 201 (1) Aggregate Base Course 42.59 Cu.m. 311 (1)a.2 Pcc Pavement (plain)-conventional Method, 200mm Thk. 124.00 Sq.m. 505 (2)a Grouted Riprap 38.55 Cu.m. 506 (1) Stone Masonry 5.50 Cu.m. Completion Of The Works Is Required 60 Calendar Days. Bidders Should Have Completed, Within Ten (10) Years From The Date Of Submission And Receipt Of Bids, A Contract Similar To The Project. The Description Of An Eligible Bidder Is Contained In The Bidding Documents, Particularly, In Section Ii. Instructions To Bidders. 2. Bidding Will Be Conducted Through Open Competitive Bidding Procedures Using Non-discretionary Pass/fail Criterion As Specified In The Implementing Rules And Regulations (irr) Of Republic Act 9184 (ra 9184), Otherwise Known As The “government Procurement Reform Act”. Bidding Is Restricted To Filipino Citizens/sole Proprietorships, Partnerships, Or Organizations With At Least Seventy Five Percent (75%) Interest Or Outstanding Capital Stock Belonging To Citizens Of The Philippines. 3. Interested Bidders May Obtain Further Information From Lgu- Bac Mapanas, Northern Samar And Inspect The Bidding Documents At The Address Given Below From November 26, 2024-december 13, 2024, 8:00 A.m. To 5:00 Pm. A Complete Set Of Bidding Documents May Be Purchased By Interested Bidders From The Address Below And Upon Payment Of A Nonrefundable Fee For The Bidding Documents In The Amount Of P1,000.00. It May Also Be Downloaded Free Of Charge From The Website Of The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity, Provided That Bidders Shall Pay The Fee For The Bidding Documents Not Later That The Submission Of Their Bids. 4. The Lgu- Mapanas, Northern Samar Will Hold A Pre-bid Conference On December 5, 2024 At 10:00 A.m. At Executive Conference, 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar, Which Shall Be Open Only To All Interested Parties Who Have Purchased The Bidding Documents. 5. Bids Must Be Delivered To The Address Below On Or Before 9:00 A.m. Of December 16, 2024 At Bac Office, @ Municipal Planning & Development Office (mpdo), Mapanas, Northern Samar. All Bids Must Be Accompanied By A Bid Security In Any Of The Acceptable Forms And In The Amount Stated In Itb Clause 18. Bids Will Be Opened In The Presence Of The Bidders’ Authorized Representatives Who Choose To Attend At The Address Below. Late Bids Shall Not Be Accepted. The Bidder May Request That The Bid Documents Be Sent To Them By Mail Or Courier, And For This, The Bidder Shall Pay The Amount In Philippine Peso To Cover The Cost Of Mail Or Courier Delivery. The Fee For Obtaining A Copy Of The Bid Documents And The Cost Of Mail Or Courier Shall Be Paid By The Bidder Thru S Cashier’s Check Or Manager’s Check Issued In Favor Of The Municipality Of Mapanas. 6. The Lgu- Mapanas, Northern Samar Reserves The Right To Accept Or Reject Any Bid, To Annul The Bidding Process, And To Reject All Bids At Any Time Prior To Contract Award, Without Thereby Incurring Any Liability To The Affected Bidder Or Bidders. 7. For Further Information, Please Refer To: Reno C. Salazar Bac Secretary Mapanas, Northern Samar Mobile # 09459852914 Ma. Teresa L. Minguez Bac Chairperson Mapanas N. Samar Mobile # 09778033758 Table Of Contents A. General 11 1. Scope Of Bid 11 2. Source Of Funds 11 3. Corrupt, Fraudulent, Collusive, And Coercive Practices 11 4. Conflict Of Interest 12 5. Eligible Bidders 14 6. Bidder’s Responsibilities 15 7. Origin Of Goods And Services 17 8. Subcontracts 17 B. Contents Of Bidding Documents 17 9. Pre-bid Conference 17 10. Clarification And Amendment Of Bidding Documents 18 C. Preparation Of Bids 18 11. Language Of Bids 18 12. Documents Comprising The Bid: Eligibility And Technical Components 18 13. Documents Comprising The Bid: Financial Component 21 14. Alternative Bids 21 15. Bid Prices 22 16. Bid Currencies 22 17. Bid Validity 23 18. Bid Security 23 19. Format And Signing Of Bids 25 20. Sealing And Marking Of Bids 26 D. Submission And Opening Of Bids 26 21. Deadline For Submission Of Bids 26 22. Late Bids 26 23. Modification And Withdrawal Of Bids 27 24. Opening And Preliminary Examination Of Bids 27 E. Evaluation And Comparison Of Bids 28 25. Process To Be Confidential 28 26. Clarification Of Bids 29 27. Detailed Evaluation And Comparison Of Bids 29 28. Post Qualification 30 29. Reservation Clause 31 F. Award Of Contract 32 30. Contract Award 32 31. Signing Of The Contract 33 32. Performance Security 33 33. Notice To Proceed 34 A. General 1. Scope Of Bid 1.1. The Procuring Entity As Defined In The Bds, Invites Bids For The Construction Of Works, As Described In Section Vi. Specifications. The Name And Identification Number Of The Contract Is Provided In The Bds. 1.2. The Successful Bidder Will Be Expected To Complete The Works By The Intended Completion Date Specified In Scc Clause 1.16. 2. Source Of Funds The Procuring Entity Has A Budget Or Has Applied For Or Received Funds From The Funding Source Named In The Bds, And In The Amount Indicated In The Bds. It Intends To Apply Part Of The Funds Received For The Project, As Defined In The Bds, To Cover Eligible Payments Under The Contract For The Works. 3. Corrupt, Fraudulent, Collusive, And Coercive Practices 3.1. Unless Otherwise Specified In The Bds, The Procuring Entity, As Well As Bidders And Contractors, Shall Observe The Highest Standard Of Ethics During The Procurement And Execution Of The Contract. In Pursuance Of This Policy, The Funding Source: (a) Defines, For Purposes Of This Provision, The Terms Set Forth Below As Follows: (i) "corrupt Practice" Means Behavior On The Part Of Officials In The Public Or Private Sectors By Which They Improperly And Unlawfully Enrich Themselves, Others, Or Induce Others To Do So, By Misusing The Position In Which They Are Placed, And Includes The Offering, Giving, Receiving, Or Soliciting Of Anything Of Value To Influence The Action Of Any Such Official In The Procurement Process Or In Contract Execution; Entering, On Behalf Of The Procuring Entity, Into Any Contract Or Transaction Manifestly And Grossly Disadvantageous To The Same, Whether Or Not The Public Officer Profited Or Will Profit Thereby, And Similar Acts As Provided In Republic Act 3019; (ii) "fraudulent Practice" Means A Misrepresentation Of Facts In Order To Influence A Procurement Process Or The Execution Of A Contract To The Detriment Of The Procuring Entity, And Includes Collusive Practices Among Bidders (prior To Or After Bid Submission) Designed To Establish Bid Prices At Artificial, Non-competitive Levels And To Deprive The Procuring Entity Of The Benefits Of Free And Open Competition; (iii) “collusive Practices” Means A Scheme Or Arrangement Between Two Or More Bidders, With Or Without The Knowledge Of The Procuring Entity, Designed To Establish Bid Prices At Artificial, Non-competitive Levels; And (iv) “coercive Practices” Means Harming Or Threatening To Harm, Directly Or Indirectly, Persons, Or Their Property To Influence Their Participation In A Procurement Process, Or Affect The Execution Of A Contract; (v) “obstructive Practice” Is (aa) Deliberately Destroying, Falsifying, Altering Or Concealing Of Evidence Material To An Administrative Proceedings Or Investigation Or Making False Statements To Investigators In Order To Materially Impede An Administrative Proceedings Or Investigation Of The Procuring Entity Or Any Foreign Government/foreign Or International Financing Institution Into Allegations Of A Corrupt, Fraudulent, Coercive Or Collusive Practice; And/or Threatening, Harassing Or Intimidating Any Party To Prevent It From Disclosing Its Knowledge Of Matters Relevant To The Administrative Proceedings Or Investigation Or From Pursuing Such Proceedings Or Investigation; Or (bb) Acts Intended To Materially Impede The Exercise Of The Inspection And Audit Rights Of The Procuring Entity Or Any Foreign Government/foreign Or International Financing Institution Herein. (b) Will Reject A Proposal For Award If It Determines That The Bidder Recommended For Award Has Engaged In Corrupt Or Fraudulent Practices In Competing For The Contract; And (c) Will Declare A Firm Ineligible, Either Indefinitely Or For A Stated Period Of Time, To Be Awarded Contract Funded By The Funding Source If It At Any Time Determines That The Firm Has Engaged In Corrupt Or Fraudulent Practices In Competing Or, Or In Executing, A Contract Funded By The Funding Source. 3.2. Further, The Procuring Entity Will Seek To Impose The Maximum Civil, Administrative, And/or Criminal Penalties Available Under The Applicable Laws On Individuals And Organizations Deemed To Be Involved In Any Of The Practices Mentioned In Itb Clause 3.1(a). 3.3. Furthermore, The Funding Source And The Procuring Entity Reserve The Right To Inspect And Audit Records And Accounts Of A Contractor In The Bidding For And Performance Of A Contract Themselves Or Through Independent Auditors As Reflected In The Gcc Clause 34. 4. Conflict Of Interest 4.1. All Bidders Found To Have Conflicting Interests Shall Be Disqualified To Participate In The Procurement At Hand, Without Prejudice To The Imposition Of Appropriate Administrative, Civil, And Criminal Sanctions. A Bidder May Be Considered To Have Conflicting Interests With Another Bidder In Any Of The Events Described In Paragraphs (a) Through (c) And A General Conflict Of Interest In Any Of The Circumstances Set Out In Paragraphs (d) Through (g) Below: (a) A Bidder Has Controlling Shareholders In Common With Another Bidder; (b) A Bidder Receives Or Has Received Any Direct Or Indirect Subsidy From Any Other Bidder; (c) A Bidder Has The Same Legal Representative As That Of Another Bidder For Purposes Of This Bid; (d) A Bidder Has A Relationship, Directly Or Through Third Parties, That Puts Them In A Position To Have Access To Information About Or Influence On The Bid Of Another Bidder Or Influence The Decisions Of The Procuring Entity Regarding This Bidding Process. This Will Include A Firm Or An Organization Who Lends, Or Temporarily Seconds, Its Personnel To Firms Or Organizations Which Are Engaged In Consulting Services For The Preparation Related To Procurement For Or Implementation Of The Project If The Personnel Would Be Involved In Any Capacity On The Same Project; (e) A Bidder Submits More Than One Bid In This Bidding Process. However, This Does Not Limit The Participation Of Subcontractors In More Than One Bid; (f) A Bidder Who Participated As A Consultant In The Preparation Of The Design Or Technical Specifications Of The Goods And Related Services That Are The Subject Of The Bid; Or (g) A Bidder Who Lends, Or Temporary Seconds, Its Personnel To Firms Or Organizations Which Are Engaged In Consulting Services For The Preparation Related To Procurement For Or Implementation Of The Project, If The Personnel Would Be Involved In Any Capacity On The Same Project. 4.2. In Accordance With Section 47 Of The Irr Of Ra 9184, All Bidding Documents Shall Be Accompanied By A Sworn Affidavit Of The Bidder That It Is Not Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), Members Of The Technical Working Group (twg), Members Of The Bac Secretariat, The Head Of The Project Management Office (pmo) Or The End-user Unit, And The Project Consultants, By Consanguinity Or Affinity Up To The Third Civil Degree. On The Part Of The Bidder, This Clause Shall Apply To The Following Persons: (a) If The Bidder Is An Individual Or A Sole Proprietorship, To The Bidder Himself; (b) If The Bidder Is A Partnership, To All Its Officers And Members; (c) If The Bidder Is A Corporation, To All Its Officers, Directors, And Controlling Stockholders; And (d) If The Bidder Is A Joint Venture (jv), The Provisions Of Items (a), (b), Or (c) Of This Clause Shall Correspondingly Apply To Each Of The Members Of The Said Jv, As May Be Appropriate. Relationship Of The Nature Described Above Or Failure To Comply With This Clause Will Result In The Automatic Disqualification Of A Bidder. 5. Eligible Bidders 5.1. Unless Otherwise Indicated In The Bds, The Following Persons Shall Be Eligible To Participate In This Bidding: (a) Duly Licensed Filipino Citizens/sole Proprietorships; (b) Partnerships Duly Organized Under The Laws Of The Philippines And Of Which At Least Seventy Five Percent (75%) Of The Interest Belongs To Citizens Of The Philippines; (c) Corporations Duly Organized Under The Laws Of The Philippines, And Of Which At Least Seventy Five Percent (75%) Of The Outstanding Capital Stock Belongs To Citizens Of The Philippines; (d) Cooperatives Duly Organized Under The Laws Of The Philippines, And Of Which At Least Seventy Five Percent (75%) Of The Interest Belongs To Citizens Of The Philippines; And (e) Persons/entities Forming Themselves Into A Jv, I.e., A Group Of Two (2) Or More Persons/entities That Intend To Be Jointly And Severally Responsible Or Liable For A Particular Contract: Provided, However, That, In Accordance With Letter Of Instructions No. 630, Filipino Ownership Or Interest Of The Joint Venture Concerned Shall Be At Least Seventy Five Percent (75%): Provided, Further, That Joint Ventures In Which Filipino Ownership Or Interest Is Less Than Seventy Five Percent (75%) May Be Eligible Where The Structures To Be Built Require The Application Of Techniques And/or Technologies Which Are Not Adequately Possessed By A Person/entity Meeting The Seventy Five Percent (75%) Filipino Ownership Requirement: Provided, Finally, That In The Latter Case, Filipino Ownership Or Interest Shall Not Be Less Than Twenty Five Percent (25%). For This Purpose Filipino Ownership Or Interest Shall Be Based On The Contributions Of Each Of The Members Of The Joint Venture As Specified In Their Jva. 5.2. The Procuring Entity May Also Invite Foreign Bidders When Provided For Under Any Treaty Or International Or Executive Agreement As Specified In The Bds. 5.3. Government Corporate Entities May Be Eligible To Participate Only If They Can Establish That They (a) Are Legally And Financially Autonomous, (b) Operate Under Commercial Law, And (c) Are Not Dependent Agencies Of The Gop Or The Procuring Entity. 5.4. (a) Unless Otherwise Provided In The Bds, The Bidder Must Have Completed, Within Ten (10) Years From The Submission Of Bids, A Single Contract That Is Similar To This Project, Equivalent To At Least Fifty Percent (50%) Of The Abc Adjusted To Current Prices Using The National Statistics Office Consumer Price Index. (b) For Foreign-funded Procurement, The Procuring Entity And The Foreign Government/foreign Or International Financing Institution May Agree On Another Track Record Requirement, As Specified In The Bds. For This Purpose, Contracts Similar To The Project Shall Be Those Described In Thebds, And Completed Within The Period Stated In The Invitation To Bid And Itb Clause 12.1(a)(iii). 5.5. The Bidder Must Submit A Computation Of Its Net Financial Contracting Capacity (nfcc) Or A Commitment From A Universal Or Commercial Bank To Extend A Credit Line In Its Favor If Awarded The Contract For This Project (clc). The Nfcc, Computed Using The Following Formula, Must Be At Least Equal To The Abc To Be Bid: Nfcc = [(current Assets Minus Current Liabilities) (k)] Minus The Value Of All Outstanding Or Uncompleted Portions Of The Projects Under Ongoing Contracts, Including Awarded Contracts Yet To Be Started Coinciding With The Contract For This Project. Where: K = 10 For A Contract Duration Of One Year Or Less, 15 For A Contract Duration Of More Than One Year Up To Two Years, And 20 For A Contract Duration Of More Than Two Years. The Clc Must Be At Least Equal To Ten Percent (10%) Of The Abc For This Project. If Issued By A Foreign Bank, It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank. In The Case Of Local Government Units (lgus), The Bidder May Also Submit Clc From Other Banks Certified By The Bangko Sentral Ng Pilipinas (bsp) As Authorized To Issue Such Financial Instrument. 6. Bidder’s Responsibilities 6.1. The Bidder Or Its Duly Authorized Representative Shall Submit A Sworn Statement In The Form Prescribed In Section Ix. Bidding Forms As Required In Itb Clause 12.1(b)(iii). 6.2. The Bidder Is Responsible For The Following: (a) Having Taken Steps To Carefully Examine All Of The Bidding Documents; (b) Having Acknowledged All Conditions, Local Or Otherwise, Affecting The Implementation Of The Contract; (c) Having Made An Estimate Of The Facilities Available And Needed For The Contract To Be Bid, If Any; (d) Having Complied With Its Responsibility To Inquire Or Secure Supplemental/bid Bulletin/s As Provided Under Itb Clause 10.3. (e) Ensuring That It Is Not “blacklisted” Or Barred From Bidding By The Gop Or Any Of Its Agencies, Offices, Corporations, Or Lgus, Including Foreign Government/foreign Or International Financing Institution Whose Blacklisting Rules Have Been Recognized By The Gppb; (f) Ensuring That Each Of The Documents Submitted In Satisfaction Of The Bidding Requirements Is An Authentic Copy Of The Original, Complete, And All Statements And Information Provided Therein Are True And Correct; (g) Authorizing The Head Of The Procuring Entity Or Its Duly Authorized Representative/s To Verify All The Documents Submitted; (h) Ensuring That The Signatory Is The Duly Authorized Representative Of The Bidder, And Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary And/or To Represent The Bidder In The Bidding, With The Duly Notarized Secretary’s Certificate Attesting To Such Fact, If The Bidder Is A Corporation, Partnership, Cooperative, Or Joint Venture; (i) Complying With The Disclosure Provision Under Section 47 Of The Act In Relation To Other Provisions Of Republic Act 3019; And (j) Complying With Existing Labor Laws And Standards, If Applicable. Failure To Observe Any Of The Above Responsibilities Shall Be At The Risk Of The Bidder Concerned. 6.3. The Bidder, By The Act Of Submitting Its Bid, Shall Be Deemed To Have Inspected The Site, Determined The General Characteristics Of The Contract Works And The Conditions For This Project And Examine All Instructions, Forms, Terms, And Project Requirements In The Bidding Documents. 6.4. It Shall Be The Sole Responsibility Of The Prospective Bidder To Determine And To Satisfy Itself By Such Means As It Considers Necessary Or Desirable As To All Matters Pertaining To This Project, Including: (a) The Location And The Nature Of The Contract, Project, Or Work; (b) Climatic Conditions; (c) Transportation Facilities; (c) Nature And Condition Of The Terrain, Geological Conditions At The Site Communication Facilities, Requirements, Location And Availability Of Construction Aggregates And Other Materials, Labor, Water, Electric Power And Access Roads; And (d) Other Factors That May Affect The Cost, Duration And Execution Or Implementation Of The Contract, Project, Or Work. 6.5. The Procuring Entity Shall Not Assume Any Responsibility Regarding Erroneous Interpretations Or Conclusions By The Prospective Or Eligible Bidder Out Of The Data Furnished By The Procuring Entity. 6.6. Before Submitting Their Bids, The Bidders Are Deemed To Have Become Familiar With All Existing Laws, Decrees, Ordinances, Acts And Regulations Of The Philippines Which May Affect The Contract In Any Way. 6.7. The Bidder Shall Bear All Costs Associated With The Preparation And Submission Of His Bid, And The Procuring Entity Will In No Case Be Responsible Or Liable For Those Costs, Regardless Of The Conduct Or Outcome Of The Bidding Process. 6.8. Bidders Should Note That The Procuring Entity Will Only Accept Bids Only From Those That Have Paid The Nonrefundable Fee For The Bidding Documents At The Office Indicated In The Invitation To Bid. 7. Origin Of Goods And Services There Is No Restriction On The Origin Of Goods, Or Contracting Of Works Or Services Other Than Those Prohibited By A Decision Of The United Nations Security Council Taken Under Chapter Vii Of The Charter Of The United Nations. 8. Subcontracts 8.1. Unless Otherwise Specified In The Bds, The Bidder May Subcontract Portions Of The Works To An Extent As May Be Approved By The Procuring Entity And Stated In The Bds. However, Subcontracting Of Any Portion Shall Not Relieve The Bidder From Any Liability Or Obligation That May Arise From The Contract For This Project. 8.2. Subcontractors Must Submit The Documentary Requirements Under Itb Clause 12 And Comply With The Eligibility Criteria Specified In The Bds. In The Event That Any Subcontractor Is Found By The Procuring Entity To Be Ineligible, The Subcontracting Of Such Portion Of The Works Shall Be Disallowed. 8.3. The Bidder May Identify The Subcontractor To Whom A Portion Of The Works Will Be Subcontracted At Any Stage Of The Bidding Process Or During Contract Implementation. If The Bidder Opts To Disclose The Name Of The Subcontractor During Bid Submission, The Bidder Shall Include The Required Documents As Part Of The Technical Component Of Its Bid. B. Contents Of Bidding Documents 9. Pre-bid Conference 9.1. (a) If So Specified In The Bds, A Pre-bid Conference Shall Be Held At The Venue And On The Date Indicated Therein, To Clarify And Address The Bidders’ Questions On The Technical And Financial Components Of This Project. (b) The Pre-bid Conference Shall Be Held At Least Twelve (12) Calendar Days Before The Deadline For The Submission Of And Receipt Of Bids. If The Procuring Entity Determines That, By Reason Of The Method, Nature, Or Complexity Of The Contract To Be Bid, Or When International Participation Will Be More Advantageous To The Gop, A Longer Period For The Preparation Of Bids Is Necessary, The Pre-bid Conference Shall Be Held At Least Thirty (30) Calendar Days Before The Deadline For The Submission And Receipt Of Bids, As Specified In The Bds. 9.2. Bidders Are Encouraged To Attend The Pre-bid Conference To Ensure That They Fully Understand The Procuring Entity’s Requirements. Non-attendance Of The Bidder Will In No Way Prejudice Its Bid; However, The Bidder Is Expected To Know The Changes And/or Amendments To The Bidding Documents As Recorded In The Minutes Of The Pre-bid Conference And The Supplemental/bid Bulletin. 9.3. Any Statement Made At The Pre-bid Conference Shall Not Modify The Terms Of The Bidding Documents Unless Such Statement Is Specifically Identified In Writing As An Amendment Thereto And Issued As A Supplemental/bid Bulletin. 10. Clarification And Amendment Of Bidding Documents 10.1. Bidders Who Have Purchased The Bidding Documents May Request For Clarification(s) On Any Part Of The Bidding Documents Or For An Interpretation. Such A Request Must Be In Writing And Submitted To The Procuring Entity At The Address Indicated In The Bds At Least Ten (10) Calendar Days Before The Deadline Set For The Submission And Receipt Of Bids. 10.2. Supplemental/bid Bulletins May Be Issued Upon The Procuring Entity’s Initiative For Purposes Of Clarifying Or Modifying Any Provision Of The Bidding Documents Not Later Than Seven (7) Calendar Days Before The Deadline For The Submission And Receipt Of Bids. Any Modification To The Bidding Documents Shall Be Identified As An Amendment. 10.3. Any Supplemental/bid Bulletin Issued By The Bac Shall Also Be Posted On The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity Concerned, If Available. Unless, Otherwise Provided In The Bds, It Shall Be The Responsibility Of All Bidders Who Secure The Bidding Documents To Inquire And Secure Supplemental/bid Bulletins That May Be Issued By The Bac. However, Bidders Who Have Submitted Bids Before The Issuance Of The Supplemental/bid Bulletin Must Be Informed And Allowed To Modify Or Withdraw Their Bids In Accordance With Itb Clause 23. C. Preparation Of Bids 11. Language Of Bids The Bid, As Well As All Correspondence And Documents Relating To The Bid Exchanged By The Bidder And The Procuring Entity, Shall Be Written In English. Supporting Documents And Printed Literature Furnished By The Bidder May Be In Another Language Provided They Are Accompanied By An Accurate Translation In English Certified By The Appropriate Embassy Or Consulate In The Philippines, In Which Case The English Translation Shall Govern, For Purposes Of Interpretation Of The Bid. 12. Documents Comprising The Bid: Eligibility And Technical Components 12.1. Unless Otherwise Indicated In The Bds, The First Envelope Shall Contain The Following Eligibility And Technical Documents: (a) Eligibility Documents – Class "a" Documents: (i) Registration Certificate From The Securities And Exchange Commission (sec), Department Of Trade And Industry (dti) For Sole Proprietorship, Or Cooperative Development Authority (cda) For Cooperatives, Or Any Proof Of Such Registration As Stated In The Bds; (ii) Mayor’s Permit Issued By The City Or Municipality Where The Principal Place Of Business Of The Prospective Bidder Is Located; (iii) Statement Of All Its Ongoing And Completed Government And Private Contracts Within Ten (10) Years From The Submission Of Bids, Including Contracts Awarded But Not Yet Started, If Any. The Statement Shall Include, For Each Contract, The Following: (iii.1) Name Of The Contract; (iii.2) Date Of The Contract; (iii.3) Contract Duration; (iii.4) Owner’s Name And Address; (iii.5) Nature Of Work; (iii.6) Contractor’s Role (whether Sole Contractor, Subcontractor, Or Partner In A Jv) And Percentage Of Participation; (iii.7) Total Contract Value At Award; (iii.8) Date Of Completion Or Estimated Completion Time; (iii.9) Total Contract Value At Completion, If Applicable; (iii.10) Percentages Of Planned And Actual Accomplishments, If Applicable; (iii.11) Value Of Outstanding Works, If Applicable; (iii.12) The Statement Shall Be Supported By The Notices Of Award And/or Notices To Proceed Issued By The Owners; And (iii.13) The Statement Shall Be Supported By The Constructors Performance Evaluation System (cpes) Rating Sheets, And/or Certificates Of Completion And Owner’s Acceptance, If Applicable; (iv) Unless Otherwise Provided In The Bds, Valid Philippine Contractors Accreditation Board (pcab) License And Registration For The Type And Cost Of The Contract For This Project; (v) Audited Financial Statements, Showing, Among Others, The Prospective Total And Current Assets And Liabilities, Stamped “received” By The Bir Or Its Duly Accredited And Authorized Institutions, For The Preceding Calendar Year Which Should Not Be Earlier Than Two (2) Years From The Date Of Bid Submission; (vi) Nfcc Computation Or Clc In Accordance With Itb Clause 5.5; And Class "b" Document: (vii) If Applicable, Valid Joint Venture Agreement (jva) Or, In Lieu Thereof, Duly Notarized Statements From All The Potential Joint Venture Partners Stating That They Will Enter Into And Abide By The Provisions Of The Jva In The Instance That The Bid Is Successful Shall Be Included In The Bid. (b) Technical Documents – (i) Bid Security As Prescribed In Itb Clause 18. If The Bidder Opts To Submit The Bid Security In The Form Of: (i.1) A Bank Draft/guarantee Or An Irrevocable Letter Of Credit Issued By A Foreign Bank, It Shall Be Accompanied By A Confirmation From A Universal Or Commercial Bank; Or (i.2) A Surety Bond Accompanied By A Certification Coming From An Authorized Insurance Commission That A Surety Or Insurance Company Is Authorized To Issue Such Instrument; (ii) Project Requirements, Which Shall Include The Following: (ii.1) Organizational Chart For The Contract To Be Bid; (ii.2) List Of Contractor’s Personnel (viz, Project Manager, Project Engineers, Materials Engineers, And Foremen), To Be Assigned To The Contract To Be Bid, With Their Complete Qualification And Experience Data; And (ii.3) List Of Contractor’s Equipment Units, Which Are Owned, Leased, And/or Under Purchase Agreements, Supported By Certification Of Availability Of Equipment From The Equipment Lessor/vendor For The Duration Of The Project; And (iii) Sworn Statement In Accordance With Section 25.2(b)(iv) Of The Irr Of Ra 9184 And Using The Form Prescribed In Section Ix. Bidding Forms. 13. Documents Comprising The Bid: Financial Component 13.1. Unless Otherwise Stated In The Bds, The Financial Component Of The Bid Shall Contain The Following: (a) Financial Bid Form In Accordance With The Form Prescribed In Section Ix. Bidding Forms; And (b) Any Other Document Related To The Financial Component Of The Bid As Stated In The Bds. 13.2. (a) Unless Indicated In The Bds, All Bids That Exceed The Abc Shall Not Be Accepted. (b) Unless Otherwise Indicated In The Bds, For Foreign-funded Procurement, A Ceiling May Be Applied To Bid Prices Provided The Following Conditions Are Met: (i) Bidding Documents Are Obtainable Free Of Charge On A Freely Accessible Website. If Payment Of Bidding Documents Is Required By The Procuring Entity, Payment Could Be Made Upon The Submission Of Bids. (ii) The Procuring Entity Has Procedures In Place To Ensure That The Abc Is Based On Recent Estimates Made By The Engineer Or The Responsible Unit Of The Procuring Entity And That The Estimates Are Based On Adequate Detailed Engineering (in The Case Of Works) And Reflect The Quality, Supervision And Risk And Inflationary Factors, As Well As Prevailing Market Prices, Associated With The Types Of Works Or Goods To Be Procured. (iii) The Procuring Entity Has Trained Cost Estimators On Estimating Prices And Analyzing Bid Variances. In The Case Of Infrastructure Projects, The Procuring Entity Must Also Have Trained Quantity Surveyors. (iv) The Procuring Entity Has Established A System To Monitor And Report Bid Prices Relative To Abc And Engineer’s/procuring Entity’s Estimate. (v) The Procuring Entity Has Established A Monitoring And Evaluation System For Contract Implementation To Provide A Feedback On Actual Total Costs Of Goods And Works. 14. Alternative Bids 14.1. Alternative Bids Shall Be Rejected. For This Purpose, Alternative Bid Is An Offer Made By A Bidder In Addition Or As A Substitute To Its Original Bid Which May Be Included As Part Of Its Original Bid Or Submitted Separately Therewith For Purposes Of Bidding. A Bid With Options Is Considered An Alternative Bid Regardless Of Whether Said Bid Proposal Is Contained In A Single Envelope Or Submitted In Two (2) Or More Separate Bid Envelopes. 14.2. Bidders Shall Submit Offers That Comply With The Requirements Of The Bidding Documents, Including The Basic Technical Design As Indicated In The Drawings And Specifications. Unless There Is A Value Engineering Clause In The Bds, Alternative Bids Shall Not Be Accepted. 14.3. Each Bidder Shall Submit Only One Bid, Either Individually Or As A Partner In A Jv. A Bidder Who Submits Or Participates In More Than One Bid (other Than As A Subcontractor If A Subcontractor Is Permitted To Participate In More Than One Bid) Will Cause All The Proposals With The Bidder’s Participation To Be Disqualified. This Shall Be Without Prejudice To Any Applicable Criminal, Civil And Administrative Penalties That May Be Imposed Upon The Persons And Entities Concerned. 15. Bid Prices 15.1. The Contract Shall Be For The Whole Works, As Described In Itb Clause 1.1, Based On The Priced Bill Of Quantities Submitted By The Bidder. 15.2. The Bidder Shall Fill In Rates And Prices For All Items Of The Works Described In The Bill Of Quantities. Bids Not Addressing Or Providing All Of The Required Items In The Bidding Documents Including, Where Applicable, Bill Of Quantities, Shall Be Considered Non-responsive And, Thus, Automatically Disqualified. In This Regard, Where A Required Item Is Provided, But No Price Is Indicated, The Same Shall Be Considered As Non-responsive, But Specifying A "0" (zero) For The Said Item Would Mean That It Is Being Offered For Free To The Government. 15.3. All Duties, Taxes, And Other Levies Payable By The Contractor Under The Contract, Or For Any Other Cause, Prior To The Deadline For Submission Of Bids, Shall Be Included In The Rates, Prices, And Total Bid Price Submitted By The Bidder. 15.4. All Bid Prices For The Given Scope Of Work In The Contract As Awarded Shall Be Considered As Fixed Prices, And Therefore Not Subject To Price Escalation During Contract Implementation, Except Under Extraordinary Circumstances As Specified In Gcc Clause 48. Price Escalation May Be Allowed In Extraordinary Circumstances As May Be Determined By The National Economic And Development Authority In Accordance With The Civil Code Of The Philippines, And Upon The Recommendation Of The Procuring Entity. Furthermore, In Cases Where The Cost Of The Awarded Contract Is Affected By Any Applicable New Laws, Ordinances, Regulations, Or Other Acts Of The Gop, Promulgated After The Date Of Bid Opening, A Contract Price Adjustment Shall Be Made Or Appropriate Relief Shall Be Applied On A No Loss-no Gain Basis. 16. Bid Currencies 16.1. All Bid Prices Shall Be Quoted In Philippine Pesos Unless Otherwise Provided In The Bds. However, For Purposes Of Bid Evaluation, Bids Denominated In Foreign Currencies Shall Be Converted To Philippine Currency Based On The Exchange Rate Prevailing On The Day Of The Bid Opening. 16.2. If So Allowed In Accordance With Itb Clause 16.1, The Procuring Entity For Purposes Of Bid Evaluation And Comparing The Bid Prices Will Convert The Amounts In Various Currencies In Which The Bid Price Is Expressed To Philippine Pesos At The Exchange Rate As Published In The Bsp Reference Rate Bulletin On The Day Of The Bid Opening. 16.3. Unless Otherwise Specified In The Bds, Payment Of The Contract Price Shall Be Made In Philippine Pesos. 17. Bid Validity 17.1. Bids Shall Remain Valid For The Period Specified In The Bds Which Shall Not Exceed One Hundred Twenty (120) Calendar Days From The Date Of The Opening Of Bids. 17.2. In Exceptional Circumstances, Prior To The Expiration Of The Bid Validity Period, The Procuring Entity May Request Bidders To Extend The Period Of Validity Of Their Bids. The Request And The Responses Shall Be Made In Writing. The Bid Security Described In Itb Clause 18 Should Also Be Extended Corresponding To The Extension Of The Bid Validity Period At The Least. A Bidder May Refuse The Request Without Forfeiting Its Bid Security, But His Bid Shall No Longer Be Considered For Further Evaluation And Award. A Bidder Granting The Request Shall Not Be Required Or Permitted To Modify Its Bid. 18. Bid Security 18.1. The Bid Security In The Amount Stated In The Bds Shall Be Equal To The Percentage Of The Abc In Accordance With The Following Schedule: Form Of Bid Security Amount Of Bid Security (equal To Percentage Of The Abc) (a) Cash Or Cashier’s/manager’s Check Issued By A Universal Or Commercial Bank. Two Percent (2%) (b) Bank Draft/guarantee Or Irrevocable Letter Of Credit Issued By A Universal Or Commercial Bank: Provided, However, That It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank. (c) Surety Bond Callable Upon Demand Issued By A Surety Or Insurance Company Duly Certified By The Insurance Commission As Authorized To Issue Such Security; And/or Five Percent (5%) (d) Any Combination Of The Foregoing. Proportionate To Share Of Form With Respect To Total Amount Of Security For Biddings Conducted By Local Government Units, The Bidder May Also Submit Bid Securities In The Form Of Cashier’s/manager’s Check, Bank Draft/guarantee, Or Irrevocable Letter Of Credit From Other Banks Certified By The Bsp As Authorized To Issue Such Financial Statement. 18.2. The Bid Security Should Be Valid For The Period Specified In The Bds. Any Bid Not Accompanied By An Acceptable Bid Security Shall Be Rejected By The Procuring Entity As Non-responsive. 18.3. No Bid Securities Shall Be Returned To Bidders After The Opening Of Bids And Before Contract Signing, Except To Those That Failed Or Declared As Post-disqualified, Upon Submission Of A Written Waiver Of Their Right To File A Motion For Reconsideration And/or Protest. Without Prejudice On Its Forfeiture, Bid Securities Shall Be Returned Only After The Bidder With The Lowest Calculated Responsive Bid Has Signed The Contract And Furnished The Performance Security, But In No Case Later Than The Expiration Of The Bid Security Validity Period Indicated In Itb Clause 18.2. 18.4. Upon Signing And Execution Of The Contract, Pursuant To Itb Clause 31, And The Posting Of The Performance Security, Pursuant To Itb Clause 32, The Successful Bidder’s Bid Security Will Be Discharged, But In No Case Later Than The Bid Security Validity Period As Indicated In Itb Clause 18.2. 18.5. The Bid Security May Be Forfeited: (a) If A Bidder: (i) Withdraws Its Bid During The Period Of Bid Validity Specified In Itb Clause 17; (ii) Does Not Accept The Correction Of Errors Pursuant To Itb Clause 27.3(b); (iii) Fails To Submit The Requirements Within The Prescribed Period, Or A Finding Against Their Veracity, As Stated In Itb Clause 28.2; (iv) Submission Of Eligibility Requirements Containing False Information Or Falsified Documents; (v) Submission Of Bids That Contain False Information Or Falsified Documents, Or The Concealment Of Such Information In The Bids In Order To Influence The Outcome Of Eligibility Screening Or Any Other Stage Of The Public Bidding; (vi) Allowing The Use Of One’s Name, Or Using The Name Of Another For Purposes Of Public Bidding; (vii) Withdrawal Of A Bid, Or Refusal To Accept An Award, Or Enter Into Contract With The Government Without Justifiable Cause, After The Bidder Had Been Adjudged As Having Submitted The Lowest Calculated And Responsive Bid; (viii) Refusal Or Failure To Post The Required Performance Security Within The Prescribed Time; (ix) Refusal To Clarify Or Validate In Writing Its Bid During Post-qualification Within A Period Of Seven (7) Calendar Days From Receipt Of The Request For Clarification; (x) Any Documented Attempt By A Bidder To Unduly Influence The Outcome Of The Bidding In His Favor; (xi) Failure Of The Potential Joint Venture Partners To Enter Into The Joint Venture After The Bid Is Declared Successful; Or (xii) All Other Acts That Tend To Defeat The Purpose Of The Competitive Bidding, Such As Habitually Withdrawing From Bidding, Submitting Late Bids Or Patently Insufficient Bid, For At Least Three (3) Times Within A Year, Except For Valid Reasons. (b) If The Successful Bidder: (i) Fails To Sign The Contract In Accordance With Itb Clause 31; (ii) Fails To Furnish Performance Security In Accordance With Itb Clause 32. 19. Format And Signing Of Bids 19.1. Bidders Shall Submit Their Bids Through Their Duly Authorized Representative Using The Appropriate Forms Provided In Section Ix. Bidding Forms On Or Before The Deadline Specified In The Itb Clause 21 In Two (2) Separate Sealed Bid Envelopes, And Which Shall Be Submitted Simultaneously. The First Shall Contain The Technical Component Of The Bid, Including The Eligibility Requirements Under Itb Clause 12.1, And The Second Shall Contain The Financial Component Of The Bid. 19.2. Forms As Mentioned In Itb Clause 19.1 Must Be Completed Without Any Alterations To Their Format, And No Substitute Form Shall Be Accepted. All Blank Spaces Shall Be Filled In With The Information Requested. 19.3. The Bidder Shall Prepare An Original Of The First And Second Envelopes As Described In Itb Clauses 12 And 13. In Addition, The Bidder Shall Submit Copies Of The First And Second Envelopes. In The Event Of Any Discrepancy Between The Original And The Copies, The Original Shall Prevail. 19.4. The Bid, Except For Unamended Printed Literature, Shall Be Signed, And Each And Every Page Thereof Shall Be Initialed, By The Duly Authorized Representative/s Of The Bidder. 19.5. Any Interlineations, Erasures, Or Overwriting Shall Be Valid Only If They Are Signed Or Initialed By The Duly Authorized Representative/s Of The Bidder. 20. Sealing And Marking Of Bids 20.1. Bidders Shall Enclose Their Original Eligibility And Technical Documents Described In Itb Clause 12, In One Sealed Envelope Marked “original - Technical Component”, And The Original Of Their Financial Component In Another Sealed Envelope Marked “original - Financial Component”, Sealing Them All In An Outer Envelope Marked “original Bid”. 20.2. Each Copy Of The First And Second Envelopes Shall Be Similarly Sealed Duly Marking The Inner Envelopes As “copy No. ___ - Technical Component” And “copy No. ___ – Financial Component” And The Outer Envelope As “copy No. ___”, Respectively. These Envelopes Containing The Original And The Copies Shall Then Be Enclosed In One Single Envelope. 20.3. The Original And The Number Of Copies Of The Bid As Indicated In The Bds Shall Be Typed Or Written In Indelible Ink And Shall Be Signed By The Bidder Or Its Duly Authorized Representative/s. 20.4. All Envelopes Shall: (a) Contain The Name Of The Contract To Be Bid In Capital Letters; (b) Bear The Name And Address Of The Bidder In Capital Letters; (c) Be Addressed To The Procuring Entity’s Bac Identified In Itb Clause 10.1; (d) Bear The Specific Identification Of This Bidding Process Indicated In The Invitation To Bid; And (e) Bear A Warning “do Not Open Before…” The Date And Time For The Opening Of Bids, In Accordance With Itb Clause 21. 20.5. If Bids Are Not Sealed And Marked As Required, The Procuring Entity Will Assume No Responsibility For The Misplacement Or Premature Opening Of The Bid. D. Submission And Opening Of Bids 21. Deadline For Submission Of Bids Bids Must Be Received By The Procuring Entity’s Bac At The Address And On Or Before The Date And Time Indicated In The Bds. 22. Late Bids Any Bid Submitted After The Deadline For Submission And Receipt Of Bids Prescribed By The Procuring Entity, Pursuant To Itb Clause 21, Shall Be Declared “late” And Shall Not Be Accepted By The Procuring Entity. 23. Modification And Withdrawal Of Bids 23.1. The Bidder May Modify Its Bid After It Has Been Submitted; Provided That The Modification Is Received By The Procuring Entity Prior To The Deadline Prescribed For Submission And Receipt Of Bids. The Bidder Shall Not Be Allowed To Retrieve Its Original Bid, But Shall Be Allowed To Submit Another Bid Equally Sealed, Properly Identified, Linked To Its Original Bid Marked As “technical Modification” Or “financial Modification” And Stamped “received” By The Bac. Bid Modifications Received After The Applicable Deadline Shall Not Be Considered And Shall Be Returned To The Bidder Unopened. 23.2. A Bidder May, Through A Letter Of Withdrawal, Withdraw Its Bid After It Has Been Submitted, For Valid And Justifiable Reason; Provided That The Letter Of Withdrawal Is Received By The Procuring Entity Prior To The Deadline Prescribed For Submission And Receipt Of Bids. 23.3. Bids Requested To Be Withdrawn In Accordance With Itb Clause 23.1 Shall Be Returned Unopened To The Bidders. A Bidder May Also Express Its Intention Not To Participate In The Bidding Through A Letter Which Should Reach And Be Stamped By The Bac Before The Deadline For Submission And Receipt Of Bids. A Bidder That Withdraws Its Bid Shall Not Be Permitted To Submit Another Bid, Directly Or Indirectly, For The Same Contract. 23.4. No Bid May Be Modified After The Deadline For Submission Of Bids. No Bid May Be Withdrawn In The Interval Between The Deadline For Submission Of Bids And The Expiration Of The Period Of Bid Validity Specified By The Bidder On The Financial Bid Form. Withdrawal Of A Bid During This Interval Shall Result In The Forfeiture Of The Bidder’s Bid Security, Pursuant To Itb Clause 18.5, And The Imposition Of Administrative, Civil, And Criminal Sanctions As Prescribed By Ra 9184 And Its Irr. 24. Opening And Preliminary Examination Of Bids 24.1. The Bac Shall Open The First Bid Envelopes Of Bidders In Public As Specified In The Bds To Determine Each Bidder’s Compliance With The Documents Prescribed In Itb Clause 12. For This Purpose, The Bac Shall Check The Submitted Documents Of Each Bidder Against A Checklist Of Required Documents To Ascertain If They Are All Present, Using A Non-discretionary “pass/fail” Criterion. If A Bidder Submits The Required Document, It Shall Be Rated “passed” For That Particular Requirement. In This Regard, Bids That Fail To Include Any Requirement Or Are Incomplete Or Patently Insufficient Shall Be Considered As “failed”. Otherwise, The Bac Shall Rate The Said First Bid Envelope As “passed”. 24.2. Unless Otherwise Specified In The Bds, Immediately After Determining Compliance With The Requirements In The First Envelope, The Bac Shall Forthwith Open The Second Bid Envelope Of Each Remaining Eligible Bidder Whose First Bid Envelope Was Rated “passed”. The Second Envelope Of Each Complying Bidder Shall Be Opened Within The Same Day. In Case One Or More Of The Requirements In The Second Envelope Of A Particular Bid Is Missing, Incomplete Or Patently Insufficient, And/or If The Submitted Total Bid Price Exceeds The Abc Unless Otherwise Provided In Itb Clause 13.1(b), The Bac Shall Rate The Bid Concerned As “failed”. Only Bids That Are Determined To Contain All The Bid Requirements For Both Components Shall Be Rated “passed” And Shall Immediately Be Considered For Evaluation And Comparison. 24.3. Letters Of Withdrawal Shall Be Read Out And Recorded During Bid Opening, And The Envelope Containing The Corresponding Withdrawn Bid Shall Be Returned To The Bidder Unopened. If The Withdrawing Bidder’s Representative Is In Attendance, The Original Bid And All Copies Thereof Shall Be Returned To The Representative During The Bid Opening. If The Representative Is Not In Attendance, The Bid Shall Be Returned Unopened By Registered Mail. The Bidder May Withdraw Its Bid Prior To The Deadline For The Submission And Receipt Of Bids, Provided That The Corresponding Letter Of Withdrawal Contains A Valid Authorization Requesting For Such Withdrawal, Subject To Appropriate Administrative Sanctions. 24.4. If A Bidder Has Previously Secured A Certification From The Procuring Entity To The Effect That It Has Previously Submitted The Above-enumerated Class “a” Documents, The Said Certification May Be Submitted In Lieu Of The Requirements Enumerated In Itb Clause 12.1(a), Items (i) To (vi). 24.5. In The Case Of An Eligible Foreign Bidder As Described In Itb Clause 5, The Class “a” Documents Enumerated In Itb Clause 12.1(a) May Be Substituted With The Appropriate Equivalent Documents, If Any, Issued By The Country Of The Foreign Bidder Concerned. 24.6. Each Partner Of A Joint Venture Agreement Shall Likewise Submit The Documents Required In Itb Clauses 12.1(a)(i) And 12.1(a)(ii). Submission Of Documents Required Under Itb Clauses 12.1(a)(iii) To 12.1(a)(vi) By Any Of The Joint Venture Partners Constitutes Compliance. 24.7. A Bidder Determined As “failed” Has Three (3) Calendar Days Upon Written Notice Or, If Present At The Time Of Bid Opening, Upon Verbal Notification Within Which To File A Request For Reconsideration With The Bac: Provided, However, That The Request For Reconsideration Shall Not Be Granted If It Is Established That The Finding Of Failure Is Due To The Fault Of The Bidder Concerned: Provided, Further, That The Bac Shall Decide On The Request For Reconsideration Within Seven (7) Calendar Days From Receipt Thereof. If A Failed Bidder Signifies His Intent To File A Request For Reconsideration, The Bac Shall Keep The Bid Envelopes Of The Said Failed Bidder Unopened And/or Duly Sealed Until Such Time That The Request For Reconsideration Or Protest Has Been Resolved. E. Evaluation And Comparison Of Bids 25. Process To Be Confidential 25.1. Members Of The Bac, Including Its Staff And Personnel, As Well As Its Secretariat And Twg, Are Prohibited From Making Or Accepting Any Kind Of Communication With Any Bidder Regarding The Evaluation Of Their Bids Until The Issuance Of The Notice Of Award, Unless N The Case Of Itb Clause 26. 25.2. Any Effort By A Bidder To Influence The Procuring Entity In The Procuring Entity’s Decision In Respect Of Bid Evaluation, Bid Comparison Or Contract Award Will Result In The Rejection Of The Bidder’s Bid. 26. Clarification Of Bids To Assist In The Evaluation, Comparison And Post-qualification Of The Bids, The Procuring Entity May Ask In Writing Any Bidder For A Clarification Of Its Bid. All Responses To Requests For Clarification Shall Be In Writing. Any Clarification Submitted By A Bidder In Respect To Its Bid And That Is Not In Response To A Request By The Procuring Entity Shall Not Be Considered 27. Detailed Evaluation And Comparison Of Bids 27.1. The Procuring Entity Will Undertake The Detailed Evaluation And Comparison Of Bids Which Have Passed The Opening And Preliminary Examination Of Bids, Pursuant To Itb Clause 24, In Order To Determine The Lowest Calculated Bid. 27.2. In Evaluating The Bids To Get The Lowest Calculated Bid, The Procuring Entity Shall Undertake The Following: (a) The Detailed Evaluation Of The Financial Component Of The Bids, To Establish The Correct Calculated Prices Of The Bids; And (b) The Ranking Of The Total Bid Prices As So Calculated From The Lowest To Highest. The Bid With The Lowest Price Shall Be Identified As The Lowest Calculated Bid. 27.3. The Procuring Entity's Bac Shall Immediately Conduct A Detailed Evaluation Of All Bids Rated “passed,” Using Non-discretionary “pass/fail” Criterion. The Bac Shall Consider The Following In The Evaluation Of Bids: (a) Completeness Of The Bid. Unless The Itb Specifically Allows Partial Bids, Bids Not Addressing Or Providing All Of The Required Items In The Schedule Of Requirements Including, Where Applicable, Bill Of Quantities, Shall Be Considered Non-responsive And, Thus, Automatically Disqualified. In This Regard, Where A Required Item Is Provided, But No Price Is Indicated, The Same Shall Be Considered As Non-responsive, But Specifying A "0" (zero) For The Said Item Would Mean That It Is Being Offered For Free To The Procuring Entity; And (b) Arithmetical Corrections. Consider Computational Errors And Omissions To Enable Proper Comparison Of All Eligible Bids. It May Also Consider Bid Modifications If Expressly Allowed In The Bds. Any Adjustment Shall Be Calculated In Monetary Terms To Determine The Calculated Prices. 27.4. Based On The Detailed Evaluation Of Bids, Those That Comply With The Above-mentioned Requirements Shall Be Ranked In The Ascending Order Of Their Total Calculated Bid Prices, As Evaluated And Corrected For Computational Errors, Discounts And Other Modifications, To Identify The Lowest Calculated Bid. Total Calculated Bid Prices, As Evaluated And Corrected For Computational Errors, Discounts And Other Modifications, Which Exceed The Abc Shall Not Be Considered, Unless Otherwise Indicated In The Bds. 27.5. The Procuring Entity’s Evaluation Of Bids Shall Only Be Based On The Bid Price Quoted In The Financial Bid Form 27.6. Bids Shall Be Evaluated On An Equal Footing To Ensure Fair Competition. For This Purpose, All Bidders Shall Be Required To Include In Their Bids The Cost Of All Taxes, Such As, But Not Limited To, Value Added Tax (vat), Income Tax, Local Taxes, And Other Fiscal Levies And Duties Which Shall Be Itemized In The Bid Form And Reflected In The Detailed Estimates. Such Bids, Including Said Taxes, Shall Be The Basis For Bid Evaluation And Comparison. 28. Post Qualification 28.1. The Procuring Entity Shall Determine To Its Satisfaction Whether The Bidder That Is Evaluated As Having Submitted The Lowest Calculated Bid (lcb) Complies With And Is Responsive To All The Requirements And Conditions Specified In Itb Clauses 5, 12, And 13. 28.2. Within A Non-extendible Period Of Three (3) Calendar Days From Receipt By The Bidder Of The Notice From The Bac That It Submitted The Lcb, The Bidder Shall Submit The Following Documentary Requirements: (a) Tax Clearance Per Executive Order 398, Series Of 2005; (b) Latest Income And Business Tax Returns In The Form Specified In The Bds; (c) Certificate Of Philgeps Registration; And (d) Other Appropriate Licenses And Permits Required By Law And Stated In The Bds. Failure Of The Bidder Declared As Lcb To Duly Submit The Requirements Under This Clause Or A Finding Against The Veracity Of Such, Shall Be Ground For Forfeiture Of The Bid Security And Disqualification Of The Bidder For Award. 28.3. The Determination Shall Be Based Upon An Examination Of The Documentary Evidence Of The Bidder’s Qualifications Submitted Pursuant To Itb Clauses 12 And 13, As Well As Other Information As The Procuring Entity Deems Necessary And Appropriate, Using A Non-discretionary “pass/fail” Criterion. 28.4. If The Bac Determines That The Bidder With The Lowest Calculated Bid Passes All The Criteria For Post-qualification, It Shall Declare The Said Bid As The Lowest Calculated Responsive Bid, And Recommend To The Head Of The Procuring Entity The Award Of Contract To The Said Bidder At Its Submitted Price Or Its Calculated Bid Price, Whichever Is Lower, Subject To Itb Clause 30.3. 28.5. A Negative Determination Shall Result In Rejection Of The Bidder’s Bid, In Which Event The Procuring Entity Shall Proceed To The Next Lowest Calculated Bid To Make A Similar Determination Of That Bidder’s Capabilities To Perform Satisfactorily. If The Second Bidder, However, Fails The Post Qualification, The Procedure For Post Qualification Shall Be Repeated For The Bidder With The Next Lowest Calculated Bid, And So On Until The Lowest Calculated And Responsive Bid Is Determined For Contract Award. 28.6. Within A Period Not Exceeding Seven (7) Calendar Days From The Date Of Receipt Of The Recommendation Of The Bac, The Head Of The Procuring Entity Shall Approve Or Disapprove The Said Recommendation. In The Case Of Government Owned And Government-owned And/or -controlled Corporations (goccs) And Government Financial Institutions (gfis), The Period Provided Herein Shall Be Fifteen (15) Calendar Days. 29. Reservation Clause 29.1. Notwithstanding The Eligibility Or Post-qualification Of A Bidder, The Procuring Entity Concerned Reserves The Right To Review Its Qualifications At Any Stage Of The Procurement Process If It Has Reasonable Grounds To Believe That A Misrepresentation Has Been Made By The Said Bidder, Or That There Has Been A Change In The Bidder’s Capability To Undertake The Project From The Time It Submitted Its Eligibility Requirements. Should Such Review Uncover Any Misrepresentation Made In The Eligibility And Bidding Requirements, Statements Or Documents, Or Any Changes In The Situation Of The Bidder Which Will Affect Its Capability To Undertake The Project So That It Fails The Preset Eligibility Or Bid Evaluation Criteria, The Procuring Entity Shall Consider The Said Bidder As Ineligible And Shall Disqualify It From Submitting A Bid Or From Obtaining An Award Or Contract. 29.2. Based On The Following Grounds, The Procuring Entity Reserves The Right To Reject Any And All Bids, Declare A Failure Of Bidding At Any Time Prior To The Contract Award, Or Not To Award The Contract, Without Thereby Incurring Any Liability, And Make No Assurance That A Contract Shall Be Entered Into As A Result Of The Bidding: (a) If There Is Prima Facie Evidence Of Collusion Between Appropriate Public Officers Or Employees Of The Procuring Entity, Or Between The Bac And Any Of The Bidders, Or If The Collusion Is Between Or Among The Bidders Themselves, Or Between A Bidder And A Third Party, Including Any Act Which Restricts, Suppresses Or Nullifies Or Tends To Restrict, Suppress Or Nullify Competition; (b) If The Procuring Entity’s Bac Is Found To Have Failed In Following The Prescribed Bidding Procedures; Or (c) For Any Justifiable And Reasonable Ground Where The Award Of The Contract Will Not Redound To The Benefit Of The Government As Follows: (i) If The Physical And Economic Conditions Have Significantly Changed So As To Render The Project No Longer Economically, Financially Or Technically Feasible As Determined By The Head Of The Procuring Entity; (ii) If The Project Is No Longer Necessary As Determined By The Head Of The Procuring Entity; And (iii) If The Source Of Funds For The Project Has Been Withheld Or Reduced Through No Fault Of The Procuring Entity. 29.3. In Addition, The Procuring Entity May Likewise Declare A Failure Of Bidding When: (a) No Bids Are Received; (b) All Prospective Bidders Are Declared Ineligible; (c) All Bids Fail To Comply With All The Bid Requirements Or Fail Post-qualification; Or (d) The Bidder With The Lowest Calculated Responsive Bid Refuses, Without Justifiable Cause To Accept The Award Of Contract, And No Award Is Made. F. Award Of Contract 30. Contract Award 30.1. Subject To Itb Clause 28, The Procuring Entity Shall Award The Contract To The Bidder Whose Bid Has Been Determined To Be The Lowest Calculated And Responsive Bid (lcrb). 30.2. Prior To The Expiration Of The Period Of Bid Validity, The Procuring Entity Shall Notify The Successful Bidder In Writing That Its Bid Has Been Accepted, Through A Notice Of Award Received Personally Or Sent By Registered Mail Or Electronically, Receipt Of Which Must Be Confirmed In Writing Within Two (2) Days By The Lcrb And Submitted Personally Or Sent By Registered Mail Or Electronically To The Procuring Entity. 30.3. Notwithstanding The Issuance Of The Notice Of Award, Award Of Contract Shall Be Subject To The Following Conditions: (a) Submission Of The Following Documents Within The Prescribed Period From Receipt By The Bidder Of The Notice That It Has The Lowest Calculated And Responsive Bid: (i) Valid Jva, If Applicable, Within Ten (10) Calendar Days; (ii) Valid Pcab License And Registration For The Type And Cost Of The Contract To Be Bid For Foreign Bidders, Within Thirty (30) Calendar Days, If Allowed Under A Treaty Or International Or Executive Agreement Mentioned In Itb Clause 12.1(a)(iv); (b) Posting Of The Performance Security In Accordance With Itb Clause 32; (c) Signing Of The Contract As Provided In Itb Clause 31; And (d) Approval By Higher Authority, If Required. 31. Signing Of The Contract 31.1. At The Same Time As The Procuring Entity Notifies The Successful Bidder That Its Bid Has Been Accepted, The Procuring Entity Shall Send The Contract Form To The Bidder, Which Contract Has Been Provided In The Bidding Documents, Incorporating Therein All Agreements Between The Parties. 31.2. Within Ten (10) Calendar Days From Receipt Of The Notice Of Award, The Successful Bidder Shall Post The Required Performance Security, Sign And Date The Contract And Return It To The Procuring Entity. 31.3. The Procuring Entity Shall Enter Into Contract With The Successful Bidder Within The Same Ten (10) Calendar Day Period Provided That All The Documentary Requirements Are Complied With. 31.4. The Following Documents Shall Form Part Of The Contract: (a) Contract Agreement; (b) Bidding Documents; (c) Winning Bidder’s Bid, Including The Technical And Financial Proposals, And All Other Documents/statements Submitted; (d) Performance Security; (e) Credit Line In Accordance With Itb Clause 5.5, If Applicable; (f) Notice Of Award Of Contract; And (g) Other Contract Documents That May Be Required By Existing Laws And/or Specified In The Bds. 32. Performance Security 32.1. To Guarantee The Faithful Performance By The Winning Bidder Of Its Obligations Under The Contract, It Shall Post A Performance Security Within A Maximum Period Of Ten (10) Calendar Days From The Receipt Of The Notice Of Award From The Procuring Entity And In No Case Later Than The Signing Of The Contract. 32.2. The Performance Security Shall Be Denominated In Philippine Pesos And Posted In Favor Of The Procuring Entity In An Amount Equal To The Percentage Of The Total Contract Price As Stated In The Bds In Accordance With The Following Schedule: 33. 33.1. Form Of Performance Security Amount Of Performance Security (equal To Percentage Of The Total Contract Price) (a) Cash Or Cashier’s/manager’s Check Issued By A Universal Or Commercial Bank. Ten Percent (10%) (b) Bank Draft/guarantee Or Irrevocable Letter Of Credit Issued By A Universal Or Commercial Bank: Provided, However, That It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank. (c) Surety Bond Callable Upon Demand Issued By A Surety Or Insurance Company Duly Certified By The Insurance Commission As Authorized To Issue Such Security; And/or Thirty Percent (30%) (d) Any Combination Of The Foregoing. Proportionate To Share Of Form With Respect To Total Amount Of Security 33.2. Failure Of The Successful Bidder To Comply With The Above-mentioned Requirement Shall Constitute Sufficient Ground For The Annulment Of The Award And Forfeiture Of The Bid Security, In Which Event The Procuring Entity Shall Initiate And Complete The Post Qualification Of The Second Lowest Calculated Bid. The Procedure Shall Be Repeated Until The Lowest Calculated And Responsive Bid Is Identified And Selected For Contract Award. However If No Bidder Passed Post-qualification, The Bac Shall Declare The Bidding A Failure And Conduct A Re-bidding With Re-advertisement. 34. Notice To Proceed 34.1. Within Three (3) Calendar Days From The Date Of Approval Of The Contract By The Appropriate Government Approving Authority, The Procuring Entity Shall Issue Its Notice To Proceed To The Bidder. 34.2. The Contract Effectivity Date Shall Be Provided In The Notice To Proceed By The Procuring Entity, Which Date Shall Not Be Later Than Seven (7) Calendar Days From The Issuance Of The Notice To Proceed. Section Iii. Bid Data Sheet Bid Data Sheet Itb Clause 1.1 The Procuring Entity Is Lgu- Mapanas, Northern Samar. The Name Of The Contract Is Completion Of Naparasan-quezon Fmr Brgy. Quezon, Mapanas N. Samar The Identification Number Of The Contract Is Pr No-2024-11-105___ 2 The Funding Source Is: 20% Economic Development Fund (edf) For Fy 2023. The Name Of The Project Is: Completion Of Naparasan-quezon Fmr Brgy. Quezon, Mapanas N. Samar 3.1 No Further Instructions. 5.1 No Further Instructions. 5.2 Bidding Is Restricted To Eligible Bidders As Defined In Itb Clause 5.1. 5.4 For This Purpose, Similar Contracts Shall Refer To Bidder’s Annual Turnover From All Works Average Over The Last Three Years Shall Be Equal To 50% Of The Estimated Cost Of The Contract Being Procured. The Bidder Must Have Completed, Within The Past Ten (10) Years From The Submission Of Bids, A Single Contract That Is Similar To This Project, Equivalent To At Least Eighty Percent (80%) Of The Abc. 8.1 “subcontracting Is Not Allowed.” 8.2 “not Applicable”. 9.1 The Procuring Entity Will Hold A Pre-bid Conference For This Project On December 05, 2024 At 10:00 A.m. At Executive Conference 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar. 10.1 The Procuring Entity’s Address Is: The Municipality Of Mapanas, Province Of Northern Samar Ma. Teresa L. Minguez Lgu-bac Chairperson Tel. No. 09778033758 10.3 No Further Instructions. 12.1 Not Applicable 12.1(a)(i) “no Other Acceptable Proof Of Registration Is Recognized.” 12.1(a)(iv) No Further Instructions. 13.1 “no Additional Requirements” 13.1(b) The Abc Is Php985,863.77 Any Bid With A Financial Component Exceeding This Amount Shall Not Be Accepted. 14.2 “no Further Instructions.” 15.4 No Further Instruction. 16.1 The Bid Prices Shall Be Quoted In Philippine Pesos. 17.1 Bids Will Be Valid Until 60 Calendar Days After The Bid Submission Deadline Date As Prescribed By The Procuring Entity) 18.1 The Bid Security Shall Be In The Following Amount: 1. The Amount Of P19,717.28 If Bid Security Is In Cash, Cashier’s/manager’s Check, Bank Draft/guarantee Or Irrevocable Letter Of Credit; 2. The Amount Of P49,293.19 If Bid Security Is In Surety Bond; Or 3. Any Combination Of The Foregoing Proportionate To The Share Of Form With Respect To Total Amount Of Security. 18.2 The Bid Security Shall Be Valid Twenty Eight Days Beyond The Validity Period Of The Bid. 20.3 Each Bidder Shall Submit One Original And One Copy Of The First And Second Components Of Its Bid. 21 The Address For Submission Of Bids Is Ma. Teresa L. Minguez Lgu-bac Chairperson Bac Office @ Mpdo, 1st Floor, New Municipal Bldg. Municipality Of Mapanas, Northern Samar The Deadline For Submission Of Bids Is 9:00 A.m. On December 16 , 2024. 22 The Place Of Bid Opening Is Executive Conference Room, 2nd Floor, New Municipal Bldg. Municipality Of Mapanas, Northern Samar. The Date And Time Of Bid Opening Is Dcember 16, 2024 At Exactly 10:00 A.m. 24.2 No Further Instructions. 27.3(b) Bid Modification Is Not Allowed. 27.4 No Further Instructions. 28.2(b) Bidders Have Option To Submit Manually Filed Tax Returns Or Tax Returns Filed Through The Electronic Filing And Payments System (efps). Note: The Latest Income And Business Tax Returns Are Those Within The Last Six Months Preceding The Date Of Bid Submission. 28.2(d) List Licenses And Permits Relevant To The Project And The Corresponding Law Requiring It. 1. Taxpayer’s Identification Number 2. Vat Registration 3. Philippine Contractors Accreditation Board (pcab) License The Requirements Are Applicable Only In A Case Where The Lowest Calculated Bid (lcb) Is Submitted By A Domestic Bidder, And If The Lowest Calculated Bid (lcb) Is Submitted By A Foreign Bidder, This Requirements Are Not Applicable 31.4(g) List Additional Contract Documents Relevant To The Project That May Be Required By Existing Laws And/or The Procuring Entity, Such As Construction Schedule And S-curve, Manpower Schedule, Construction Methods, Equipment Utilization Schedule, Construction Safety And Health Program Approved By The Department Of Labor And Employment, And Pert/cpm. 32.2 The Performance Security Shall Be In The Following Amount: 1. The Amount Of 10% Of Contract If Performance Security Is In Cash, Cashier’s/manager’s Check, Bank Draft/guarantee Or Irrevocable Letter Of Credit; 2. The Amount Of 30% Of Contract If Performance Security Is In Surety Bond; Or 3. Any Combination Of The Foregoing Proportionate To The Share Of Form With Respect To Total Amount Of Security. Section Iv. General Conditions Of Contract Table Of Contents 1. Definitions 41 2. Interpretation 43 3. Governing Language And Law 43 4. Communications 43 5. Possession Of Site 43 6. The Contractor’s Obligations 44 7. Performance Security 45 8. Subcontracting 46 9. Liquidated Damages 46 10. Site Investigation Reports 47 11. The Procuring Entity, Licenses And Permits 47 12. Contractor’s Risk And Warranty Security 47 13. Liability Of The Contractor 49 14. Procuring Entity’s Risk 49 15. Insurance 49 16. Termination For Default Of Contractor 51 17. Termination For Default Of Procuring Entity 51 18. Termination For Other Causes 52 19. Procedures For Termination Of Contracts 53 20. Force Majeure, Release From Performance 56 21. Resolution Of Disputes 56 22. Suspension Of Loan, Credit, Grant, Or Appropriation 57 23. Procuring Entity’s Representative’s Decisions 57 24. Approval Of Drawings And Temporary Works By The Procuring Entity’s Representative 57 25. Acceleration And Delays Ordered By The Procuring Entity’s Representative 58 26. Extension Of The Intended Completion Date 58 27. Right To Vary 58 28. Contractors Right To Claim 59 29. Dayworks 59 30. Early Warning 59 31. Program Of Work 59 32. Management Conferences 60 33. Bill Of Quantities 60 34. Instructions, Inspections And Audits 61 35. Identifying Defects 61 36. Cost Of Repairs 61 37. Correction Of Defects 61 38. Uncorrected Defects 62 39. Advance Payment 62 40. Progress Payments 62 41. Payment Certificates 63 42. Retention 63 43. Variation Orders 64 44. Contract Completion 66 45. Suspension Of Work 66 46. Payment On Termination 67 47. Extension Of Contract Time 67 48. Price Adjustment 68 49. Completion 68 50. Taking Over 69 51. Operating And Maintenance Manuals 69 1. Definitions For Purposes Of This Clause, Boldface Type Is Used To Identify Defined Terms. 1.1. The Arbiter Is The Person Appointed Jointly By The Procuring Entity And The Contractor To Resolve Disputes In The First Instance, As Provided For In Gcc Clause 21. 1.2. Bill Of Quantities Refers To A List Of The Specific Items Of The Work And Their Corresponding Unit Prices, Lump Sums, And/or Provisional Sums. 1.3. The Completion Date Is The Date Of Completion Of The Works As Certified By The Procuring Entity’s Representative, In Accordance With Gcc Clause 49. 1.4. The Contract Is The Contract Between The Procuring Entity And The Contractor To Execute, Complete, And Maintain The Works. 1.5. The Contract Price Is The Price Stated In The Letter Of Acceptance And Thereafter To Be Paid By The Procuring Entity To The Contractor For The Execution Of The Works In Accordance With This Contract. 1.6. Contract Time Extension Is The Allowable Period For The Contractor To Complete The Works In Addition To The Original Completion Date Stated In This Contract. 1.7. The Contractor Is The Juridical Entity Whose Proposal Has Been Accepted By The Procuring Entity And To Whom The Contract To Execute The Work Was Awarded. 1.8. The Contractor’s Bid Is The Signed Offer Or Proposal Submitted By The Contractor To The Procuring Entity In Response To The Bidding Documents. 1.9. Days Are Calendar Days; Months Are Calendar Months. 1.10. Dayworks Are Varied Work Inputs Subject To Payment On A Time Basis For The Contractor’s Employees And Equipment, In Addition To Payments For Associated Materials And Plant. 1.11. A Defect Is Any Part Of The Works Not Completed In Accordance With The Contract. 1.12. The Defects Liability Certificate Is The Certificate Issued By Procuring Entity’s Representative Upon Correction Of Defects By The Contractor. 1.13. The Defects Liability Period Is The One Year Period Between Contract Completion And Final Acceptance Within Which The Contractor Assumes The Responsibility To Undertake The Repair Of Any Damage To The Works At His Own Expense. 1.14. Drawings Are Graphical Presentations Of The Works. They Include All Supplementary Details, Shop Drawings, Calculations, And Other Information Provided Or Approved For The Execution Of This Contract. 1.15. Equipment Refers To All Facilities, Supplies, Appliances, Materials Or Things Required For The Execution And Completion Of The Work Provided By The Contractor And Which Shall Not Form Or Are Not Intended To Form Part Of The Permanent Works. 1.16. The Intended Completion Date Refers To The Date Specified In The Scc When The Contractor Is Expected To Have Completed The Works. The Intended Completion Date May Be Revised Only By The Procuring Entity’s Representative By Issuing An Extension Of Time Or An Acceleration Order. 1.17. Materials Are All Supplies, Including Consumables, Used By The Contractor For Incorporation In The Works. 1.18. The Notice To Proceed Is A Written Notice Issued By The Procuring Entity Or The Procuring Entity’s Representative To The Contractor Requiring The Latter To Begin The Commencement Of The Work Not Later Than A Specified Or Determinable Date. 1.19. Permanent Works All Permanent Structures And All Other Project Features And Facilities Required To Be Constructed And Completed In Accordance With This Contract Which Shall Be Delivered To The Procuring Entity And Which Shall Remain At The Site After The Removal Of All Temporary Works. 1.20. Plant Refers To The Machinery, Apparatus, And The Like Intended To Form An Integral Part Of The Permanent Works. 1.21. The Procuring Entity Is The Party Who Employs The Contractor To Carry Out The Works Stated In The Scc. 1.22. The Procuring Entity’s Representative Refers To The Head Of The Procuring Entity Or His Duly Authorized Representative, Identified In The Scc, Who Shall Be Responsible For Supervising The Execution Of The Works And Administering This Contract. 1.23. The Site Is The Place Provided By The Procuring Entity Where The Works Shall Be Executed And Any Other Place Or Places Which May Be Designated In The Scc, Or Notified To The Contractor By The Procuring Entity’s Representative As Forming Part Of The Site. 1.24. Site Investigation Reports Are Those That Were Included In The Bidding Documents And Are Factual And Interpretative Reports About The Surface And Subsurface Conditions At The Site. 1.25. Slippage Is A Delay In Work Execution Occurring When Actual Accomplishment Falls Below The Target As Measured By The Difference Between The Scheduled And Actual Accomplishment Of The Work By The Contractor As Established From The Work Schedule. This Is Actually Described As A Percentage Of The Whole Works. 1.26. Specifications Means The Description Of Works To Be Done And The Qualities Of Materials To Be Used, The Equipment To Be Installed And The Mode Of Construction. 1.27. The Start Date, As Specified In The Scc, Is The Date When The Contractor Is Obliged To Commence Execution Of The Works. It Does Not Necessarily Coincide With Any Of The Site Possession Dates. 1.28. A Subcontractor Is Any Person Or Organization To Whom A Part Of The Works Has Been Subcontracted By The Contractor, As Allowed By The Procuring Entity, But Not Any Assignee Of Such Person. 1.29. Temporary Works Are Works Designed, Constructed, Installed, And Removed By The Contractor That Are Needed For Construction Or Installation Of The Permanent Works. 1.30. Work(s)refer To The Permanent Works And Temporary Works To Be Executed By The Contractor In Accordance With This Contract, Including (i) The Furnishing Of All Labor, Materials, Equipment And Others Incidental, Necessary Or Convenient To The Complete Execution Of The Works; (ii) The Passing Of Any Tests Before Acceptance By The Procuring Entity’s Representative; (iii) And The Carrying Out Of All Duties And Obligations Of The Contractor Imposed By This Contract As Described In The Scc. 2. Interpretation 2.1. In Interpreting The Conditions Of Contract, Singular Also Means Plural, Male Also Means Female Or Neuter, And The Other Way Around. Headings Have No Significance. Words Have Their Normal Meaning Under The Language Of This Contract Unless Specifically Defined. The Procuring Entity’s Representative Will Provide Instructions Clarifying Queries About The Conditions Of Contract. 2.2. If Sectional Completion Is Specified In The Scc, References In The Conditions Of Contract To The Works, The Completion Date, And The Intended Completion Date Apply To Any Section Of The Works (other Than References To The Completion Date And Intended Completion Date For The Whole Of The Works). 3. Governing Language And Law 3.1. This Contract Has Been Executed In The English Language, Which Shall Be The Binding And Controlling Language For All Matters Relating To The Meaning Or Interpretation Of This Contract. All Correspondence And Other Documents Pertaining To This Contract Which Are Exchanged By The Parties Shall Be Written In English. 3.2. This Contract Shall Be Interpreted In Accordance With The Laws Of The Republic Of The Philippines. 4. Communications Communications Between Parties That Are Referred To In The Conditions Shall Be Effective Only When In Writing. A Notice Shall Be Effective Only When It Is Received By The Concerned Party. 5. Possession Of Site 5.1. On The Date Specified In The Scc, The Procuring Entity Shall Grant The Contractor Possession Of So Much Of The Site As May Be Required To Enable It To Proceed With The Execution Of The Works. If The Contractor Suffers Delay Or Incurs Cost From Failure On The Part Of The Procuring Entity To Give Possession In Accordance With The Terms Of This Clause, The Procuring Entity’s Representative Shall Give The Contractor A Contract Time Extension And Certify Such Sum As Fair To Cover The Cost Incurred, Which Sum Shall Be Paid By Procuring Entity. 5.2. If Possession Of A Portion Is Not Given By The Date Stated In The Scc Clause 5.1, The Procuring Entity Will Be Deemed To Have Delayed The Start Of The Relevant Activities. The Resulting Adjustments In Contact Time To Address Such Delay Shall Be In Accordance With Gcc Clause 47. 5.3. The Contractor Shall Bear All Costs And Charges For Special Or Temporary Right-of-way Required By It In Connection With Access To The Site. The Contractor Shall Also Provide At His Own Cost Any Additional Facilities Outside The Site Required By It For Purposes Of The Works. 5.4. The Contractor Shall Allow The Procuring Entity’s Representative And Any Person Authorized By The Procuring Entity’s Representative Access To The Site And To Any Place Where Work In Connection With This Contract Is Being Carried Out Or Is Intended To Be Carried Out. 6. The Contractor’s Obligations 6.1. The Contractor Shall Carry Out The Works Properly And In Accordance With This Contract. The Contractor Shall Provide All Supervision, Labor, Materials, Plant And Contractor's Equipment, Which May Be Required. All Materials And Plant On Site Shall Be Deemed To Be The Property Of The Procuring Entity. 6.2. The Contractor Shall Commence Execution Of The Works On The Start Date And Shall Carry Out The Works In Accordance With The Program Of Work Submitted By The Contractor, As Updated With The Approval Of The Procuring Entity’s Representative, And Complete Them By The Intended Completion Date. 6.3. The Contractor Shall Be Responsible For The Safety Of All Activities On The Site. 6.4. The Contractor Shall Carry Out All Instructions Of The Procuring Entity’s Representative That Comply With The Applicable Laws Where The Site Is Located. 6.5. The Contractor Shall Employ The Key Personnel Named In The Schedule Of Key Personnel, As Referred To In The Scc, To Carry Out The Supervision Of The Works. The Procuring Entity Will Approve Any Proposed Replacement Of Key Personnel Only If Their Relevant Qualifications And Abilities Are Equal To Or Better Than Those Of The Personnel Listed In The Schedule. 6.6. If The Procuring Entity’s Representative Asks The Contractor To Remove A Member Of The Contractor’s Staff Or Work Force, For Justifiable Cause, The Contractor Shall Ensure That The Person Leaves The Site Within Seven (7) Days And Has No Further Connection With The Work In This Contract. 6.7. During Contract Implementation, The Contractor And His Subcontractors Shall Abide At All Times By All Labor Laws, Including Child Labor Related Enactments, And Other Relevant Rules. 6.8. The Contractor Shall Submit To The Procuring Entity For Consent The Name And Particulars Of The Person Authorized To Receive Instructions On Behalf Of The Contractor. 6.9. The Contractor Shall Cooperate And Share The Site With Other Contractors, Public Authorities, Utilities, And The Procuring Entity Between The Dates Given In The Schedule Of Other Contractors Particularly When They Shall Require Access To The Site. The Contractor Shall Also Provide Facilities And Services For Them During This Period. The Procuring Entity May Modify The Schedule Of Other Contractors, And Shall Notify The Contractor Of Any Such Modification Thereto. 6.10. Should Anything Of Historical Or Other Interest Or Of Significant Value Be Unexpectedly Discovered On The Site, It Shall Be The Property Of The Procuring Entity. The Contractor Shall Notify The Procuring Entity’s Representative Of Such Discoveries And Carry Out The Procuring Entity’s Representative’s Instructions In Dealing With Them. 7. Performance Security 7.1. Within Ten (10) Calendar Days From Receipt Of The Notice Of Award From The Procuring Entity But In No Case Later Than The Signing Of The Contract By Both Parties, The Contractor Shall Furnish The Performance Security In Any The Forms Prescribed In Itb Clause 32.2. 7.2. The Performance Security Posted In Favor Of The Procuring Entity Shall Be Forfeited In The Event It Is Established That The Contractor Is In Default In Any Of Its Obligations Under The Contract. 7.3. The Performance Security Shall Remain Valid Until Issuance By The Procuring Entity Of The Certificate Of Final Acceptance. 7.4. The Performance Security May Be Released By The Procuring Entity And Returned To The Contractor After The Issuance Of The Certificate Of Final Acceptance Subject To The Following Conditions: (a) There Are No Pending Claims Against The Contractor Or The Surety Company Filed By The Procuring Entity; (b) The Contractor Has No Pending Claims For Labor And Materials Filed Against It; And (c) Other Terms Specified In The Scc. 7.5. The Contractor Shall Post An Additional Performance Security Following The Amount And Form Specified In Itb Clause 32.2 To Cover Any Cumulative Increase Of More Than Ten Percent (10%) Over The Original Value Of The Contract As A Result Of Amendments To Order Or Change Orders, Extra Work Orders And Supplemental Agreements, As The Case May Be. The Contractor Shall Cause The Extension Of The Validity Of The Performance Security To Cover Approved Contract Time Extensions. 7.6. In Case Of A Reduction In The Contract Value Or For Partially Completed Works Under The Contract Which Are Usable And Accepted By The Procuring Entity The Use Of Which, In The Judgment Of The Implementing Agency Or The Procuring Entity, Will Not Affect The Structural Integrity Of The Entire Project, The Procuring Entity Shall Allow A Proportional Reduction In The Original Performance Security, Provided That Any Such Reduction Is More Than Ten Percent (10%) And That The Aggregate Of Such Reductions Is Not More Than Fifty Percent (50%) Of The Original Performance Security. 7.7. Unless Otherwise Indicated In The Scc, The Contractor, By Entering Into The Contract With The Procuring Entity, Acknowledges The Right Of The Procuring Entity To Institute Action Pursuant To Act 3688 Against Any Subcontractor Be They An Individual, Firm, Partnership, Corporation, Or Association Supplying The Contractor With Labor, Materials And/or Equipment For The Performance Of This Contract. 8. Subcontracting 8.1. Unless Otherwise Indicated In The Scc, The Contractor Cannot Subcontract Works More Than The Percentage Specified In Itb Clause 8.1. 8.2. Subcontracting Of Any Portion Of The Works Does Not Relieve The Contractor Of Any Liability Or Obligation Under This Contract. The Contractor Will Be Responsible For The Acts, Defaults, And Negligence Of Any Subcontractor, Its Agents, Servants Or Workmen As Fully As If These Were The Contractor’s Own Acts, Defaults, Or Negligence, Or Those Of Its Agents, Servants Or Workmen. 8.3. Subcontractors Disclosed And Identified During The Bidding May Be Changed During The Implementation Of This Contract, Subject To Compliance With The Required Qualifications And The Approval Of The Procuring Entity. 9. Liquidated Damages 9.1. The Contractor Shall Pay Liquidated Damages To The Procuring Entity For Each Day That The Completion Date Is Later Than The Intended Completion Date. The Applicable Liquidated Damages Is At Least One-tenth (1/10) Of A Percent Of The Cost Of The Unperformed Portion For Every Day Of Delay. The Total Amount Of Liquidated Damages Shall Not Exceed Ten Percent (10%) Of The Amount Of The Contract. The Procuring Entity May Deduct Liquidated Damages From Payments Due To The Contractor. Payment Of Liquidated Damages Shall Not Affect The Contractor. Once The Cumulative Amount Of Liquidated Damages Reaches Ten Percent (10%) Of The Amount Of This Contract, The Procuring Entity Shall Rescind This Contract, Without Prejudice To Other Courses Of Action And Remedies Open To It. 9.2. If The Intended Completion Date Is Extended After Liquidated Damages Have Been Paid, The Engineer Of The Procuring Entity Shall Correct Any Overpayment Of Liquidated Damages By The Contractor By Adjusting The Next Payment Certificate. The Contractor Shall Be Paid Interest On The Overpayment, Calculated From The Date Of Payment To The Date Of Repayment, At The Rates Specified In Gcc Clause 40.3. 10. Site Investigation Reports The Contractor, In Preparing The Bid, Shall Rely On Any Site Investigation Reports Referred To In The Scc Supplemented By Any Information Obtained By The Contractor. 11. The Procuring Entity, Licenses And Permits The Procuring Entity Shall, If Requested By The Contractor, Assist Him In Applying For Permits, Licenses Or Approvals, Which Are Required For The Works. 12. Contractor’s Risk And Warranty Security 12.1. The Contractor Shall Assume Full Responsibility For The Works From The Time Project Construction Commenced Up To Final Acceptance By The Procuring Entity And Shall Be Held Responsible For Any Damage Or Destruction Of The Works Except Those Occasioned By Force Majeure. The Contractor Shall Be Fully Responsible For The Safety, Protection, Security, And Convenience Of His Personnel, Third Parties, And The Public At Large, As Well As The Works, Equipment, Installation, And The Like To Be Affected By His Construction Work. 12.2. The Defects Liability Period For Infrastructure Projects Shall Be One Year From Contract Completion Up To Final Acceptance By The Procuring Entity. During This Period, The Contractor Shall Undertake The Repair Works, At His Own Expense, Of Any Damage To The Works On Account Of The Use Of Materials Of Inferior Quality Within Ninety (90) Days From The Time The Head Of The Procuring Entity Has Issued An Order To Undertake Repair. In Case Of Failure Or Refusal To Comply With This Mandate, The Procuring Entity Shall Undertake Such Repair Works And Shall Be Entitled To Full Reimbursement Of Expenses Incurred Therein Upon Demand. 12.3. Unless Otherwise Indicated In The Scc, In Case The Contractor Fails To Comply With The Preceding Paragraph, The Procuring Entity Shall Forfeit Its Performance Security, Subject Its Property (ies) To Attachment Or Garnishment Proceedings, And Perpetually Disqualify It From Participating In Any Public Bidding. All Payables Of The Gop In His Favor Shall Be Offset To Recover The Costs. 12.4. After Final Acceptance Of The Works By The Procuring Entity, The Contractor Shall Be Held Responsible For “structural Defects”, I.e., Major Faults/flaws/deficiencies In One Or More Key Structural Elements Of The Project Which May Lead To Structural Failure Of The Completed Elements Or Structure, Or “structural Failures”, I.e., Where One Or More Key Structural Elements In An Infrastructure Facility Fails Or Collapses, Thereby Rendering The Facility Or Part Thereof Incapable Of Withstanding The Design Loads, And/or Endangering The Safety Of The Users Or The General Public: (a) Contractor – Where Structural Defects/failures Arise Due To Faults Attributable To Improper Construction, Use Of Inferior Quality/substandard Materials, And Any Violation Of The Contract Plans And Specifications, The Contractor Shall Be Held Liable; (b) Consultants – Where Structural Defects/failures Arise Due To Faulty And/or Inadequate Design And Specifications As Well As Construction Supervision, Then The Consultant Who Prepared The Design Or Undertook Construction Supervision For The Project Shall Be Held Liable; (c) Procuring Entity’s Representatives/project Manager/construction Managers And Supervisors – The Project Owner’s Representative(s), Project Manager, Construction Manager, And Supervisor(s) Shall Be Held Liable In Cases Where The Structural Defects/failures Are Due To His/their Willful Intervention In Altering The Designs And Other Specifications; Negligence Or Omission In Not Approving Or Acting On Proposed Changes To Noted Defects Or Deficiencies In The Design And/or Specifications; And The Use Of Substandard Construction Materials In The Project; (d) Third Parties - Third Parties Shall Be Held Liable In Cases Where Structural Defects/failures Are Caused By Work Undertaken By Them Such As Leaking Pipes, Diggings Or Excavations, Underground Cables And Electrical Wires, Underground Tunnel, Mining Shaft And The Like, In Which Case The Applicable Warranty To Such Structure Should Be Levied To Third Parties For Their Construction Or Restoration Works. (e) Users - In Cases Where Structural Defects/failures Are Due To Abuse/misuse By The End User Of The Constructed Facility And/or Non–compliance By A User With The Technical Design Limits And/or Intended Purpose Of The Same, Then The User Concerned Shall Be Held Liable. 12.5. The Warranty Against Structural Defects/failures, Except Those Occasioned On Force Majeure, Shall Cover The Period Specified In The Scc Reckoned From The Date Of Issuance Of The Certificate Of Final Acceptance By The Procuring Entity. 12.6. The Contractor Shall Be Required To Put Up A Warranty Security In The Form Of Cash, Bank Guarantee, Letter Of Credit, Gsis Or Surety Bond Callable On Demand, In Accordance With The Following Schedule: Form Of Warranty Minimum Amount In Percentage (%) Of Total Contract Price (a) Cash Or Letter Of Credit Issued By Universal Or Commercial Bank: Provided, However, That The Letter Of Credit Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank Five Percent (5%) (b) Bank Guarantee Confirmed By Universal Or Commercial Bank: Provided, However, That The Letter Of Credit Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank Ten Percent (10%) (c) Surety Bond Callable Upon Demand Issued By Gsis Or Any Surety Or Insurance Company Duly Certified By The Insurance Commission Thirty Percent (30%) 12.7. The Warranty Security Shall Be Stated In Philippine Pesos And Shall Remain Effective For One Year From The Date Of Issuance Of The Certificate Of Final Acceptance By The Procuring Entity, And Returned Only After The Lapse Of Said One Year Period. 12.8. In Case Of Structural Defects/failure Occurring During The Applicable Warranty Period Provided In Gcc Clause 12.5, The Procuring Entity Shall Undertake The Necessary Restoration Or Reconstruction Works And Shall Be Entitled To Full Reimbursement By The Parties Found To Be Liable For Expenses Incurred Therein Upon Demand, Without Prejudice To The Filing Of Appropriate Administrative, Civil, And/or Criminal Charges Against The Responsible Persons As Well As The Forfeiture Of The Warranty Security Posted In Favor Of The Procuring Entity. 13. Liability Of The Contractor Subject To Additional Provisions, If Any, Set Forth In The Scc, The Contractor’s Liability Under This Contract Shall Be As Provided By The Laws Of The Republic Of The Philippines. 14. Procuring Entity’s Risk 14.1. From The Start Date Until The Certificate Of Final Acceptance Has Been Issued, The Following Are Risks Of The Procuring Entity: (a) The Risk Of Personal Injury, Death, Or Loss Of Or Damage To Property (excluding The Works, Plant, Materials, And Equipment), Which Are Due To: (i) Any Type Of Use Or Occupation Of The Site Authorized By The Procuring Entity After The Official Acceptance Of The Works; Or (ii) Negligence, Breach Of Statutory Duty, Or Interference With Any Legal Right By The Procuring Entity Or By Any Person Employed By Or Contracted To Him Except The Contractor. (b) The Risk Of Damage To The Works, Plant, Materials, And Equipment To The Extent That It Is Due To A Fault Of The Procuring Entity Or In The Procuring Entity’s Design, Or Due To War Or Radioactive Contamination Directly Affecting The Country Where The Works Are To Be Executed. 15. Insurance 15.1. The Contractor Shall, Under His Name And At His Own Expense, Obtain And Maintain, For The Duration Of This Contract, The Following Insurance Coverage: (a) Contractor’s All Risk Insurance; (b) Transportation To The Project Site Of Equipment, Machinery, And Supplies Owned By The Contractor; (c) Personal Injury Or Death Of Contractor’s Employees; And (d) Comprehensive Insurance For Third Party Liability To Contractor’s Direct Or Indirect Act Or Omission Causing Damage To Third Persons. 15.2. The Contractor Shall Provide Evidence To The Procuring Entity’s Representative That The Insurances Required Under This Contract Have Been Effected And Shall, Within A Reasonable Time, Provide Copies Of The Insurance Policies To The Procuring Entity’s Representative. Such Evidence And Such Policies Shall Be Provided To The Procuring Entity’s Through The Procuring Entity’s Representative. 15.3. The Contractor Shall Notify The Insurers Of Changes In The Nature, Extent, Or Program For The Execution Of The Works And Ensure The Adequacy Of The Insurances At All Times In Accordance With The Terms Of This Contract And Shall Produce To The Procuring Entity’s Representative The Insurance Policies In Force Including The Receipts For Payment Of The Current Premiums. The Above Insurance Policies Shall Be Obtained From Any Reputable Insurance Company Approved By The Procuring Entity’s Representative. 15.4. If The Contractor Fails To Obtain And Keep In Force The Insurances Referred To Herein Or Any Other Insurance Which He May Be Required To Obtain Under The Terms Of This Contract, The Procuring Entity May Obtain And Keep In Force Any Such Insurances And Pay Such Premiums As May Be Necessary For The Purpose. From Time To Time, The Procuring Entity May Deduct The Amount It Shall Pay For Said Premiums Including Twenty Five Percent (25%) Therein From Any Monies Due, Or Which May Become Due, To The Contractor, Without Prejudice To The Procuring Entity Exercising Its Right To Impose Other Sanctions Against The Contractor Pursuant To The Provisions Of This Contract. 15.5. In The Event The Contractor Fails To Observe The Above Safeguards, The Procuring Entity May, At The Contractor’s Expense, Take Whatever Measure Is Deemed Necessary For Its Protection And That Of The Contractor’s Personnel And Third Parties, And/or Order The Interruption Of Dangerous Works. In Addition, The Procuring Entity May Refuse To Make The Payments Under Gcc Clause 40 Until The Contractor Complies With This Clause. 15.6. The Contractor Shall Immediately Replace The Insurance Policy Obtained As Required In This Contract, Without Need Of The Procuring Entity’s Demand, With A New Policy Issued By A New Insurance Company Acceptable To The Procuring Entity For Any Of The Following Grounds: (a) The Issuer Of The Insurance Policy To Be Replaced Has: (i) Become Bankrupt; (ii) Been Placed Under Receivership Or Under A Management Committee; (iii) Been Sued For Suspension Of Payment; Or (iv) Been Suspended By The Insurance Commission And Its License To Engage In Business Or Its Authority To Issue Insurance Policies Cancelled; Or (v) Where Reasonable Grounds Exist That The Insurer May Not Be Able, Fully And Promptly, To Fulfill Its Obligation Under The Insurance Policy. 16. Termination For Default Of Contractor 16.1. The Procuring Entity Shall Terminate This Contract For Default When Any Of The Following Conditions Attend Its Implementation: 16.2. Due To The Contractor’s Fault And While The Project Is On-going, It Has Incurred Negative Slippage Of Fifteen Percent (15%) Or More In Accordance With Presidential Decree 1870, Regardless Of Whether Or Not Previous Warnings And Notices Have Been Issued For The Contractor To Improve His Performance; 16.3. Due To Its Own Fault And After This Contract Time Has Expired, The Contractor Incurs Delay In The Completion Of The Work After This Contract Has Expired; Or 16.4. The Contractor: (a) Abandons The Contract Works, Refuses Or Fails To Comply With A Valid Instruction Of The Procuring Entity Or Fails To Proceed Expeditiously And Without Delay Despite A Written Notice By The Procuring Entity; (b) Does Not Actually Have On The Project Site The Minimum Essential Equipment Listed On The Bid Necessary To Prosecute The Works In Accordance With The Approved Program Of Work And Equipment Deployment Schedule As Required For The Project; (c) Does Not Execute The Works In Accordance With This Contract Or Persistently Or Flagrantly Neglects To Carry Out Its Obligations Under This Contract; (d) Neglects Or Refuses To Remove Materials Or To Perform A New Work That Has Been Rejected As Defective Or Unsuitable; Or (e) Sub-lets Any Part Of This Contract Without Approval By The Procuring Entity. 16.5. All Materials On The Site, Plant, Equipment, And Works Shall Be Deemed To Be The Property Of The Procuring Entity If This Contract Is Rescinded Because Of The Contractor’s Default. 17. Termination For Default Of Procuring Entity The Contractor May Terminate This Contract With The Procuring Entity If The Works Are Completely Stopped For A Continuous Period Of At Least Sixty (60) Calendar Days Through No Fault Of Its Own, Due To Any Of The Following Reasons: (a) Failure Of The Procuring Entity To Deliver, Within A Reasonable Time, Supplies, Materials, Right-of-way, Or Other Items It Is Obligated To Furnish Under The Terms Of This Contract; Or (b) The Prosecution Of The Work Is Disrupted By The Adverse Peace And Order Situation, As Certified By The Armed Forces Of The Philippines Provincial Commander And Approved By The Secretary Of National Defense. 18. Termination For Other Causes 18.1. The Procuring Entity May Terminate This Contract, In Whole Or In Part, At Any Time For Its Convenience. The Head Of The Procuring Entity May Terminate This Contract For The Convenience Of The Procuring Entity If He Has Determined The Existence Of Conditions That Make Project Implementation Economically, Financially Or Technically Impractical And/or Unnecessary, Such As, But Not Limited To, Fortuitous Event(s) Or Changes In Law And National Government Policies. 18.2. The Procuring Entity Or The Contractor May Terminate This Contract If The Other Party Causes A Fundamental Breach Of This Contract. 18.3. Fundamental Breaches Of Contract Shall Include, But Shall Not Be Limited To, The Following: (a) The Contractor Stops Work For Twenty Eight (28) Days When No Stoppage Of Work Is Shown On The Current Program Of Work And The Stoppage Has Not Been Authorized By The Procuring Entity’s Representative; (b) The Procuring Entity’s Representative Instructs The Contractor To Delay The Progress Of The Works, And The Instruction Is Not Withdrawn Within Twenty Eight (28) Days; (c) The Procuring Entity Shall Terminate This Contract If The Contractor Is Declared Bankrupt Or Insolvent As Determined With Finality By A Court Of Competent Jurisdiction. In This Event, Termination Will Be Without Compensation To The Contractor, Provided That Such Termination Will Not Prejudice Or Affect Any Right Of Action Or Remedy Which Has Accrued Or Will Accrue Thereafter To The Procuring Entity And/or The Contractor. In The Case Of The Contractor's Insolvency, Any Contractor's Equipment Which The Procuring Entity Instructs In The Notice Is To Be Used Until The Completion Of The Works; (d) A Payment Certified By The Procuring Entity’s Representative Is Not Paid By The Procuring Entity To The Contractor Within Eighty Four (84) Days From The Date Of The Procuring Entity’s Representative’s Certificate; (e) The Procuring Entity’s Representative Gives Notice That Failure To Correct A Particular Defect Is A Fundamental Breach Of Contract And The Contractor Fails To Correct It Within A Reasonable Period Of Time Determined By The Procuring Entity’s Representative; (f) The Contractor Does Not Maintain A Security, Which Is Required; (g) The Contractor Has Delayed The Completion Of The Works By The Number Of Days For Which The Maximum Amount Of Liquidated Damages Can Be Paid, As Defined In The Gcc Clause 9; And (h) In Case It Is Determined Prima Facie By The Procuring Entity That The Contractor Has Engaged, Before Or During The Implementation Of The Contract, In Unlawful Deeds And Behaviors Relative To Contract Acquisition And Implementation, Such As, But Not Limited To, The Following: (i) Corrupt, Fraudulent, Collusive, Coercive, And Obstructive Practices As Defined In Itb Clause 3.1(a), Unless Otherwise Specified In The Scc; (ii) Drawing Up Or Using Forged Documents; (iii) Using Adulterated Materials, Means Or Methods, Or Engaging In Production Contrary To Rules Of Science Or The Trade; And (iv) Any Other Act Analogous To The Foregoing. 18.4. The Funding Source Or The Procuring Entity, As Appropriate, Will Seek To Impose The Maximum Civil, Administrative And/or Criminal Penalties Available Under The Applicable Law On Individuals And Organizations Deemed To Be Involved With Corrupt, Fraudulent, Or Coercive Practices. 18.5. When Persons From Either Party To This Contract Gives Notice Of A Fundamental Breach To The Procuring Entity’s Representative In Order To Terminate The Existing Contract For A Cause Other Than Those Listed Under Gcc Clause 18.3, The Procuring Entity’s Representative Shall Decide Whether The Breach Is Fundamental Or Not. 18.6. If This Contract Is Terminated, The Contractor Shall Stop Work Immediately, Make The Site Safe And Secure, And Leave The Site As Soon As Reasonably Possible. 19. Procedures For Termination Of Contracts 19.1. The Following Provisions Shall Govern The Procedures For The Termination Of This Contract: (a) Upon Receipt Of A Written Report Of Acts Or Causes Which May Constitute Ground(s) For Termination As Aforementioned, Or Upon Its Own Initiative, The Procuring Entity Shall, Within A Period Of Seven (7) Calendar Days, Verify The Existence Of Such Ground(s) And Cause The Execution Of A Verified Report, With All Relevant Evidence Attached; (b) Upon Recommendation By The Procuring Entity, The Head Of The Procuring Entity Shall Terminate This Contract Only By A Written Notice To The Contractor Conveying The Termination Of This Contract. The Notice Shall State: (i) That This Contract Is Being Terminated For Any Of The Ground(s) Afore-mentioned, And A Statement Of The Acts That Constitute The Ground(s) Constituting The Same; (ii) The Extent Of Termination, Whether In Whole Or In Part; (iii) An Instruction To The Contractor To Show Cause As To Why This Contract Should Not Be Terminated; And (iv) Special Instructions Of The Procuring Entity, If Any. The Notice To Terminate Shall Be Accompanied By A Copy Of The Verified Report; (c) Within A Period Of Seven (7) Calendar Days From Receipt Of The Notice Of Termination, The Contractor Shall Submit To The Head Of The Procuring Entity A Verified Position Paper Stating Why The Contract Should Not Be Terminated. If The Contractor Fails To Show Cause After The Lapse Of The Seven (7) Day Period, Either By Inaction Or By Default, The Head Of The Procuring Entity Shall Issue An Order Terminating The Contract; (d) The Procuring Entity May, At Anytime Before Receipt Of The Bidder’s Verified Position Paper Described In Item (c) Above Withdraw The Notice To Terminate If It Is Determined That Certain Items Or Works Subject Of The Notice Had Been Completed, Delivered, Or Performed Before The Contractor’s Receipt Of The Notice; (e) Within A Non-extendible Period Of Ten (10) Calendar Days From Receipt Of The Verified Position Paper, The Head Of The Procuring Entity Shall Decide Whether Or Not To Terminate This Contract. It Shall Serve A Written Notice To The Contractor Of Its Decision And, Unless Otherwise Provided In The Said Notice, This Contract Is Deemed Terminated From Receipt Of The Contractor Of The Notice Of Decision. The Termination Shall Only Be Based On The Ground(s) Stated In The Notice To Terminate; And (f) The Head Of The Procuring Entity May Create A Contract Termination Review Committee (ctrc) To Assist Him In The Discharge Of This Function. All Decisions Recommended By The Ctrc Shall Be Subject To The Approval Of The Head Of The Procuring Entity. 19.2. Pursuant To Section 69(f) Of Ra 9184 And Without Prejudice To The Imposition Of Additional Administrative Sanctions As The Internal Rules Of The Agency May Provide And/or Further Criminal Prosecution As Provided By Applicable Laws, The Procuring Entity Shall Impose On Contractors After The Termination Of The Contract The Penalty Of Suspension For One (1) Year For The First Offense, Suspension For Two (2) Years For The Second Offense From Participating In The Public Bidding Process, For Violations Committed During The Contract Implementation Stage, Which Include But Not Limited To The Following: (a) Failure Of The Contractor, Due Solely To His Fault Or Negligence, To Mobilize And Start Work Or Performance Within The Specified Period In The Notice To Proceed (“ntp”); (b) Failure By The Contractor To Fully And Faithfully Comply With Its Contractual Obligations Without Valid Cause, Or Failure By The Contractor To Comply With Any Written Lawful Instruction Of The Procuring Entity Or Its Representative(s) Pursuant To The Implementation Of The Contract. For The Procurement Of Infrastructure Projects Or Consultancy Contracts, Lawful Instructions Include But Are Not Limited To The Following: (i) Employment Of Competent Technical Personnel, Competent Engineers And/or Work Supervisors; (ii) Provision Of Warning Signs And Barricades In Accordance With Approved Plans And Specifications And Contract Provisions; (iii) Stockpiling In Proper Places Of All Materials And Removal From The Project Site Of Waste And Excess Materials, Including Broken Pavement And Excavated Debris In Accordance With Approved Plans And Specifications And Contract Provisions; (iv) Deployment Of Committed Equipment, Facilities, Support Staff And Manpower; And (v) Renewal Of The Effectivity Dates Of The Performance Security After Its Expiration During The Course Of Contract Implementation. (c) Assignment And Subcontracting Of The Contract Or Any Part Thereof Or Substitution Of Key Personnel Named In The Proposal Without Prior Written Approval By The Procuring Entity. (d) Poor Performance By The Contractor Or Unsatisfactory Quality And/or Progress Of Work Arising From His Fault Or Negligence As Reflected In The Constructor's Performance Evaluation System (“cpes”) Rating Sheet. In The Absence Of The Cpes Rating Sheet, The Existing Performance Monitoring System Of The Procuring Entity Shall Be Applied. Any Of The Following Acts By The Contractor Shall Be Construed As Poor Performance: (i) Negative Slippage Of 15% And Above Within The Critical Path Of The Project Due Entirely To The Fault Or Negligence Of The Contractor; And (ii) Quality Of Materials And Workmanship Not Complying With The Approved Specifications Arising From The Contractor's Fault Or Negligence. (e) Willful Or Deliberate Abandonment Or Non-performance Of The Project Or Contract By The Contractor Resulting To Substantial Breach Thereof Without Lawful And/or Just Cause. In Addition To The Penalty Of Suspension, The Performance Security Posted By The Contractor Shall Also Be Forfeited. 20. Force Majeure, Release From Performance 20.1. For Purposes Of This Contract The Terms “force Majeure” And “fortuitous Event” May Be Used Interchangeably. In This Regard, A Fortuitous Event Or Force Majeure Shall Be Interpreted To Mean An Event Which The Contractor Could Not Have Foreseen, Or Which Though Foreseen, Was Inevitable. It Shall Not Include Ordinary Unfavorable Weather Conditions; And Any Other Cause The Effects Of Which Could Have Been Avoided With The Exercise Of Reasonable Diligence By The Contractor. 20.2. If This Contract Is Discontinued By An Outbreak Of War Or By Any Other Event Entirely Outside The Control Of Either The Procuring Entity Or The Contractor, The Procuring Entity’s Representative Shall Certify That This Contract Has Been Discontinued. The Contractor Shall Make The Site Safe And Stop Work As Quickly As Possible After Receiving This Certificate And Shall Be Paid For All Works Carried Out Before Receiving It And For Any Work Carried Out Afterwards To Which A Commitment Was Made. 20.3. If The Event Continues For A Period Of Eighty Four (84) Days, Either Party May Then Give Notice Of Termination, Which Shall Take Effect Twenty Eight (28) Days After The Giving Of The Notice. 20.4. After Termination, The Contractor Shall Be Entitled To Payment Of The Unpaid Balance Of The Value Of The Works Executed And Of The Materials And Plant Reasonably Delivered To The Site, Adjusted By The Following: (a) Any Sum To Which The Contractor Is Entitled Under Gcc Clause 28; (b) The Cost Of His Suspension And Demobilization; (c) Any Sum To Which The Procuring Entity Is Entitled. 20.5. The Net Balance Due Shall Be Paid Or Repaid Within A Reasonable Time Period From The Time Of The Notice Of Termination. 21. Resolution Of Disputes 21.1. If Any Dispute Or Difference Of Any Kind Whatsoever Shall Arise Between The Parties In Connection With The Implementation Of The Contract Covered By The Act And This Irr, The Parties Shall Make Every Effort To Resolve Amicably Such Dispute Or Difference By Mutual Consultation. 21.2. If The Contractor Believes That A Decision Taken By The Procuring Entity’s Representative Was Either Outside The Authority Given To The Procuring Entity’s Representative By This Contract Or That The Decision Was Wrongly Taken, The Decision Shall Be Referred To The Arbiter Indicated In The Scc Within Fourteen (14) Days Of The Notification Of The Procuring Entity’s Representative’s Decision. 21.3. Any And All Disputes Arising From The Implementation Of This Contract Covered By The R.a. 9184 And Its Irr Shall Be Submitted To Arbitration In The Philippines According To The Provisions Of Republic Act No. 876, Otherwise Known As The “ Arbitration Law” And Republic Act 9285, Otherwise Known As The “alternative Dispute Resolution Act Of 2004”: Provided, However, That, Disputes That Are Within The Competence Of The Construction Industry Arbitration Commission To Resolve Shall Be Referred Thereto. The Process Of Arbitration Shall Be Incorporated As A Provision In This Contract That Will Be Executed Pursuant To The Provisions Of The Act And Its Irr: Provided, Further, That, By Mutual Agreement, The Parties May Agree In Writing To Resort To Other Alternative Modes Of Dispute Resolution. 22. Suspension Of Loan, Credit, Grant, Or Appropriation In The Event That The Funding Source Suspends The Loan, Credit, Grant, Or Appropriation To The Procuring Entity, From Which Part Of The Payments To The Contractor Are Being Made: (a) The Procuring Entity Is Obligated To Notify The Contractor Of Such Suspension Within Seven (7) Days Of Having Received The Suspension Notice. (b) If The Contractor Has Not Received Sums Due It For Work Already Done Within Forty Five (45) Days From The Time The Contractor’s Claim For Payment Has Been Certified By The Procuring Entity’s Representative, The Contractor May Immediately Issue A Suspension Of Work Notice In Accordance With Gcc Clause 45.2. 23. Procuring Entity’s Representative’s Decisions 23.1. Except Where Otherwise Specifically Stated, The Procuring Entity’s Representative Will Decide Contractual Matters Between The Procuring Entity And The Contractor In The Role Representing The Procuring Entity. 23.2. The Procuring Entity’s Representative May Delegate Any Of His Duties And Responsibilities To Other People, Except To The Arbiter, After Notifying The Contractor, And May Cancel Any Delegation After Notifying The Contractor. 24. Approval Of Drawings And Temporary Works By The Procuring Entity’s Representative 24.1. All Drawings Prepared By The Contractor For The Execution Of The Temporary Works, Are Subject To Prior Approval By The Procuring Entity’s Representative Before Its Use. 24.2. The Contractor Shall Be Responsible For Design Of Temporary Works. 24.3. The Procuring Entity’s Representative’s Approval Shall Not Alter The Contractor’s Responsibility For Design Of The Temporary Works. 24.4. The Contractor Shall Obtain Approval Of Third Parties To The Design Of The Temporary Works, When Required By The Procuring Entity. 25. Acceleration And Delays Ordered By The Procuring Entity’s Representative 25.1. When The Procuring Entity Wants The Contractor To Finish Before The Intended Completion Date, The Procuring Entity’s Representative Will Obtain Priced Proposals For Achieving The Necessary Acceleration From The Contractor. If The Procuring Entity Accepts These Proposals, The Intended Completion Date Will Be Adjusted Accordingly And Confirmed By Both The Procuring Entity And The Contractor. 25.2. If The Contractor’s Financial Proposals For An Acceleration Are Accepted By The Procuring Entity, They Are Incorporated In The Contract Price And Treated As A Variation. 26. Extension Of The Intended Completion Date 26.1. The Procuring Entity’s Representative Shall Extend The Intended Completion Date If A Variation Is Issued Which Makes It Impossible For The Intended Completion Date To Be Achieved By The Contractor Without Taking Steps To Accelerate The Remaining Work, Which Would Cause The Contractor To Incur Additional Costs. No Payment Shall Be Made For Any Event Which May Warrant The Extension Of The Intended Completion Date. 26.2. The Procuring Entity’s Representative Shall Decide Whether And By How Much To Extend The Intended Completion Date Within Twenty One (21) Days Of The Contractor Asking The Procuring Entity’s Representative For A Decision Thereto After Fully Submitting All Supporting Information. If The Contractor Has Failed To Give Early Warning Of A Delay Or Has Failed To Cooperate In Dealing With A Delay, The Delay By This Failure Shall Not Be Considered In Assessing The New Intended Completion Date. 27. Right To Vary 27.1. The Procuring Entity’s Representative With The Prior Approval Of The Procuring Entity May Instruct Variations, Up To A Maximum Cumulative Amount Of Ten Percent (10%) Of The Original Contract Cost. 27.2. Variations Shall Be Valued As Follows: (a) At A Lump Sum Price Agreed Between The Parties; (b) Where Appropriate, At Rates In This Contract; (c) In The Absence Of Appropriate Rates, The Rates In This Contract Shall Be Used As The Basis For Valuation; Or Failing Which (d) At Appropriate New Rates, Equal To Or Lower Than Current Industry Rates And To Be Agreed Upon By Both Parties And Approved By The Head Of The Procuring Entity. 28. Contractor's Right To Claim If The Contractor Incurs Cost As A Result Of Any Of The Events Under Gcc Clause 13, The Contractor Shall Be Entitled To The Amount Of Such Cost. If As A Result Of Any Of The Said Events, It Is Necessary To Change The Works, This Shall Be Dealt With As A Variation. 29. Dayworks 29.1. Subject To Gcc Clause 43 On Variation Order, And If Applicable As Indicated In The Scc, The Day Works Rates In The Contractor’s Bid Shall Be Used For Small Additional Amounts Of Work Only When The Procuring Entity’s Representative Has Given Written Instructions In Advance For Additional Work To Be Paid For In That Way. 29.2. All Work To Be Paid For As Day Works Shall Be Recorded By The Contractor On Forms Approved By The Procuring Entity’s Representative. Each Completed Form Shall Be Verified And Signed By The Procuring Entity’s Representative Within Two Days Of The Work Being Done. 29.3. The Contractor Shall Be Paid For Day Works Subject To Obtaining Signed Dayworks Forms. 30. Early Warning 30.1. The Contractor Shall Warn The Procuring Entity’s Representative At The Earliest Opportunity Of Specific Likely Future Events Or Circumstances That May Adversely Affect The Quality Of The Work, Increase The Contract Price, Or Delay The Execution Of The Works. The Procuring Entity’s Representative May Require The Contractor To Provide An Estimate Of The Expected Effect Of The Future Event Or Circumstance On The Contract Price And Completion Date. The Estimate Shall Be Provided By The Contractor As Soon As Reasonably Possible. 30.2. The Contractor Shall Cooperate With The Procuring Entity’s Representative In Making And Considering Proposals For How The Effect Of Such An Event Or Circumstance Can Be Avoided Or Reduced By Anyone Involved In The Work And In Carrying Out Any Resulting Instruction Of The Procuring Entity’s Representative. 31. Program Of Work 31.1. Within The Time Stated In The Scc, The Contractor Shall Submit To The Procuring Entity’s Representative For Approval A Program Of Work Showing The General Methods, Arrangements, Order, And Timing For All The Activities In The Works. 31.2. An Update Of The Program Of Work Shall The Show The Actual Progress Achieved On Each Activity And The Effect Of The Progress Achieved On The Timing Of The Remaining Work, Including Any Changes To The Sequence Of The Activities. 31.3. The Contractor Shall Submit To The Procuring Entity’s Representative For Approval An Updated Program Of Work At Intervals No Longer Than The Period Stated In The Scc. If The Contractor Does Not Submit An Updated Program Of Work Within This Period, The Procuring Entity’s Representative May Withhold The Amount Stated In The Scc From The Next Payment Certificate And Continue To Withhold This Amount Until The Next Payment After The Date On Which The Overdue Program Of Work Has Been Submitted. 31.4. The Procuring Entity’s Representative’s Approval Of The Program Of Work Shall Not Alter The Contractor’s Obligations. The Contractor May Revise The Program Of Work And Submit It To The Procuring Entity’s Representative Again At Any Time. A Revised Program Of Work Shall Show The Effect Of Any Approved Variations. 31.5. When The Program Of Work Is Updated, The Contractor Shall Provide The Procuring Entity’s Representative With An Updated Cash Flow Forecast. The Cash Flow Forecast Shall Include Different Currencies, As Defined In The Contract, Converted As Necessary Using The Contract Exchange Rates. 31.6. All Variations Shall Be Included In Updated Program Of Work Produced By The Contractor. 32. Management Conferences 32.1. Either The Procuring Entity’s Representative Or The Contractor May Require The Other To Attend A Management Conference. The Management Conference Shall Review The Plans For Remaining Work And Deal With Matters Raised In Accordance With The Early Warning Procedure. 32.2. The Procuring Entity’s Representative Shall Record The Business Of Management Conferences And Provide Copies Of The Record To Those Attending The Conference And To The Procuring Entity . The Responsibility Of The Parties For Actions To Be Taken Shall Be Decided By The Procuring Entity’s Representative Either At The Management Conference Or After The Management Conference And Stated In Writing To All Who Attended The Conference. 33. Bill Of Quantities 33.1. The Bill Of Quantities Shall Contain Items Of Work For The Construction, Installation, Testing, And Commissioning Of Work To Be Done By The Contractor. 33.2. The Bill Of Quantities Is Used To Calculate The Contract Price. The Contractor Is Paid For The Quantity Of The Work Done At The Rate In The Bill Of Quantities For Each Item. 33.3. If The Final Quantity Of Any Work Done Differs From The Quantity In The Bill Of Quantities For The Particular Item And Is Not More Than Twenty Five Percent (25%) Of The Original Quantity, Provided The Aggregate Changes For All Items Do Not Exceed Ten Percent (10%) Of The Contract Price, The Procuring Entity’s Representative Shall Make The Necessary Adjustments To Allow For The Changes Subject To Applicable Laws, Rules, And Regulations. 33.4. If Requested By The Procuring Entity’s Representative, The Contractor Shall Provide The Procuring Entity’s Representative With A Detailed Cost Breakdown Of Any Rate In The Bill Of Quantities. 34. Instructions, Inspections And Audits 34.1. The Procuring Entity’s Personnel Shall At All Reasonable Times During Construction Of The Work Be Entitled To Examine, Inspect, Measure And Test The Materials And Workmanship, And To Check The Progress Of The Construction. 34.2. If The Procuring Entity’s Representative Instructs The Contractor To Carry Out A Test Not Specified In The Specification To Check Whether Any Work Has A Defect And The Test Shows That It Does, The Contractor Shall Pay For The Test And Any Samples. If There Is No Defect, The Test Shall Be A Compensation Event. 34.3. The Contractor Shall Permit The Funding Source Named In The Scc To Inspect The Contractor’s Accounts And Records Relating To The Performance Of The Contractor And To Have Them Audited By Auditors Appointed By The Funding Source, If So Required By The Funding Source. 35. Identifying Defects The Procuring Entity’s Representative Shall Check The Contractor’s Work And Notify The Contractor Of Any Defects That Are Found. Such Checking Shall Not Affect The Contractor’s Responsibilities. The Procuring Entity’s Representative May Instruct The Contractor To Search Uncover Defects And Test Any Work That The Procuring Entity’s Representative Considers Below Standards And Defective. 36. Cost Of Repairs Loss Or Damage To The Works Or Materials To Be Incorporated In The Works Between The Start Date And The End Of The Defects Liability Periods Shall Be Remedied By The Contractor At The Contractor’s Cost If The Loss Or Damage Arises From The Contractor’s Acts Or Omissions. 37. Correction Of Defects 37.1. The Procuring Entity’s Representative Shall Give Notice To The Contractor Of Any Defects Before The End Of The Defects Liability Period, Which Isone (1) Year From Project Completion Up To Final Acceptance By The Procuring Entity’s. 37.2. Every Time Notice Of A Defect Is Given, The Contractor Shall Correct The Notified Defect Within The Length Of Time Specified In The Procuring Entity’s Representative’s Notice. 37.3. The Contractor Shall Correct The Defects Which He Notices Himself Before The End Of The Defects Liability Period. 37.4. The Procuring Entity Shall Certify That All Defects Have Been Corrected. If The Procuring Entity Considers That Correction Of A Defect Is Not Essential, He Can Request The Contractor To Submit A Quotation For The Corresponding Reduction In The Contract Price. If The Procuring Entity Accepts The Quotation, The Corresponding Change In The Scc Is A Variation. 38. Uncorrected Defects 38.1. The Procuring Entity Shall Give The Contractor At Least Fourteen (14) Days Notice Of His Intention To Use A Third Party To Correct A Defect. If The Contractor Does Not Correct The Defect Himself Within The Period, The Procuring Entity May Have The Defect Corrected By The Third Party. The Cost Of The Correction Will Be Deducted From The Contract Price. 38.2. The Use Of A Third Party To Correct Defects That Are Uncorrected By The Contractor Will In No Way Relieve The Contractor Of Its Liabilities And Warranties Under The Contract. 39. Advance Payment 39.1. The Procuring Entity Shall, Upon A Written Request Of The Contractor Which Shall Be Submitted As A Contract Document, Make An Advance Payment To The Contractor In An Amount Not Exceeding Fifteen Percent (15%) Of The Total Contract Price, To Be Made In Lump Sum Or, At The Most Two, Installments According To A Schedule Specified In The Scc. 39.2. The Advance Payment Shall Be Made Only Upon The Submission To And Acceptance By The Procuring Entity Of An Irrevocable Standby Letter Of Credit Of Equivalent Value From A Commercial Bank, A Bank Guarantee Or A Surety Bond Callable Upon Demand, Issued By A Surety Or Insurance Company Duly Licensed By The Insurance Commission And Confirmed By The Procuring Entity. 39.3. The Advance Payment Shall Be Repaid By The Contractor By An Amount Equal To The Percentage Of The Total Contract Price Used For The Advance Payment. 39.4. The Contractor May Reduce His Standby Letter Of Credit Or Guarantee Instrument By The Amounts Refunded By The Monthly Certificates In The Advance Payment. 39.5. The Procuring Entity Will Provide An Advance Payment On The Contract Price As Stipulated In The Conditions Of Contract, Subject To The Maximum Amount Stated In Scc Clause 39.1. 40. Progress Payments 40.1. The Contractor May Submit A Request For Payment For Work Accomplished. Such Request For Payment Shall Be Verified And Certified By The Procuring Entity’s Representative/project Engineer. Except As Otherwise Stipulated In The Scc, Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Not Be Included For Payment. 40.2. The Procuring Entity Shall Deduct The Following From The Certified Gross Amounts To Be Paid To The Contractor As Progress Payment: (a) Cumulative Value Of The Work Previously Certified And Paid For. (b) Portion Of The Advance Payment To Be Recouped For The Month. (c) Retention Money In Accordance With The Condition Of Contract. (d) Amount To Cover Third Party Liabilities. (e) Amount To Cover Uncorrected Discovered Defects In The Works. 40.3. Payments Shall Be Adjusted By Deducting There From The Amounts For Advance Payments And Retention. The Procuring Entity Shall Pay The Contractor The Amounts Certified By The Procuring Entity’s Representative Within Twenty Eight (28) Days From The Date Each Certificate Was Issued. No Payment Of Interest For Delayed Payments And Adjustments Shall Be Made By The Procuring Entity. 40.4. The First Progress Payment May Be Paid By The Procuring Entity To The Contractor Provided That At Least Twenty Percent (20%) Of The Work Has Been Accomplished As Certified By The Procuring Entity’s Representative. 40.5. Items Of The Works For Which A Price Of “0” (zero) Has Been Entered Will Not Be Paid For By The Procuring Entity And Shall Be Deemed Covered By Other Rates And Prices In The Contract. 41. Payment Certificates 41.1. The Contractor Shall Submit To The Procuring Entity’s Representative Monthly Statements Of The Estimated Value Of The Work Executed Less The Cumulative Amount Certified Previously. 41.2. The Procuring Entity’s Representative Shall Check The Contractor’s Monthly Statement And Certify The Amount To Be Paid To The Contractor. 41.3. The Value Of Work Executed Shall: (a) Be Determined By The Procuring Entity’s Representative; (b) Comprise The Value Of The Quantities Of The Items In The Bill Of Quantities Completed; And (c) Include The Valuations Of Approved Variations. 41.4. The Procuring Entity’s Representative May Exclude Any Item Certified In A Previous Certificate Or Reduce The Proportion Of Any Item Previously Certified In Any Certificate In The Light Of Later Information. 42. Retention 42.1. The Procuring Entity Shall Retain From Each Payment Due To The Contractor An Amount Equal To A Percentage Thereof Using The Rate As Specified In Itb Sub-clause 42.2. 42.2. Progress Payments Are Subject To Retention Of Ten Percent (10%), Referred To As The “retention Money.” Such Retention Shall Be Based On The Total Amount Due To The Contractor Prior To Any Deduction And Shall Be Retained From Every Progress Payment Until Fifty Percent (50%) Of The Value Of Works, As Determined By The Procuring Entity, Are Completed. If, After Fifty Percent (50%) Completion, The Work Is Satisfactorily Done And On Schedule, No Additional Retention Shall Be Made; Otherwise, The Ten Percent (10%) Retention Shall Again Be Imposed Using The Rate Specified Therefore. 42.3. The Total “retention Money” Shall Be Due For Release Upon Final Acceptance Of The Works. The Contractor May, However, Request The Substitution Of The Retention Money For Each Progress Billing With Irrevocable Standby Letters Of Credit From A Commercial Bank, Bank Guarantees Or Surety Bonds Callable On Demand, Of Amounts Equivalent To The Retention Money Substituted For And Acceptable To The Procuring Entity, Provided That The Project Is On Schedule And Is Satisfactorily Undertaken. Otherwise, The Ten (10%) Percent Retention Shall Be Made. Said Irrevocable Standby Letters Of Credit, Bank Guarantees And/or Surety Bonds, To Be Posted In Favor Of The Government Shall Be Valid For A Duration To Be Determined By The Concerned Implementing Office/agency Or Procuring Entity And Will Answer For The Purpose For Which The Ten (10%) Percent Retention Is Intended, I.e., To Cover Uncorrected Discovered Defects And Third Party Liabilities. 42.4. On Completion Of The Whole Works, The Contractor May Substitute Retention Money With An “on Demand” Bank Guarantee In A Form Acceptable To The Procuring Entity. 43. Variation Orders 43.1. Variation Orders May Be Issued By The Procuring Entity To Cover Any Increase/decrease In Quantities, Including The Introduction Of New Work Items That Are Not Included In The Original Contract Or Reclassification Of Work Items That Are Either Due To Change Of Plans, Design Or Alignment To Suit Actual Field Conditions Resulting In Disparity Between The Preconstruction Plans Used For Purposes Of Bidding And The “as Staked Plans” Or Construction Drawings Prepared After A Joint Survey By The Contractor And The Procuring Entity After Award Of The Contract, Provided That The Cumulative Amount Of The Variation Order Does Not Exceed Ten Percent (10%) Of The Original Project Cost. The Addition/deletion Of Works Should Be Within The General Scope Of The Project As Bid And Awarded. The Scope Of Works Shall Not Be Reduced So As To Accommodate A Positive Variation Order. A Variation Order May Either Be In The Form Of A Change Order Or Extra Work Order. 43.2. A Change Order May Be Issued By The Procuring Entity To Cover Any Increase/decrease In Quantities Of Original Work Items In The Contract. 43.3. An Extra Work Order May Be Issued By The Procuring Entity To Cover The Introduction Of New Work Necessary For The Completion, Improvement Or Protection Of The Project Which Were Not Included As Items Of Work In The Original Contract, Such As, Where There Are Subsurface Or Latent Physical Conditions At The Site Differing Materially From Those Indicated In The Contract, Or Where There Are Duly Unknown Physical Conditions At The Site Of An Unusual Nature Differing Materially From Those Ordinarily Encountered And Generally Recognized As Inherent In The Work Or Character Provided For In The Contract. 43.4. Any Cumulative Variation Order Beyond Ten Percent (10%) Shall Be Subject Of Another Contract To Be Bid Out If The Works Are Separable From The Original Contract. In Exceptional Cases Where It Is Urgently Necessary To Complete The Original Scope Of Work, The Head Of The Procuring Entity May Authorize A Positive Variation Order Go Beyond Ten Percent (10%) But Not More Than Twenty Percent (20%) Of The Original Contract Price, Subject To The Guidelines To Be Determined By The Gppb: Provided, However, That Appropriate Sanctions Shall Be Imposed On The Designer, Consultant Or Official Responsible For The Original Detailed Engineering Design Which Failed To Consider The Variation Order Beyond Ten Percent (10%). 43.5. In Claiming For Any Variation Order, The Contractor Shall, Within Seven (7) Calendar Days After Such Work Has Been Commenced Or After The Circumstances Leading To Such Condition(s) Leading To The Extra Cost, And Within Twenty-eight (28) Calendar Days Deliver A Written Communication Giving Full And Detailed Particulars Of Any Extra Cost In Order That It May Be Investigated At That Time. Failure To Provide Either Of Such Notices In The Time Stipulated Shall Constitute A Waiver By The Contractor For Any Claim. The Preparation And Submission Of Variation Orders Are As Follows: (a) If The Procuring Entity’s Representative/project Engineer Believes That A Change Order Or Extra Work Order Should Be Issued, He Shall Prepare The Proposed Order Accompanied With The Notices Submitted By The Contractor, The Plans Therefore, His Computations As To The Quantities Of The Additional Works Involved Per Item Indicating The Specific Stations Where Such Works Are Needed, The Date Of His Inspections And Investigations Thereon, And The Log Book Thereof, And A Detailed Estimate Of The Unit Cost Of Such Items Of Work, Together With His Justifications For The Need Of Such Change Order Or Extra Work Order, And Shall Submit The Same To The Head Of The Procuring Entity For Approval. (b) The Head Of The Procuring Entity Or His Duly Authorized Representative, Upon Receipt Of The Proposed Change Order Or Extra Work Order Shall Immediately Instruct The Technical Staff Of The Procuring Entity’s To Conduct An On-the-spot Investigation To Verify The Need For The Work To Be Prosecuted. A Report Of Such Verification Shall Be Submitted Directly To The Head Of The Procuring Entity Or His Duly Authorized Representative. (c) The, Head Of The Procuring Entity Or His Duly Authorized Representative, After Being Satisfied That Such Change Order Or Extra Work Order Is Justified And Necessary, Shall Review The Estimated Quantities And Prices And Forward The Proposal With The Supporting Documentation To The Head Of Procuring Entity For Consideration. (d) If, After Review Of The Plans, Quantities And Estimated Unit Cost Of The Items Of Work Involved, The Proper Office Of The Procuring Entity Empowered To Review And Evaluate Change Orders Or Extra Work Orders Recommends Approval Thereof, Head Of The Procuring Entity Or His Duly Authorized Representative, Believing The Change Order Or Extra Work Order To Be In Order, Shall Approve The Same. (e) The Timeframe For The Processing Of Variation Orders From The Preparation Up To The Approval By The Head Of The Procuring Entity Concerned Shall Not Exceed Thirty (30) Calendar Days. 44. Contract Completion Once The Project Reaches An Accomplishment Of Ninety Five (95%) Of The Total Contract Amount, The Procuring Entity May Create An Inspectorate Team To Make Preliminary Inspection And Submit A Punch-list To The Contractor In Preparation For The Final Turnover Of The Project. Said Punch-list Will Contain, Among Others, The Remaining Works, Work Deficiencies For Necessary Corrections, And The Specific Duration/time To Fully Complete The Project Considering The Approved Remaining Contract Time. This, However, Shall Not Preclude The Claim Of The Procuring Entity For Liquidated Damages. 45. Suspension Of Work 45.1. The Procuring Entity Shall Have The Authority To Suspend The Work Wholly Or Partly By Written Order For Such Period As May Be Deemed Necessary, Due To Force Majeure Or Any Fortuitous Events Or For Failure On The Part Of The Contractor To Correct Bad Conditions Which Are Unsafe For Workers Or For The General Public, To Carry Out Valid Orders Given By The Procuring Entity Or To Perform Any Provisions Of The Contract, Or Due To Adjustment Of Plans To Suit Field Conditions As Found Necessary During Construction. The Contractor Shall Immediately Comply With Such Order To Suspend The Work Wholly Or Partly. 45.2. The Contractor Or Its Duly Authorized Representative Shall Have The Right To Suspend Work Operation On Any Or All Projects/activities Along The Critical Path Of Activities After Fifteen (15) Calendar Days From Date Of Receipt Of Written Notice From The Contractor To The District Engineer/regional Director/consultant Or Equivalent Official, As The Case May Be, Due To The Following: (a) There Exist Right-of-way Problems Which Prohibit The Contractor From Performing Work In Accordance With The Approved Construction Schedule. (b) Requisite Construction Plans Which Must Be Owner-furnished Are Not Issued To The Contractor Precluding Any Work Called For By Such Plans. (c) Peace And Order Conditions Make It Extremely Dangerous, If Not Possible, To Work. However, This Condition Must Be Certified In Writing By The Philippine National Police (pnp) Station Which Has Responsibility Over The Affected Area And Confirmed By The Department Of Interior And Local Government (dilg) Regional Director. (d) There Is Failure On The Part Of The Procuring Entity To Deliver Government-furnished Materials And Equipment As Stipulated In The Contract. (e) Delay In The Payment Of Contractor’s Claim For Progress Billing Beyond Forty-five (45) Calendar Days From The Time The Contractor’s Claim Has Been Certified To By The Procuring Entity’s Authorized Representative That The Documents Are Complete Unless There Are Justifiable Reasons Thereof Which Shall Be Communicated In Writing To The Contractor. 45.3. In Case Of Total Suspension, Or Suspension Of Activities Along The Critical Path, Which Is Not Due To Any Fault Of The Contractor, The Elapsed Time Between The Effective Order Of Suspending Operation And The Order To Resume Work Shall Be Allowed The Contractor By Adjusting The Contract Time Accordingly. 46. Payment On Termination 46.1. If The Contract Is Terminated Because Of A Fundamental Breach Of Contract By The Contractor, The Procuring Entity’s Representative Shall Issue A Certificate For The Value Of The Work Done And Materials Ordered Less Advance Payments Received Up To The Date Of The Issue Of The Certificate And Less The Percentage To Apply To The Value Of The Work Not Completed, As Indicated In The Scc. Additional Liquidated Damages Shall Not Apply. If The Total Amount Due To The Procuring Entity Exceeds Any Payment Due To The Contractor, The Difference Shall Be A Debt Payable To The Procuring Entity. 46.2. If The Contract Is Terminated For The Procuring Entity’s Convenience Or Because Of A Fundamental Breach Of Contract By The Procuring Entity, The Procuring Entity’s Representative Shall Issue A Certificate For The Value Of The Work Done, Materials Ordered, The Reasonable Cost Of Removal Of Equipment, Repatriation Of The Contractor’s Personnel Employed Solely On The Works, And The Contractor’s Costs Of Protecting And Securing The Works, And Less Advance Payments Received Up To The Date Of The Certificate. 46.3. The Net Balance Due Shall Be Paid Or Repaid Within Twenty Eight (28) Days From The Notice Of Termination. 46.4. If The Contractor Has Terminated The Contract Under Gcc Clauses 17 Or 18, The Procuring Entity Shall Promptly Return The Performance Security To The Contractor. 47. Extension Of Contract Time 47.1. Should The Amount Of Additional Work Of Any Kind Or Other Special Circumstances Of Any Kind Whatsoever Occur Such As To Fairly Entitle The Contractor To An Extension Of Contract Time, The Procuring Entity Shall Determine The Amount Of Such Extension; Provided That The Procuring Entity Is Not Bound To Take Into Account Any Claim For An Extension Of Time Unless The Contractor Has, Prior To The Expiration Of The Contract Time And Within Thirty (30) Calendar Days After Such Work Has Been Commenced Or After The Circumstances Leading To Such Claim Have Arisen, Delivered To The Procuring Entity Notices In Order That It Could Have Investigated Them At That Time. Failure To Provide Such Notice Shall Constitute A Waiver By The Contractor Of Any Claim. Upon Receipt Of Full And Detailed Particulars, The Procuring Entity Shall Examine The Facts And Extent Of The Delay And Shall Extend The Contract Time Completing The Contract Work When, In The Procuring Entity’s Opinion, The Findings Of Facts Justify An Extension. 47.2. No Extension Of Contract Time Shall Be Granted The Contractor Due To (a) Ordinary Unfavorable Weather Conditions And (b) Inexcusable Failure Or Negligence Of Contractor To Provide The Required Equipment, Supplies Or Materials. 47.3. Extension Of Contract Time May Be Granted Only When The Affected Activities Fall Within The Critical Path Of The Pert/cpm Network. 47.4. No Extension Of Contract Time Shall Be Granted When The Reason Given To Support The Request For Extension Was Already Considered In The Determination Of The Original Contract Time During The Conduct Of Detailed Engineering And In The Preparation Of The Contract Documents As Agreed Upon By The Parties Before Contract Perfection. 47.5. Extension Of Contract Time Shall Be Granted For Rainy/unworkable Days Considered Unfavorable For The Prosecution Of The Works At The Site, Based On The Actual Conditions Obtained At The Site, In Excess Of The Number Of Rainy/unworkable Days Pre-determined By The Procuring Entity In Relation To The Original Contract Time During The Conduct Of Detailed Engineering And In The Preparation Of The Contract Documents As Agreed Upon By The Parties Before Contract Perfection, And/or For Equivalent Period Of Delay Due To Major Calamities Such As Exceptionally Destructive Typhoons, Floods And Earthquakes, And Epidemics, And For Causes Such As Non-delivery On Time Of Materials, Working Drawings, Or Written Information To Be Furnished By The Procuring Entity, Non-acquisition Of Permit To Enter Private Properties Within The Right-of-way Resulting In Complete Paralyzation Of Construction Activities, And Other Meritorious Causes As Determined By The Procuring Entity’s Representative And Approved By The Head Of The Procuring Entity. Shortage Of Construction Materials, General Labor Strikes, And Peace And Order Problems That Disrupt Construction Operations Through No Fault Of The Contractor May Be Considered As Additional Grounds For Extension Of Contract Time Provided They Are Publicly Felt And Certified By Appropriate Government Agencies Such As Dti, Dole, Dilg, And Dnd, Among Others. The Written Consent Of Bondsmen Must Be Attached To Any Request Of The Contractor For Extension Of Contract Time And Submitted To The Procuring Entity For Consideration And The Validity Of The Performance Security Shall Be Correspondingly Extended. 48. Price Adjustment Except For Extraordinary Circumstances As Determined By Neda And Approved By The Gppb, No Price Adjustment Shall Be Allowed. Nevertheless, In Cases Where The Cost Of The Awarded Contract Is Affected By Any Applicable New Laws, Ordinances, Regulations, Or Other Acts Of The Gop, Promulgated After The Date Of Bid Opening, A Contract Price Adjustment Shall Be Made Or Appropriate Relief Shall Be Applied On A No Loss-no Gain Basis. 49. Completion The Contractor Shall Request The Procuring Entity’s Representative To Issue A Certificate Of Completion Of The Works, And The Procuring Entity’s Representative Will Do So Upon Deciding That The Work Is Completed. 50. Taking Over The Procuring Entity Shall Take Over The Site And The Works Within Seven (7) Days From The Date The Procuring Entity’s Representative Issues A Certificate Of Completion. 51. Operating And Maintenance Manuals 51.1. If “as Built” Drawings And/or Operating And Maintenance Manuals Are Required, The Contractor Shall Supply Them By The Dates Stated In The Scc. 51.2. If The Contractor Does Not Supply The Drawings And/or Manuals By The Dates Stated In The Scc, Or They Do Not Receive The Procuring Entity’s Representative’s Approval, The Procuring Entity’s Representative Shall Withhold The Amount Stated In The Scc From Payments Due To The Contractor. Section V. Special Conditions Of Contract Gcc Clause 1.16 The Intended Completion Date Is 60 Cd From Ntp. 1.21 The Procuring Entity Is Lgu- Mapanas, Northern Samar. 1.22 The Procuring Entity’s Representative Is Atty. Ronn Michael L. Tejano Municipal Mayor Municipality Of Mapanas Province Of Northern Samar 1.23 The Site Is Located At Mapanas, Northern Samar. 1.27 The Start Date Is: Upon Receipt Of Notice To Proceed. 1.30 Completion Of Naparasan-quezon Fmr, Brgy. Quezon, Mapanas, Northern Samar B.5 Project Billboard/signboard 1.00 Each B.7 (2) Occupational Safety And Health Program 1.00 L.s. B.9 Mobilization And Demobiliation 1.00 L.s. 102 (2)b Surplus Common Excavation 71.77 Cu.m. 104 (1)a Embankment From Roadway Excavation (common Soil) 71.77 Cu.m. 104 (2)a Embankment From Borrow (common Soil 164.50 Cu.m. 105 (1) Subgrade Preparation (common Material) 186.00 Sq.m. 200 (1) Aggregate Subbase Course 45.11 Cu.m. 201 (1) Aggregate Base Course 42.59 Cu.m. 311 (1)a.2 Pcc Pavement (plain)-conventional Method, 200mm Thk. 124.00 Sq.m. 505 (2)a Grouted Riprap 38.55 Cu.m. 506 (1) Stone Masonry 5.50 Cu.m. 2.2 Note: The Items To Follow 5.1 The Procuring Entity Shall Give Possession Of All Parts Of The Site To The Contractor Upon The Issuance Of Notice To Proceed. 6.5 The Contractor Shall Employ The Following Key Personnel: Key Personnel Number Civil Engineer 1 Construction Foreman 1 Labor Workers 3 7.4(c) “no Further Instructions”. 7.7 No Further Instructions. 8.1 No Further Instructions. 10 The Site Investigation Reports Are: None 12.3 No Further Instructions. 12.5 In Case Of Semi-permanent Structures, Such As Buildings Of Types 1, 2, And 3 As Classified Under The National Building Code Of The Philippines, Concrete/asphalt Roads, Concrete River Control, Drainage, Irrigation Lined Canals, River Landing, Deep Wells, Rock Causeway, Pedestrian Overpass, And Other Similar Semi-permanent Structures: Five (5) Years. 13 “no Additional Provision.” 18.3(h)(i) No Further Instructions. 21.2 The Arbiter Is: Construction Industry Arbitration Commission 29.1 No Day Works Are Applicable To The Contract. 31.1 The Contractor Shall Submit The Program Of Work To The Procuring Entity’s Representative Within 15days Of Delivery Of The Letter Of Acceptance. 31.3 The Period Between Program Of Work Updates Is 15days. The Amount To Be Withheld For Late Submission Of An Updated Program Of Work Is P 1,000.00. 34.3 The Funding Source Is Coming From Nia 39.1 The Amount Of The Advance Payment Is 15% Of The Contract Price (lump Sum) And Shall Be Release Once Upon Presentation Of The Following Documents As Required: 1. Letter Request For Advance Payment From The Contractor 2. Bank Guarantee For Advance Payment 40.1 Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Be Included For Payment. 51.1 The Date By Which Operating And Maintenance Manuals Are Required Is Not Applicable. The Date By Which “as Built” Drawings Are Required Is 20 Days Upon Completion Of The Subproject. 51.2 The Amount To Be Withheld For Failing To Produce “as Built” Drawings And/or Operating And Maintenance Manuals By The Date Required Is P1,000.00. Section Vi. Specifications Project Name: Completion Of Naparasan-quezon Fmr Location : Brgy. Quezon, Mapanas, Northern Samar Item No. Description Qty. Unit. B.5 Project Billboard/signboard 1.00 Each A. 1 Labor A. Construction Foreman 1.00 B. Skilled Laborer 1.00 C. Unskilled Laborer 2.00 A.2 Labor Construction Foreman Skilled Laborer Unskilled Laborer Name And Capacity B. 1 Equipment B. 2 Equipment C. 1 Total A.1+b.1- As Evaluated C.2 Total A.2+b.2- As Submitted D.1 Output Per Hour- As Submitted D.2 Output Per Hour- As Evaluated E.1 Direct Unit Cost (c.1 + D.1)- As Submitted E.2 Direct Unit Cost (c.1 + D.1)- Evaluated Name And Specification F.1 Materials A. Tarpaulin (8’ X 8”) 1.00 Pc. B. Coco Lumber 84.00 Bd.ft. C. Plywood Marine, (0.0125m X 1.2m X 2.44m) 2.00 Pc. D. Assorted Common Wire Nail 0.50 Kg. F.2 Materials A. A. Tarpaulin (8’ X 8”) B. Coco Lumber C. Plywood Marine, (0.0125m X 1.2m X 2.44m) D. Assorted Common Wire Nail G.1 Direct Unit Cost (e.1 + F.1)- As Submitted G.2 Direct Unit Cost (e.1 + F.1)- As Evaluated H.1 Overhead Contingencies & Miscellaneous (ocm)- As Submitted H.2 Overhead Contingencies & Miscellaneous (ocm)- As Evaluated I.1 Contractor’s Profit (cp)- As Submitted I.2 Contractor’s Profit (cp)- As Evaluated J.1 Value Added Tax (vat)- As Submitted J.2 Value Added Tax (vat)- As Evaluated K.1 Total Unit Cost- As Submitted K.2 Total Unit Cost- As Evaluated B.7 (2) Occupational Safety And Health Program 1.00 L.s A.1 Labor A. Safety Practitioner/officer (part Time) 6.00 1 B. Health Personnel (full Time) 24.00 1 A.2 Labor A. Safety Practitioner/officer (part Time) B. Health Personnel (full Time) Name And Capacity B.1 Equipment A. Safety Shoes 55.00 Man-day B. Safety Helmet 55.00 Man-day C. Safety/working Gloves 55.00 Man-day D. Safety Vest 55.00 Man-day E. Rubber Boots 55.00 Man-day F. Rain Coats (30% Of The Duration) Optional 17.00 Man-day B.2 Equipment Safety Shoes Safety Helmet Safety/working Gloves Safety Vest Rubber Boots Rain Coats (30% Of The Duration) Optional C. 1 Total A.1+b.1- As Evaluated C.2 Total A.2+b.2- As Submitted D.1 Output Per Hour- As Submitted D.2 Output Per Hour- As Evaluated E.1 Direct Unit Cost (c.1 + D.1)- As Submitted E.2 Direct Unit Cost (c.1 + D.1)- Evaluated Name And Specification F.1 Materials F.2 Materials G.1 Direct Unit Cost (e.1 + F.1)- As Submitted G.2 Direct Unit Cost (e.1 + F.1)- As Evaluated H.1 Overhead Contingencies & Miscellaneous (ocm)- As Submitted H.2 Overhead Contingencies & Miscellaneous (ocm)- As Evaluated I.1 Contractor’s Profit (cp)- As Submitted I.2 Contractor’s Profit (cp)- As Evaluated J.1 Value Added Tax (vat)- As Submitted J.2 Value Added Tax (vat)- As Evaluated K.1 Total Unit Cost- As Submitted K.2 Total Unit Cost- As Evaluated B.9 Mobilization/demobilization 1.00 L.s. A.1 Labor A.2 Labor Name And Capacity B.1 Equipment Dumptruck (12 Cu.yd) 16.00 2 Payloader (1.5 Cu.m.), Lx80-2c 16.00 1 Bulldozer, D6h Series Ii Psds/dd 16.00 1 Backhoe W/ Breaker (0.80 Cu.m.) 16.00 1 B.2 Equipment C. 1 Total A.1+b.1- As Evaluated C.2 Total A.2+b.2- As Submitted D.1 Output Per Hour- As Submitted D.2 Output Per Hour- As Evaluated E.1 Direct Unit Cost (c.1 + D.1)- As Submitted E.2 Direct Unit Cost (c.1 + D.1)- Evaluated Name And Specification F.1 Materials F.2 Materials G.1 Direct Unit Cost (e.1 + F.1)- As Submitted G.2 Direct Unit Cost (e.1 + F.1)- As Evaluated H.1 Overhead Contingencies & Miscellaneous (ocm)- As Submitted H.2 Overhead Contingencies & Miscellaneous (ocm)- As Evaluated I.1 Contractor’s Profit (cp)- As Submitted I.2 A. Contractor’s Profit (cp)- As Evaluated J.1 B. Value Added Tax (vat)- As Submitted J.2 C. Value Added Tax (vat)- As Evaluated K.1 D. Total Unit Cost- As Submitted K.2 Total Unit Cost- As Evaluated 102 (2)b Surplus Common Excavation 71.77 Cu.m. A.1 Labor A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 A.2 Labor Construction Foreman Unskilled Laborer Name And Capacity B.1 Equipment A. Bulldozer, D6h Series Ii Psds/dd 1.00 1 B. Payloader (1.5 Cu.m.) 1.00 1 C. Payloader (1.5 Cu.m.) 0.30 1 D. Dump Truck (12 Cu.yd.) 1.00 3 E. Backhoe (0.80 Cu.m.) 1.00 1 B.1 Equipment A. Bulldozer, D6h Series Ii Psds/dd B. Payloader (1.5 Cu.m.) C. Payloader (1.5 Cu.m.) D. Dump Truck (12 Cu.yd.) E. Backhoe (0.80 Cu.m.) C. 1 Total A.1+b.1- As Evaluated C.2 Total A.2+b.2- As Submitted D.1 Output Per Hour- As Submitted D.2 Output Per Hour- As Evaluated E.1 Direct Unit Cost (c.1 + D.1)- As Submitted E.2 Direct Unit Cost (c.1 + D.1)- Evaluated Name And Specification F.1 Materials F.2 Materials G.1 Direct Unit Cost (e.1 + F.1)- As Submitted G.2 Direct Unit Cost (e.1 + F.1)- As Evaluated H.1 Overhead Contingencies & Miscellaneous (ocm)- As Submitted H.2 Overhead Contingencies & Miscellaneous (ocm)- As Evaluated I.1 Contractor’s Profit (cp)- As Submitted I.2 Contractor’s Profit (cp)- As Evaluated J.1 Value Added Tax (vat)- As Submitted J.2 Value Added Tax (vat)- As Evaluated K.1 Total Unit Cost- As Submitted K.2 Total Unit Cost- As Evaluated 104 (2) A Embankment From Borrow (common Soil) 164.50 Cu.m. A.1 Labor A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 A.2 Labor A. Construction Foreman B. Unskilled Laborer Name And Capacity B.1 Equipment A. Motorized Road Grader, G710a 1.00 1 B. Vibratory Roller (10 M.t), Sd100dc 1.00 1 C. Water Truck/pump (16000 L) 0.25 1 B.2 Equipment A. Motorized Road Grader, G710a B. Vibratory Roller (10 M.t), Sd100dc C. Water Truck/pump (16000 L) C. 1 Total A.1+b.1- As Evaluated C.2 Total A.2+b.2- As Submitted D.1 Output Per Hour- As Submitted D.2 Output Per Hour- As Evaluated E.1 Direct Unit Cost (c.1 + D.1)- As Submitted E.2 Direct Unit Cost (c.1 + D.1)- Evaluated Name And Specification F.1 Materials A. Common Borrow (w/ 25% Shrinkage Factor) 1.25 Cu.m. F.2 Materials A. Common Borrow (w/ 25% Shrinkage Factor) G.1 Direct Unit Cost (e.1 + F.1)- As Submitted G.2 Direct Unit Cost (e.1 + F.1)- As Evaluated H.1 Overhead Contingencies & Miscellaneous (ocm)- As Submitted H.2 Overhead Contingencies & Miscellaneous (ocm)- As Evaluated I.1 Contractor’s Profit (cp)- As Submitted I.2 Contractor’s Profit (cp)- As Evaluated J.1 Value Added Tax (vat)- As Submitted J.2 Value Added Tax (vat)- As Evaluated K.1 Total Unit Cost- As Submitted K.2 Total Unit Cost- As Evaluated 104 (1)a Embankment From Roadway Excavation (common Soil) 71.77 Cu.m. A.1 Labor For Excavation Work: A. Construction Foreman 0.83 1 B. Unskilled Laborer 0.83 2 Spreading And Compaction: A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 A.2 Labor For Excavation Work: A. Construction Foreman B. Unskilled Laborer Spreading And Compaction: A. Construction Foreman B. Unskilled Laborer Name And Capacity B.1 Equipment For Excavation Work: A. Bulldozer, D6h Series Ii Psds/dd 0.83 1 B. Payloader (1.50 Cu.m.), Lx80-2c 0.83 1 C. Dump Truck (12 Cu.yd.) 0.83 2 Spreading And Compaction A. Motorized Road Grader 1.00 1 B. Vibrator Roller (10 M.t), Sd100dc 1.00 1 C. Water Truck/pump (16000 L) 0.25 1 B.1 Equipment For Excavation Work: A. Bulldozer, D6h Series Ii Psds/dd B. Payloader (1.50 Cu.m.), Lx80-2c C. Dump Truck (12 Cu.yd.) Spreading And Compaction A. Motorized Road Grader B. Vibrator Roller (10 M.t), Sd100dc C. Water Truck/pump (16000 L) C. 1 Total A.1+b.1- As Evaluated C.2 Total A.2+b.2- As Submitted D.1 Output Per Hour- As Submitted D.2 Output Per Hour- As Evaluated E.1 Direct Unit Cost (c.1 + D.1)- As Submitted E.2 Direct Unit Cost (c.1 + D.1)- Evaluated Name And Specification F.1 Materials F.2 Materials G.1 Direct Unit Cost (e.1 + F.1)- As Submitted G.2 Direct Unit Cost (e.1 + F.1)- As Evaluated H.1 Overhead Contingencies & Miscellaneous (ocm)- As Submitted H.2 Overhead Contingencies & Miscellaneous (ocm)- As Evaluated I.1 Contractor’s Profit (cp)- As Submitted I.2 Contractor’s Profit (cp)- As Evaluated J.1 Value Added Tax (vat)- As Submitted J.2 Value Added Tax (vat)- As Evaluated K.1 Total Unit Cost- As Submitted K.2 Total Unit Cost- As Evaluated 105 (1) Subgrade Preparation (common Material) 186.00 Sq.m. A.1 Labor A. Construction Foreman 1.00 1 B. Unskilled Laborer 1.00 2 A.2 Labor Construction Foreman Unskilled Laborer Name And Capacity B.1 Equipment A. Motorized Road Grader 1.00 1 B. Vibrator Roller (10 M.t), Sd100dc 1.00 1 C. Water Truck/pump (16000 L) 0.25 1 B.2 Equipment Motorized Road Grader Vibrator Roller (10 M.t), Sd100dc Water Truck/pump (16000 L) C. 1 Total A.1+b.1- As Evaluated C.2 Total A.2+b.2- As Submitted D.1 Output Per Hour- As Submitted D.2 Output Per Hour- As Evaluated E.1 Direct Unit Cost (c.1 + D.1)- As Submitted E.2 Direct Unit Cost (c.1 + D.1)- Evaluated Name And Specification F.1 Materials F.2 Materials G.1 Direct Unit Cost (e.1 + F.1)- As Submitted G.2 Direct Unit Cost (e.1 + F.1)- As Evaluated H.1 Overhead Contingencies & Miscellaneous (ocm)- As Submitted H.2 Overhead Contingencies & Miscellaneous (ocm)- As Evaluated I.1 Contractor’s Profit (cp)- As Submitted I.2 Contractor’s Profit (cp)- As Evaluated J.1 Value Added Tax (vat)- As Submitted J.2 Value Added Tax (vat)- As Evaluated K.1 Total Unit Cost- As Submitted K.2 Total Unit Cost- As Evaluated 200(1) Aggregate Subbase Course 45.11 Cu.m. A.1 Labor Construction Foreman 1.00 1 Unskilled Laborer 1.00 2 A.2 Labor Construction Foreman Unskilled Laborer Name And Capacity B.1 Equipment Motorized Road Grader, G710a 1.00 1 Vibrator Roller (10 M.t), Sd100dc 1.00 1 Water Truck/pump (16000 L) 0.25 1 B.2 Equipment Motorized Road Grader Vibrator Roller (10 M.t), Sd100dc Water Truck/pump (16000 L) C. 1 Total A.1+b.1- As Evaluated C.2 Total A.2+b.2- As Submitted D.1 Output Per Hour- As Submitted D.2 Output Per Hour- As Evaluated E.1 Direct Unit Cost (c.1 + D.1)- As Submitted E.2 Direct Unit Cost (c.1 + D.1)- Evaluated Name And Specification F.1 Materials A. Aggregate Subbase Course (w/ 15% Shrinkage Factor) 1.15 Cu.m. F.2 Materials A. Aggregate Subbase Course (w/ 15% Shrinkage Factor) 201 (1) Aggregate Base Course 42.59 Cu.m. A.1 Labor Construction Foreman 1.00 1 Unskilled Laborer 1.00 2 A.2 Labor Construction Foreman Unskilled Laborer Name And Capacity B.1 Equipment Motorized Road Grader, G710a 1.00 1 Vibrator Roller (10 M.t), Sd100dc 1.00 1 Water Truck/pump (16000 L) 0.25 1 B.2 Equipment Motorized Road Grader Vibrator Roller (10 M.t), Sd100dc Water Truck/pump (16000 L) C. 1 Total A.1+b.1- As Evaluated C.2 Total A.2+b.2- As Submitted D.1 Output Per Hour- As Submitted D.2 Output Per Hour- As Evaluated E.1 Direct Unit Cost (c.1 + D.1)- As Submitted E.2 Direct Unit Cost (c.1 + D.1)- Evaluated Name And Specification F.1 Materials A. Aggregate Subbase Course (w/ 15% Shrinkage Factor) 1.15 Cu.m. F.2 Materials A. Aggregate Subbase Course (w/ 15% Shrinkage Factor) 311 (1)a.2 Pcc Pavement (plain)- Conventional Method, 200mm Thk. 124.00 Sq.m. A.1 Labor A. Construction Foreman 1.00 1 B. Skilled Laborer 1.00 4 C. Unskilled Laborer 1.00 12 Name And Capacity B.1 Equipment A. Transit Mixer (5-6 Cu.yd) 1.00 4 B. Concrete Vibrator 1.00 2 C. Concrete Batch Plant (30 Cu.m.) 1.00 1 D. Payloader (1.50 Cu.m.), Lx80-2c 1.00 1 E. Concrete Screeder (5.5 Hp) 1.00 1 F. Water Truck/pump (16000l) 1.00 1 G. Concrete Saw, Blade Ǿ 14” (7.5 Hp) 1.00 1 H. Bar Cutter, Single Phase 0.10 1 I. Joint Sealer Machine 0.25 1 Name And Specification F.1 Materials A. Reinforcing Steel Bar, Grade 40 0.39 Kg. B. Curing Compound 0.29 Lit. C. Asphalt Sealant 0.12 Lit. D. Steel Forms (rental) 0.46 L.m. E. Sand 0.1100 Cu.m. F. Gravel 0.20 Cu.m. G. Portland Cement, Type 1 1.90 Bag H. Concrete Saw (diamond Blade 14”) 0.00015 Pc I. Pipe Sleeve, 2” Dia 0.0086 L.m. J. Grease Tar 0.0056 Lit. 505 (2) A Grouted Riprap 38.55 Cu.m. A.1 Labor Construction Foreman 1.00 1 Skilled Laborer 1.00 2 Unskilled Laborer 1.00 8 Name And Capacity B.1 Equipment A. One Bagger Mixer 1.00 1 B. Water Truck (16000 L) 0.05 1 Minor Tools (5% Of Labor Cost) Name And Specification F.1 Materials Portland Cement 3.00 Bag Sand 0.25 Cu.m. Gravel Fill 0.015 Cu.m. Weep Holes (pvc) 0.30 M. Filter Cloth 0.015 Sq.m. Boulder (15-25 Kg) 1,05 Cu.m. Miscellaneous (1% Of Material Cost) 506 (1) Stone Masonry 5.50 Cu.m. A.1 Labor Construction Foreman 1.00 1 Skilled Laborer 1.00 2 Unskilled Laborer 1.00 8 Name And Capacity B.1 Equipment One Bagger Mixer 1.00 1 Water Truck (16000 L) 0.05 1 Backhoe (wheel Type 0.28 Cu.m.) 0.10 1 Minor Tools (10% Of Labor Cost) Name And Specification F.1 Materials Portland Cement 3.00 Bag Sand 0.25 Cu.m. Gravel Fill 0.015 Cu.m. Weep Holes (pvc) 0.30 M. Filter Cloth 0.015 Sq.m. Boulder (15-25 Kg) 1.05 Cu.m. Miscellaneous (1% Of Material Cost) Section Vii. Drawings Bill Of Quantities Item No. Scope Of Work Quantity Unit Unit Cost Total Amount 1.) Completion Of Naparasan-quezon Fmr, Brgy. Quezon, Mapanas, Northern Samar B.5 Project Billboard/signboard 1.00 Each 10,959.69 10,959.69 B.7 (2) Occupational Safety And Health Program 1.00 L.s. 20,707.17 20,707.17 B.9 Mobilization And Demobiliation 1.00 L.s. 7,572.97 7,572.97 102 (2)b Surplus Common Excavation 71.77 Cu.m. 204.24 14,658.30 104 (1)a Embankment From Roadway Excavation (common Soil) 71.77 Cu.m. 310.07 22,253.72 104 (2)a Embankment From Borrow (common Soil 164.50 Cu.m. 1,193.18 196,278.11 105 (1) Subgrade Preparation (common Material) 186.00 Sq.m. 21.14 3,932.04 200 (1) Aggregate Subbase Course 45.11 Cu.m. 1,632.65 73.628.50 201 (1) Aggregate Base Course 42.59 Cu.m. 2,843.65 121.122.43 311 (1)a.2 Pcc Pavement (plain)-conventional Method, 200mm Thk. 124.00 Sq.m. 2160.51 267,903.24 505 (2)a Grouted Riprap 38.55 Cu.m. 5,618.79 216,630.76 506 (1) Stone Masonry 5.50 Cu.m. 5,493.97 30,216.84 Total 985,863.77 Total Cost Of All Line Item Includes Cost Of Contractor’s Profit, Taxes And Ocm. Attached Detailed Cost Estimates Section Ix. Bidding Forms Table Of Contents Bid Form 79 Form Of Contract Agreement 81 Omnibus Sworn Statement 83 Bid Form Date: Iaeb No: To: Lgu-mapanas Northern Samar Address: Mapanas Northern Samar We, The Undersigned, Declare That: We Have Examined And Have No Reservation To The Bidding Documents, Including Addenda, For The Contract Completion Of Naparasan -quezon Fmr (a) We Offer To Execute The Works For This Contract In Accordance With The Bid And Bid Data Sheet, General And Special Conditions Of Contract Accompanying This Bid; The Total Price Of Our Bid, Excluding Any Discounts Offered In Item (d) Below Is: [insert Information]; The Discounts Offered And The Methodology For Their Application Are: [insert Information]; (b) Our Bid Shall Be Valid For A Period Of 60 Days From The Date Fixed For The Bid Submission Deadline In Accordance With The Bidding Documents, And It Shall Remain Binding Upon Us And May Be Accepted At Any Time Before The Expiration Of That Period; (c) If Our Bid Is Accepted, We Commit To Obtain A Performance Security In The Amount Of [insert Percentage Amount] Percent Of The Contract Price For The Due Performance Of The Contract; (d) Our Firm, Including Any Subcontractors Or Suppliers For Any Part Of The Contract, Have Nationalities From The Following Eligible Countries: [insert Information]; (e) We Are Not Participating, As Bidders, In More Than One Bid In This Bidding Process, Other Than Alternative Offers In Accordance With The Bidding Documents; (f) Our Firm, Its Affiliates Or Subsidiaries, Including Any Subcontractors Or Suppliers For Any Part Of The Contract, Has Not Been Declared Ineligible By The Funding Source; (g) We Understand That This Bid, Together With Your Written Acceptance Thereof Included In Your Notification Of Award, Shall Constitute A Binding Contract Between Us, Until A Formal Contract Is Prepared And Executed; And (h) We Understand That You Are Not Bound To Accept The Lowest Evaluated Bid Or Any Other Bid That You May Receive. Name: In The Capacity Of: Signed: Duly Authorized To Sign The Bid For And On Behalf Of: Date: ___________ Form Of Contract Agreement This Agreement, Made This [insert Date] Day Of [insert Month], [insert Year] Between [name And Address Of Procuring Entity](hereinafter Called The “entity”) And [name And Address Of Contractor] (hereinafter Called The “contractor”). Whereas, The Entity Is Desirous That The Contractor Execute [name And Identification Number Of Contract] (hereinafter Called “the Works”) And The Entity Has Accepted The Bid For [insert The Amount In Specified Currency In Numbers And Words] By The Contractor For The Execution And Completion Of Such Works And The Remedying Of Any Defects Therein. Now This Agreement Witnesseth As Follows: 1. In This Agreement, Words And Expressions Shall Have The Same Meanings As Are Respectively Assigned To Them In The Conditions Of Contract Hereinafter Referred To. 2. The Following Documents Shall Be Attached, Deemed To Form, And Be Read And Construed As Part Of This Agreement, To Wit: (a) General And Special Conditions Of Contract; (b) Drawings/plans; (c) Specifications; (d) Invitation To Apply For Eligibility And To Bid; (e) Instructions To Bidders; (f) Bid Data Sheet; (g) Addenda And/or Supplemental/bid Bulletins, If Any; (h) Bid Form, Including All The Documents/statements Contained In The Bidder’s Bidding Envelopes, As Annexes; (i) Eligibility Requirements, Documents And/or Statements; (j) Performance Security; (k) Credit Line Issued By A Licensed Bank, If Any; (l) Notice Of Award Of Contract And The Bidder’s Conforme Thereto; (m) Other Contract Documents That May Be Required By Existing Laws And/or The Entity. 3. In Consideration Of The Payments To Be Made By The Entity To The Contractor As Hereinafter Mentioned, The Contractor Hereby Covenants With The Entity To Execute And Complete The Works And Remedy Any Defects Therein In Conformity With The Provisions Of This Contract In All Respects. 4. The Entity Hereby Covenants To Pay The Contractor In Consideration Of The Execution And Completion Of The Works And The Remedying Of Defects Wherein, The Contract Price Or Such Other Sum As May Become Payable Under The Provisions Of This Contract At The Times And In The Manner Prescribed By This Contract. In Witness Whereof The Parties Thereto Have Caused This Agreement To Be Executed The Day And Year First Before Written. Signed, Sealed, Delivered By The (for The Entity) Signed, Sealed, Delivered By The (for The Contractor). Binding Signature Of Procuring Entity ________________________________________________ Binding Signature Of Contractor _____________________________________________ [addendum Showing The Corrections, If Any, Made During The Bid Evaluation Should Be Attached With This Agreement] Omnibus Sworn Statement Republic Of The Philippines ) City/municipality Of ______ ) S.s. Affidavit I, [name Of Affiant], Of Legal Age, [civil Status], [nationality], And Residing At [address Of Affiant], After Having Been Duly Sworn In Accordance With Law, Do Hereby Depose And State That: 1. Select One, Delete The Other: If A Sole Proprietorship: I Am The Sole Proprietor Of [name Of Bidder] With Office Address At [address Of Bidder]; If A Partnership, Corporation, Cooperative, Or Joint Venture: I Am The Duly Authorized And Designated Representative Of [name Of Bidder] With Office Address At [address Of Bidder]; 2. Select One, Delete The Other: If A Sole Proprietorship: As The Owner And Sole Proprietor Of [name Of Bidder], I Have Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary To Represent It In The Bidding For [name Of The Project] Of The [name Of The Procuring Entity]; If A Partnership, Corporation, Cooperative, Or Joint Venture: I Am Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary And/or To Represent The [name Of Bidder] In The Bidding As Shown In The Attached [state Title Of Attached Document Showing Proof Of Authorization (e.g., Duly Notarized Secretary’s Certificate Issued By The Corporation Or The Members Of The Joint Venture)]; 3. [name Of Bidder] Is Not “blacklisted” Or Barred From Bidding By The Government Of The Philippines Or Any Of Its Agencies, Offices, Corporations, Or Local Government Units, Foreign Government/foreign Or International Financing Institution Whose Blacklisting Rules Have Been Recognized By The Government Procurement Policy Board; 4. Each Of The Documents Submitted In Satisfaction Of The Bidding Requirements Is An Authentic Copy Of The Original, Complete, And All Statements And Information Provided Therein Are True And Correct; 5. [name Of Bidder]is Authorizing The Head Of The Procuring Entity Or Its Duly Authorized Representative(s) To Verify All The Documents Submitted; 6. Select One, Delete The Rest: If A Sole Proprietorship: I Am Not Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; If A Partnership Or Cooperative: None Of The Officers And Members Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; If A Corporation Or Joint Venture: None Of The Officers, Directors, And Controlling Stockholders Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; 7. [name Of Bidder] Complies With Existing Labor Laws And Standards; And 8. [name Of Bidder] Is Aware Of And Has Undertaken The Following Responsibilities As A Bidder: A) Carefully Examine All Of The Bidding Documents; B) Acknowledge All Conditions, Local Or Otherwise, Affecting The Implementation Of The Contract; C) Made An Estimate Of The Facilities Available And Needed For The Contract To Be Bid, If Any; And D) Inquire Or Secure Supplemental/bid Bulletin(s) Issued For The [name Of The Project]. In Witness Whereof, I Have Hereunto Set My Hand This __ Day Of ___, 20__ At ____________, Philippines. _____________________________________ Bidder’s Representative/authorized Signatory [jurat] * This Form Will Not Apply For Wb Funded Projects.
Closing Date16 Dec 2024
Tender AmountPHP 985.8 K (USD 16.6 K)
Municipality Of Mapanas, Northern Samar Tender
Civil And Construction...+1Civil Works Others
Philippines
Details: Description Bidding Documents Procurement Of Infrastructure Projects Name Of Project: Repair And Rehabilitation Of Mapanas-rhu Barangay Del Norte, Mapanas Northern Samar Contract Reference No. 2024-11-094 Table Of Contents Section I. Invitation To Bid 3 Section Ii. Instructions To Bidders 7 Section Iii. Bid Data Sheet 35 Section Iv. General Conditions Of Contract 38 Section V. Special Conditions Of Contract 70 Section Vi. Specifications 72 Section Vii. Drawings 75 Section Viii. Bill Of Quantities Error! Bookmark Not Defined. Section Ix. Bidding Forms 77 Section X. Foreign-assisted Projects Error! Bookmark Not Defined. Section I. Invitation To Bid Bid Notice Abstract Invitation To Bid (itb) Republic Of The Philippines Province Of Northern Samar Municipality Of Mapanas Invitation To Bid For Project: Repair And Rehabilitation Of Mapanas Rhu, Brgy. Del Norte, Mapanas N. Samar. The Lgu- Mapanas, Northern Samar, Through The Ldrrm Fund Of Fy 2023 Intends To Apply The Sum Of One Million Forty Nine Thousand Pesos 57/100 Only (p1,049,465.57) Being The Approved Budget For The Contract (abc) To Payments Under The Contract For : Repair/rehabilitation Of Mapanas Rhu, Barangay Del Norte, Mapanas N. Samar Bids Received In Excess Of The Abc Shall Be Automatically Rejected At Bid Opening. 1. The Lgu- Mapanas, Northern Samar Now Invites Bids For The Following Description Of Works To Be Procured: Item No. Scope Of Work Quantity Unit Repair/rehabilitation Of Mapanas Rhu, Barangay Del Norte, Mapanas, N. Samar. B. 5 Project Billboard/signboard 1.00 Lot B.7 Construction Safety And Health 1.00 Lot B.9 Mobilization And Demobilization 1.00 Lot 801(7)a Removal Of Structures And Obstruction 1.00 Is 900(1)c1 Structural Concrete (class A), 28 Days 9.15 Cu.m. 902(1) A Reinforcing Steel, Deformed Grade 40 541.72 Kg 903 Formworks And Falseworks 53.38 Sq.m. 1047 Metal Structures 84.00 In.m 1013 Corrugated Metal Roofing, Gauge 24 9.00 Sq.m. 1046 Masonry Works 75.60 Sq.m. 1003 Carpentry And Joinery Works 38.78 Sq.m. 1005 Doors And Windows 3.00 Sets 1002 Plumbing Works 1.00 Lot 1032 Painting Varnishing And Other Related Works 411.00 Sq.m. 1101 Wires And Wiring Devices 1.00 Is 1002 (1) Panel Board With Main Breaker And Branc 1.00 Is 1103 Lighting Fixtures And Lamps 1.00 Is Spcl1 Signages 1.00 Lot Completion Of The Works Is Required 90 Calendar Days. Bidders Should Have Completed, Within Ten (10) Years From The Date Of Submission And Receipt Of Bids, A Contract Similar To The Project. The Description Of An Eligible Bidder Is Contained In The Bidding Documents, Particularly, In Section Ii. Instructions To Bidders. Section Ii. Instructions To Bidders. 2. Bidding Will Be Conducted Through Open Competitive Bidding Procedures Using Non-discretionary Pass/fail Criterion As Specified In The Implementing Rules And Regulations (irr) Of Republic Act 9184 (ra 9184), Otherwise Known As The “government Procurement Reform Act”. Bidding Is Restricted To Filipino Citizens/sole Proprietorships, Partnerships, Or Organizations With At Least Seventy Five Percent (75%) Interest Or Outstanding Capital Stock Belonging To Citizens Of The Philippines. 4. Interested Bidders May Obtain Further Information From Lgu- Bac Mapanas, Northern Samar And Inspect The Bidding Documents At The Address Given Below From November 06, 2024-november 26, 2024, 8:00 A.m. To 5:00 Pm. A Complete Set Of Bidding Documents May Be Purchased By Interested Bidders From The Address Below And Upon Payment Of A Nonrefundable Fee For The Bidding Documents In The Amount Of P5,000.00. It May Also Be Downloaded Free Of Charge From The Website Of The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity, Provided That Bidders Shall Pay The Fee For The Bidding Documents Not Later That The Submission Of Their Bids. 5. The Lgu- Mapanas, Northern Samar Will Hold A Pre-bid Conference On November, 15, 2024 At 10:00 A.m. At Executive Conference, 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar, Which Shall Be Open Only To All Interested Parties Who Have Purchased The Bidding Documents. 6. Bids Must Be Delivered To The Address Below On Or Before 9:00 A.m. Of November 26, 2024 At Bac Office, @ Municipal Planning & Development Office (mpdo), Mapanas, Northern Samar. All Bids Must Be Accompanied By A Bid Security In Any Of The Acceptable Forms And In The Amount Stated In Itb Clause 18. Bids Will Be Opened In The Presence Of The Bidders’ Authorized Representatives Who Choose To Attend At The Address Below. Late Bids Shall Not Be Accepted. The Bidder May Request That The Bid Documents Be Sent To Them By Mail Or Courier, And For This, The Bidder Shall Pay The Amount In Philippine Peso To Cover The Cost Of Mail Or Courier Delivery. The Fee For Obtaining A Copy Of The Bid Documents And The Cost Of Mail Or Courier Shall Be Paid By The Bidder Thru S Cashier’s Check Or Manager’s Check Issued In Favor Of The Municipality Of Mapanas. 7. The Lgu- Mapanas, Northern Samar Reserves The Right To Accept Or Reject Any Bid, To Annul The Bidding Process, And To Reject All Bids At Any Time Prior To Contract Award, Without Thereby Incurring Any Liability To The Affected Bidder Or Bidders. 8. For Further Information, Please Refer To: Reno C. Salazar Bac Secretary Mapanas, Northern Samar Mobile # 09459852914 Ma. Teresa L. Minguez Bac Chairperson Mapanas, Northern Samar Mobile # 09778033758 Section Ii. Instructions To Bidders 1. The Bids Must Be Delivered On Or Before November 26, 2024 At 9:00 A.m And Failure To Submit The Bid Proposal May Ground For Disqualification Of The Bid. 2. Bids Received In Excess Of The Abc Shall Be Automatically Rejected At Bid Opening. 1. The Lgu- Mapanas, Northern Samar Now Invites Bids For The Following Description Of Works To Be Procured: Item No. Scope Of Work Quantity Unit Repair/rehabilitation Of Mapanas Rhu, Barangay Del Norte, Mapanas, N. Samar. B. 5 Project Billboard/signboard 1.00 Lot B.7 Construction Safety And Health 1.00 Lot B.9 Mobilization And Demobilization 1.00 Lot 801(7)a Removal Of Structures And Obstruction 1.00 Is 900(1)c1 Structural Concrete (class A), 28 Days 9.15 Cu.m. 902(1) A Reinforcing Steel, Deformed Grade 40 541.72 Kg 903 Formworks And Falseworks 53.38 Sq.m. 1047 Metal Structures 84.00 In.m 1013 Corrugated Metal Roofing, Gauge 24 9.00 Sq.m. 1046 Masonry Works 75.60 Sq.m. 1003 Carpentry And Joinery Works 38.78 Sq.m. 1005 Doors And Windows 3.00 Sets 1002 Plumbing Works 1.00 Lot 1032 Painting Varnishing And Other Related Works 411.00 Sq.m. 1101 Wires And Wiring Devices 1.00 Is 1002 (1) Panel Board With Main Breaker And Branc 1.00 Is 1103 Lighting Fixtures And Lamps 1.00 Is Spcl1 Signages 1.00 Lot Completion Of The Works Is Required 90 Calendar Days. Bidders Should Have Completed, Within Ten (10) Years From The Date Of Submission And Receipt Of Bids, A Contract Similar To The Project. The Description Of An Eligible Bidder Is Contained In The Bidding Documents, Particularly, In Section Ii. Instructions To Bidders. 2. Bidding Will Be Conducted Through Open Competitive Bidding Procedures Using Non-discretionary Pass/fail Criterion As Specified In The Implementing Rules And Regulations (irr) Of Republic Act 9184 (ra 9184), Otherwise Known As The “government Procurement Reform Act”. Bidding Is Restricted To Filipino Citizens/sole Proprietorships, Partnerships, Or Organizations With At Least Seventy Five Percent (75%) Interest Or Outstanding Capital Stock Belonging To Citizens Of The Philippines. 3. Interested Bidders May Obtain Further Information From Lgu- Bac Mapanas, Northern Samar And Inspect The Bidding Documents At The Address Given Below From November 06, 2024-november 25, 2024, 8:00 A.m. To 5:00 Pm. A Complete Set Of Bidding Documents May Be Purchased By Interested Bidders From The Address Below And Upon Payment Of A Nonrefundable Fee For The Bidding Documents In The Amount Of P5,000.00. It May Also Be Downloaded Free Of Charge From The Website Of The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity, Provided That Bidders Shall Pay The Fee For The Bidding Documents Not Later That The Submission Of Their Bids. 4. The Lgu- Mapanas, Northern Samar Will Hold A Pre-bid Conference On November 15, 2024 At 10:00 A.m. At Executive Conference, 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar, Which Shall Be Open Only To All Interested Parties Who Have Purchased The Bidding Documents. 5. Bids Must Be Delivered To The Address Below On Or Before 9:00 A.m. Of November 26, 2024 At Bac Office, @ Municipal Planning & Development Office (mpdo), Mapanas, Northern Samar. All Bids Must Be Accompanied By A Bid Security In Any Of The Acceptable Forms And In The Amount Stated In Itb Clause 18. Bids Will Be Opened In The Presence Of The Bidders’ Authorized Representatives Who Choose To Attend At The Address Below. Late Bids Shall Not Be Accepted. The Bidder May Request That The Bid Documents Be Sent To Them By Mail Or Courier, And For This, The Bidder Shall Pay The Amount In Philippine Peso To Cover The Cost Of Mail Or Courier Delivery. The Fee For Obtaining A Copy Of The Bid Documents And The Cost Of Mail Or Courier Shall Be Paid By The Bidder Thru S Cashier’s Check Or Manager’s Check Issued In Favor Of The Municipality Of Mapanas. 6. The Lgu- Mapanas, Northern Samar Reserves The Right To Accept Or Reject Any Bid, To Annul The Bidding Process, And To Reject All Bids At Any Time Prior To Contract Award, Without Thereby Incurring Any Liability To The Affected Bidder Or Bidders. 7. For Further Information, Please Refer To: Reno C. Salazar Bac Secretary Mapanas, Northern Samar Mobile # 09459852914 Ma. Teresa L. Minguez Bac Chairperson Mapanas N. Samar Mobile # 09778033758 Table Of Contents A. General 11 1. Scope Of Bid 11 2. Source Of Funds 11 3. Corrupt, Fraudulent, Collusive, And Coercive Practices 11 4. Conflict Of Interest 12 5. Eligible Bidders 14 6. Bidder’s Responsibilities 15 7. Origin Of Goods And Services 17 8. Subcontracts 17 B. Contents Of Bidding Documents 17 9. Pre-bid Conference 17 10. Clarification And Amendment Of Bidding Documents 18 C. Preparation Of Bids 18 11. Language Of Bids 18 12. Documents Comprising The Bid: Eligibility And Technical Components 18 13. Documents Comprising The Bid: Financial Component 21 14. Alternative Bids 21 15. Bid Prices 22 16. Bid Currencies 22 17. Bid Validity 23 18. Bid Security 23 19. Format And Signing Of Bids 25 20. Sealing And Marking Of Bids 26 D. Submission And Opening Of Bids 26 21. Deadline For Submission Of Bids 26 22. Late Bids 26 23. Modification And Withdrawal Of Bids 27 24. Opening And Preliminary Examination Of Bids 27 E. Evaluation And Comparison Of Bids 28 25. Process To Be Confidential 28 26. Clarification Of Bids 29 27. Detailed Evaluation And Comparison Of Bids 29 28. Post Qualification 30 29. Reservation Clause 31 F. Award Of Contract 32 30. Contract Award 32 31. Signing Of The Contract 33 32. Performance Security 33 33. Notice To Proceed 34 A. General 1. Scope Of Bid 1.1. The Procuring Entity As Defined In The Bds, Invites Bids For The Construction Of Works, As Described In Section Vi. Specifications. The Name And Identification Number Of The Contract Is Provided In The Bds. 1.2. The Successful Bidder Will Be Expected To Complete The Works By The Intended Completion Date Specified In Scc Clause 1.16. 2. Source Of Funds The Procuring Entity Has A Budget Or Has Applied For Or Received Funds From The Funding Source Named In The Bds, And In The Amount Indicated In The Bds. It Intends To Apply Part Of The Funds Received For The Project, As Defined In The Bds, To Cover Eligible Payments Under The Contract For The Works. 3. Corrupt, Fraudulent, Collusive, And Coercive Practices 3.1. Unless Otherwise Specified In The Bds, The Procuring Entity, As Well As Bidders And Contractors, Shall Observe The Highest Standard Of Ethics During The Procurement And Execution Of The Contract. In Pursuance Of This Policy, The Funding Source: (a) Defines, For Purposes Of This Provision, The Terms Set Forth Below As Follows: (i) "corrupt Practice" Means Behavior On The Part Of Officials In The Public Or Private Sectors By Which They Improperly And Unlawfully Enrich Themselves, Others, Or Induce Others To Do So, By Misusing The Position In Which They Are Placed, And Includes The Offering, Giving, Receiving, Or Soliciting Of Anything Of Value To Influence The Action Of Any Such Official In The Procurement Process Or In Contract Execution; Entering, On Behalf Of The Procuring Entity, Into Any Contract Or Transaction Manifestly And Grossly Disadvantageous To The Same, Whether Or Not The Public Officer Profited Or Will Profit Thereby, And Similar Acts As Provided In Republic Act 3019; (ii) "fraudulent Practice" Means A Misrepresentation Of Facts In Order To Influence A Procurement Process Or The Execution Of A Contract To The Detriment Of The Procuring Entity, And Includes Collusive Practices Among Bidders (prior To Or After Bid Submission) Designed To Establish Bid Prices At Artificial, Non-competitive Levels And To Deprive The Procuring Entity Of The Benefits Of Free And Open Competition; (iii) “collusive Practices” Means A Scheme Or Arrangement Between Two Or More Bidders, With Or Without The Knowledge Of The Procuring Entity, Designed To Establish Bid Prices At Artificial, Non-competitive Levels; And (iv) “coercive Practices” Means Harming Or Threatening To Harm, Directly Or Indirectly, Persons, Or Their Property To Influence Their Participation In A Procurement Process, Or Affect The Execution Of A Contract; (v) “obstructive Practice” Is (aa) Deliberately Destroying, Falsifying, Altering Or Concealing Of Evidence Material To An Administrative Proceedings Or Investigation Or Making False Statements To Investigators In Order To Materially Impede An Administrative Proceedings Or Investigation Of The Procuring Entity Or Any Foreign Government/foreign Or International Financing Institution Into Allegations Of A Corrupt, Fraudulent, Coercive Or Collusive Practice; And/or Threatening, Harassing Or Intimidating Any Party To Prevent It From Disclosing Its Knowledge Of Matters Relevant To The Administrative Proceedings Or Investigation Or From Pursuing Such Proceedings Or Investigation; Or (bb) Acts Intended To Materially Impede The Exercise Of The Inspection And Audit Rights Of The Procuring Entity Or Any Foreign Government/foreign Or International Financing Institution Herein. (b) Will Reject A Proposal For Award If It Determines That The Bidder Recommended For Award Has Engaged In Corrupt Or Fraudulent Practices In Competing For The Contract; And (c) Will Declare A Firm Ineligible, Either Indefinitely Or For A Stated Period Of Time, To Be Awarded Contract Funded By The Funding Source If It At Any Time Determines That The Firm Has Engaged In Corrupt Or Fraudulent Practices In Competing Or, Or In Executing, A Contract Funded By The Funding Source. 3.2. Further, The Procuring Entity Will Seek To Impose The Maximum Civil, Administrative, And/or Criminal Penalties Available Under The Applicable Laws On Individuals And Organizations Deemed To Be Involved In Any Of The Practices Mentioned In Itb Clause 3.1(a). 3.3. Furthermore, The Funding Source And The Procuring Entity Reserve The Right To Inspect And Audit Records And Accounts Of A Contractor In The Bidding For And Performance Of A Contract Themselves Or Through Independent Auditors As Reflected In The Gcc Clause 34. 4. Conflict Of Interest 4.1. All Bidders Found To Have Conflicting Interests Shall Be Disqualified To Participate In The Procurement At Hand, Without Prejudice To The Imposition Of Appropriate Administrative, Civil, And Criminal Sanctions. A Bidder May Be Considered To Have Conflicting Interests With Another Bidder In Any Of The Events Described In Paragraphs (a) Through (c) And A General Conflict Of Interest In Any Of The Circumstances Set Out In Paragraphs (d) Through (g) Below: (a) A Bidder Has Controlling Shareholders In Common With Another Bidder; (b) A Bidder Receives Or Has Received Any Direct Or Indirect Subsidy From Any Other Bidder; (c) A Bidder Has The Same Legal Representative As That Of Another Bidder For Purposes Of This Bid; (d) A Bidder Has A Relationship, Directly Or Through Third Parties, That Puts Them In A Position To Have Access To Information About Or Influence On The Bid Of Another Bidder Or Influence The Decisions Of The Procuring Entity Regarding This Bidding Process. This Will Include A Firm Or An Organization Who Lends, Or Temporarily Seconds, Its Personnel To Firms Or Organizations Which Are Engaged In Consulting Services For The Preparation Related To Procurement For Or Implementation Of The Project If The Personnel Would Be Involved In Any Capacity On The Same Project; (e) A Bidder Submits More Than One Bid In This Bidding Process. However, This Does Not Limit The Participation Of Subcontractors In More Than One Bid; (f) A Bidder Who Participated As A Consultant In The Preparation Of The Design Or Technical Specifications Of The Goods And Related Services That Are The Subject Of The Bid; Or (g) A Bidder Who Lends, Or Temporary Seconds, Its Personnel To Firms Or Organizations Which Are Engaged In Consulting Services For The Preparation Related To Procurement For Or Implementation Of The Project, If The Personnel Would Be Involved In Any Capacity On The Same Project. 4.2. In Accordance With Section 47 Of The Irr Of Ra 9184, All Bidding Documents Shall Be Accompanied By A Sworn Affidavit Of The Bidder That It Is Not Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), Members Of The Technical Working Group (twg), Members Of The Bac Secretariat, The Head Of The Project Management Office (pmo) Or The End-user Unit, And The Project Consultants, By Consanguinity Or Affinity Up To The Third Civil Degree. On The Part Of The Bidder, This Clause Shall Apply To The Following Persons: (a) If The Bidder Is An Individual Or A Sole Proprietorship, To The Bidder Himself; (b) If The Bidder Is A Partnership, To All Its Officers And Members; (c) If The Bidder Is A Corporation, To All Its Officers, Directors, And Controlling Stockholders; And (d) If The Bidder Is A Joint Venture (jv), The Provisions Of Items (a), (b), Or (c) Of This Clause Shall Correspondingly Apply To Each Of The Members Of The Said Jv, As May Be Appropriate. Relationship Of The Nature Described Above Or Failure To Comply With This Clause Will Result In The Automatic Disqualification Of A Bidder. 5. Eligible Bidders 5.1. Unless Otherwise Indicated In The Bds, The Following Persons Shall Be Eligible To Participate In This Bidding: (a) Duly Licensed Filipino Citizens/sole Proprietorships; (b) Partnerships Duly Organized Under The Laws Of The Philippines And Of Which At Least Seventy Five Percent (75%) Of The Interest Belongs To Citizens Of The Philippines; (c) Corporations Duly Organized Under The Laws Of The Philippines, And Of Which At Least Seventy Five Percent (75%) Of The Outstanding Capital Stock Belongs To Citizens Of The Philippines; (d) Cooperatives Duly Organized Under The Laws Of The Philippines, And Of Which At Least Seventy Five Percent (75%) Of The Interest Belongs To Citizens Of The Philippines; And (e) Persons/entities Forming Themselves Into A Jv, I.e., A Group Of Two (2) Or More Persons/entities That Intend To Be Jointly And Severally Responsible Or Liable For A Particular Contract: Provided, However, That, In Accordance With Letter Of Instructions No. 630, Filipino Ownership Or Interest Of The Joint Venture Concerned Shall Be At Least Seventy Five Percent (75%): Provided, Further, That Joint Ventures In Which Filipino Ownership Or Interest Is Less Than Seventy Five Percent (75%) May Be Eligible Where The Structures To Be Built Require The Application Of Techniques And/or Technologies Which Are Not Adequately Possessed By A Person/entity Meeting The Seventy Five Percent (75%) Filipino Ownership Requirement: Provided, Finally, That In The Latter Case, Filipino Ownership Or Interest Shall Not Be Less Than Twenty Five Percent (25%). For This Purpose Filipino Ownership Or Interest Shall Be Based On The Contributions Of Each Of The Members Of The Joint Venture As Specified In Their Jva. 5.2. The Procuring Entity May Also Invite Foreign Bidders When Provided For Under Any Treaty Or International Or Executive Agreement As Specified In The Bds. 5.3. Government Corporate Entities May Be Eligible To Participate Only If They Can Establish That They (a) Are Legally And Financially Autonomous, (b) Operate Under Commercial Law, And (c) Are Not Dependent Agencies Of The Gop Or The Procuring Entity. 5.4. (a) Unless Otherwise Provided In The Bds, The Bidder Must Have Completed, Within Ten (10) Years From The Submission Of Bids, A Single Contract That Is Similar To This Project, Equivalent To At Least Fifty Percent (50%) Of The Abc Adjusted To Current Prices Using The National Statistics Office Consumer Price Index. (b) For Foreign-funded Procurement, The Procuring Entity And The Foreign Government/foreign Or International Financing Institution May Agree On Another Track Record Requirement, As Specified In The Bds. For This Purpose, Contracts Similar To The Project Shall Be Those Described In Thebds, And Completed Within The Period Stated In The Invitation To Bid And Itb Clause 12.1(a)(iii). 5.5. The Bidder Must Submit A Computation Of Its Net Financial Contracting Capacity (nfcc) Or A Commitment From A Universal Or Commercial Bank To Extend A Credit Line In Its Favor If Awarded The Contract For This Project (clc). The Nfcc, Computed Using The Following Formula, Must Be At Least Equal To The Abc To Be Bid: Nfcc = [(current Assets Minus Current Liabilities) (k)] Minus The Value Of All Outstanding Or Uncompleted Portions Of The Projects Under Ongoing Contracts, Including Awarded Contracts Yet To Be Started Coinciding With The Contract For This Project. Where: K = 10 For A Contract Duration Of One Year Or Less, 15 For A Contract Duration Of More Than One Year Up To Two Years, And 20 For A Contract Duration Of More Than Two Years. The Clc Must Be At Least Equal To Ten Percent (10%) Of The Abc For This Project. If Issued By A Foreign Bank, It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank. In The Case Of Local Government Units (lgus), The Bidder May Also Submit Clc From Other Banks Certified By The Bangko Sentral Ng Pilipinas (bsp) As Authorized To Issue Such Financial Instrument. 6. Bidder’s Responsibilities 6.1. The Bidder Or Its Duly Authorized Representative Shall Submit A Sworn Statement In The Form Prescribed In Section Ix. Bidding Forms As Required In Itb Clause 12.1(b)(iii). 6.2. The Bidder Is Responsible For The Following: (a) Having Taken Steps To Carefully Examine All Of The Bidding Documents; (b) Having Acknowledged All Conditions, Local Or Otherwise, Affecting The Implementation Of The Contract; (c) Having Made An Estimate Of The Facilities Available And Needed For The Contract To Be Bid, If Any; (d) Having Complied With Its Responsibility To Inquire Or Secure Supplemental/bid Bulletin/s As Provided Under Itb Clause 10.3. (e) Ensuring That It Is Not “blacklisted” Or Barred From Bidding By The Gop Or Any Of Its Agencies, Offices, Corporations, Or Lgus, Including Foreign Government/foreign Or International Financing Institution Whose Blacklisting Rules Have Been Recognized By The Gppb; (f) Ensuring That Each Of The Documents Submitted In Satisfaction Of The Bidding Requirements Is An Authentic Copy Of The Original, Complete, And All Statements And Information Provided Therein Are True And Correct; (g) Authorizing The Head Of The Procuring Entity Or Its Duly Authorized Representative/s To Verify All The Documents Submitted; (h) Ensuring That The Signatory Is The Duly Authorized Representative Of The Bidder, And Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary And/or To Represent The Bidder In The Bidding, With The Duly Notarized Secretary’s Certificate Attesting To Such Fact, If The Bidder Is A Corporation, Partnership, Cooperative, Or Joint Venture; (i) Complying With The Disclosure Provision Under Section 47 Of The Act In Relation To Other Provisions Of Republic Act 3019; And (j) Complying With Existing Labor Laws And Standards, If Applicable. Failure To Observe Any Of The Above Responsibilities Shall Be At The Risk Of The Bidder Concerned. 6.3. The Bidder, By The Act Of Submitting Its Bid, Shall Be Deemed To Have Inspected The Site, Determined The General Characteristics Of The Contract Works And The Conditions For This Project And Examine All Instructions, Forms, Terms, And Project Requirements In The Bidding Documents. 6.4. It Shall Be The Sole Responsibility Of The Prospective Bidder To Determine And To Satisfy Itself By Such Means As It Considers Necessary Or Desirable As To All Matters Pertaining To This Project, Including: (a) The Location And The Nature Of The Contract, Project, Or Work; (b) Climatic Conditions; (c) Transportation Facilities; (c) Nature And Condition Of The Terrain, Geological Conditions At The Site Communication Facilities, Requirements, Location And Availability Of Construction Aggregates And Other Materials, Labor, Water, Electric Power And Access Roads; And (d) Other Factors That May Affect The Cost, Duration And Execution Or Implementation Of The Contract, Project, Or Work. 6.5. The Procuring Entity Shall Not Assume Any Responsibility Regarding Erroneous Interpretations Or Conclusions By The Prospective Or Eligible Bidder Out Of The Data Furnished By The Procuring Entity. 6.6. Before Submitting Their Bids, The Bidders Are Deemed To Have Become Familiar With All Existing Laws, Decrees, Ordinances, Acts And Regulations Of The Philippines Which May Affect The Contract In Any Way. 6.7. The Bidder Shall Bear All Costs Associated With The Preparation And Submission Of His Bid, And The Procuring Entity Will In No Case Be Responsible Or Liable For Those Costs, Regardless Of The Conduct Or Outcome Of The Bidding Process. 6.8. Bidders Should Note That The Procuring Entity Will Only Accept Bids Only From Those That Have Paid The Nonrefundable Fee For The Bidding Documents At The Office Indicated In The Invitation To Bid. 7. Origin Of Goods And Services There Is No Restriction On The Origin Of Goods, Or Contracting Of Works Or Services Other Than Those Prohibited By A Decision Of The United Nations Security Council Taken Under Chapter Vii Of The Charter Of The United Nations. 8. Subcontracts 8.1. Unless Otherwise Specified In The Bds, The Bidder May Subcontract Portions Of The Works To An Extent As May Be Approved By The Procuring Entity And Stated In The Bds. However, Subcontracting Of Any Portion Shall Not Relieve The Bidder From Any Liability Or Obligation That May Arise From The Contract For This Project. 8.2. Subcontractors Must Submit The Documentary Requirements Under Itb Clause 12 And Comply With The Eligibility Criteria Specified In The Bds. In The Event That Any Subcontractor Is Found By The Procuring Entity To Be Ineligible, The Subcontracting Of Such Portion Of The Works Shall Be Disallowed. 8.3. The Bidder May Identify The Subcontractor To Whom A Portion Of The Works Will Be Subcontracted At Any Stage Of The Bidding Process Or During Contract Implementation. If The Bidder Opts To Disclose The Name Of The Subcontractor During Bid Submission, The Bidder Shall Include The Required Documents As Part Of The Technical Component Of Its Bid. B. Contents Of Bidding Documents 9. Pre-bid Conference 9.1. (a) If So Specified In The Bds, A Pre-bid Conference Shall Be Held At The Venue And On The Date Indicated Therein, To Clarify And Address The Bidders’ Questions On The Technical And Financial Components Of This Project. (b) The Pre-bid Conference Shall Be Held At Least Twelve (12) Calendar Days Before The Deadline For The Submission Of And Receipt Of Bids. If The Procuring Entity Determines That, By Reason Of The Method, Nature, Or Complexity Of The Contract To Be Bid, Or When International Participation Will Be More Advantageous To The Gop, A Longer Period For The Preparation Of Bids Is Necessary, The Pre-bid Conference Shall Be Held At Least Thirty (30) Calendar Days Before The Deadline For The Submission And Receipt Of Bids, As Specified In The Bds. 9.2. Bidders Are Encouraged To Attend The Pre-bid Conference To Ensure That They Fully Understand The Procuring Entity’s Requirements. Non-attendance Of The Bidder Will In No Way Prejudice Its Bid; However, The Bidder Is Expected To Know The Changes And/or Amendments To The Bidding Documents As Recorded In The Minutes Of The Pre-bid Conference And The Supplemental/bid Bulletin. 9.3. Any Statement Made At The Pre-bid Conference Shall Not Modify The Terms Of The Bidding Documents Unless Such Statement Is Specifically Identified In Writing As An Amendment Thereto And Issued As A Supplemental/bid Bulletin. 10. Clarification And Amendment Of Bidding Documents 10.1. Bidders Who Have Purchased The Bidding Documents May Request For Clarification(s) On Any Part Of The Bidding Documents Or For An Interpretation. Such A Request Must Be In Writing And Submitted To The Procuring Entity At The Address Indicated In The Bds At Least Ten (10) Calendar Days Before The Deadline Set For The Submission And Receipt Of Bids. 10.2. Supplemental/bid Bulletins May Be Issued Upon The Procuring Entity’s Initiative For Purposes Of Clarifying Or Modifying Any Provision Of The Bidding Documents Not Later Than Seven (7) Calendar Days Before The Deadline For The Submission And Receipt Of Bids. Any Modification To The Bidding Documents Shall Be Identified As An Amendment. 10.3. Any Supplemental/bid Bulletin Issued By The Bac Shall Also Be Posted On The Philippine Government Electronic Procurement System (philgeps) And The Website Of The Procuring Entity Concerned, If Available. Unless, Otherwise Provided In The Bds, It Shall Be The Responsibility Of All Bidders Who Secure The Bidding Documents To Inquire And Secure Supplemental/bid Bulletins That May Be Issued By The Bac. However, Bidders Who Have Submitted Bids Before The Issuance Of The Supplemental/bid Bulletin Must Be Informed And Allowed To Modify Or Withdraw Their Bids In Accordance With Itb Clause 23. C. Preparation Of Bids 11. Language Of Bids The Bid, As Well As All Correspondence And Documents Relating To The Bid Exchanged By The Bidder And The Procuring Entity, Shall Be Written In English. Supporting Documents And Printed Literature Furnished By The Bidder May Be In Another Language Provided They Are Accompanied By An Accurate Translation In English Certified By The Appropriate Embassy Or Consulate In The Philippines, In Which Case The English Translation Shall Govern, For Purposes Of Interpretation Of The Bid. 12. Documents Comprising The Bid: Eligibility And Technical Components 12.1. Unless Otherwise Indicated In The Bds, The First Envelope Shall Contain The Following Eligibility And Technical Documents: (a) Eligibility Documents – Class "a" Documents: (i) Registration Certificate From The Securities And Exchange Commission (sec), Department Of Trade And Industry (dti) For Sole Proprietorship, Or Cooperative Development Authority (cda) For Cooperatives, Or Any Proof Of Such Registration As Stated In The Bds; (ii) Mayor’s Permit Issued By The City Or Municipality Where The Principal Place Of Business Of The Prospective Bidder Is Located; (iii) Statement Of All Its Ongoing And Completed Government And Private Contracts Within Ten (10) Years From The Submission Of Bids, Including Contracts Awarded But Not Yet Started, If Any. The Statement Shall Include, For Each Contract, The Following: (iii.1) Name Of The Contract; (iii.2) Date Of The Contract; (iii.3) Contract Duration; (iii.4) Owner’s Name And Address; (iii.5) Nature Of Work; (iii.6) Contractor’s Role (whether Sole Contractor, Subcontractor, Or Partner In A Jv) And Percentage Of Participation; (iii.7) Total Contract Value At Award; (iii.8) Date Of Completion Or Estimated Completion Time; (iii.9) Total Contract Value At Completion, If Applicable; (iii.10) Percentages Of Planned And Actual Accomplishments, If Applicable; (iii.11) Value Of Outstanding Works, If Applicable; (iii.12) The Statement Shall Be Supported By The Notices Of Award And/or Notices To Proceed Issued By The Owners; And (iii.13) The Statement Shall Be Supported By The Constructors Performance Evaluation System (cpes) Rating Sheets, And/or Certificates Of Completion And Owner’s Acceptance, If Applicable; (iv) Unless Otherwise Provided In The Bds, Valid Philippine Contractors Accreditation Board (pcab) License And Registration For The Type And Cost Of The Contract For This Project; (v) Audited Financial Statements, Showing, Among Others, The Prospective Total And Current Assets And Liabilities, Stamped “received” By The Bir Or Its Duly Accredited And Authorized Institutions, For The Preceding Calendar Year Which Should Not Be Earlier Than Two (2) Years From The Date Of Bid Submission; (vi) Nfcc Computation Or Clc In Accordance With Itb Clause 5.5; And Class "b" Document: (vii) If Applicable, Valid Joint Venture Agreement (jva) Or, In Lieu Thereof, Duly Notarized Statements From All The Potential Joint Venture Partners Stating That They Will Enter Into And Abide By The Provisions Of The Jva In The Instance That The Bid Is Successful Shall Be Included In The Bid. (b) Technical Documents – (i) Bid Security As Prescribed In Itb Clause 18. If The Bidder Opts To Submit The Bid Security In The Form Of: (i.1) A Bank Draft/guarantee Or An Irrevocable Letter Of Credit Issued By A Foreign Bank, It Shall Be Accompanied By A Confirmation From A Universal Or Commercial Bank; Or (i.2) A Surety Bond Accompanied By A Certification Coming From An Authorized Insurance Commission That A Surety Or Insurance Company Is Authorized To Issue Such Instrument; (ii) Project Requirements, Which Shall Include The Following: (ii.1) Organizational Chart For The Contract To Be Bid; (ii.2) List Of Contractor’s Personnel (viz, Project Manager, Project Engineers, Materials Engineers, And Foremen), To Be Assigned To The Contract To Be Bid, With Their Complete Qualification And Experience Data; And (ii.3) List Of Contractor’s Equipment Units, Which Are Owned, Leased, And/or Under Purchase Agreements, Supported By Certification Of Availability Of Equipment From The Equipment Lessor/vendor For The Duration Of The Project; And (iii) Sworn Statement In Accordance With Section 25.2(b)(iv) Of The Irr Of Ra 9184 And Using The Form Prescribed In Section Ix. Bidding Forms. 13. Documents Comprising The Bid: Financial Component 13.1. Unless Otherwise Stated In The Bds, The Financial Component Of The Bid Shall Contain The Following: (a) Financial Bid Form In Accordance With The Form Prescribed In Section Ix. Bidding Forms; And (b) Any Other Document Related To The Financial Component Of The Bid As Stated In The Bds. 13.2. (a) Unless Indicated In The Bds, All Bids That Exceed The Abc Shall Not Be Accepted. (b) Unless Otherwise Indicated In The Bds, For Foreign-funded Procurement, A Ceiling May Be Applied To Bid Prices Provided The Following Conditions Are Met: (i) Bidding Documents Are Obtainable Free Of Charge On A Freely Accessible Website. If Payment Of Bidding Documents Is Required By The Procuring Entity, Payment Could Be Made Upon The Submission Of Bids. (ii) The Procuring Entity Has Procedures In Place To Ensure That The Abc Is Based On Recent Estimates Made By The Engineer Or The Responsible Unit Of The Procuring Entity And That The Estimates Are Based On Adequate Detailed Engineering (in The Case Of Works) And Reflect The Quality, Supervision And Risk And Inflationary Factors, As Well As Prevailing Market Prices, Associated With The Types Of Works Or Goods To Be Procured. (iii) The Procuring Entity Has Trained Cost Estimators On Estimating Prices And Analyzing Bid Variances. In The Case Of Infrastructure Projects, The Procuring Entity Must Also Have Trained Quantity Surveyors. (iv) The Procuring Entity Has Established A System To Monitor And Report Bid Prices Relative To Abc And Engineer’s/procuring Entity’s Estimate. (v) The Procuring Entity Has Established A Monitoring And Evaluation System For Contract Implementation To Provide A Feedback On Actual Total Costs Of Goods And Works. 14. Alternative Bids 14.1. Alternative Bids Shall Be Rejected. For This Purpose, Alternative Bid Is An Offer Made By A Bidder In Addition Or As A Substitute To Its Original Bid Which May Be Included As Part Of Its Original Bid Or Submitted Separately Therewith For Purposes Of Bidding. A Bid With Options Is Considered An Alternative Bid Regardless Of Whether Said Bid Proposal Is Contained In A Single Envelope Or Submitted In Two (2) Or More Separate Bid Envelopes. 14.2. Bidders Shall Submit Offers That Comply With The Requirements Of The Bidding Documents, Including The Basic Technical Design As Indicated In The Drawings And Specifications. Unless There Is A Value Engineering Clause In The Bds, Alternative Bids Shall Not Be Accepted. 14.3. Each Bidder Shall Submit Only One Bid, Either Individually Or As A Partner In A Jv. A Bidder Who Submits Or Participates In More Than One Bid (other Than As A Subcontractor If A Subcontractor Is Permitted To Participate In More Than One Bid) Will Cause All The Proposals With The Bidder’s Participation To Be Disqualified. This Shall Be Without Prejudice To Any Applicable Criminal, Civil And Administrative Penalties That May Be Imposed Upon The Persons And Entities Concerned. 15. Bid Prices 15.1. The Contract Shall Be For The Whole Works, As Described In Itb Clause 1.1, Based On The Priced Bill Of Quantities Submitted By The Bidder. 15.2. The Bidder Shall Fill In Rates And Prices For All Items Of The Works Described In The Bill Of Quantities. Bids Not Addressing Or Providing All Of The Required Items In The Bidding Documents Including, Where Applicable, Bill Of Quantities, Shall Be Considered Non-responsive And, Thus, Automatically Disqualified. In This Regard, Where A Required Item Is Provided, But No Price Is Indicated, The Same Shall Be Considered As Non-responsive, But Specifying A "0" (zero) For The Said Item Would Mean That It Is Being Offered For Free To The Government. 15.3. All Duties, Taxes, And Other Levies Payable By The Contractor Under The Contract, Or For Any Other Cause, Prior To The Deadline For Submission Of Bids, Shall Be Included In The Rates, Prices, And Total Bid Price Submitted By The Bidder. 15.4. All Bid Prices For The Given Scope Of Work In The Contract As Awarded Shall Be Considered As Fixed Prices, And Therefore Not Subject To Price Escalation During Contract Implementation, Except Under Extraordinary Circumstances As Specified In Gcc Clause 48. Price Escalation May Be Allowed In Extraordinary Circumstances As May Be Determined By The National Economic And Development Authority In Accordance With The Civil Code Of The Philippines, And Upon The Recommendation Of The Procuring Entity. Furthermore, In Cases Where The Cost Of The Awarded Contract Is Affected By Any Applicable New Laws, Ordinances, Regulations, Or Other Acts Of The Gop, Promulgated After The Date Of Bid Opening, A Contract Price Adjustment Shall Be Made Or Appropriate Relief Shall Be Applied On A No Loss-no Gain Basis. 16. Bid Currencies 16.1. All Bid Prices Shall Be Quoted In Philippine Pesos Unless Otherwise Provided In The Bds. However, For Purposes Of Bid Evaluation, Bids Denominated In Foreign Currencies Shall Be Converted To Philippine Currency Based On The Exchange Rate Prevailing On The Day Of The Bid Opening. 16.2. If So Allowed In Accordance With Itb Clause 16.1, The Procuring Entity For Purposes Of Bid Evaluation And Comparing The Bid Prices Will Convert The Amounts In Various Currencies In Which The Bid Price Is Expressed To Philippine Pesos At The Exchange Rate As Published In The Bsp Reference Rate Bulletin On The Day Of The Bid Opening. 16.3. Unless Otherwise Specified In The Bds, Payment Of The Contract Price Shall Be Made In Philippine Pesos. 17. Bid Validity 17.1. Bids Shall Remain Valid For The Period Specified In The Bds Which Shall Not Exceed One Hundred Twenty (120) Calendar Days From The Date Of The Opening Of Bids. 17.2. In Exceptional Circumstances, Prior To The Expiration Of The Bid Validity Period, The Procuring Entity May Request Bidders To Extend The Period Of Validity Of Their Bids. The Request And The Responses Shall Be Made In Writing. The Bid Security Described In Itb Clause 18 Should Also Be Extended Corresponding To The Extension Of The Bid Validity Period At The Least. A Bidder May Refuse The Request Without Forfeiting Its Bid Security, But His Bid Shall No Longer Be Considered For Further Evaluation And Award. A Bidder Granting The Request Shall Not Be Required Or Permitted To Modify Its Bid. 18. Bid Security 18.1. The Bid Security In The Amount Stated In The Bds Shall Be Equal To The Percentage Of The Abc In Accordance With The Following Schedule: Form Of Bid Security Amount Of Bid Security (equal To Percentage Of The Abc) (a) Cash Or Cashier’s/manager’s Check Issued By A Universal Or Commercial Bank. Two Percent (2%) (b) Bank Draft/guarantee Or Irrevocable Letter Of Credit Issued By A Universal Or Commercial Bank: Provided, However, That It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank. (c) Surety Bond Callable Upon Demand Issued By A Surety Or Insurance Company Duly Certified By The Insurance Commission As Authorized To Issue Such Security; And/or Five Percent (5%) (d) Any Combination Of The Foregoing. Proportionate To Share Of Form With Respect To Total Amount Of Security For Biddings Conducted By Local Government Units, The Bidder May Also Submit Bid Securities In The Form Of Cashier’s/manager’s Check, Bank Draft/guarantee, Or Irrevocable Letter Of Credit From Other Banks Certified By The Bsp As Authorized To Issue Such Financial Statement. 18.2. The Bid Security Should Be Valid For The Period Specified In The Bds. Any Bid Not Accompanied By An Acceptable Bid Security Shall Be Rejected By The Procuring Entity As Non-responsive. 18.3. No Bid Securities Shall Be Returned To Bidders After The Opening Of Bids And Before Contract Signing, Except To Those That Failed Or Declared As Post-disqualified, Upon Submission Of A Written Waiver Of Their Right To File A Motion For Reconsideration And/or Protest. Without Prejudice On Its Forfeiture, Bid Securities Shall Be Returned Only After The Bidder With The Lowest Calculated Responsive Bid Has Signed The Contract And Furnished The Performance Security, But In No Case Later Than The Expiration Of The Bid Security Validity Period Indicated In Itb Clause 18.2. 18.4. Upon Signing And Execution Of The Contract, Pursuant To Itb Clause 31, And The Posting Of The Performance Security, Pursuant To Itb Clause 32, The Successful Bidder’s Bid Security Will Be Discharged, But In No Case Later Than The Bid Security Validity Period As Indicated In Itb Clause 18.2. 18.5. The Bid Security May Be Forfeited: (a) If A Bidder: (i) Withdraws Its Bid During The Period Of Bid Validity Specified In Itb Clause 17; (ii) Does Not Accept The Correction Of Errors Pursuant To Itb Clause 27.3(b); (iii) Fails To Submit The Requirements Within The Prescribed Period, Or A Finding Against Their Veracity, As Stated In Itb Clause 28.2; (iv) Submission Of Eligibility Requirements Containing False Information Or Falsified Documents; (v) Submission Of Bids That Contain False Information Or Falsified Documents, Or The Concealment Of Such Information In The Bids In Order To Influence The Outcome Of Eligibility Screening Or Any Other Stage Of The Public Bidding; (vi) Allowing The Use Of One’s Name, Or Using The Name Of Another For Purposes Of Public Bidding; (vii) Withdrawal Of A Bid, Or Refusal To Accept An Award, Or Enter Into Contract With The Government Without Justifiable Cause, After The Bidder Had Been Adjudged As Having Submitted The Lowest Calculated And Responsive Bid; (viii) Refusal Or Failure To Post The Required Performance Security Within The Prescribed Time; (ix) Refusal To Clarify Or Validate In Writing Its Bid During Post-qualification Within A Period Of Seven (7) Calendar Days From Receipt Of The Request For Clarification; (x) Any Documented Attempt By A Bidder To Unduly Influence The Outcome Of The Bidding In His Favor; (xi) Failure Of The Potential Joint Venture Partners To Enter Into The Joint Venture After The Bid Is Declared Successful; Or (xii) All Other Acts That Tend To Defeat The Purpose Of The Competitive Bidding, Such As Habitually Withdrawing From Bidding, Submitting Late Bids Or Patently Insufficient Bid, For At Least Three (3) Times Within A Year, Except For Valid Reasons. (b) If The Successful Bidder: (i) Fails To Sign The Contract In Accordance With Itb Clause 31; (ii) Fails To Furnish Performance Security In Accordance With Itb Clause 32. 19. Format And Signing Of Bids 19.1. Bidders Shall Submit Their Bids Through Their Duly Authorized Representative Using The Appropriate Forms Provided In Section Ix. Bidding Forms On Or Before The Deadline Specified In The Itb Clause 21 In Two (2) Separate Sealed Bid Envelopes, And Which Shall Be Submitted Simultaneously. The First Shall Contain The Technical Component Of The Bid, Including The Eligibility Requirements Under Itb Clause 12.1, And The Second Shall Contain The Financial Component Of The Bid. 19.2. Forms As Mentioned In Itb Clause 19.1 Must Be Completed Without Any Alterations To Their Format, And No Substitute Form Shall Be Accepted. All Blank Spaces Shall Be Filled In With The Information Requested. 19.3. The Bidder Shall Prepare An Original Of The First And Second Envelopes As Described In Itb Clauses 12 And 13. In Addition, The Bidder Shall Submit Copies Of The First And Second Envelopes. In The Event Of Any Discrepancy Between The Original And The Copies, The Original Shall Prevail. 19.4. The Bid, Except For Unamended Printed Literature, Shall Be Signed, And Each And Every Page Thereof Shall Be Initialed, By The Duly Authorized Representative/s Of The Bidder. 19.5. Any Interlineations, Erasures, Or Overwriting Shall Be Valid Only If They Are Signed Or Initialed By The Duly Authorized Representative/s Of The Bidder. 20. Sealing And Marking Of Bids 20.1. Bidders Shall Enclose Their Original Eligibility And Technical Documents Described In Itb Clause 12, In One Sealed Envelope Marked “original - Technical Component”, And The Original Of Their Financial Component In Another Sealed Envelope Marked “original - Financial Component”, Sealing Them All In An Outer Envelope Marked “original Bid”. 20.2. Each Copy Of The First And Second Envelopes Shall Be Similarly Sealed Duly Marking The Inner Envelopes As “copy No. ___ - Technical Component” And “copy No. ___ – Financial Component” And The Outer Envelope As “copy No. ___”, Respectively. These Envelopes Containing The Original And The Copies Shall Then Be Enclosed In One Single Envelope. 20.3. The Original And The Number Of Copies Of The Bid As Indicated In The Bds Shall Be Typed Or Written In Indelible Ink And Shall Be Signed By The Bidder Or Its Duly Authorized Representative/s. 20.4. All Envelopes Shall: (a) Contain The Name Of The Contract To Be Bid In Capital Letters; (b) Bear The Name And Address Of The Bidder In Capital Letters; (c) Be Addressed To The Procuring Entity’s Bac Identified In Itb Clause 10.1; (d) Bear The Specific Identification Of This Bidding Process Indicated In The Invitation To Bid; And (e) Bear A Warning “do Not Open Before…” The Date And Time For The Opening Of Bids, In Accordance With Itb Clause 21. 20.5. If Bids Are Not Sealed And Marked As Required, The Procuring Entity Will Assume No Responsibility For The Misplacement Or Premature Opening Of The Bid. D. Submission And Opening Of Bids 21. Deadline For Submission Of Bids Bids Must Be Received By The Procuring Entity’s Bac At The Address And On Or Before The Date And Time Indicated In The Bds. 22. Late Bids Any Bid Submitted After The Deadline For Submission And Receipt Of Bids Prescribed By The Procuring Entity, Pursuant To Itb Clause 21, Shall Be Declared “late” And Shall Not Be Accepted By The Procuring Entity. 23. Modification And Withdrawal Of Bids 23.1. The Bidder May Modify Its Bid After It Has Been Submitted; Provided That The Modification Is Received By The Procuring Entity Prior To The Deadline Prescribed For Submission And Receipt Of Bids. The Bidder Shall Not Be Allowed To Retrieve Its Original Bid, But Shall Be Allowed To Submit Another Bid Equally Sealed, Properly Identified, Linked To Its Original Bid Marked As “technical Modification” Or “financial Modification” And Stamped “received” By The Bac. Bid Modifications Received After The Applicable Deadline Shall Not Be Considered And Shall Be Returned To The Bidder Unopened. 23.2. A Bidder May, Through A Letter Of Withdrawal, Withdraw Its Bid After It Has Been Submitted, For Valid And Justifiable Reason; Provided That The Letter Of Withdrawal Is Received By The Procuring Entity Prior To The Deadline Prescribed For Submission And Receipt Of Bids. 23.3. Bids Requested To Be Withdrawn In Accordance With Itb Clause 23.1 Shall Be Returned Unopened To The Bidders. A Bidder May Also Express Its Intention Not To Participate In The Bidding Through A Letter Which Should Reach And Be Stamped By The Bac Before The Deadline For Submission And Receipt Of Bids. A Bidder That Withdraws Its Bid Shall Not Be Permitted To Submit Another Bid, Directly Or Indirectly, For The Same Contract. 23.4. No Bid May Be Modified After The Deadline For Submission Of Bids. No Bid May Be Withdrawn In The Interval Between The Deadline For Submission Of Bids And The Expiration Of The Period Of Bid Validity Specified By The Bidder On The Financial Bid Form. Withdrawal Of A Bid During This Interval Shall Result In The Forfeiture Of The Bidder’s Bid Security, Pursuant To Itb Clause 18.5, And The Imposition Of Administrative, Civil, And Criminal Sanctions As Prescribed By Ra 9184 And Its Irr. 24. Opening And Preliminary Examination Of Bids 24.1. The Bac Shall Open The First Bid Envelopes Of Bidders In Public As Specified In The Bds To Determine Each Bidder’s Compliance With The Documents Prescribed In Itb Clause 12. For This Purpose, The Bac Shall Check The Submitted Documents Of Each Bidder Against A Checklist Of Required Documents To Ascertain If They Are All Present, Using A Non-discretionary “pass/fail” Criterion. If A Bidder Submits The Required Document, It Shall Be Rated “passed” For That Particular Requirement. In This Regard, Bids That Fail To Include Any Requirement Or Are Incomplete Or Patently Insufficient Shall Be Considered As “failed”. Otherwise, The Bac Shall Rate The Said First Bid Envelope As “passed”. 24.2. Unless Otherwise Specified In The Bds, Immediately After Determining Compliance With The Requirements In The First Envelope, The Bac Shall Forthwith Open The Second Bid Envelope Of Each Remaining Eligible Bidder Whose First Bid Envelope Was Rated “passed”. The Second Envelope Of Each Complying Bidder Shall Be Opened Within The Same Day. In Case One Or More Of The Requirements In The Second Envelope Of A Particular Bid Is Missing, Incomplete Or Patently Insufficient, And/or If The Submitted Total Bid Price Exceeds The Abc Unless Otherwise Provided In Itb Clause 13.1(b), The Bac Shall Rate The Bid Concerned As “failed”. Only Bids That Are Determined To Contain All The Bid Requirements For Both Components Shall Be Rated “passed” And Shall Immediately Be Considered For Evaluation And Comparison. 24.3. Letters Of Withdrawal Shall Be Read Out And Recorded During Bid Opening, And The Envelope Containing The Corresponding Withdrawn Bid Shall Be Returned To The Bidder Unopened. If The Withdrawing Bidder’s Representative Is In Attendance, The Original Bid And All Copies Thereof Shall Be Returned To The Representative During The Bid Opening. If The Representative Is Not In Attendance, The Bid Shall Be Returned Unopened By Registered Mail. The Bidder May Withdraw Its Bid Prior To The Deadline For The Submission And Receipt Of Bids, Provided That The Corresponding Letter Of Withdrawal Contains A Valid Authorization Requesting For Such Withdrawal, Subject To Appropriate Administrative Sanctions. 24.4. If A Bidder Has Previously Secured A Certification From The Procuring Entity To The Effect That It Has Previously Submitted The Above-enumerated Class “a” Documents, The Said Certification May Be Submitted In Lieu Of The Requirements Enumerated In Itb Clause 12.1(a), Items (i) To (vi). 24.5. In The Case Of An Eligible Foreign Bidder As Described In Itb Clause 5, The Class “a” Documents Enumerated In Itb Clause 12.1(a) May Be Substituted With The Appropriate Equivalent Documents, If Any, Issued By The Country Of The Foreign Bidder Concerned. 24.6. Each Partner Of A Joint Venture Agreement Shall Likewise Submit The Documents Required In Itb Clauses 12.1(a)(i) And 12.1(a)(ii). Submission Of Documents Required Under Itb Clauses 12.1(a)(iii) To 12.1(a)(vi) By Any Of The Joint Venture Partners Constitutes Compliance. 24.7. A Bidder Determined As “failed” Has Three (3) Calendar Days Upon Written Notice Or, If Present At The Time Of Bid Opening, Upon Verbal Notification Within Which To File A Request For Reconsideration With The Bac: Provided, However, That The Request For Reconsideration Shall Not Be Granted If It Is Established That The Finding Of Failure Is Due To The Fault Of The Bidder Concerned: Provided, Further, That The Bac Shall Decide On The Request For Reconsideration Within Seven (7) Calendar Days From Receipt Thereof. If A Failed Bidder Signifies His Intent To File A Request For Reconsideration, The Bac Shall Keep The Bid Envelopes Of The Said Failed Bidder Unopened And/or Duly Sealed Until Such Time That The Request For Reconsideration Or Protest Has Been Resolved. E. Evaluation And Comparison Of Bids 25. Process To Be Confidential 25.1. Members Of The Bac, Including Its Staff And Personnel, As Well As Its Secretariat And Twg, Are Prohibited From Making Or Accepting Any Kind Of Communication With Any Bidder Regarding The Evaluation Of Their Bids Until The Issuance Of The Notice Of Award, Unless N The Case Of Itb Clause 26. 25.2. Any Effort By A Bidder To Influence The Procuring Entity In The Procuring Entity’s Decision In Respect Of Bid Evaluation, Bid Comparison Or Contract Award Will Result In The Rejection Of The Bidder’s Bid. 26. Clarification Of Bids To Assist In The Evaluation, Comparison And Post-qualification Of The Bids, The Procuring Entity May Ask In Writing Any Bidder For A Clarification Of Its Bid. All Responses To Requests For Clarification Shall Be In Writing. Any Clarification Submitted By A Bidder In Respect To Its Bid And That Is Not In Response To A Request By The Procuring Entity Shall Not Be Considered 27. Detailed Evaluation And Comparison Of Bids 27.1. The Procuring Entity Will Undertake The Detailed Evaluation And Comparison Of Bids Which Have Passed The Opening And Preliminary Examination Of Bids, Pursuant To Itb Clause 24, In Order To Determine The Lowest Calculated Bid. 27.2. In Evaluating The Bids To Get The Lowest Calculated Bid, The Procuring Entity Shall Undertake The Following: (a) The Detailed Evaluation Of The Financial Component Of The Bids, To Establish The Correct Calculated Prices Of The Bids; And (b) The Ranking Of The Total Bid Prices As So Calculated From The Lowest To Highest. The Bid With The Lowest Price Shall Be Identified As The Lowest Calculated Bid. 27.3. The Procuring Entity's Bac Shall Immediately Conduct A Detailed Evaluation Of All Bids Rated “passed,” Using Non-discretionary “pass/fail” Criterion. The Bac Shall Consider The Following In The Evaluation Of Bids: (a) Completeness Of The Bid. Unless The Itb Specifically Allows Partial Bids, Bids Not Addressing Or Providing All Of The Required Items In The Schedule Of Requirements Including, Where Applicable, Bill Of Quantities, Shall Be Considered Non-responsive And, Thus, Automatically Disqualified. In This Regard, Where A Required Item Is Provided, But No Price Is Indicated, The Same Shall Be Considered As Non-responsive, But Specifying A "0" (zero) For The Said Item Would Mean That It Is Being Offered For Free To The Procuring Entity; And (b) Arithmetical Corrections. Consider Computational Errors And Omissions To Enable Proper Comparison Of All Eligible Bids. It May Also Consider Bid Modifications If Expressly Allowed In The Bds. Any Adjustment Shall Be Calculated In Monetary Terms To Determine The Calculated Prices. 27.4. Based On The Detailed Evaluation Of Bids, Those That Comply With The Above-mentioned Requirements Shall Be Ranked In The Ascending Order Of Their Total Calculated Bid Prices, As Evaluated And Corrected For Computational Errors, Discounts And Other Modifications, To Identify The Lowest Calculated Bid. Total Calculated Bid Prices, As Evaluated And Corrected For Computational Errors, Discounts And Other Modifications, Which Exceed The Abc Shall Not Be Considered, Unless Otherwise Indicated In The Bds. 27.5. The Procuring Entity’s Evaluation Of Bids Shall Only Be Based On The Bid Price Quoted In The Financial Bid Form 27.6. Bids Shall Be Evaluated On An Equal Footing To Ensure Fair Competition. For This Purpose, All Bidders Shall Be Required To Include In Their Bids The Cost Of All Taxes, Such As, But Not Limited To, Value Added Tax (vat), Income Tax, Local Taxes, And Other Fiscal Levies And Duties Which Shall Be Itemized In The Bid Form And Reflected In The Detailed Estimates. Such Bids, Including Said Taxes, Shall Be The Basis For Bid Evaluation And Comparison. 28. Post Qualification 28.1. The Procuring Entity Shall Determine To Its Satisfaction Whether The Bidder That Is Evaluated As Having Submitted The Lowest Calculated Bid (lcb) Complies With And Is Responsive To All The Requirements And Conditions Specified In Itb Clauses 5, 12, And 13. 28.2. Within A Non-extendible Period Of Three (3) Calendar Days From Receipt By The Bidder Of The Notice From The Bac That It Submitted The Lcb, The Bidder Shall Submit The Following Documentary Requirements: (a) Tax Clearance Per Executive Order 398, Series Of 2005; (b) Latest Income And Business Tax Returns In The Form Specified In The Bds; (c) Certificate Of Philgeps Registration; And (d) Other Appropriate Licenses And Permits Required By Law And Stated In The Bds. Failure Of The Bidder Declared As Lcb To Duly Submit The Requirements Under This Clause Or A Finding Against The Veracity Of Such, Shall Be Ground For Forfeiture Of The Bid Security And Disqualification Of The Bidder For Award. 28.3. The Determination Shall Be Based Upon An Examination Of The Documentary Evidence Of The Bidder’s Qualifications Submitted Pursuant To Itb Clauses 12 And 13, As Well As Other Information As The Procuring Entity Deems Necessary And Appropriate, Using A Non-discretionary “pass/fail” Criterion. 28.4. If The Bac Determines That The Bidder With The Lowest Calculated Bid Passes All The Criteria For Post-qualification, It Shall Declare The Said Bid As The Lowest Calculated Responsive Bid, And Recommend To The Head Of The Procuring Entity The Award Of Contract To The Said Bidder At Its Submitted Price Or Its Calculated Bid Price, Whichever Is Lower, Subject To Itb Clause 30.3. 28.5. A Negative Determination Shall Result In Rejection Of The Bidder’s Bid, In Which Event The Procuring Entity Shall Proceed To The Next Lowest Calculated Bid To Make A Similar Determination Of That Bidder’s Capabilities To Perform Satisfactorily. If The Second Bidder, However, Fails The Post Qualification, The Procedure For Post Qualification Shall Be Repeated For The Bidder With The Next Lowest Calculated Bid, And So On Until The Lowest Calculated And Responsive Bid Is Determined For Contract Award. 28.6. Within A Period Not Exceeding Seven (7) Calendar Days From The Date Of Receipt Of The Recommendation Of The Bac, The Head Of The Procuring Entity Shall Approve Or Disapprove The Said Recommendation. In The Case Of Government Owned And Government-owned And/or -controlled Corporations (goccs) And Government Financial Institutions (gfis), The Period Provided Herein Shall Be Fifteen (15) Calendar Days. 29. Reservation Clause 29.1. Notwithstanding The Eligibility Or Post-qualification Of A Bidder, The Procuring Entity Concerned Reserves The Right To Review Its Qualifications At Any Stage Of The Procurement Process If It Has Reasonable Grounds To Believe That A Misrepresentation Has Been Made By The Said Bidder, Or That There Has Been A Change In The Bidder’s Capability To Undertake The Project From The Time It Submitted Its Eligibility Requirements. Should Such Review Uncover Any Misrepresentation Made In The Eligibility And Bidding Requirements, Statements Or Documents, Or Any Changes In The Situation Of The Bidder Which Will Affect Its Capability To Undertake The Project So That It Fails The Preset Eligibility Or Bid Evaluation Criteria, The Procuring Entity Shall Consider The Said Bidder As Ineligible And Shall Disqualify It From Submitting A Bid Or From Obtaining An Award Or Contract. 29.2. Based On The Following Grounds, The Procuring Entity Reserves The Right To Reject Any And All Bids, Declare A Failure Of Bidding At Any Time Prior To The Contract Award, Or Not To Award The Contract, Without Thereby Incurring Any Liability, And Make No Assurance That A Contract Shall Be Entered Into As A Result Of The Bidding: (a) If There Is Prima Facie Evidence Of Collusion Between Appropriate Public Officers Or Employees Of The Procuring Entity, Or Between The Bac And Any Of The Bidders, Or If The Collusion Is Between Or Among The Bidders Themselves, Or Between A Bidder And A Third Party, Including Any Act Which Restricts, Suppresses Or Nullifies Or Tends To Restrict, Suppress Or Nullify Competition; (b) If The Procuring Entity’s Bac Is Found To Have Failed In Following The Prescribed Bidding Procedures; Or (c) For Any Justifiable And Reasonable Ground Where The Award Of The Contract Will Not Redound To The Benefit Of The Government As Follows: (i) If The Physical And Economic Conditions Have Significantly Changed So As To Render The Project No Longer Economically, Financially Or Technically Feasible As Determined By The Head Of The Procuring Entity; (ii) If The Project Is No Longer Necessary As Determined By The Head Of The Procuring Entity; And (iii) If The Source Of Funds For The Project Has Been Withheld Or Reduced Through No Fault Of The Procuring Entity. 29.3. In Addition, The Procuring Entity May Likewise Declare A Failure Of Bidding When: (a) No Bids Are Received; (b) All Prospective Bidders Are Declared Ineligible; (c) All Bids Fail To Comply With All The Bid Requirements Or Fail Post-qualification; Or (d) The Bidder With The Lowest Calculated Responsive Bid Refuses, Without Justifiable Cause To Accept The Award Of Contract, And No Award Is Made. F. Award Of Contract 30. Contract Award 30.1. Subject To Itb Clause 28, The Procuring Entity Shall Award The Contract To The Bidder Whose Bid Has Been Determined To Be The Lowest Calculated And Responsive Bid (lcrb). 30.2. Prior To The Expiration Of The Period Of Bid Validity, The Procuring Entity Shall Notify The Successful Bidder In Writing That Its Bid Has Been Accepted, Through A Notice Of Award Received Personally Or Sent By Registered Mail Or Electronically, Receipt Of Which Must Be Confirmed In Writing Within Two (2) Days By The Lcrb And Submitted Personally Or Sent By Registered Mail Or Electronically To The Procuring Entity. 30.3. Notwithstanding The Issuance Of The Notice Of Award, Award Of Contract Shall Be Subject To The Following Conditions: (a) Submission Of The Following Documents Within The Prescribed Period From Receipt By The Bidder Of The Notice That It Has The Lowest Calculated And Responsive Bid: (i) Valid Jva, If Applicable, Within Ten (10) Calendar Days; (ii) Valid Pcab License And Registration For The Type And Cost Of The Contract To Be Bid For Foreign Bidders, Within Thirty (30) Calendar Days, If Allowed Under A Treaty Or International Or Executive Agreement Mentioned In Itb Clause 12.1(a)(iv); (b) Posting Of The Performance Security In Accordance With Itb Clause 32; (c) Signing Of The Contract As Provided In Itb Clause 31; And (d) Approval By Higher Authority, If Required. 31. Signing Of The Contract 31.1. At The Same Time As The Procuring Entity Notifies The Successful Bidder That Its Bid Has Been Accepted, The Procuring Entity Shall Send The Contract Form To The Bidder, Which Contract Has Been Provided In The Bidding Documents, Incorporating Therein All Agreements Between The Parties. 31.2. Within Ten (10) Calendar Days From Receipt Of The Notice Of Award, The Successful Bidder Shall Post The Required Performance Security, Sign And Date The Contract And Return It To The Procuring Entity. 31.3. The Procuring Entity Shall Enter Into Contract With The Successful Bidder Within The Same Ten (10) Calendar Day Period Provided That All The Documentary Requirements Are Complied With. 31.4. The Following Documents Shall Form Part Of The Contract: (a) Contract Agreement; (b) Bidding Documents; (c) Winning Bidder’s Bid, Including The Technical And Financial Proposals, And All Other Documents/statements Submitted; (d) Performance Security; (e) Credit Line In Accordance With Itb Clause 5.5, If Applicable; (f) Notice Of Award Of Contract; And (g) Other Contract Documents That May Be Required By Existing Laws And/or Specified In The Bds. 32. Performance Security 32.1. To Guarantee The Faithful Performance By The Winning Bidder Of Its Obligations Under The Contract, It Shall Post A Performance Security Within A Maximum Period Of Ten (10) Calendar Days From The Receipt Of The Notice Of Award From The Procuring Entity And In No Case Later Than The Signing Of The Contract. 32.2. The Performance Security Shall Be Denominated In Philippine Pesos And Posted In Favor Of The Procuring Entity In An Amount Equal To The Percentage Of The Total Contract Price As Stated In The Bds In Accordance With The Following Schedule: 33. 33.1. Form Of Performance Security Amount Of Performance Security (equal To Percentage Of The Total Contract Price) (a) Cash Or Cashier’s/manager’s Check Issued By A Universal Or Commercial Bank. Ten Percent (10%) (b) Bank Draft/guarantee Or Irrevocable Letter Of Credit Issued By A Universal Or Commercial Bank: Provided, However, That It Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank. (c) Surety Bond Callable Upon Demand Issued By A Surety Or Insurance Company Duly Certified By The Insurance Commission As Authorized To Issue Such Security; And/or Thirty Percent (30%) (d) Any Combination Of The Foregoing. Proportionate To Share Of Form With Respect To Total Amount Of Security 33.2. Failure Of The Successful Bidder To Comply With The Above-mentioned Requirement Shall Constitute Sufficient Ground For The Annulment Of The Award And Forfeiture Of The Bid Security, In Which Event The Procuring Entity Shall Initiate And Complete The Post Qualification Of The Second Lowest Calculated Bid. The Procedure Shall Be Repeated Until The Lowest Calculated And Responsive Bid Is Identified And Selected For Contract Award. However If No Bidder Passed Post-qualification, The Bac Shall Declare The Bidding A Failure And Conduct A Re-bidding With Re-advertisement. 34. Notice To Proceed 34.1. Within Three (3) Calendar Days From The Date Of Approval Of The Contract By The Appropriate Government Approving Authority, The Procuring Entity Shall Issue Its Notice To Proceed To The Bidder. 34.2. The Contract Effectivity Date Shall Be Provided In The Notice To Proceed By The Procuring Entity, Which Date Shall Not Be Later Than Seven (7) Calendar Days From The Issuance Of The Notice To Proceed. Section Iii. Bid Data Sheet Bid Data Sheet Itb Clause 1.1 The Procuring Entity Is Lgu- Mapanas, Northern Samar. The Name Of The Contract Is Repair/rehabilitation Of Mapanas Rhu, Brgy. Del Norte, Mapanas N. Samar The Identification Number Of The Contract Is Pr No-2024-11-094___ 2 The Funding Source Is: Trust Fund (edf) For Fy 2023. The Name Of The Project Is: Repair/rehabilitation Of Mapanas Rhu, Brgy. Del Norte, Mapanas N. Samar. 3.1 No Further Instructions. 5.1 No Further Instructions. 5.2 Bidding Is Restricted To Eligible Bidders As Defined In Itb Clause 5.1. 5.4 For This Purpose, Similar Contracts Shall Refer To Bidder’s Annual Turnover From All Works Average Over The Last Three Years Shall Be Equal To 50% Of The Estimated Cost Of The Contract Being Procured. The Bidder Must Have Completed, Within The Past Ten (10) Years From The Submission Of Bids, A Single Contract That Is Similar To This Project, Equivalent To At Least Eighty Percent (80%) Of The Abc. 8.1 “subcontracting Is Not Allowed.” 8.2 “not Applicable”. 9.1 The Procuring Entity Will Hold A Pre-bid Conference For This Project On November 15, 2024 At 10:00 A.m. At Executive Conference 2nd Floor Of New Municipal Bldg. Mapanas, Northern Samar. 10.1 The Procuring Entity’s Address Is: The Municipality Of Mapanas, Province Of Northern Samar Ma. Teresa L. Minguez Lgu-bac Chairperson Tel. No. 09778033758 10.3 No Further Instructions. 12.1 Not Applicable 12.1(a)(i) “no Other Acceptable Proof Of Registration Is Recognized.” 12.1(a)(iv) No Further Instructions. 13.1 “no Additional Requirements” 13.1(b) The Abc Is Php1,049,465.57 Any Bid With A Financial Component Exceeding This Amount Shall Not Be Accepted. 14.2 “no Further Instructions.” 15.4 No Further Instruction. 16.1 The Bid Prices Shall Be Quoted In Philippine Pesos. 17.1 Bids Will Be Valid Until 120 Calendar Days After The Bid Submission Deadline Date As Prescribed By The Procuring Entity) 18.1 The Bid Security Shall Be In The Following Amount: 1. The Amount Of 20,989.31 If Bid Security Is In Cash, Cashier’s/manager’s Check, Bank Draft/guarantee Or Irrevocable Letter Of Credit; 2. The Amount Of P52,473.28 If Bid Security Is In Surety Bond; Or 3. Any Combination Of The Foregoing Proportionate To The Share Of Form With Respect To Total Amount Of Security. 18.2 The Bid Security Shall Be Valid Twenty Eight Days Beyond The Validity Period Of The Bid. 20.3 Each Bidder Shall Submit One Original And One Copy Of The First And Second Components Of Its Bid. 21 The Address For Submission Of Bids Is Ma. Teresa L. Minguez Lgu-bac Chairperson Bac Office @ Mpdo, 1st Floor, New Municipal Bldg. Municipality Of Mapanas, Northern Samar The Deadline For Submission Of Bids Is 9:00 A.m. On November 26, 2024. 22 The Place Of Bid Opening Is Executive Conference Room, 2nd Floor, New Municipal Bldg. Municipality Of Mapanas, Northern Samar. The Date And Time Of Bid Opening Is November 26, 2024 At Exactly 10:00 A.m. 24.2 No Further Instructions. 27.3(b) Bid Modification Is Not Allowed. 27.4 No Further Instructions. 28.2(b) Bidders Have Option To Submit Manually Filed Tax Returns Or Tax Returns Filed Through The Electronic Filing And Payments System (efps). Note: The Latest Income And Business Tax Returns Are Those Within The Last Six Months Preceding The Date Of Bid Submission. 28.2(d) List Licenses And Permits Relevant To The Project And The Corresponding Law Requiring It. 1. Taxpayer’s Identification Number 2. Vat Registration 3. Philippine Contractors Accreditation Board (pcab) License The Requirements Are Applicable Only In A Case Where The Lowest Calculated Bid (lcb) Is Submitted By A Domestic Bidder, And If The Lowest Calculated Bid (lcb) Is Submitted By A Foreign Bidder, This Requirements Are Not Applicable 31.4(g) List Additional Contract Documents Relevant To The Project That May Be Required By Existing Laws And/or The Procuring Entity, Such As Construction Schedule And S-curve, Manpower Schedule, Construction Methods, Equipment Utilization Schedule, Construction Safety And Health Program Approved By The Department Of Labor And Employment, And Pert/cpm. 32.2 The Performance Security Shall Be In The Following Amount: 1. The Amount Of 10% Of Contract If Performance Security Is In Cash, Cashier’s/manager’s Check, Bank Draft/guarantee Or Irrevocable Letter Of Credit; 2. The Amount Of 30% Of Contract If Performance Security Is In Surety Bond; Or 3. Any Combination Of The Foregoing Proportionate To The Share Of Form With Respect To Total Amount Of Security. Section Iv. General Conditions Of Contract Table Of Contents 1. Definitions 41 2. Interpretation 43 3. Governing Language And Law 43 4. Communications 43 5. Possession Of Site 43 6. The Contractor’s Obligations 44 7. Performance Security 45 8. Subcontracting 46 9. Liquidated Damages 46 10. Site Investigation Reports 47 11. The Procuring Entity, Licenses And Permits 47 12. Contractor’s Risk And Warranty Security 47 13. Liability Of The Contractor 49 14. Procuring Entity’s Risk 49 15. Insurance 49 16. Termination For Default Of Contractor 51 17. Termination For Default Of Procuring Entity 51 18. Termination For Other Causes 52 19. Procedures For Termination Of Contracts 53 20. Force Majeure, Release From Performance 56 21. Resolution Of Disputes 56 22. Suspension Of Loan, Credit, Grant, Or Appropriation 57 23. Procuring Entity’s Representative’s Decisions 57 24. Approval Of Drawings And Temporary Works By The Procuring Entity’s Representative 57 25. Acceleration And Delays Ordered By The Procuring Entity’s Representative 58 26. Extension Of The Intended Completion Date 58 27. Right To Vary 58 28. Contractors Right To Claim 59 29. Dayworks 59 30. Early Warning 59 31. Program Of Work 59 32. Management Conferences 60 33. Bill Of Quantities 60 34. Instructions, Inspections And Audits 61 35. Identifying Defects 61 36. Cost Of Repairs 61 37. Correction Of Defects 61 38. Uncorrected Defects 62 39. Advance Payment 62 40. Progress Payments 62 41. Payment Certificates 63 42. Retention 63 43. Variation Orders 64 44. Contract Completion 66 45. Suspension Of Work 66 46. Payment On Termination 67 47. Extension Of Contract Time 67 48. Price Adjustment 68 49. Completion 68 50. Taking Over 69 51. Operating And Maintenance Manuals 69 1. Definitions For Purposes Of This Clause, Boldface Type Is Used To Identify Defined Terms. 1.1. The Arbiter Is The Person Appointed Jointly By The Procuring Entity And The Contractor To Resolve Disputes In The First Instance, As Provided For In Gcc Clause 21. 1.2. Bill Of Quantities Refers To A List Of The Specific Items Of The Work And Their Corresponding Unit Prices, Lump Sums, And/or Provisional Sums. 1.3. The Completion Date Is The Date Of Completion Of The Works As Certified By The Procuring Entity’s Representative, In Accordance With Gcc Clause 49. 1.4. The Contract Is The Contract Between The Procuring Entity And The Contractor To Execute, Complete, And Maintain The Works. 1.5. The Contract Price Is The Price Stated In The Letter Of Acceptance And Thereafter To Be Paid By The Procuring Entity To The Contractor For The Execution Of The Works In Accordance With This Contract. 1.6. Contract Time Extension Is The Allowable Period For The Contractor To Complete The Works In Addition To The Original Completion Date Stated In This Contract. 1.7. The Contractor Is The Juridical Entity Whose Proposal Has Been Accepted By The Procuring Entity And To Whom The Contract To Execute The Work Was Awarded. 1.8. The Contractor’s Bid Is The Signed Offer Or Proposal Submitted By The Contractor To The Procuring Entity In Response To The Bidding Documents. 1.9. Days Are Calendar Days; Months Are Calendar Months. 1.10. Dayworks Are Varied Work Inputs Subject To Payment On A Time Basis For The Contractor’s Employees And Equipment, In Addition To Payments For Associated Materials And Plant. 1.11. A Defect Is Any Part Of The Works Not Completed In Accordance With The Contract. 1.12. The Defects Liability Certificate Is The Certificate Issued By Procuring Entity’s Representative Upon Correction Of Defects By The Contractor. 1.13. The Defects Liability Period Is The One Year Period Between Contract Completion And Final Acceptance Within Which The Contractor Assumes The Responsibility To Undertake The Repair Of Any Damage To The Works At His Own Expense. 1.14. Drawings Are Graphical Presentations Of The Works. They Include All Supplementary Details, Shop Drawings, Calculations, And Other Information Provided Or Approved For The Execution Of This Contract. 1.15. Equipment Refers To All Facilities, Supplies, Appliances, Materials Or Things Required For The Execution And Completion Of The Work Provided By The Contractor And Which Shall Not Form Or Are Not Intended To Form Part Of The Permanent Works. 1.16. The Intended Completion Date Refers To The Date Specified In The Scc When The Contractor Is Expected To Have Completed The Works. The Intended Completion Date May Be Revised Only By The Procuring Entity’s Representative By Issuing An Extension Of Time Or An Acceleration Order. 1.17. Materials Are All Supplies, Including Consumables, Used By The Contractor For Incorporation In The Works. 1.18. The Notice To Proceed Is A Written Notice Issued By The Procuring Entity Or The Procuring Entity’s Representative To The Contractor Requiring The Latter To Begin The Commencement Of The Work Not Later Than A Specified Or Determinable Date. 1.19. Permanent Works All Permanent Structures And All Other Project Features And Facilities Required To Be Constructed And Completed In Accordance With This Contract Which Shall Be Delivered To The Procuring Entity And Which Shall Remain At The Site After The Removal Of All Temporary Works. 1.20. Plant Refers To The Machinery, Apparatus, And The Like Intended To Form An Integral Part Of The Permanent Works. 1.21. The Procuring Entity Is The Party Who Employs The Contractor To Carry Out The Works Stated In The Scc. 1.22. The Procuring Entity’s Representative Refers To The Head Of The Procuring Entity Or His Duly Authorized Representative, Identified In The Scc, Who Shall Be Responsible For Supervising The Execution Of The Works And Administering This Contract. 1.23. The Site Is The Place Provided By The Procuring Entity Where The Works Shall Be Executed And Any Other Place Or Places Which May Be Designated In The Scc, Or Notified To The Contractor By The Procuring Entity’s Representative As Forming Part Of The Site. 1.24. Site Investigation Reports Are Those That Were Included In The Bidding Documents And Are Factual And Interpretative Reports About The Surface And Subsurface Conditions At The Site. 1.25. Slippage Is A Delay In Work Execution Occurring When Actual Accomplishment Falls Below The Target As Measured By The Difference Between The Scheduled And Actual Accomplishment Of The Work By The Contractor As Established From The Work Schedule. This Is Actually Described As A Percentage Of The Whole Works. 1.26. Specifications Means The Description Of Works To Be Done And The Qualities Of Materials To Be Used, The Equipment To Be Installed And The Mode Of Construction. 1.27. The Start Date, As Specified In The Scc, Is The Date When The Contractor Is Obliged To Commence Execution Of The Works. It Does Not Necessarily Coincide With Any Of The Site Possession Dates. 1.28. A Subcontractor Is Any Person Or Organization To Whom A Part Of The Works Has Been Subcontracted By The Contractor, As Allowed By The Procuring Entity, But Not Any Assignee Of Such Person. 1.29. Temporary Works Are Works Designed, Constructed, Installed, And Removed By The Contractor That Are Needed For Construction Or Installation Of The Permanent Works. 1.30. Work(s)refer To The Permanent Works And Temporary Works To Be Executed By The Contractor In Accordance With This Contract, Including (i) The Furnishing Of All Labor, Materials, Equipment And Others Incidental, Necessary Or Convenient To The Complete Execution Of The Works; (ii) The Passing Of Any Tests Before Acceptance By The Procuring Entity’s Representative; (iii) And The Carrying Out Of All Duties And Obligations Of The Contractor Imposed By This Contract As Described In The Scc. 2. Interpretation 2.1. In Interpreting The Conditions Of Contract, Singular Also Means Plural, Male Also Means Female Or Neuter, And The Other Way Around. Headings Have No Significance. Words Have Their Normal Meaning Under The Language Of This Contract Unless Specifically Defined. The Procuring Entity’s Representative Will Provide Instructions Clarifying Queries About The Conditions Of Contract. 2.2. If Sectional Completion Is Specified In The Scc, References In The Conditions Of Contract To The Works, The Completion Date, And The Intended Completion Date Apply To Any Section Of The Works (other Than References To The Completion Date And Intended Completion Date For The Whole Of The Works). 3. Governing Language And Law 3.1. This Contract Has Been Executed In The English Language, Which Shall Be The Binding And Controlling Language For All Matters Relating To The Meaning Or Interpretation Of This Contract. All Correspondence And Other Documents Pertaining To This Contract Which Are Exchanged By The Parties Shall Be Written In English. 3.2. This Contract Shall Be Interpreted In Accordance With The Laws Of The Republic Of The Philippines. 4. Communications Communications Between Parties That Are Referred To In The Conditions Shall Be Effective Only When In Writing. A Notice Shall Be Effective Only When It Is Received By The Concerned Party. 5. Possession Of Site 5.1. On The Date Specified In The Scc, The Procuring Entity Shall Grant The Contractor Possession Of So Much Of The Site As May Be Required To Enable It To Proceed With The Execution Of The Works. If The Contractor Suffers Delay Or Incurs Cost From Failure On The Part Of The Procuring Entity To Give Possession In Accordance With The Terms Of This Clause, The Procuring Entity’s Representative Shall Give The Contractor A Contract Time Extension And Certify Such Sum As Fair To Cover The Cost Incurred, Which Sum Shall Be Paid By Procuring Entity. 5.2. If Possession Of A Portion Is Not Given By The Date Stated In The Scc Clause 5.1, The Procuring Entity Will Be Deemed To Have Delayed The Start Of The Relevant Activities. The Resulting Adjustments In Contact Time To Address Such Delay Shall Be In Accordance With Gcc Clause 47. 5.3. The Contractor Shall Bear All Costs And Charges For Special Or Temporary Right-of-way Required By It In Connection With Access To The Site. The Contractor Shall Also Provide At His Own Cost Any Additional Facilities Outside The Site Required By It For Purposes Of The Works. 5.4. The Contractor Shall Allow The Procuring Entity’s Representative And Any Person Authorized By The Procuring Entity’s Representative Access To The Site And To Any Place Where Work In Connection With This Contract Is Being Carried Out Or Is Intended To Be Carried Out. 6. The Contractor’s Obligations 6.1. The Contractor Shall Carry Out The Works Properly And In Accordance With This Contract. The Contractor Shall Provide All Supervision, Labor, Materials, Plant And Contractor's Equipment, Which May Be Required. All Materials And Plant On Site Shall Be Deemed To Be The Property Of The Procuring Entity. 6.2. The Contractor Shall Commence Execution Of The Works On The Start Date And Shall Carry Out The Works In Accordance With The Program Of Work Submitted By The Contractor, As Updated With The Approval Of The Procuring Entity’s Representative, And Complete Them By The Intended Completion Date. 6.3. The Contractor Shall Be Responsible For The Safety Of All Activities On The Site. 6.4. The Contractor Shall Carry Out All Instructions Of The Procuring Entity’s Representative That Comply With The Applicable Laws Where The Site Is Located. 6.5. The Contractor Shall Employ The Key Personnel Named In The Schedule Of Key Personnel, As Referred To In The Scc, To Carry Out The Supervision Of The Works. The Procuring Entity Will Approve Any Proposed Replacement Of Key Personnel Only If Their Relevant Qualifications And Abilities Are Equal To Or Better Than Those Of The Personnel Listed In The Schedule. 6.6. If The Procuring Entity’s Representative Asks The Contractor To Remove A Member Of The Contractor’s Staff Or Work Force, For Justifiable Cause, The Contractor Shall Ensure That The Person Leaves The Site Within Seven (7) Days And Has No Further Connection With The Work In This Contract. 6.7. During Contract Implementation, The Contractor And His Subcontractors Shall Abide At All Times By All Labor Laws, Including Child Labor Related Enactments, And Other Relevant Rules. 6.8. The Contractor Shall Submit To The Procuring Entity For Consent The Name And Particulars Of The Person Authorized To Receive Instructions On Behalf Of The Contractor. 6.9. The Contractor Shall Cooperate And Share The Site With Other Contractors, Public Authorities, Utilities, And The Procuring Entity Between The Dates Given In The Schedule Of Other Contractors Particularly When They Shall Require Access To The Site. The Contractor Shall Also Provide Facilities And Services For Them During This Period. The Procuring Entity May Modify The Schedule Of Other Contractors, And Shall Notify The Contractor Of Any Such Modification Thereto. 6.10. Should Anything Of Historical Or Other Interest Or Of Significant Value Be Unexpectedly Discovered On The Site, It Shall Be The Property Of The Procuring Entity. The Contractor Shall Notify The Procuring Entity’s Representative Of Such Discoveries And Carry Out The Procuring Entity’s Representative’s Instructions In Dealing With Them. 7. Performance Security 7.1. Within Ten (10) Calendar Days From Receipt Of The Notice Of Award From The Procuring Entity But In No Case Later Than The Signing Of The Contract By Both Parties, The Contractor Shall Furnish The Performance Security In Any The Forms Prescribed In Itb Clause 32.2. 7.2. The Performance Security Posted In Favor Of The Procuring Entity Shall Be Forfeited In The Event It Is Established That The Contractor Is In Default In Any Of Its Obligations Under The Contract. 7.3. The Performance Security Shall Remain Valid Until Issuance By The Procuring Entity Of The Certificate Of Final Acceptance. 7.4. The Performance Security May Be Released By The Procuring Entity And Returned To The Contractor After The Issuance Of The Certificate Of Final Acceptance Subject To The Following Conditions: (a) There Are No Pending Claims Against The Contractor Or The Surety Company Filed By The Procuring Entity; (b) The Contractor Has No Pending Claims For Labor And Materials Filed Against It; And (c) Other Terms Specified In The Scc. 7.5. The Contractor Shall Post An Additional Performance Security Following The Amount And Form Specified In Itb Clause 32.2 To Cover Any Cumulative Increase Of More Than Ten Percent (10%) Over The Original Value Of The Contract As A Result Of Amendments To Order Or Change Orders, Extra Work Orders And Supplemental Agreements, As The Case May Be. The Contractor Shall Cause The Extension Of The Validity Of The Performance Security To Cover Approved Contract Time Extensions. 7.6. In Case Of A Reduction In The Contract Value Or For Partially Completed Works Under The Contract Which Are Usable And Accepted By The Procuring Entity The Use Of Which, In The Judgment Of The Implementing Agency Or The Procuring Entity, Will Not Affect The Structural Integrity Of The Entire Project, The Procuring Entity Shall Allow A Proportional Reduction In The Original Performance Security, Provided That Any Such Reduction Is More Than Ten Percent (10%) And That The Aggregate Of Such Reductions Is Not More Than Fifty Percent (50%) Of The Original Performance Security. 7.7. Unless Otherwise Indicated In The Scc, The Contractor, By Entering Into The Contract With The Procuring Entity, Acknowledges The Right Of The Procuring Entity To Institute Action Pursuant To Act 3688 Against Any Subcontractor Be They An Individual, Firm, Partnership, Corporation, Or Association Supplying The Contractor With Labor, Materials And/or Equipment For The Performance Of This Contract. 8. Subcontracting 8.1. Unless Otherwise Indicated In The Scc, The Contractor Cannot Subcontract Works More Than The Percentage Specified In Itb Clause 8.1. 8.2. Subcontracting Of Any Portion Of The Works Does Not Relieve The Contractor Of Any Liability Or Obligation Under This Contract. The Contractor Will Be Responsible For The Acts, Defaults, And Negligence Of Any Subcontractor, Its Agents, Servants Or Workmen As Fully As If These Were The Contractor’s Own Acts, Defaults, Or Negligence, Or Those Of Its Agents, Servants Or Workmen. 8.3. Subcontractors Disclosed And Identified During The Bidding May Be Changed During The Implementation Of This Contract, Subject To Compliance With The Required Qualifications And The Approval Of The Procuring Entity. 9. Liquidated Damages 9.1. The Contractor Shall Pay Liquidated Damages To The Procuring Entity For Each Day That The Completion Date Is Later Than The Intended Completion Date. The Applicable Liquidated Damages Is At Least One-tenth (1/10) Of A Percent Of The Cost Of The Unperformed Portion For Every Day Of Delay. The Total Amount Of Liquidated Damages Shall Not Exceed Ten Percent (10%) Of The Amount Of The Contract. The Procuring Entity May Deduct Liquidated Damages From Payments Due To The Contractor. Payment Of Liquidated Damages Shall Not Affect The Contractor. Once The Cumulative Amount Of Liquidated Damages Reaches Ten Percent (10%) Of The Amount Of This Contract, The Procuring Entity Shall Rescind This Contract, Without Prejudice To Other Courses Of Action And Remedies Open To It. 9.2. If The Intended Completion Date Is Extended After Liquidated Damages Have Been Paid, The Engineer Of The Procuring Entity Shall Correct Any Overpayment Of Liquidated Damages By The Contractor By Adjusting The Next Payment Certificate. The Contractor Shall Be Paid Interest On The Overpayment, Calculated From The Date Of Payment To The Date Of Repayment, At The Rates Specified In Gcc Clause 40.3. 10. Site Investigation Reports The Contractor, In Preparing The Bid, Shall Rely On Any Site Investigation Reports Referred To In The Scc Supplemented By Any Information Obtained By The Contractor. 11. The Procuring Entity, Licenses And Permits The Procuring Entity Shall, If Requested By The Contractor, Assist Him In Applying For Permits, Licenses Or Approvals, Which Are Required For The Works. 12. Contractor’s Risk And Warranty Security 12.1. The Contractor Shall Assume Full Responsibility For The Works From The Time Project Construction Commenced Up To Final Acceptance By The Procuring Entity And Shall Be Held Responsible For Any Damage Or Destruction Of The Works Except Those Occasioned By Force Majeure. The Contractor Shall Be Fully Responsible For The Safety, Protection, Security, And Convenience Of His Personnel, Third Parties, And The Public At Large, As Well As The Works, Equipment, Installation, And The Like To Be Affected By His Construction Work. 12.2. The Defects Liability Period For Infrastructure Projects Shall Be One Year From Contract Completion Up To Final Acceptance By The Procuring Entity. During This Period, The Contractor Shall Undertake The Repair Works, At His Own Expense, Of Any Damage To The Works On Account Of The Use Of Materials Of Inferior Quality Within Ninety (90) Days From The Time The Head Of The Procuring Entity Has Issued An Order To Undertake Repair. In Case Of Failure Or Refusal To Comply With This Mandate, The Procuring Entity Shall Undertake Such Repair Works And Shall Be Entitled To Full Reimbursement Of Expenses Incurred Therein Upon Demand. 12.3. Unless Otherwise Indicated In The Scc, In Case The Contractor Fails To Comply With The Preceding Paragraph, The Procuring Entity Shall Forfeit Its Performance Security, Subject Its Property (ies) To Attachment Or Garnishment Proceedings, And Perpetually Disqualify It From Participating In Any Public Bidding. All Payables Of The Gop In His Favor Shall Be Offset To Recover The Costs. 12.4. After Final Acceptance Of The Works By The Procuring Entity, The Contractor Shall Be Held Responsible For “structural Defects”, I.e., Major Faults/flaws/deficiencies In One Or More Key Structural Elements Of The Project Which May Lead To Structural Failure Of The Completed Elements Or Structure, Or “structural Failures”, I.e., Where One Or More Key Structural Elements In An Infrastructure Facility Fails Or Collapses, Thereby Rendering The Facility Or Part Thereof Incapable Of Withstanding The Design Loads, And/or Endangering The Safety Of The Users Or The General Public: (a) Contractor – Where Structural Defects/failures Arise Due To Faults Attributable To Improper Construction, Use Of Inferior Quality/substandard Materials, And Any Violation Of The Contract Plans And Specifications, The Contractor Shall Be Held Liable; (b) Consultants – Where Structural Defects/failures Arise Due To Faulty And/or Inadequate Design And Specifications As Well As Construction Supervision, Then The Consultant Who Prepared The Design Or Undertook Construction Supervision For The Project Shall Be Held Liable; (c) Procuring Entity’s Representatives/project Manager/construction Managers And Supervisors – The Project Owner’s Representative(s), Project Manager, Construction Manager, And Supervisor(s) Shall Be Held Liable In Cases Where The Structural Defects/failures Are Due To His/their Willful Intervention In Altering The Designs And Other Specifications; Negligence Or Omission In Not Approving Or Acting On Proposed Changes To Noted Defects Or Deficiencies In The Design And/or Specifications; And The Use Of Substandard Construction Materials In The Project; (d) Third Parties - Third Parties Shall Be Held Liable In Cases Where Structural Defects/failures Are Caused By Work Undertaken By Them Such As Leaking Pipes, Diggings Or Excavations, Underground Cables And Electrical Wires, Underground Tunnel, Mining Shaft And The Like, In Which Case The Applicable Warranty To Such Structure Should Be Levied To Third Parties For Their Construction Or Restoration Works. (e) Users - In Cases Where Structural Defects/failures Are Due To Abuse/misuse By The End User Of The Constructed Facility And/or Non–compliance By A User With The Technical Design Limits And/or Intended Purpose Of The Same, Then The User Concerned Shall Be Held Liable. 12.5. The Warranty Against Structural Defects/failures, Except Those Occasioned On Force Majeure, Shall Cover The Period Specified In The Scc Reckoned From The Date Of Issuance Of The Certificate Of Final Acceptance By The Procuring Entity. 12.6. The Contractor Shall Be Required To Put Up A Warranty Security In The Form Of Cash, Bank Guarantee, Letter Of Credit, Gsis Or Surety Bond Callable On Demand, In Accordance With The Following Schedule: Form Of Warranty Minimum Amount In Percentage (%) Of Total Contract Price (a) Cash Or Letter Of Credit Issued By Universal Or Commercial Bank: Provided, However, That The Letter Of Credit Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank Five Percent (5%) (b) Bank Guarantee Confirmed By Universal Or Commercial Bank: Provided, However, That The Letter Of Credit Shall Be Confirmed Or Authenticated By A Universal Or Commercial Bank, If Issued By A Foreign Bank Ten Percent (10%) (c) Surety Bond Callable Upon Demand Issued By Gsis Or Any Surety Or Insurance Company Duly Certified By The Insurance Commission Thirty Percent (30%) 12.7. The Warranty Security Shall Be Stated In Philippine Pesos And Shall Remain Effective For One Year From The Date Of Issuance Of The Certificate Of Final Acceptance By The Procuring Entity, And Returned Only After The Lapse Of Said One Year Period. 12.8. In Case Of Structural Defects/failure Occurring During The Applicable Warranty Period Provided In Gcc Clause 12.5, The Procuring Entity Shall Undertake The Necessary Restoration Or Reconstruction Works And Shall Be Entitled To Full Reimbursement By The Parties Found To Be Liable For Expenses Incurred Therein Upon Demand, Without Prejudice To The Filing Of Appropriate Administrative, Civil, And/or Criminal Charges Against The Responsible Persons As Well As The Forfeiture Of The Warranty Security Posted In Favor Of The Procuring Entity. 13. Liability Of The Contractor Subject To Additional Provisions, If Any, Set Forth In The Scc, The Contractor’s Liability Under This Contract Shall Be As Provided By The Laws Of The Republic Of The Philippines. 14. Procuring Entity’s Risk 14.1. From The Start Date Until The Certificate Of Final Acceptance Has Been Issued, The Following Are Risks Of The Procuring Entity: (a) The Risk Of Personal Injury, Death, Or Loss Of Or Damage To Property (excluding The Works, Plant, Materials, And Equipment), Which Are Due To: (i) Any Type Of Use Or Occupation Of The Site Authorized By The Procuring Entity After The Official Acceptance Of The Works; Or (ii) Negligence, Breach Of Statutory Duty, Or Interference With Any Legal Right By The Procuring Entity Or By Any Person Employed By Or Contracted To Him Except The Contractor. (b) The Risk Of Damage To The Works, Plant, Materials, And Equipment To The Extent That It Is Due To A Fault Of The Procuring Entity Or In The Procuring Entity’s Design, Or Due To War Or Radioactive Contamination Directly Affecting The Country Where The Works Are To Be Executed. 15. Insurance 15.1. The Contractor Shall, Under His Name And At His Own Expense, Obtain And Maintain, For The Duration Of This Contract, The Following Insurance Coverage: (a) Contractor’s All Risk Insurance; (b) Transportation To The Project Site Of Equipment, Machinery, And Supplies Owned By The Contractor; (c) Personal Injury Or Death Of Contractor’s Employees; And (d) Comprehensive Insurance For Third Party Liability To Contractor’s Direct Or Indirect Act Or Omission Causing Damage To Third Persons. 15.2. The Contractor Shall Provide Evidence To The Procuring Entity’s Representative That The Insurances Required Under This Contract Have Been Effected And Shall, Within A Reasonable Time, Provide Copies Of The Insurance Policies To The Procuring Entity’s Representative. Such Evidence And Such Policies Shall Be Provided To The Procuring Entity’s Through The Procuring Entity’s Representative. 15.3. The Contractor Shall Notify The Insurers Of Changes In The Nature, Extent, Or Program For The Execution Of The Works And Ensure The Adequacy Of The Insurances At All Times In Accordance With The Terms Of This Contract And Shall Produce To The Procuring Entity’s Representative The Insurance Policies In Force Including The Receipts For Payment Of The Current Premiums. The Above Insurance Policies Shall Be Obtained From Any Reputable Insurance Company Approved By The Procuring Entity’s Representative. 15.4. If The Contractor Fails To Obtain And Keep In Force The Insurances Referred To Herein Or Any Other Insurance Which He May Be Required To Obtain Under The Terms Of This Contract, The Procuring Entity May Obtain And Keep In Force Any Such Insurances And Pay Such Premiums As May Be Necessary For The Purpose. From Time To Time, The Procuring Entity May Deduct The Amount It Shall Pay For Said Premiums Including Twenty Five Percent (25%) Therein From Any Monies Due, Or Which May Become Due, To The Contractor, Without Prejudice To The Procuring Entity Exercising Its Right To Impose Other Sanctions Against The Contractor Pursuant To The Provisions Of This Contract. 15.5. In The Event The Contractor Fails To Observe The Above Safeguards, The Procuring Entity May, At The Contractor’s Expense, Take Whatever Measure Is Deemed Necessary For Its Protection And That Of The Contractor’s Personnel And Third Parties, And/or Order The Interruption Of Dangerous Works. In Addition, The Procuring Entity May Refuse To Make The Payments Under Gcc Clause 40 Until The Contractor Complies With This Clause. 15.6. The Contractor Shall Immediately Replace The Insurance Policy Obtained As Required In This Contract, Without Need Of The Procuring Entity’s Demand, With A New Policy Issued By A New Insurance Company Acceptable To The Procuring Entity For Any Of The Following Grounds: (a) The Issuer Of The Insurance Policy To Be Replaced Has: (i) Become Bankrupt; (ii) Been Placed Under Receivership Or Under A Management Committee; (iii) Been Sued For Suspension Of Payment; Or (iv) Been Suspended By The Insurance Commission And Its License To Engage In Business Or Its Authority To Issue Insurance Policies Cancelled; Or (v) Where Reasonable Grounds Exist That The Insurer May Not Be Able, Fully And Promptly, To Fulfill Its Obligation Under The Insurance Policy. 16. Termination For Default Of Contractor 16.1. The Procuring Entity Shall Terminate This Contract For Default When Any Of The Following Conditions Attend Its Implementation: 16.2. Due To The Contractor’s Fault And While The Project Is On-going, It Has Incurred Negative Slippage Of Fifteen Percent (15%) Or More In Accordance With Presidential Decree 1870, Regardless Of Whether Or Not Previous Warnings And Notices Have Been Issued For The Contractor To Improve His Performance; 16.3. Due To Its Own Fault And After This Contract Time Has Expired, The Contractor Incurs Delay In The Completion Of The Work After This Contract Has Expired; Or 16.4. The Contractor: (a) Abandons The Contract Works, Refuses Or Fails To Comply With A Valid Instruction Of The Procuring Entity Or Fails To Proceed Expeditiously And Without Delay Despite A Written Notice By The Procuring Entity; (b) Does Not Actually Have On The Project Site The Minimum Essential Equipment Listed On The Bid Necessary To Prosecute The Works In Accordance With The Approved Program Of Work And Equipment Deployment Schedule As Required For The Project; (c) Does Not Execute The Works In Accordance With This Contract Or Persistently Or Flagrantly Neglects To Carry Out Its Obligations Under This Contract; (d) Neglects Or Refuses To Remove Materials Or To Perform A New Work That Has Been Rejected As Defective Or Unsuitable; Or (e) Sub-lets Any Part Of This Contract Without Approval By The Procuring Entity. 16.5. All Materials On The Site, Plant, Equipment, And Works Shall Be Deemed To Be The Property Of The Procuring Entity If This Contract Is Rescinded Because Of The Contractor’s Default. 17. Termination For Default Of Procuring Entity The Contractor May Terminate This Contract With The Procuring Entity If The Works Are Completely Stopped For A Continuous Period Of At Least Sixty (60) Calendar Days Through No Fault Of Its Own, Due To Any Of The Following Reasons: (a) Failure Of The Procuring Entity To Deliver, Within A Reasonable Time, Supplies, Materials, Right-of-way, Or Other Items It Is Obligated To Furnish Under The Terms Of This Contract; Or (b) The Prosecution Of The Work Is Disrupted By The Adverse Peace And Order Situation, As Certified By The Armed Forces Of The Philippines Provincial Commander And Approved By The Secretary Of National Defense. 18. Termination For Other Causes 18.1. The Procuring Entity May Terminate This Contract, In Whole Or In Part, At Any Time For Its Convenience. The Head Of The Procuring Entity May Terminate This Contract For The Convenience Of The Procuring Entity If He Has Determined The Existence Of Conditions That Make Project Implementation Economically, Financially Or Technically Impractical And/or Unnecessary, Such As, But Not Limited To, Fortuitous Event(s) Or Changes In Law And National Government Policies. 18.2. The Procuring Entity Or The Contractor May Terminate This Contract If The Other Party Causes A Fundamental Breach Of This Contract. 18.3. Fundamental Breaches Of Contract Shall Include, But Shall Not Be Limited To, The Following: (a) The Contractor Stops Work For Twenty Eight (28) Days When No Stoppage Of Work Is Shown On The Current Program Of Work And The Stoppage Has Not Been Authorized By The Procuring Entity’s Representative; (b) The Procuring Entity’s Representative Instructs The Contractor To Delay The Progress Of The Works, And The Instruction Is Not Withdrawn Within Twenty Eight (28) Days; (c) The Procuring Entity Shall Terminate This Contract If The Contractor Is Declared Bankrupt Or Insolvent As Determined With Finality By A Court Of Competent Jurisdiction. In This Event, Termination Will Be Without Compensation To The Contractor, Provided That Such Termination Will Not Prejudice Or Affect Any Right Of Action Or Remedy Which Has Accrued Or Will Accrue Thereafter To The Procuring Entity And/or The Contractor. In The Case Of The Contractor's Insolvency, Any Contractor's Equipment Which The Procuring Entity Instructs In The Notice Is To Be Used Until The Completion Of The Works; (d) A Payment Certified By The Procuring Entity’s Representative Is Not Paid By The Procuring Entity To The Contractor Within Eighty Four (84) Days From The Date Of The Procuring Entity’s Representative’s Certificate; (e) The Procuring Entity’s Representative Gives Notice That Failure To Correct A Particular Defect Is A Fundamental Breach Of Contract And The Contractor Fails To Correct It Within A Reasonable Period Of Time Determined By The Procuring Entity’s Representative; (f) The Contractor Does Not Maintain A Security, Which Is Required; (g) The Contractor Has Delayed The Completion Of The Works By The Number Of Days For Which The Maximum Amount Of Liquidated Damages Can Be Paid, As Defined In The Gcc Clause 9; And (h) In Case It Is Determined Prima Facie By The Procuring Entity That The Contractor Has Engaged, Before Or During The Implementation Of The Contract, In Unlawful Deeds And Behaviors Relative To Contract Acquisition And Implementation, Such As, But Not Limited To, The Following: (i) Corrupt, Fraudulent, Collusive, Coercive, And Obstructive Practices As Defined In Itb Clause 3.1(a), Unless Otherwise Specified In The Scc; (ii) Drawing Up Or Using Forged Documents; (iii) Using Adulterated Materials, Means Or Methods, Or Engaging In Production Contrary To Rules Of Science Or The Trade; And (iv) Any Other Act Analogous To The Foregoing. 18.4. The Funding Source Or The Procuring Entity, As Appropriate, Will Seek To Impose The Maximum Civil, Administrative And/or Criminal Penalties Available Under The Applicable Law On Individuals And Organizations Deemed To Be Involved With Corrupt, Fraudulent, Or Coercive Practices. 18.5. When Persons From Either Party To This Contract Gives Notice Of A Fundamental Breach To The Procuring Entity’s Representative In Order To Terminate The Existing Contract For A Cause Other Than Those Listed Under Gcc Clause 18.3, The Procuring Entity’s Representative Shall Decide Whether The Breach Is Fundamental Or Not. 18.6. If This Contract Is Terminated, The Contractor Shall Stop Work Immediately, Make The Site Safe And Secure, And Leave The Site As Soon As Reasonably Possible. 19. Procedures For Termination Of Contracts 19.1. The Following Provisions Shall Govern The Procedures For The Termination Of This Contract: (a) Upon Receipt Of A Written Report Of Acts Or Causes Which May Constitute Ground(s) For Termination As Aforementioned, Or Upon Its Own Initiative, The Procuring Entity Shall, Within A Period Of Seven (7) Calendar Days, Verify The Existence Of Such Ground(s) And Cause The Execution Of A Verified Report, With All Relevant Evidence Attached; (b) Upon Recommendation By The Procuring Entity, The Head Of The Procuring Entity Shall Terminate This Contract Only By A Written Notice To The Contractor Conveying The Termination Of This Contract. The Notice Shall State: (i) That This Contract Is Being Terminated For Any Of The Ground(s) Afore-mentioned, And A Statement Of The Acts That Constitute The Ground(s) Constituting The Same; (ii) The Extent Of Termination, Whether In Whole Or In Part; (iii) An Instruction To The Contractor To Show Cause As To Why This Contract Should Not Be Terminated; And (iv) Special Instructions Of The Procuring Entity, If Any. The Notice To Terminate Shall Be Accompanied By A Copy Of The Verified Report; (c) Within A Period Of Seven (7) Calendar Days From Receipt Of The Notice Of Termination, The Contractor Shall Submit To The Head Of The Procuring Entity A Verified Position Paper Stating Why The Contract Should Not Be Terminated. If The Contractor Fails To Show Cause After The Lapse Of The Seven (7) Day Period, Either By Inaction Or By Default, The Head Of The Procuring Entity Shall Issue An Order Terminating The Contract; (d) The Procuring Entity May, At Anytime Before Receipt Of The Bidder’s Verified Position Paper Described In Item (c) Above Withdraw The Notice To Terminate If It Is Determined That Certain Items Or Works Subject Of The Notice Had Been Completed, Delivered, Or Performed Before The Contractor’s Receipt Of The Notice; (e) Within A Non-extendible Period Of Ten (10) Calendar Days From Receipt Of The Verified Position Paper, The Head Of The Procuring Entity Shall Decide Whether Or Not To Terminate This Contract. It Shall Serve A Written Notice To The Contractor Of Its Decision And, Unless Otherwise Provided In The Said Notice, This Contract Is Deemed Terminated From Receipt Of The Contractor Of The Notice Of Decision. The Termination Shall Only Be Based On The Ground(s) Stated In The Notice To Terminate; And (f) The Head Of The Procuring Entity May Create A Contract Termination Review Committee (ctrc) To Assist Him In The Discharge Of This Function. All Decisions Recommended By The Ctrc Shall Be Subject To The Approval Of The Head Of The Procuring Entity. 19.2. Pursuant To Section 69(f) Of Ra 9184 And Without Prejudice To The Imposition Of Additional Administrative Sanctions As The Internal Rules Of The Agency May Provide And/or Further Criminal Prosecution As Provided By Applicable Laws, The Procuring Entity Shall Impose On Contractors After The Termination Of The Contract The Penalty Of Suspension For One (1) Year For The First Offense, Suspension For Two (2) Years For The Second Offense From Participating In The Public Bidding Process, For Violations Committed During The Contract Implementation Stage, Which Include But Not Limited To The Following: (a) Failure Of The Contractor, Due Solely To His Fault Or Negligence, To Mobilize And Start Work Or Performance Within The Specified Period In The Notice To Proceed (“ntp”); (b) Failure By The Contractor To Fully And Faithfully Comply With Its Contractual Obligations Without Valid Cause, Or Failure By The Contractor To Comply With Any Written Lawful Instruction Of The Procuring Entity Or Its Representative(s) Pursuant To The Implementation Of The Contract. For The Procurement Of Infrastructure Projects Or Consultancy Contracts, Lawful Instructions Include But Are Not Limited To The Following: (i) Employment Of Competent Technical Personnel, Competent Engineers And/or Work Supervisors; (ii) Provision Of Warning Signs And Barricades In Accordance With Approved Plans And Specifications And Contract Provisions; (iii) Stockpiling In Proper Places Of All Materials And Removal From The Project Site Of Waste And Excess Materials, Including Broken Pavement And Excavated Debris In Accordance With Approved Plans And Specifications And Contract Provisions; (iv) Deployment Of Committed Equipment, Facilities, Support Staff And Manpower; And (v) Renewal Of The Effectivity Dates Of The Performance Security After Its Expiration During The Course Of Contract Implementation. (c) Assignment And Subcontracting Of The Contract Or Any Part Thereof Or Substitution Of Key Personnel Named In The Proposal Without Prior Written Approval By The Procuring Entity. (d) Poor Performance By The Contractor Or Unsatisfactory Quality And/or Progress Of Work Arising From His Fault Or Negligence As Reflected In The Constructor's Performance Evaluation System (“cpes”) Rating Sheet. In The Absence Of The Cpes Rating Sheet, The Existing Performance Monitoring System Of The Procuring Entity Shall Be Applied. Any Of The Following Acts By The Contractor Shall Be Construed As Poor Performance: (i) Negative Slippage Of 15% And Above Within The Critical Path Of The Project Due Entirely To The Fault Or Negligence Of The Contractor; And (ii) Quality Of Materials And Workmanship Not Complying With The Approved Specifications Arising From The Contractor's Fault Or Negligence. (e) Willful Or Deliberate Abandonment Or Non-performance Of The Project Or Contract By The Contractor Resulting To Substantial Breach Thereof Without Lawful And/or Just Cause. In Addition To The Penalty Of Suspension, The Performance Security Posted By The Contractor Shall Also Be Forfeited. 20. Force Majeure, Release From Performance 20.1. For Purposes Of This Contract The Terms “force Majeure” And “fortuitous Event” May Be Used Interchangeably. In This Regard, A Fortuitous Event Or Force Majeure Shall Be Interpreted To Mean An Event Which The Contractor Could Not Have Foreseen, Or Which Though Foreseen, Was Inevitable. It Shall Not Include Ordinary Unfavorable Weather Conditions; And Any Other Cause The Effects Of Which Could Have Been Avoided With The Exercise Of Reasonable Diligence By The Contractor. 20.2. If This Contract Is Discontinued By An Outbreak Of War Or By Any Other Event Entirely Outside The Control Of Either The Procuring Entity Or The Contractor, The Procuring Entity’s Representative Shall Certify That This Contract Has Been Discontinued. The Contractor Shall Make The Site Safe And Stop Work As Quickly As Possible After Receiving This Certificate And Shall Be Paid For All Works Carried Out Before Receiving It And For Any Work Carried Out Afterwards To Which A Commitment Was Made. 20.3. If The Event Continues For A Period Of Eighty Four (84) Days, Either Party May Then Give Notice Of Termination, Which Shall Take Effect Twenty Eight (28) Days After The Giving Of The Notice. 20.4. After Termination, The Contractor Shall Be Entitled To Payment Of The Unpaid Balance Of The Value Of The Works Executed And Of The Materials And Plant Reasonably Delivered To The Site, Adjusted By The Following: (a) Any Sum To Which The Contractor Is Entitled Under Gcc Clause 28; (b) The Cost Of His Suspension And Demobilization; (c) Any Sum To Which The Procuring Entity Is Entitled. 20.5. The Net Balance Due Shall Be Paid Or Repaid Within A Reasonable Time Period From The Time Of The Notice Of Termination. 21. Resolution Of Disputes 21.1. If Any Dispute Or Difference Of Any Kind Whatsoever Shall Arise Between The Parties In Connection With The Implementation Of The Contract Covered By The Act And This Irr, The Parties Shall Make Every Effort To Resolve Amicably Such Dispute Or Difference By Mutual Consultation. 21.2. If The Contractor Believes That A Decision Taken By The Procuring Entity’s Representative Was Either Outside The Authority Given To The Procuring Entity’s Representative By This Contract Or That The Decision Was Wrongly Taken, The Decision Shall Be Referred To The Arbiter Indicated In The Scc Within Fourteen (14) Days Of The Notification Of The Procuring Entity’s Representative’s Decision. 21.3. Any And All Disputes Arising From The Implementation Of This Contract Covered By The R.a. 9184 And Its Irr Shall Be Submitted To Arbitration In The Philippines According To The Provisions Of Republic Act No. 876, Otherwise Known As The “ Arbitration Law” And Republic Act 9285, Otherwise Known As The “alternative Dispute Resolution Act Of 2004”: Provided, However, That, Disputes That Are Within The Competence Of The Construction Industry Arbitration Commission To Resolve Shall Be Referred Thereto. The Process Of Arbitration Shall Be Incorporated As A Provision In This Contract That Will Be Executed Pursuant To The Provisions Of The Act And Its Irr: Provided, Further, That, By Mutual Agreement, The Parties May Agree In Writing To Resort To Other Alternative Modes Of Dispute Resolution. 22. Suspension Of Loan, Credit, Grant, Or Appropriation In The Event That The Funding Source Suspends The Loan, Credit, Grant, Or Appropriation To The Procuring Entity, From Which Part Of The Payments To The Contractor Are Being Made: (a) The Procuring Entity Is Obligated To Notify The Contractor Of Such Suspension Within Seven (7) Days Of Having Received The Suspension Notice. (b) If The Contractor Has Not Received Sums Due It For Work Already Done Within Forty Five (45) Days From The Time The Contractor’s Claim For Payment Has Been Certified By The Procuring Entity’s Representative, The Contractor May Immediately Issue A Suspension Of Work Notice In Accordance With Gcc Clause 45.2. 23. Procuring Entity’s Representative’s Decisions 23.1. Except Where Otherwise Specifically Stated, The Procuring Entity’s Representative Will Decide Contractual Matters Between The Procuring Entity And The Contractor In The Role Representing The Procuring Entity. 23.2. The Procuring Entity’s Representative May Delegate Any Of His Duties And Responsibilities To Other People, Except To The Arbiter, After Notifying The Contractor, And May Cancel Any Delegation After Notifying The Contractor. 24. Approval Of Drawings And Temporary Works By The Procuring Entity’s Representative 24.1. All Drawings Prepared By The Contractor For The Execution Of The Temporary Works, Are Subject To Prior Approval By The Procuring Entity’s Representative Before Its Use. 24.2. The Contractor Shall Be Responsible For Design Of Temporary Works. 24.3. The Procuring Entity’s Representative’s Approval Shall Not Alter The Contractor’s Responsibility For Design Of The Temporary Works. 24.4. The Contractor Shall Obtain Approval Of Third Parties To The Design Of The Temporary Works, When Required By The Procuring Entity. 25. Acceleration And Delays Ordered By The Procuring Entity’s Representative 25.1. When The Procuring Entity Wants The Contractor To Finish Before The Intended Completion Date, The Procuring Entity’s Representative Will Obtain Priced Proposals For Achieving The Necessary Acceleration From The Contractor. If The Procuring Entity Accepts These Proposals, The Intended Completion Date Will Be Adjusted Accordingly And Confirmed By Both The Procuring Entity And The Contractor. 25.2. If The Contractor’s Financial Proposals For An Acceleration Are Accepted By The Procuring Entity, They Are Incorporated In The Contract Price And Treated As A Variation. 26. Extension Of The Intended Completion Date 26.1. The Procuring Entity’s Representative Shall Extend The Intended Completion Date If A Variation Is Issued Which Makes It Impossible For The Intended Completion Date To Be Achieved By The Contractor Without Taking Steps To Accelerate The Remaining Work, Which Would Cause The Contractor To Incur Additional Costs. No Payment Shall Be Made For Any Event Which May Warrant The Extension Of The Intended Completion Date. 26.2. The Procuring Entity’s Representative Shall Decide Whether And By How Much To Extend The Intended Completion Date Within Twenty One (21) Days Of The Contractor Asking The Procuring Entity’s Representative For A Decision Thereto After Fully Submitting All Supporting Information. If The Contractor Has Failed To Give Early Warning Of A Delay Or Has Failed To Cooperate In Dealing With A Delay, The Delay By This Failure Shall Not Be Considered In Assessing The New Intended Completion Date. 27. Right To Vary 27.1. The Procuring Entity’s Representative With The Prior Approval Of The Procuring Entity May Instruct Variations, Up To A Maximum Cumulative Amount Of Ten Percent (10%) Of The Original Contract Cost. 27.2. Variations Shall Be Valued As Follows: (a) At A Lump Sum Price Agreed Between The Parties; (b) Where Appropriate, At Rates In This Contract; (c) In The Absence Of Appropriate Rates, The Rates In This Contract Shall Be Used As The Basis For Valuation; Or Failing Which (d) At Appropriate New Rates, Equal To Or Lower Than Current Industry Rates And To Be Agreed Upon By Both Parties And Approved By The Head Of The Procuring Entity. 28. Contractor's Right To Claim If The Contractor Incurs Cost As A Result Of Any Of The Events Under Gcc Clause 13, The Contractor Shall Be Entitled To The Amount Of Such Cost. If As A Result Of Any Of The Said Events, It Is Necessary To Change The Works, This Shall Be Dealt With As A Variation. 29. Dayworks 29.1. Subject To Gcc Clause 43 On Variation Order, And If Applicable As Indicated In The Scc, The Day Works Rates In The Contractor’s Bid Shall Be Used For Small Additional Amounts Of Work Only When The Procuring Entity’s Representative Has Given Written Instructions In Advance For Additional Work To Be Paid For In That Way. 29.2. All Work To Be Paid For As Day Works Shall Be Recorded By The Contractor On Forms Approved By The Procuring Entity’s Representative. Each Completed Form Shall Be Verified And Signed By The Procuring Entity’s Representative Within Two Days Of The Work Being Done. 29.3. The Contractor Shall Be Paid For Day Works Subject To Obtaining Signed Dayworks Forms. 30. Early Warning 30.1. The Contractor Shall Warn The Procuring Entity’s Representative At The Earliest Opportunity Of Specific Likely Future Events Or Circumstances That May Adversely Affect The Quality Of The Work, Increase The Contract Price, Or Delay The Execution Of The Works. The Procuring Entity’s Representative May Require The Contractor To Provide An Estimate Of The Expected Effect Of The Future Event Or Circumstance On The Contract Price And Completion Date. The Estimate Shall Be Provided By The Contractor As Soon As Reasonably Possible. 30.2. The Contractor Shall Cooperate With The Procuring Entity’s Representative In Making And Considering Proposals For How The Effect Of Such An Event Or Circumstance Can Be Avoided Or Reduced By Anyone Involved In The Work And In Carrying Out Any Resulting Instruction Of The Procuring Entity’s Representative. 31. Program Of Work 31.1. Within The Time Stated In The Scc, The Contractor Shall Submit To The Procuring Entity’s Representative For Approval A Program Of Work Showing The General Methods, Arrangements, Order, And Timing For All The Activities In The Works. 31.2. An Update Of The Program Of Work Shall The Show The Actual Progress Achieved On Each Activity And The Effect Of The Progress Achieved On The Timing Of The Remaining Work, Including Any Changes To The Sequence Of The Activities. 31.3. The Contractor Shall Submit To The Procuring Entity’s Representative For Approval An Updated Program Of Work At Intervals No Longer Than The Period Stated In The Scc. If The Contractor Does Not Submit An Updated Program Of Work Within This Period, The Procuring Entity’s Representative May Withhold The Amount Stated In The Scc From The Next Payment Certificate And Continue To Withhold This Amount Until The Next Payment After The Date On Which The Overdue Program Of Work Has Been Submitted. 31.4. The Procuring Entity’s Representative’s Approval Of The Program Of Work Shall Not Alter The Contractor’s Obligations. The Contractor May Revise The Program Of Work And Submit It To The Procuring Entity’s Representative Again At Any Time. A Revised Program Of Work Shall Show The Effect Of Any Approved Variations. 31.5. When The Program Of Work Is Updated, The Contractor Shall Provide The Procuring Entity’s Representative With An Updated Cash Flow Forecast. The Cash Flow Forecast Shall Include Different Currencies, As Defined In The Contract, Converted As Necessary Using The Contract Exchange Rates. 31.6. All Variations Shall Be Included In Updated Program Of Work Produced By The Contractor. 32. Management Conferences 32.1. Either The Procuring Entity’s Representative Or The Contractor May Require The Other To Attend A Management Conference. The Management Conference Shall Review The Plans For Remaining Work And Deal With Matters Raised In Accordance With The Early Warning Procedure. 32.2. The Procuring Entity’s Representative Shall Record The Business Of Management Conferences And Provide Copies Of The Record To Those Attending The Conference And To The Procuring Entity . The Responsibility Of The Parties For Actions To Be Taken Shall Be Decided By The Procuring Entity’s Representative Either At The Management Conference Or After The Management Conference And Stated In Writing To All Who Attended The Conference. 33. Bill Of Quantities 33.1. The Bill Of Quantities Shall Contain Items Of Work For The Construction, Installation, Testing, And Commissioning Of Work To Be Done By The Contractor. 33.2. The Bill Of Quantities Is Used To Calculate The Contract Price. The Contractor Is Paid For The Quantity Of The Work Done At The Rate In The Bill Of Quantities For Each Item. 33.3. If The Final Quantity Of Any Work Done Differs From The Quantity In The Bill Of Quantities For The Particular Item And Is Not More Than Twenty Five Percent (25%) Of The Original Quantity, Provided The Aggregate Changes For All Items Do Not Exceed Ten Percent (10%) Of The Contract Price, The Procuring Entity’s Representative Shall Make The Necessary Adjustments To Allow For The Changes Subject To Applicable Laws, Rules, And Regulations. 33.4. If Requested By The Procuring Entity’s Representative, The Contractor Shall Provide The Procuring Entity’s Representative With A Detailed Cost Breakdown Of Any Rate In The Bill Of Quantities. 34. Instructions, Inspections And Audits 34.1. The Procuring Entity’s Personnel Shall At All Reasonable Times During Construction Of The Work Be Entitled To Examine, Inspect, Measure And Test The Materials And Workmanship, And To Check The Progress Of The Construction. 34.2. If The Procuring Entity’s Representative Instructs The Contractor To Carry Out A Test Not Specified In The Specification To Check Whether Any Work Has A Defect And The Test Shows That It Does, The Contractor Shall Pay For The Test And Any Samples. If There Is No Defect, The Test Shall Be A Compensation Event. 34.3. The Contractor Shall Permit The Funding Source Named In The Scc To Inspect The Contractor’s Accounts And Records Relating To The Performance Of The Contractor And To Have Them Audited By Auditors Appointed By The Funding Source, If So Required By The Funding Source. 35. Identifying Defects The Procuring Entity’s Representative Shall Check The Contractor’s Work And Notify The Contractor Of Any Defects That Are Found. Such Checking Shall Not Affect The Contractor’s Responsibilities. The Procuring Entity’s Representative May Instruct The Contractor To Search Uncover Defects And Test Any Work That The Procuring Entity’s Representative Considers Below Standards And Defective. 36. Cost Of Repairs Loss Or Damage To The Works Or Materials To Be Incorporated In The Works Between The Start Date And The End Of The Defects Liability Periods Shall Be Remedied By The Contractor At The Contractor’s Cost If The Loss Or Damage Arises From The Contractor’s Acts Or Omissions. 37. Correction Of Defects 37.1. The Procuring Entity’s Representative Shall Give Notice To The Contractor Of Any Defects Before The End Of The Defects Liability Period, Which Isone (1) Year From Project Completion Up To Final Acceptance By The Procuring Entity’s. 37.2. Every Time Notice Of A Defect Is Given, The Contractor Shall Correct The Notified Defect Within The Length Of Time Specified In The Procuring Entity’s Representative’s Notice. 37.3. The Contractor Shall Correct The Defects Which He Notices Himself Before The End Of The Defects Liability Period. 37.4. The Procuring Entity Shall Certify That All Defects Have Been Corrected. If The Procuring Entity Considers That Correction Of A Defect Is Not Essential, He Can Request The Contractor To Submit A Quotation For The Corresponding Reduction In The Contract Price. If The Procuring Entity Accepts The Quotation, The Corresponding Change In The Scc Is A Variation. 38. Uncorrected Defects 38.1. The Procuring Entity Shall Give The Contractor At Least Fourteen (14) Days Notice Of His Intention To Use A Third Party To Correct A Defect. If The Contractor Does Not Correct The Defect Himself Within The Period, The Procuring Entity May Have The Defect Corrected By The Third Party. The Cost Of The Correction Will Be Deducted From The Contract Price. 38.2. The Use Of A Third Party To Correct Defects That Are Uncorrected By The Contractor Will In No Way Relieve The Contractor Of Its Liabilities And Warranties Under The Contract. 39. Advance Payment 39.1. The Procuring Entity Shall, Upon A Written Request Of The Contractor Which Shall Be Submitted As A Contract Document, Make An Advance Payment To The Contractor In An Amount Not Exceeding Fifteen Percent (15%) Of The Total Contract Price, To Be Made In Lump Sum Or, At The Most Two, Installments According To A Schedule Specified In The Scc. 39.2. The Advance Payment Shall Be Made Only Upon The Submission To And Acceptance By The Procuring Entity Of An Irrevocable Standby Letter Of Credit Of Equivalent Value From A Commercial Bank, A Bank Guarantee Or A Surety Bond Callable Upon Demand, Issued By A Surety Or Insurance Company Duly Licensed By The Insurance Commission And Confirmed By The Procuring Entity. 39.3. The Advance Payment Shall Be Repaid By The Contractor By An Amount Equal To The Percentage Of The Total Contract Price Used For The Advance Payment. 39.4. The Contractor May Reduce His Standby Letter Of Credit Or Guarantee Instrument By The Amounts Refunded By The Monthly Certificates In The Advance Payment. 39.5. The Procuring Entity Will Provide An Advance Payment On The Contract Price As Stipulated In The Conditions Of Contract, Subject To The Maximum Amount Stated In Scc Clause 39.1. 40. Progress Payments 40.1. The Contractor May Submit A Request For Payment For Work Accomplished. Such Request For Payment Shall Be Verified And Certified By The Procuring Entity’s Representative/project Engineer. Except As Otherwise Stipulated In The Scc, Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Not Be Included For Payment. 40.2. The Procuring Entity Shall Deduct The Following From The Certified Gross Amounts To Be Paid To The Contractor As Progress Payment: (a) Cumulative Value Of The Work Previously Certified And Paid For. (b) Portion Of The Advance Payment To Be Recouped For The Month. (c) Retention Money In Accordance With The Condition Of Contract. (d) Amount To Cover Third Party Liabilities. (e) Amount To Cover Uncorrected Discovered Defects In The Works. 40.3. Payments Shall Be Adjusted By Deducting There From The Amounts For Advance Payments And Retention. The Procuring Entity Shall Pay The Contractor The Amounts Certified By The Procuring Entity’s Representative Within Twenty Eight (28) Days From The Date Each Certificate Was Issued. No Payment Of Interest For Delayed Payments And Adjustments Shall Be Made By The Procuring Entity. 40.4. The First Progress Payment May Be Paid By The Procuring Entity To The Contractor Provided That At Least Twenty Percent (20%) Of The Work Has Been Accomplished As Certified By The Procuring Entity’s Representative. 40.5. Items Of The Works For Which A Price Of “0” (zero) Has Been Entered Will Not Be Paid For By The Procuring Entity And Shall Be Deemed Covered By Other Rates And Prices In The Contract. 41. Payment Certificates 41.1. The Contractor Shall Submit To The Procuring Entity’s Representative Monthly Statements Of The Estimated Value Of The Work Executed Less The Cumulative Amount Certified Previously. 41.2. The Procuring Entity’s Representative Shall Check The Contractor’s Monthly Statement And Certify The Amount To Be Paid To The Contractor. 41.3. The Value Of Work Executed Shall: (a) Be Determined By The Procuring Entity’s Representative; (b) Comprise The Value Of The Quantities Of The Items In The Bill Of Quantities Completed; And (c) Include The Valuations Of Approved Variations. 41.4. The Procuring Entity’s Representative May Exclude Any Item Certified In A Previous Certificate Or Reduce The Proportion Of Any Item Previously Certified In Any Certificate In The Light Of Later Information. 42. Retention 42.1. The Procuring Entity Shall Retain From Each Payment Due To The Contractor An Amount Equal To A Percentage Thereof Using The Rate As Specified In Itb Sub-clause 42.2. 42.2. Progress Payments Are Subject To Retention Of Ten Percent (10%), Referred To As The “retention Money.” Such Retention Shall Be Based On The Total Amount Due To The Contractor Prior To Any Deduction And Shall Be Retained From Every Progress Payment Until Fifty Percent (50%) Of The Value Of Works, As Determined By The Procuring Entity, Are Completed. If, After Fifty Percent (50%) Completion, The Work Is Satisfactorily Done And On Schedule, No Additional Retention Shall Be Made; Otherwise, The Ten Percent (10%) Retention Shall Again Be Imposed Using The Rate Specified Therefore. 42.3. The Total “retention Money” Shall Be Due For Release Upon Final Acceptance Of The Works. The Contractor May, However, Request The Substitution Of The Retention Money For Each Progress Billing With Irrevocable Standby Letters Of Credit From A Commercial Bank, Bank Guarantees Or Surety Bonds Callable On Demand, Of Amounts Equivalent To The Retention Money Substituted For And Acceptable To The Procuring Entity, Provided That The Project Is On Schedule And Is Satisfactorily Undertaken. Otherwise, The Ten (10%) Percent Retention Shall Be Made. Said Irrevocable Standby Letters Of Credit, Bank Guarantees And/or Surety Bonds, To Be Posted In Favor Of The Government Shall Be Valid For A Duration To Be Determined By The Concerned Implementing Office/agency Or Procuring Entity And Will Answer For The Purpose For Which The Ten (10%) Percent Retention Is Intended, I.e., To Cover Uncorrected Discovered Defects And Third Party Liabilities. 42.4. On Completion Of The Whole Works, The Contractor May Substitute Retention Money With An “on Demand” Bank Guarantee In A Form Acceptable To The Procuring Entity. 43. Variation Orders 43.1. Variation Orders May Be Issued By The Procuring Entity To Cover Any Increase/decrease In Quantities, Including The Introduction Of New Work Items That Are Not Included In The Original Contract Or Reclassification Of Work Items That Are Either Due To Change Of Plans, Design Or Alignment To Suit Actual Field Conditions Resulting In Disparity Between The Preconstruction Plans Used For Purposes Of Bidding And The “as Staked Plans” Or Construction Drawings Prepared After A Joint Survey By The Contractor And The Procuring Entity After Award Of The Contract, Provided That The Cumulative Amount Of The Variation Order Does Not Exceed Ten Percent (10%) Of The Original Project Cost. The Addition/deletion Of Works Should Be Within The General Scope Of The Project As Bid And Awarded. The Scope Of Works Shall Not Be Reduced So As To Accommodate A Positive Variation Order. A Variation Order May Either Be In The Form Of A Change Order Or Extra Work Order. 43.2. A Change Order May Be Issued By The Procuring Entity To Cover Any Increase/decrease In Quantities Of Original Work Items In The Contract. 43.3. An Extra Work Order May Be Issued By The Procuring Entity To Cover The Introduction Of New Work Necessary For The Completion, Improvement Or Protection Of The Project Which Were Not Included As Items Of Work In The Original Contract, Such As, Where There Are Subsurface Or Latent Physical Conditions At The Site Differing Materially From Those Indicated In The Contract, Or Where There Are Duly Unknown Physical Conditions At The Site Of An Unusual Nature Differing Materially From Those Ordinarily Encountered And Generally Recognized As Inherent In The Work Or Character Provided For In The Contract. 43.4. Any Cumulative Variation Order Beyond Ten Percent (10%) Shall Be Subject Of Another Contract To Be Bid Out If The Works Are Separable From The Original Contract. In Exceptional Cases Where It Is Urgently Necessary To Complete The Original Scope Of Work, The Head Of The Procuring Entity May Authorize A Positive Variation Order Go Beyond Ten Percent (10%) But Not More Than Twenty Percent (20%) Of The Original Contract Price, Subject To The Guidelines To Be Determined By The Gppb: Provided, However, That Appropriate Sanctions Shall Be Imposed On The Designer, Consultant Or Official Responsible For The Original Detailed Engineering Design Which Failed To Consider The Variation Order Beyond Ten Percent (10%). 43.5. In Claiming For Any Variation Order, The Contractor Shall, Within Seven (7) Calendar Days After Such Work Has Been Commenced Or After The Circumstances Leading To Such Condition(s) Leading To The Extra Cost, And Within Twenty-eight (28) Calendar Days Deliver A Written Communication Giving Full And Detailed Particulars Of Any Extra Cost In Order That It May Be Investigated At That Time. Failure To Provide Either Of Such Notices In The Time Stipulated Shall Constitute A Waiver By The Contractor For Any Claim. The Preparation And Submission Of Variation Orders Are As Follows: (a) If The Procuring Entity’s Representative/project Engineer Believes That A Change Order Or Extra Work Order Should Be Issued, He Shall Prepare The Proposed Order Accompanied With The Notices Submitted By The Contractor, The Plans Therefore, His Computations As To The Quantities Of The Additional Works Involved Per Item Indicating The Specific Stations Where Such Works Are Needed, The Date Of His Inspections And Investigations Thereon, And The Log Book Thereof, And A Detailed Estimate Of The Unit Cost Of Such Items Of Work, Together With His Justifications For The Need Of Such Change Order Or Extra Work Order, And Shall Submit The Same To The Head Of The Procuring Entity For Approval. (b) The Head Of The Procuring Entity Or His Duly Authorized Representative, Upon Receipt Of The Proposed Change Order Or Extra Work Order Shall Immediately Instruct The Technical Staff Of The Procuring Entity’s To Conduct An On-the-spot Investigation To Verify The Need For The Work To Be Prosecuted. A Report Of Such Verification Shall Be Submitted Directly To The Head Of The Procuring Entity Or His Duly Authorized Representative. (c) The, Head Of The Procuring Entity Or His Duly Authorized Representative, After Being Satisfied That Such Change Order Or Extra Work Order Is Justified And Necessary, Shall Review The Estimated Quantities And Prices And Forward The Proposal With The Supporting Documentation To The Head Of Procuring Entity For Consideration. (d) If, After Review Of The Plans, Quantities And Estimated Unit Cost Of The Items Of Work Involved, The Proper Office Of The Procuring Entity Empowered To Review And Evaluate Change Orders Or Extra Work Orders Recommends Approval Thereof, Head Of The Procuring Entity Or His Duly Authorized Representative, Believing The Change Order Or Extra Work Order To Be In Order, Shall Approve The Same. (e) The Timeframe For The Processing Of Variation Orders From The Preparation Up To The Approval By The Head Of The Procuring Entity Concerned Shall Not Exceed Thirty (30) Calendar Days. 44. Contract Completion Once The Project Reaches An Accomplishment Of Ninety Five (95%) Of The Total Contract Amount, The Procuring Entity May Create An Inspectorate Team To Make Preliminary Inspection And Submit A Punch-list To The Contractor In Preparation For The Final Turnover Of The Project. Said Punch-list Will Contain, Among Others, The Remaining Works, Work Deficiencies For Necessary Corrections, And The Specific Duration/time To Fully Complete The Project Considering The Approved Remaining Contract Time. This, However, Shall Not Preclude The Claim Of The Procuring Entity For Liquidated Damages. 45. Suspension Of Work 45.1. The Procuring Entity Shall Have The Authority To Suspend The Work Wholly Or Partly By Written Order For Such Period As May Be Deemed Necessary, Due To Force Majeure Or Any Fortuitous Events Or For Failure On The Part Of The Contractor To Correct Bad Conditions Which Are Unsafe For Workers Or For The General Public, To Carry Out Valid Orders Given By The Procuring Entity Or To Perform Any Provisions Of The Contract, Or Due To Adjustment Of Plans To Suit Field Conditions As Found Necessary During Construction. The Contractor Shall Immediately Comply With Such Order To Suspend The Work Wholly Or Partly. 45.2. The Contractor Or Its Duly Authorized Representative Shall Have The Right To Suspend Work Operation On Any Or All Projects/activities Along The Critical Path Of Activities After Fifteen (15) Calendar Days From Date Of Receipt Of Written Notice From The Contractor To The District Engineer/regional Director/consultant Or Equivalent Official, As The Case May Be, Due To The Following: (a) There Exist Right-of-way Problems Which Prohibit The Contractor From Performing Work In Accordance With The Approved Construction Schedule. (b) Requisite Construction Plans Which Must Be Owner-furnished Are Not Issued To The Contractor Precluding Any Work Called For By Such Plans. (c) Peace And Order Conditions Make It Extremely Dangerous, If Not Possible, To Work. However, This Condition Must Be Certified In Writing By The Philippine National Police (pnp) Station Which Has Responsibility Over The Affected Area And Confirmed By The Department Of Interior And Local Government (dilg) Regional Director. (d) There Is Failure On The Part Of The Procuring Entity To Deliver Government-furnished Materials And Equipment As Stipulated In The Contract. (e) Delay In The Payment Of Contractor’s Claim For Progress Billing Beyond Forty-five (45) Calendar Days From The Time The Contractor’s Claim Has Been Certified To By The Procuring Entity’s Authorized Representative That The Documents Are Complete Unless There Are Justifiable Reasons Thereof Which Shall Be Communicated In Writing To The Contractor. 45.3. In Case Of Total Suspension, Or Suspension Of Activities Along The Critical Path, Which Is Not Due To Any Fault Of The Contractor, The Elapsed Time Between The Effective Order Of Suspending Operation And The Order To Resume Work Shall Be Allowed The Contractor By Adjusting The Contract Time Accordingly. 46. Payment On Termination 46.1. If The Contract Is Terminated Because Of A Fundamental Breach Of Contract By The Contractor, The Procuring Entity’s Representative Shall Issue A Certificate For The Value Of The Work Done And Materials Ordered Less Advance Payments Received Up To The Date Of The Issue Of The Certificate And Less The Percentage To Apply To The Value Of The Work Not Completed, As Indicated In The Scc. Additional Liquidated Damages Shall Not Apply. If The Total Amount Due To The Procuring Entity Exceeds Any Payment Due To The Contractor, The Difference Shall Be A Debt Payable To The Procuring Entity. 46.2. If The Contract Is Terminated For The Procuring Entity’s Convenience Or Because Of A Fundamental Breach Of Contract By The Procuring Entity, The Procuring Entity’s Representative Shall Issue A Certificate For The Value Of The Work Done, Materials Ordered, The Reasonable Cost Of Removal Of Equipment, Repatriation Of The Contractor’s Personnel Employed Solely On The Works, And The Contractor’s Costs Of Protecting And Securing The Works, And Less Advance Payments Received Up To The Date Of The Certificate. 46.3. The Net Balance Due Shall Be Paid Or Repaid Within Twenty Eight (28) Days From The Notice Of Termination. 46.4. If The Contractor Has Terminated The Contract Under Gcc Clauses 17 Or 18, The Procuring Entity Shall Promptly Return The Performance Security To The Contractor. 47. Extension Of Contract Time 47.1. Should The Amount Of Additional Work Of Any Kind Or Other Special Circumstances Of Any Kind Whatsoever Occur Such As To Fairly Entitle The Contractor To An Extension Of Contract Time, The Procuring Entity Shall Determine The Amount Of Such Extension; Provided That The Procuring Entity Is Not Bound To Take Into Account Any Claim For An Extension Of Time Unless The Contractor Has, Prior To The Expiration Of The Contract Time And Within Thirty (30) Calendar Days After Such Work Has Been Commenced Or After The Circumstances Leading To Such Claim Have Arisen, Delivered To The Procuring Entity Notices In Order That It Could Have Investigated Them At That Time. Failure To Provide Such Notice Shall Constitute A Waiver By The Contractor Of Any Claim. Upon Receipt Of Full And Detailed Particulars, The Procuring Entity Shall Examine The Facts And Extent Of The Delay And Shall Extend The Contract Time Completing The Contract Work When, In The Procuring Entity’s Opinion, The Findings Of Facts Justify An Extension. 47.2. No Extension Of Contract Time Shall Be Granted The Contractor Due To (a) Ordinary Unfavorable Weather Conditions And (b) Inexcusable Failure Or Negligence Of Contractor To Provide The Required Equipment, Supplies Or Materials. 47.3. Extension Of Contract Time May Be Granted Only When The Affected Activities Fall Within The Critical Path Of The Pert/cpm Network. 47.4. No Extension Of Contract Time Shall Be Granted When The Reason Given To Support The Request For Extension Was Already Considered In The Determination Of The Original Contract Time During The Conduct Of Detailed Engineering And In The Preparation Of The Contract Documents As Agreed Upon By The Parties Before Contract Perfection. 47.5. Extension Of Contract Time Shall Be Granted For Rainy/unworkable Days Considered Unfavorable For The Prosecution Of The Works At The Site, Based On The Actual Conditions Obtained At The Site, In Excess Of The Number Of Rainy/unworkable Days Pre-determined By The Procuring Entity In Relation To The Original Contract Time During The Conduct Of Detailed Engineering And In The Preparation Of The Contract Documents As Agreed Upon By The Parties Before Contract Perfection, And/or For Equivalent Period Of Delay Due To Major Calamities Such As Exceptionally Destructive Typhoons, Floods And Earthquakes, And Epidemics, And For Causes Such As Non-delivery On Time Of Materials, Working Drawings, Or Written Information To Be Furnished By The Procuring Entity, Non-acquisition Of Permit To Enter Private Properties Within The Right-of-way Resulting In Complete Paralyzation Of Construction Activities, And Other Meritorious Causes As Determined By The Procuring Entity’s Representative And Approved By The Head Of The Procuring Entity. Shortage Of Construction Materials, General Labor Strikes, And Peace And Order Problems That Disrupt Construction Operations Through No Fault Of The Contractor May Be Considered As Additional Grounds For Extension Of Contract Time Provided They Are Publicly Felt And Certified By Appropriate Government Agencies Such As Dti, Dole, Dilg, And Dnd, Among Others. The Written Consent Of Bondsmen Must Be Attached To Any Request Of The Contractor For Extension Of Contract Time And Submitted To The Procuring Entity For Consideration And The Validity Of The Performance Security Shall Be Correspondingly Extended. 48. Price Adjustment Except For Extraordinary Circumstances As Determined By Neda And Approved By The Gppb, No Price Adjustment Shall Be Allowed. Nevertheless, In Cases Where The Cost Of The Awarded Contract Is Affected By Any Applicable New Laws, Ordinances, Regulations, Or Other Acts Of The Gop, Promulgated After The Date Of Bid Opening, A Contract Price Adjustment Shall Be Made Or Appropriate Relief Shall Be Applied On A No Loss-no Gain Basis. 49. Completion The Contractor Shall Request The Procuring Entity’s Representative To Issue A Certificate Of Completion Of The Works, And The Procuring Entity’s Representative Will Do So Upon Deciding That The Work Is Completed. 50. Taking Over The Procuring Entity Shall Take Over The Site And The Works Within Seven (7) Days From The Date The Procuring Entity’s Representative Issues A Certificate Of Completion. 51. Operating And Maintenance Manuals 51.1. If “as Built” Drawings And/or Operating And Maintenance Manuals Are Required, The Contractor Shall Supply Them By The Dates Stated In The Scc. 51.2. If The Contractor Does Not Supply The Drawings And/or Manuals By The Dates Stated In The Scc, Or They Do Not Receive The Procuring Entity’s Representative’s Approval, The Procuring Entity’s Representative Shall Withhold The Amount Stated In The Scc From Payments Due To The Contractor. Section V. Special Conditions Of Contract Gcc Clause 1.16 The Intended Completion Date Is 90 Cd From Ntp. 1.21 The Procuring Entity Is Lgu- Mapanas, Northern Samar. 1.22 The Procuring Entity’s Representative Is Atty. Ronn Michael L. Tejano Municipal Mayor Municipality Of Mapanas Province Of Northern Samar 1.23 The Site Is Located At Mapanas, Northern Samar. 1.27 The Start Date Is: Upon Receipt Of Notice To Proceed. 1.30 The Works Consist Of: Item No. Scope Of Work Quantity Unit Repair/rehabilitation Of Mapanas Rhu, Barangay Del Norte, Mapanas, N. Samar. B. 5 Project Billboard/signboard 1.00 Lot Lot B.7 Construction Safety And Health 1.00 Lot Lot B.9 Mobilization And Demobilization 1.00 Lot Lot 801(7)a Removal Of Structures And Obstruction 1.00 Is Is 900(1)c1 Structural Concrete (class A), 28 Days 9.15 Cu.m. Cu.m. 902(1) A Reinforcing Steel, Deformed Grade 40 541.72 Kg. Kg 903 Formworks And Falseworks 53.38 Sq.m. Sq.m. 1047 Metal Structures 84.00 In.m. In.m 1013 Corrugated Metal Roofing, Gauge 24 9.00 Sq.m. Sq.m. 1046 Masonry Works 75.60 Sq.m. Sq.m. 1003 Carpentry And Joinery Works 38.78 Sq.m. Sq.m. 1005 Doors And Windows 3.00 Sets Sets 1002 Plumbing Works 1.00 Lot Lot 1032 Painting Varnishing And Other Related Works 411.00 Sq.m. Sq.m. 1101 Wires And Wiring Devices 1.00 Is Is 1002 (1) Panel Board With Main Breaker And Branc 1.00 Is Is 1103 Lighting Fixtures And Lamps 1.00 Is Is Spcl1 Signages 1.00 Lot Lot 2.2 Note: The Items To Follow 5.1 The Procuring Entity Shall Give Possession Of All Parts Of The Site To The Contractor Upon The Issuance Of Notice To Proceed. 6.5 The Contractor Shall Employ The Following Key Personnel: Key Personnel Number Civil Engineer 1 Construction Foreman 1 Skilled Workers 3 Welder 3 7.4(c) “no Further Instructions”. 7.7 No Further Instructions. 8.1 No Further Instructions. 10 The Site Investigation Reports Are: None 12.3 No Further Instructions. 12.5 In Case Of Semi-permanent Structures, Such As Buildings Of Types 1, 2, And 3 As Classified Under The National Building Code Of The Philippines, Concrete/asphalt Roads, Concrete River Control, Drainage, Irrigation Lined Canals, River Landing, Deep Wells, Rock Causeway, Pedestrian Overpass, And Other Similar Semi-permanent Structures: Five (5) Years. 13 “no Additional Provision.” 18.3(h)(i) No Further Instructions. 21.2 The Arbiter Is: Construction Industry Arbitration Commission 29.1 No Day Works Are Applicable To The Contract. 31.1 The Contractor Shall Submit The Program Of Work To The Procuring Entity’s Representative Within 15days Of Delivery Of The Letter Of Acceptance. 31.3 The Period Between Program Of Work Updates Is 15days. The Amount To Be Withheld For Late Submission Of An Updated Program Of Work Is P 1,000.00. 34.3 The Funding Source Is Coming From Nia 39.1 The Amount Of The Advance Payment Is 15% Of The Contract Price (lump Sum) And Shall Be Release Once Upon Presentation Of The Following Documents As Required: 1. Letter Request For Advance Payment From The Contractor 2. Bank Guarantee For Advance Payment 40.1 Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Be Included For Payment. 51.1 The Date By Which Operating And Maintenance Manuals Are Required Is Not Applicable. The Date By Which “as Built” Drawings Are Required Is 20 Days Upon Completion Of The Subproject. 51.2 The Amount To Be Withheld For Failing To Produce “as Built” Drawings And/or Operating And Maintenance Manuals By The Date Required Is P1,000.00. Section Vi. Specifications Project Name: Repair/rehabilitation Of Mapanas Rhu Location : Brgy. Del Norte, Mapanas, Northern Samar Item No. Description Qty. Unit. B.5 Project Billborad/signboard 1.00 Lot A. Material A. Tarpaulin ( 4’x8’) 1.00 Set B. Plywood Marine (1/4”x1.2mx2.44) 1.00 Pc C. Coco Lumber, 2”x3”x12” 42.00 Bd.ft. D. Common Nails Assorted 0.50 Kg B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) (1 Gang = Foreman 1 Carpenter, 1 Laborer 1.00 1.00 E. Labor Requirement Foreman 1.00 1.00 Skilled Carpenter 1.00 1.00 Unskilled 1.00 1.00 B. 7 Construction Safety And Health 1.00 Lot A Material A. Safety Helmet 5.00 Pc B. Safety Shoes 5.00 Pc C. Safety Vest 5.00 Pc D. Working Gloves 5.00 Pc E. Face Mask (surgical/cloth) 5.00 Box F. Eye Goggles 5.00 Pc G. Sanitizing Solution 3.00 Lit H. Ethyl Alcohol 3.00 Lit I. Disinfectant Spray 3.00 Can J. Liquid Hand Soap 3.00 Lit B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) E. Labor Requirement A. Safety Officer 1.00 15.00 B. Health Personnel (full Time First Aider) 1.00 15.00 C. Sanitation Aide 1.00 15.00 B. 9 Mobilization And Demobilization 1.00 Lot A. Material B. Freight And Handling C. Name And Capacity Equipment Cargo/service Truck (2-5mt) 1.00 2.00 D. Labor Derivation (subsidiary Work Description) E. Labor Requirement 900(1)c1 Structural Concrete (class A), 28 Days 9.15 Cu.m. A. Material A Portland Cement, Typ1 1 83.00 Bag B. Gravel, ¾” 8.00 Cu.m. C. Sand, Washed 5.00 Cu.m. B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) E. Labor Requirement Foreman 1.00 2.00 Skilled Mason 2.00 2.00 Unskilled 8.00 2.00 I Total Estimated Direct Cost Ii Indirect Cost Ocm (up To 12-15%) Contractor’s Profit Cost (8-10%) Vat (5%) Iii A. Material A. Rsb, Deformed, 10mmo 34 Pcs B. Rsb, Deformed, 12mmo 78 Pcs. C. Tie Wire# 16 10.00 Kg B. Freight And Handling C. Name And Capacity Of Equipment Bar Cutter, Single Phase 1.00 2.00 D. Labor Derivation (subsidiary Work Description) (1 Gang=1-foreman, 1 Steelman, 1-laborer 80kgs/day/gang 541.72 80.00 E. Labor Requirement Foreman 1 2.00 Skilled Steel Man 4.00 2.00 Unskilled 4.00 2.00 I Total Estimated Direct Cost Ii Indirect Cost Ocm (up To 12-15%) Contractor’s Profit, Cost (8-10%) Vat (5%) 1047 Metal Structures A. Material A. Tubular 2”x4”x6m 14.00 Pc B. Sliding Mechanism 1.00 Set C. Grinding Desk 8.00 Pc D. Cutting Desk 20.00 Pc E. Welding Rod 25.00 Kg F. Paint Red Lead 1.00 Gal G. Paint Brush, 2” 4.00 Pc H. Epoxy Paint Finish 2.00 Gal I. Barrel Bolt Set Padlock 1.00 Set B. Freight And Handling C. Name And Capacity Of Equipment Welding Machine, Electric Driven/dc Outpit 1.00 10.00 D. Labor Derivation (subsidiary Work Description) 84.00 9.00 E. Labor Requirement Foreman 1.00 10.00 Skilled Welder 2.00 10.00 Unskilled 3.00 10.00 I Total Estimated Direct Cost Ii Indirect Cost Ocm (up To 12-15%) Contractor’s Profit Cost (8-10%) Vat (5%) 1013 Corrugated Metal Roofing, Gauge 24 9.00 Sq.m. A. Pre-painted Metal Roofing Sheet Ga. 24x2.44m.) 9.00 In.m. B. J Bolt 1/4x21”, With Nut And Bonded Washer 72.00 Pc. C. Touchup Paint 4.00 L D. Paint Brush, 2” 2.00 Pc E. Pre-painted Metal Ridge Cap Ga. 24x2.44m 6.00 Pc F. Pre-painted Metal End Wall Flashing Ga. 24x2.44m 3.00 Pc G. Pre-painted Metal Gutter Ga. 24x2.44m 18.00 Pc B. Freight And Handling C. Name And Capacity Of Equipment A.scaffolding 1.00 3.00 D. Labor Derivation (subsidiary Work Description) Roofing Sheets Installation Install: 1 Gang= 1foreman, 1 Carpenter, 3- Laborers 9.00 20.00 Roofing Gutter, Wall Flashing And Ridge Cap Installation Install: 1 Gang=1-foreman, 1-carpenter, 3-laborers Capability: 12 Pcs/day/gang 27.00 12.00 E. Labor Requirement Foreman 1.00 3.00 Skilled Carpenter 1.00 3.00 Unskilled 3.00 3.00 I. Total Estimated Direct Cost Ii. Indirect Cost Ocm (up To 12-15%) Contractor’s Profit Cost (8-10%) Vat (5%) 1046 Masonry Works 75.60 Sq.m. A Material Chb Laying A. Chb Ordinary, 4” 331.00 Pc. B. Portland Cement, Type I 20.00 Bag C. Sand, Washed 1.00 Cu.m. D. Rsb, Deformed, 10mmo 18.00 Pcs. E. Tie Wire # 16 5.00 Kg F. Hacksaw Blade, Heavy Duty 2.00 Pc. G. Concrete Baluster 306 Pcs. Plastering A. Portland Cement, Type 1 10.00 Bag B. Sand, Washed 1.00 Cu.m. B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) Chb Laying Install 1 Gang= 1-foreman, 2 Mason, 3 Laborers Capacity, 230 Pcs. Chb /day/gang 331.00 1.00 Chb Plastering Install: 1 Gang= 1 Foreman, 2-mason, 3 Laborers Capability: 12 Sq.m/day/gang 50.00 1.00 Baluster Laying Install: 1 Gang=1 Foreman, 2-mason, 3-laborers Capability: 130 Pcs Chb/day/gang 306.00 1.00 E. Labor Requirement Chb Laying Foreman 1.00 2.00 Skilled Mason 2.00 2.00 Unskilled 3.00 2.00 Chb Plastering Foreman 1.00 5.00 Skilled Mason 2.00 5.00 Unskilled 2.00 5.00 Baluster Laying Foreman 1.00 3.00 Skilled Mason 2.00 3.00 Unskilled 3.00 3.00 1003 Carpentry And Joinery Works 38.78 Sq.m. A. Material Ceiling A. Plywood Marine (1/4”x1.2mx2.44m) 14.00 Pc. B. Lumber Good ( Joist) 179.00 Bd.ft. C. Assorted Cwn (1 Kg.)/100 Bd. Ft. Of Lumber) 2.00 Kg D. Assorted Finishing Nails 2.00 Kg. E. Concrete Nails Assorted 1.00 Kg. B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) Ceiling Installation Install: 1 Gang=1 Foreman, 2-carpenters , 2 Laborers Capacity: 15 Sq.m/day/gang 38.78 15.00 E. Labor Requirement Foreman 1.00 3.00 Skilled Carpenter 2.00 3.00 Unskilled 2.00 3.00 1005 Doors And Windows 3.00 Sets A. Material Doors A. D1-powder Coated Aluminum Casement Door (2.1mx2.1m, W/0.4m. Transom) Aluminum Glass Door 4.41 2.00 Sets D2-panel Door For Pwd C.r. With Kick Plate (0.9mx2.1m, W/0.4m Transom) Flush Door 1.89 1.00 Sets 8.82 1.89 Sq.m. Sq.m. B. Lever-type Plush Botton Door Knob 5.00 Set B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) Door Installation Install: 1 Gang = 1-foreman, 1-skilled, 1 Laborer Capability: 10 Sq.m. (doors)day/gang 15.71 10.00 Jamb Installation Install:1 Gang= 1 Foreman, 1 Skilled, 1 Laborer Capability: 4 Sets (jamb) Day/gang 4.00 Window Installation Install: 1 Gang= 1-foreman, 1 Skilled, 1 Laborer Capability: 2.88 Sq.m. (window) /day/gang 2.00 E. Labor Requirement Foreman 1.00 2.00 Skilled Carpenter 1.00 2.00 Unskilled 1.00 2.00 1002 Plumbing Works 1.00 Lot A. Material Cold Water Line A. Pvc Pipes (25.4mm D) 2.00 Pc B. Pvc Pipes (12.7mm D) 6.00 Pc. C. Pvc Coupling (12.7mm D) 3.00 Pc Sewer Line Works D Pvc Elbow (50mm D) 16.00 Pc E. Upvc Pipe, 50mm Dia.x 3m, 5-1000 32.00 Pc F. Solvent Cement, 400cc 2.00 Can Fixtures G. Grab Bar Inwall Support W/ Lift Up Function 32 1.00 Set H. Wall Faucet, ½”x 4”, Stainless Steel 6.00 Pc I. Tissue Holder, Stainless Steel 304, Wall Mounted 1.00 Set J. Soap Holder 1.00 Set B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) Plumbing Installation Install: 1 Gang = 1-foreman, 1 Plumber, 1-laborer Capacity: 8 Pcs. Pipes /day/gang E. Labor Requirement Foreman 1.00 6.00 Skilled Plumber 1.00 6.00 Unskilled 1.00 6.00 1032 Painting, Varnishing And Other Related Works A. Material Concrete/masonry Walls/ceiling A. Concrete Neutralizer 9.00 Gal B. Skimcoat, 20kg 11.00 Bag C. Acrylic, Solvent Based Paint 14.00 Gal D. Paint Latex Flat Elastomeric 14.00 Gal E. Sand Paper 125.00 Pc. F. Paint Brush, 2” 20.00 Pc. G. Paint Roller 20.00 Pc. B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) Plumbing Installation Install : 1 Gang = 1 Foreman, 1-paintor, 1-laborer, Capability: 30 Sq.m. (roller)/day/gang 411.21 30.00 E. Labor Requirement Foreman 1.00 7.00 Skilled Painter 2.00 7.00 Unskilled 2.00 7.00 1101 Wires And Wiring Devices A. Material A. Electric Wires Thnn/thhn 3.5 Mm2 150.00 M B. Electric Wires Thwn/thhn 5.5mm2 50.00 M Wiring Devices E Electrical Tape ¾”x20yds 2.00 Pc. B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) Wirings Install: 1 Gang= 1 Foreman, 1electrician, 1 Laborer Capability: 144m/day/gang 200.00 144.00 E. Labor Requirement Foreman 1.00 2.00 Skilled Electrician 1.00 2.00 Unskilled 1.00 2.00 1002 (1) Panel Board With Main Breaker And Branches A. Material A. Panel Board & Cabinets, 2p Main With 6br/2p Bolt On Type 1.00 Set B. Rated 60amp-manual Transfer Switch Breaker Type Nema3 Enclosure 1.00 Set C. 15at,2p,60hz, 230vac Plug In Type Mechanical Lug Circuit Breaker 2.00 Set D. 20at, 2p, 60hz, 230vac Plug In Type Mechanical Lug Circuit Breaker 2.00 Set E. 30at, 2p, 60hz, 230vac Plug In Type Mechanical Lug Circuit Breaker 2.00 Set F. 60at, 2p, 60hz, 230vac Plug In Type Mechanical Lug Circuit Breaker 1.00 Set B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) Panel Board Installation Install: 1gang = 1foreman, 1-electrician, 1-laborer Capability : 1 Set/day/gang 2.00 1.00 E. Labor Requirement Foreman 1.00 2.00 Skilled Electrician 1.00 2.00 Unskilled 1.00 2.00 1103 Lighting Fixtures And Lamps 1.00 Is A. Material A. Solar Lights Lantern Type 22.00 Set B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) Lighting Fixtures Installation Install: 1 Gang =1-foreman, 1-electrician, 1 Laborer Capacity: 8 Pcs/day/gang 22.00 8.00 E. Labor Requirement Foreman 1.00 3.00 Skilled Electrician 1.00 3.00 Unskilled 1.00 3.00 801 (7) A Removal Of Structures And Obstruction 1.00 Is A. Material B. Freight And Handling C. Name And Capacity Of Equipment Welding Machine, Electric Driven/dc Output 1.00 3.00 Cutting Output 1.00 3.00 Cargo/service Truck (2-5 Mt) 1.00 1.00 D. Labor Derivation (subsidiary Work Description) Removal Of Steel Railings Install: 1 Gang = 1foreman, 1 Electrician, 1 Laborer 17.00 8.00 Removal Of Ceiling, Gutter And Roofing Install : 1 Gang= 1 Foreman, 1 Electrician, 1-laborer Capacity: 25 Sq.m./day/gang E. Labor Requiremnt Foreman 1.00 16.00 Skilled Electrician 1.00 16.00 Unskilled 1.00 16.00 Spcl-1 Signages 1.00 Lot A. Material Municipal Signages Pana Flex W/ Electrical Wiring 1.00 Lot B. Freight And Handling C. Name And Capacity Of Equipment D. Labor Derivation (subsidiary Work Description) Installation Of Signages Install: 1 Gang= 1foreman: 1-electrician, 1 Laborer Capability: 4 Set/day/gang 8.00 4.00 Wirings Install: 1 Gang= 1 Foreman, 1-electrician, 1-laborer Capability: 144m/day/gang 150.00 144.00 E. Labor Requirement Foreman 1.00 4.00 Skilled Electrician 1.00 4.00 Unskilled 1.00 4.00 Section Vii. Drawings Bill Of Quantities Item No. Scope Of Work Quantity Unit Unit Cost Total Amount 1.) Repair And Rehabilitation Of Mapanas Rhu, Brgy. Del Norte, Mapanas, N. Samar B.5 Project Billboard 1.00 Lot 5,364.36 5,364.36 B.7 Construction Safety And Haelth 1.00 Lot 39,087.00 39,087.00 B.9 Mobilization And Demobilization 1.00 Lot 12,528.00 12,528.00 801(7)a Removal Of Structures And Obstruction 1.00 Is 44,152.56 44,152.56 900(1)c.1 Structural Concrete (class A), 28 Days 9.15 Cu.m. 7,460.98 68,268.00 902(1) A Reinforcing Steel Deformed Grade 40 541.72 Kg. 75.61 40,958.24 903 Formworks And Falseworks 53.38 Sq.m, 633.38 33,806.56 1047 Metal Structures 84.00 In.m. 1,316.02 110,546.00 1013 Corrugated Metal Roofing, Gauge 24 9.00 Sq.m. 3,893.42 35,040.80 1046 Masonry Works 75.60 Sq.m. 1,946.65 147,166.40 1003 Carpentry And Joinery Works 38.78 Sq.m. 815.55 31,626.84 1005 Doors And Windows 3.00 Sets 18,342.24 55,026.72 1002 Plumbing Works 1.00 Lot 31,754.16 31,754.16 1032 Painting, Varnishing, And Other Related 411.21 Sq.m. 146.77 60,351.96 1101 Wires And Wiring Devices 1.00 Is 12,046.72 12,046.72 1002(1) Panel Board With Main Breaker And Brand 1.00 Is 11,434.72 11,434.72 1103 Lighting Fixtures And Lamps 1.00 Is 52,550.08 52,550.08 Spcl1 Signages 1.00 Lot 36,853.44 36,853.44 Total 828,562.56 Total Cost Of All Line Item Includes Cost Of Contractor’s Profit, Taxes And Ocm. Attached Detailed Cost Estimates Section Ix. Bidding Forms Table Of Contents Bid Form 79 Form Of Contract Agreement 81 Omnibus Sworn Statement 83 Bid Form Date: Iaeb No: To: Lgu-mapanas Northern Samar Address: Mapanas Northern Samar We, The Undersigned, Declare That: We Have Examined And Have No Reservation To The Bidding Documents, Including Addenda, For The Contract Repair/rehabilitation Of Mapanas Rhu, Barangay Del Norte , Mapanas N. Samar (a) We Offer To Execute The Works For This Contract In Accordance With The Bid And Bid Data Sheet, General And Special Conditions Of Contract Accompanying This Bid; The Total Price Of Our Bid, Excluding Any Discounts Offered In Item (d) Below Is: [insert Information]; The Discounts Offered And The Methodology For Their Application Are: [insert Information]; (b) Our Bid Shall Be Valid For A Period Of 120 Days From The Date Fixed For The Bid Submission Deadline In Accordance With The Bidding Documents, And It Shall Remain Binding Upon Us And May Be Accepted At Any Time Before The Expiration Of That Period; (c) If Our Bid Is Accepted, We Commit To Obtain A Performance Security In The Amount Of [insert Percentage Amount] Percent Of The Contract Price For The Due Performance Of The Contract; (d) Our Firm, Including Any Subcontractors Or Suppliers For Any Part Of The Contract, Have Nationalities From The Following Eligible Countries: [insert Information]; (e) We Are Not Participating, As Bidders, In More Than One Bid In This Bidding Process, Other Than Alternative Offers In Accordance With The Bidding Documents; (f) Our Firm, Its Affiliates Or Subsidiaries, Including Any Subcontractors Or Suppliers For Any Part Of The Contract, Has Not Been Declared Ineligible By The Funding Source; (g) We Understand That This Bid, Together With Your Written Acceptance Thereof Included In Your Notification Of Award, Shall Constitute A Binding Contract Between Us, Until A Formal Contract Is Prepared And Executed; And (h) We Understand That You Are Not Bound To Accept The Lowest Evaluated Bid Or Any Other Bid That You May Receive. Name: In The Capacity Of: Signed: Duly Authorized To Sign The Bid For And On Behalf Of: Date: ___________ Form Of Contract Agreement This Agreement, Made This [insert Date] Day Of [insert Month], [insert Year] Between [name And Address Of Procuring Entity](hereinafter Called The “entity”) And [name And Address Of Contractor] (hereinafter Called The “contractor”). Whereas, The Entity Is Desirous That The Contractor Execute [name And Identification Number Of Contract] (hereinafter Called “the Works”) And The Entity Has Accepted The Bid For [insert The Amount In Specified Currency In Numbers And Words] By The Contractor For The Execution And Completion Of Such Works And The Remedying Of Any Defects Therein. Now This Agreement Witnesseth As Follows: 1. In This Agreement, Words And Expressions Shall Have The Same Meanings As Are Respectively Assigned To Them In The Conditions Of Contract Hereinafter Referred To. 2. The Following Documents Shall Be Attached, Deemed To Form, And Be Read And Construed As Part Of This Agreement, To Wit: (a) General And Special Conditions Of Contract; (b) Drawings/plans; (c) Specifications; (d) Invitation To Apply For Eligibility And To Bid; (e) Instructions To Bidders; (f) Bid Data Sheet; (g) Addenda And/or Supplemental/bid Bulletins, If Any; (h) Bid Form, Including All The Documents/statements Contained In The Bidder’s Bidding Envelopes, As Annexes; (i) Eligibility Requirements, Documents And/or Statements; (j) Performance Security; (k) Credit Line Issued By A Licensed Bank, If Any; (l) Notice Of Award Of Contract And The Bidder’s Conforme Thereto; (m) Other Contract Documents That May Be Required By Existing Laws And/or The Entity. 3. In Consideration Of The Payments To Be Made By The Entity To The Contractor As Hereinafter Mentioned, The Contractor Hereby Covenants With The Entity To Execute And Complete The Works And Remedy Any Defects Therein In Conformity With The Provisions Of This Contract In All Respects. 4. The Entity Hereby Covenants To Pay The Contractor In Consideration Of The Execution And Completion Of The Works And The Remedying Of Defects Wherein, The Contract Price Or Such Other Sum As May Become Payable Under The Provisions Of This Contract At The Times And In The Manner Prescribed By This Contract. In Witness Whereof The Parties Thereto Have Caused This Agreement To Be Executed The Day And Year First Before Written. Signed, Sealed, Delivered By The (for The Entity) Signed, Sealed, Delivered By The (for The Contractor). Binding Signature Of Procuring Entity ________________________________________________ Binding Signature Of Contractor _____________________________________________ [addendum Showing The Corrections, If Any, Made During The Bid Evaluation Should Be Attached With This Agreement] Omnibus Sworn Statement Republic Of The Philippines ) City/municipality Of ______ ) S.s. Affidavit I, [name Of Affiant], Of Legal Age, [civil Status], [nationality], And Residing At [address Of Affiant], After Having Been Duly Sworn In Accordance With Law, Do Hereby Depose And State That: 1. Select One, Delete The Other: If A Sole Proprietorship: I Am The Sole Proprietor Of [name Of Bidder] With Office Address At [address Of Bidder]; If A Partnership, Corporation, Cooperative, Or Joint Venture: I Am The Duly Authorized And Designated Representative Of [name Of Bidder] With Office Address At [address Of Bidder]; 2. Select One, Delete The Other: If A Sole Proprietorship: As The Owner And Sole Proprietor Of [name Of Bidder], I Have Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary To Represent It In The Bidding For [name Of The Project] Of The [name Of The Procuring Entity]; If A Partnership, Corporation, Cooperative, Or Joint Venture: I Am Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary And/or To Represent The [name Of Bidder] In The Bidding As Shown In The Attached [state Title Of Attached Document Showing Proof Of Authorization (e.g., Duly Notarized Secretary’s Certificate Issued By The Corporation Or The Members Of The Joint Venture)]; 3. [name Of Bidder] Is Not “blacklisted” Or Barred From Bidding By The Government Of The Philippines Or Any Of Its Agencies, Offices, Corporations, Or Local Government Units, Foreign Government/foreign Or International Financing Institution Whose Blacklisting Rules Have Been Recognized By The Government Procurement Policy Board; 4. Each Of The Documents Submitted In Satisfaction Of The Bidding Requirements Is An Authentic Copy Of The Original, Complete, And All Statements And Information Provided Therein Are True And Correct; 5. [name Of Bidder]is Authorizing The Head Of The Procuring Entity Or Its Duly Authorized Representative(s) To Verify All The Documents Submitted; 6. Select One, Delete The Rest: If A Sole Proprietorship: I Am Not Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; If A Partnership Or Cooperative: None Of The Officers And Members Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; If A Corporation Or Joint Venture: None Of The Officers, Directors, And Controlling Stockholders Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; 7. [name Of Bidder] Complies With Existing Labor Laws And Standards; And 8. [name Of Bidder] Is Aware Of And Has Undertaken The Following Responsibilities As A Bidder: A) Carefully Examine All Of The Bidding Documents; B) Acknowledge All Conditions, Local Or Otherwise, Affecting The Implementation Of The Contract; C) Made An Estimate Of The Facilities Available And Needed For The Contract To Be Bid, If Any; And D) Inquire Or Secure Supplemental/bid Bulletin(s) Issued For The [name Of The Project]. In Witness Whereof, I Have Hereunto Set My Hand This __ Day Of ___, 20__ At ____________, Philippines. _____________________________________ Bidder’s Representative/authorized Signatory [jurat] * This Form Will Not Apply For Wb Funded Projects.
Closing Soon3 Dec 2024
Tender AmountPHP 1 Million (USD 17.7 K)
BULACAN AGRICULTURAL STATE COLLEGE Tender
Civil And Construction...+1Construction Material
Philippines
Details: Description Bulacan Agricultural State College Early Procurement Activity For Construction Of 2-storey Agroforestry Building With Rainwater Catchment Facility November, 2024 Preface These Philippine Bidding Documents (pbds) For The Procurement Of Infrastructure Projects (hereinafter Referred To Also As The “works”) Through Competitive Bidding Have Been Prepared By The Government Of The Philippines For Use By All Branches, Agencies, Departments, Bureaus, Offices, Or Instrumentalities Of The Government, Including Government-owned And/or -controlled Corporations, Government Financial Institutions, State Universities And Colleges, Local Government Units, And Autonomous Regional Government. The Procedures And Practices Presented In This Document Have Been Developed Through Broad Experience, And Are For Mandatory Use In Projects That Are Financed In Whole Or In Part By The Government Of The Philippines Or Any Foreign Government/foreign Or International Financing Institution In Accordance With The Provisions Of The 2016 Revised Implementing Rules And Regulations (irr) Of Republic Act (ra) No. 9184. The Pbds Are Intended As A Model For Admeasurements (unit Prices Or Unit Rates In A Bill Of Quantities) Types Of Contract, Which Are The Most Common In Works Contracting. The Bidding Documents Shall Clearly And Adequately Define, Among Others: (i) The Objectives, Scope, And Expected Outputs And/or Results Of The Proposed Contract; (ii) The Eligibility Requirements Of Bidders; (iii) The Expected Contract Duration; And (iv) The Obligations, Duties, And/or Functions Of The Winning Bidder. Care Should Be Taken To Check The Relevance Of The Provisions Of The Pbds Against The Requirements Of The Specific Works To Be Procured. If Duplication Of A Subject Is Inevitable In Other Sections Of The Document Prepared By The Procuring Entity, Care Must Be Exercised To Avoid Contradictions Between Clauses Dealing With The Same Matter. Moreover, Each Section Is Prepared With Notes Intended Only As Information For The Procuring Entity Or The Person Drafting The Bidding Documents. They Shall Not Be Included In The Final Documents. The Following General Directions Should Be Observed When Using The Documents: A. All The Documents Listed In The Table Of Contents Are Normally Required For The Procurement Of Infrastructure Projects. However, They Should Be Adapted As Necessary To The Circumstances Of The Particular Project. B. Specific Details, Such As The “name Of The Procuring Entity” And “address For Bid Submission,” Should Be Furnished In The Instructions To Bidders, Bid Data Sheet, And Special Conditions Of Contract. The Final Documents Should Contain Neither Blank Spaces Nor Options. C. This Preface And The Footnotes Or Notes In Italics Included In The Invitation To Bid, Bds, General Conditions Of Contract, Special Conditions Of Contract, Specifications, Drawings, And Bill Of Quantities Are Not Part Of The Text Of The Final Document, Although They Contain Instructions That The Procuring Entity Should Strictly Follow. D. The Cover Should Be Modified As Required To Identify The Bidding Documents As To The Names Of The Project, Contract, And Procuring Entity, In Addition To Date Of Issue. E. Modifications For Specific Procurement Project Details Should Be Provided In The Special Conditions Of Contract As Amendments To The Conditions Of Contract. For Easy Completion, Whenever Reference Has To Be Made To Specific Clauses In The Bid Data Sheet Or Special Conditions Of Contract, These Terms Shall Be Printed In Bold Typeface On Sections I (instructions To Bidders) And Iii (general Conditions Of Contract), Respectively. F. For Guidelines On The Use Of Bidding Forms And The Procurement Of Foreign-assisted Projects, These Will Be Covered By A Separate Issuance Of The Government Procurement Policy Board. Table Of Contents Glossary Of Terms, Abbreviations, And Acronyms 5 Section I. Invitation To Bid 8 Section Ii. Instructions To Bidders 11 1. Scope Of Bid 12 2. Funding Information 12 3. Bidding Requirements 12 4. Corrupt, Fraudulent, Collusive, Coercive, And Obstructive Practices 12 5. Eligible Bidders 13 6. Origin Of Associated Goods 13 7. Subcontracts 13 8. Pre-bid Conference 13 9. Clarification And Amendment Of Bidding Documents 13 10. Documents Comprising The Bid: Eligibility And Technical Components 14 11. Documents Comprising The Bid: Financial Component 14 12. Alternative Bids 14 13. Bid Prices 15 14. Bid And Payment Currencies 15 15. Bid Security 15 16. Sealing And Marking Of Bids 15 17. Deadline For Submission Of Bids 16 18. Opening And Preliminary Examination Of Bids 16 19. Detailed Evaluation And Comparison Of Bids 16 20. Post Qualification 16 21. Signing Of The Contract 16 Section Iii. Bid Data Sheet 17 Section Iv. General Conditions Of Contract 20 1. Scope Of Contract 21 2. Sectional Completion Of Works 21 3. Possession Of Site 21 4. The Contractor’s Obligations 21 5. Performance Security 22 6. Site Investigation Reports 22 7. Warranty 22 8. Liability Of The Contractor 22 9. Termination For Other Causes 22 10. Dayworks 23 11. Program Of Work 23 12. Instructions, Inspections And Audits 23 13. Advance Payment 23 14. Progress Payments 23 15. Operating And Maintenance Manuals 24 Section V. Special Conditions Of Contract 25 Section Vi. Specifications 27 Section Vii. Drawings 37 Section Viii. Bill Of Quantities 58 Section Ix. Checklist Of Technical And Financial Documents 67 Glossary Of Terms, Abbreviations, And Acronyms Abc – Approved Budget For The Contract. Arcc – Allowable Range Of Contract Cost. Bac – Bids And Awards Committee. Bid – A Signed Offer Or Proposal To Undertake A Contract Submitted By A Bidder In Response To And In Consonance With The Requirements Of The Bidding Documents. Also Referred To As Proposal And Tender. (2016 Revised Irr, Section 5[c]) Bidder – Refers To A Contractor, Manufacturer, Supplier, Distributor And/or Consultant Who Submits A Bid In Response To The Requirements Of The Bidding Documents. (2016 Revised Irr, Section 5[d]) Bidding Documents – The Documents Issued By The Procuring Entity As The Bases For Bids, Furnishing All Information Necessary For A Prospective Bidder To Prepare A Bid For The Goods, Infrastructure Projects, And/or Consulting Services Required By The Procuring Entity. (2016 Revised Irr, Section 5[e]) Bir – Bureau Of Internal Revenue. Bsp – Bangko Sentral Ng Pilipinas. Cda – Cooperative Development Authority. Consulting Services – Refer To Services For Infrastructure Projects And Other Types Of Projects Or Activities Of The Gop Requiring Adequate External Technical And Professional Expertise That Are Beyond The Capability And/or Capacity Of The Gop To Undertake Such As, But Not Limited To: (i) Advisory And Review Services; (ii) Pre-investment Or Feasibility Studies; (iii) Design; (iv) Construction Supervision; (v) Management And Related Services; And (vi) Other Technical Services Or Special Studies. (2016 Revised Irr, Section 5[i]) Contract – Refers To The Agreement Entered Into Between The Procuring Entity And The Supplier Or Manufacturer Or Distributor Or Service Provider For Procurement Of Goods And Services; Contractor For Procurement Of Infrastructure Projects; Or Consultant Or Consulting Firm For Procurement Of Consulting Services; As The Case May Be, As Recorded In The Contract Form Signed By The Parties, Including All Attachments And Appendices Thereto And All Documents Incorporated By Reference Therein. Contractor – Is A Natural Or Juridical Entity Whose Proposal Was Accepted By The Procuring Entity And To Whom The Contract To Execute The Work Was Awarded. Contractor As Used In These Bidding Documents May Likewise Refer To A Supplier, Distributor, Manufacturer, Or Consultant. Cpi – Consumer Price Index. Dole – Department Of Labor And Employment. Dti – Department Of Trade And Industry. Foreign-funded Procurement Or Foreign-assisted Project – Refers To Procurement Whose Funding Source Is From A Foreign Government, Foreign Or International Financing Institution As Specified In The Treaty Or International Or Executive Agreement. (2016 Revised Irr, Section 5[b]). Gfi – Government Financial Institution. Gocc – Government-owned And/or –controlled Corporation. Goods – Refer To All Items, Supplies, Materials And General Support Services, Except Consulting Services And Infrastructure Projects, Which May Be Needed In The Transaction Of Public Businesses Or In The Pursuit Of Any Government Undertaking, Project Or Activity, Whether In The Nature Of Equipment, Furniture, Stationery, Materials For Construction, Or Personal Property Of Any Kind, Including Non-personal Or Contractual Services Such As The Repair And Maintenance Of Equipment And Furniture, As Well As Trucking, Hauling, Janitorial, Security, And Related Or Analogous Services, As Well As Procurement Of Materials And Supplies Provided By The Procuring Entity For Such Services. The Term “related” Or “analogous Services” Shall Include, But Is Not Limited To, Lease Or Purchase Of Office Space, Media Advertisements, Health Maintenance Services, And Other Services Essential To The Operation Of The Procuring Entity. (2016 Revised Irr, Section 5[r]) Gop – Government Of The Philippines. Infrastructure Projects – Include The Construction, Improvement, Rehabilitation, Demolition, Repair, Restoration Or Maintenance Of Roads And Bridges, Railways, Airports, Seaports, Communication Facilities, Civil Works Components Of Information Technology Projects, Irrigation, Flood Control And Drainage, Water Supply, Sanitation, Sewerage And Solid Waste Management Systems, Shore Protection, Energy/power And Electrification Facilities, National Buildings, School Buildings, Hospital Buildings, And Other Related Construction Projects Of The Government. Also Referred To As Civil Works Or Works. (2016 Revised Irr, Section 5[u]) Lgus – Local Government Units. Nfcc – Net Financial Contracting Capacity. Nga – National Government Agency. Pcab – Philippine Contractors Accreditation Board. Philgeps - Philippine Government Electronic Procurement System. Procurement Project – Refers To A Specific Or Identified Procurement Covering Goods, Infrastructure Project Or Consulting Services. A Procurement Project Shall Be Described, Detailed, And Scheduled In The Project Procurement Management Plan Prepared By The Agency Which Shall Be Consolidated In The Procuring Entity's Annual Procurement Plan. (gppb Circular No. 06-2019 Dated 17 July 2019) Psa – Philippine Statistics Authority. Sec – Securities And Exchange Commission. Slcc – Single Largest Completed Contract. Un – United Nations. Section I. Invitation To Bid Notes On The Invitation To Bid The Invitation To Bid (ib) Provides Information That Enables Potential Bidders To Decide Whether To Participate In The Procurement At Hand. The Ib Shall Be Posted In Accordance With Section 21.2 Of The 2016 Revised Irr Of Ra No. 9184. Apart From The Essential Items Listed In The Bidding Documents, The Ib Should Also Indicate The Following: A. The Date Of Availability Of The Bidding Documents, Which Shall Be From The Time The Ib Is First Advertised/posted Until The Deadline For The Submission And Receipt Of Bids; B. The Place Where The Bidding Documents May Be Acquired Or The Website Where It May Be Downloaded; C. The Deadline For The Submission And Receipt Of Bids; And D. Any Important Bid Evaluation Criteria. The Ib Should Be Incorporated Into The Bidding Documents. The Information Contained In The Ib Must Conform To The Bidding Documents And In Particular To The Relevant Information In The Bid Data Sheet. Bulacan Agricultural State College San Ildefonso, Bulacan, 3010 Invitation To Bid For Early Procurement Activity Construction Of 2-storey Agroforestry Building With Water Catchment Facility] 1. The Bulacan Agricultural State College, Through The General Appropriations Act Of 2025 (gaa) Under The Capital Outlay For The Fy 2025 Intends To Apply The Sum Of Twenty Five Million Pesos (php 25,000,000.00) Being The Approved Budget For The Contract (abc) To Payments Under The Contract For 2024-01-infra: Construction Of 2-storey Agroforestry Building With Water Catchment Facility. Bids Received In Excess Of The Abc Shall Be Automatically Rejected At Bid Opening. 2. The Bulacan Agricultural State College Now Invites Bids For The Above Procurement Project. Completion Of The Works Is Required On Or Before The Two Hundred Seventy (270) Calendar Days. Bidders Should Have Completed A Contract Similar To The Project. The Description Of An Eligible Bidder Is Contained In The Bidding Documents, Particularly, In Section Ii (instructions To Bidders). 3. Bidding Will Be Conducted Through Open Competitive Bidding Procedures Using Non-discretionary “pass/fail” Criterion As Specified In The 2016 Revised Implementing Rules And Regulations (irr) Of Republic Act (ra) No. 9184. 4. Interested Bidders May Obtain Further Information From Bulacan Agricultural State College And Inspect The Bidding Documents At The Address Given Below From From 8:30 Am To 4:30 Pm. 5. A Complete Set Of Bidding Documents May Be Acquired By Interested Bidders On November 9, 2024 To December 2, 2024 From Given Address And Website/s Below And Upon Payment Of The Applicable Fee For The Bidding Documents, Pursuant To The Latest Guidelines Issued By The Gppb, In The Amount Of Twenty Five Thousand Pesos (php 25,000.00). Procuring Entity Shall Allow The Bidder To Present Its Proof Of Payment For The Fees By Presenting The Receipt Upon Submission Of Their Bid Documents. 6. The Bulacan Agricultural State College Will Hold A Pre-bid Conference On November 18, 2024, 09:00 Am Via Zoom Platform (meeting Id: 828 5597 7530; Passcode: 662401) Which Shall Be Open To Prospective Bidders. 7. Bids Must Be Duly Received By The Bac Secretariat Through Manual Submission At The Office Address As Indicated Below On Or Before 08:30 Am Of December 2, 2024. Late Bids Shall Not Be Accepted. 8. All Bids Must Be Accompanied By A Bid Security In Any Of The Acceptable Forms And In The Amount Stated In Itb Clause 16. 9. Bid Opening Shall Be On December 2, 2024, 9:00am At The The Conference Room, Ground Floor, Farmers Training Center, Basc, San Ildefonso, Bulacan. Bids Will Be Opened In The Presence Of The Bidders’ Representatives Who Choose To Attend The Activity. 10. Observers Will Be Invited To Attend And Witness The Bid Proceedings. 11. The Bulacan Agricultural State College Reserves The Right To Reject Any And All Bids, Declare A Failure Of Bidding, Or Not Award The Contract At Any Time Prior To Contract Award In Accordance With Sections 35.6 And 41 Of The 2016 Revised Irr Of Ra No. 9184, Without Thereby Incurring Any Liability To The Affected Bidder Or Bidders. 12. For Further Information, Please Refer To: Rona Angela O. Clarin Bac Secretariat Head Bulacan Agricultural State College Brgy. Pinaod, San Ildefonso, Bulacan (044) 697-1240 And 0923-108-1526 Ronaangela_clarin@basc.edu.ph Www.basc.edu.ph 13. You May Visit The Following Websites: Www.basc.edu.ph November 9, 2024 Ronald Reagan T. Alonzo,ph.d. Bac Chairperson Section Ii. Instructions To Bidders Notes On The Instructions To Bidders This Section On The Instruction To Bidders (itb) Provides The Information Necessary For Bidders To Prepare Responsive Bids, In Accordance With The Requirements Of The Procuring Entity. It Also Provides Information On Bid Submission, Eligibility Check, Opening And Evaluation Of Bids, Post-qualification, And On The Award Of Contract. 1. Scope Of Bid The Procuring Entity, Bulacan Agricultural State College Invites Bids For The Proposed Construction Of 2-storey Agroforestry Building With Water Catchment Facility, With Project Identification Number 2024-01-infra. The Procurement Project (proposed Construction Of 2-storey Agroforestry Building With Water Catchment Facility) Is For The Construction Of Works, As Described In Section Vi (specifications). 2. Funding Information 2.1. The Gop Through The Source Of Funding As Indicated Below For Gaa Fy 2025 In The Amount Of Php25,000,000.00 2.2. The Source Of Funding Is: A. Nga, The National Expenditure Program. 3. Bidding Requirements The Bidding For The Project Shall Be Governed By All The Provisions Of Ra No. 9184 And Its 2016 Revised Irr, Including Its Generic Procurement Manual And Associated Policies, Rules And Regulations As The Primary Source Thereof, While The Herein Clauses Shall Serve As The Secondary Source Thereof. Any Amendments Made To The Irr And Other Gppb Issuances Shall Be Applicable Only To The Ongoing Posting, Advertisement, Or Invitation To Bid By The Bac Through The Issuance Of A Supplemental Or Bid Bulletin. The Bidder, By The Act Of Submitting Its Bid, Shall Be Deemed To Have Inspected The Site, Determined The General Characteristics Of The Contracted Works And The Conditions For This Project, Such As The Location And The Nature Of The Work; (b) Climatic Conditions; (c) Transportation Facilities; (c) Nature And Condition Of The Terrain, Geological Conditions At The Site Communication Facilities, Requirements, Location And Availability Of Construction Aggregates And Other Materials, Labor, Water, Electric Power And Access Roads; And (d) Other Factors That May Affect The Cost, Duration And Execution Or Implementation Of The Contract, Project, Or Work And Examine All Instructions, Forms, Terms, And Project Requirements In The Bidding Documents. 4. Corrupt, Fraudulent, Collusive, Coercive, And Obstructive Practices The Procuring Entity, As Well As The Bidders And Contractors, Shall Observe The Highest Standard Of Ethics During The Procurement And Execution Of The Contract. They Or Through An Agent Shall Not Engage In Corrupt, Fraudulent, Collusive, Coercive, And Obstructive Practices Defined Under Annex “i” Of The 2016 Revised Irr Of Ra No. 9184 Or Other Integrity Violations In Competing For The Project. 5. Eligible Bidders 5.1. Only Bids Of Bidders Found To Be Legally, Technically, And Financially Capable Will Be Evaluated. 5.2. The Bidder Must Have An Experience Of Having Completed A Single Largest Completed Contract (slcc) That Is Similar To This Project, Equivalent To At Least Fifty Percent (50%) Of The Abc Adjusted, If Necessary, By The Bidder To Current Prices Using The Psa’s Cpi, Except Under Conditions Provided For In Section 23.4.2.4 Of The 2016 Revised Irr Of Ra No. 9184. A Contract Is Considered To Be “similar” To The Contract To Be Bid If It Has The Major Categories Of Work Stated In The Bds. 5.3. For Foreign-funded Procurement, The Procuring Entity And The Foreign Government/foreign Or International Financing Institution May Agree On Another Track Record Requirement, As Specified In The Bidding Document Prepared For This Purpose. 5.4. The Bidders Shall Comply With The Eligibility Criteria Under Section 23.4.2 Of The 2016 Irr Of Ra No. 9184. 6. Origin Of Associated Goods There Is No Restriction On The Origin Of Goods Other Than Those Prohibited By A Decision Of The Un Security Council Taken Under Chapter Vii Of The Charter Of The Un. 7. Subcontracts 7.1. The Procuring Entity Has Prescribed That: A. Subcontracting Is Not Allowed. 8. Pre-bid Conference The Procuring Entity Will Hold A Pre-bid Conference For This Project On The Specified Date And Time Via Online Platform As Indicated In Paragraph 6 Of The Ib. 9. Clarification And Amendment Of Bidding Documents Prospective Bidders May Request For Clarification On And/or Interpretation Of Any Part Of The Bidding Documents. Such Requests Must Be In Writing And Received By The Procuring Entity, Either At Its Given Address Or Through Electronic Mail Indicated In The Ib, At Least Ten (10) Calendar Days Before The Deadline Set For The Submission And Receipt Of Bids. 10. Documents Comprising The Bid: Eligibility And Technical Components 10.1. The First Envelope Shall Contain The Eligibility And Technical Documents Of The Bid As Specified In Section Ix. Checklist Of Technical And Financial Documents. 10.2. If The Eligibility Requirements Or Statements, The Bids, And All Other Documents For Submission To The Bac Are In Foreign Language Other Than English, It Must Be Accompanied By A Translation In English, Which Shall Be Authenticated By The Appropriate Philippine Foreign Service Establishment, Post, Or The Equivalent Office Having Jurisdiction Over The Foreign Bidder’s Affairs In The Philippines. For Contracting Parties To The Apostille Convention, Only The Translated Documents Shall Be Authenticated Through An Apostille Pursuant To Gppb Resolution No. 13-2019 Dated 23 May 2019. The English Translation Shall Govern, For Purposes Of Interpretation Of The Bid. 10.3. A Valid Pcab License Is Required, And In Case Of Joint Ventures, A Valid Special Pcab License, And Registration For The Type And Cost Of The Contract For This Project. Any Additional Type Of Contractor License Or Permit Shall Be Indicated In The Bds. 10.4. A List Of Contractor’s Key Personnel (e.g., Project Manager, Project Engineers, Materials Engineers, And Foremen) Assigned To The Contract To Be Bid, With Their Complete Qualification And Experience Data Shall Be Provided. These Key Personnel Must Meet The Required Minimum Years Of Experience Set In The Bds. 10.5. A List Of Contractor’s Major Equipment Units, Which Are Owned, Leased, And/or Under Purchase Agreements, Supported By Proof Of Ownership, Certification Of Availability Of Equipment From The Equipment Lessor/vendor For The Duration Of The Project, As The Case May Be, Must Meet The Minimum Requirements For The Contract Set In The Bds. 11. Documents Comprising The Bid: Financial Component 11.1. The Second Bid Envelope Shall Contain The Financial Documents For The Bid As Specified In Section Ix. Checklist Of Technical And Financial Documents. 11.2. Any Bid Exceeding The Abc Indicated In Paragraph 1 Of The Ib Shall Not Be Accepted. 11.3. For Foreign-funded Procurement, A Ceiling May Be Applied To Bid Prices Provided The Conditions Are Met Under Section 31.2 Of The 2016 Revised Irr Of Ra No. 9184. 12. Alternative Bids Bidders Shall Submit Offers That Comply With The Requirements Of The Bidding Documents, Including The Basic Technical Design As Indicated In The Drawings And Specifications. Unless There Is A Value Engineering Clause In The Bds, Alternative Bids Shall Not Be Accepted. 13. Bid Prices All Bid Prices For The Given Scope Of Work In The Project As Awarded Shall Be Considered As Fixed Prices, And Therefore Not Subject To Price Escalation During Contract Implementation, Except Under Extraordinary Circumstances As Determined By The Neda And Approved By The Gppb Pursuant To The Revised Guidelines For Contract Price Escalation Guidelines. 14. Bid And Payment Currencies 14.1. Bid Prices May Be Quoted In The Local Currency Or Tradeable Currency Accepted By The Bsp At The Discretion Of The Bidder. However, For Purposes Of Bid Evaluation, Bids Denominated In Foreign Currencies Shall Be Converted To Philippine Currency Based On The Exchange Rate As Published In The Bsp Reference Rate Bulletin On The Day Of The Bid Opening. 14.2. Payment Of The Contract Price Shall Be Made In: A. Philippine Pesos. 15. Bid Security 15.1. The Bidder Shall Submit A Bid Securing Declaration Or Any Form Of Bid Security In The Amount Indicated In The Bds, Which Shall Be Not Less Than The Percentage Of The Abc In Accordance With The Schedule In The Bds. 15.2. The Bid And Bid Security Shall Be Valid Until 120 Days From The Opening Of Bids. Any Bid Not Accompanied By An Acceptable Bid Security Shall Be Rejected By The Procuring Entity As Non-responsive. 16. Sealing And Marking Of Bids Each Bidder Shall Submit One Copy Of The Original Of The First And Second Components Of Its Bid And Plus Two (2) Copies Of Each Kind, Labeled As Copy 1 And Copy 2. Each Bidder Shall Submit One Copy Of The First And Second Components Of Its Bid. The Procuring Entity May Request Additional Hard Copies And/or Electronic Copies Of The Bid. However, Failure Of The Bidders To Comply With The Said Request Shall Not Be A Ground For Disqualification. If The Procuring Entity Allows The Submission Of Bids Through Online Submission To The Given Website Or Any Other Electronic Means, The Bidder Shall Submit An Electronic Copy Of Its Bid, Which Must Be Digitally Signed. An Electronic Copy That Cannot Be Opened Or Is Corrupted Shall Be Considered Non-responsive And, Thus, Automatically Disqualified. 17. Deadline For Submission Of Bids The Bidders Shall Submit On The Specified Date And Time And Either At Its Physical Address Or Through Online Submission As Indicated In Paragraph 7 Of The Ib. 18. Opening And Preliminary Examination Of Bids 18.1. The Bac Shall Open The Bids In Public At The Time, On The Date, And At The Place Specified In Paragraph 9 Of The Ib. The Bidders’ Representatives Who Are Present Shall Sign A Register Evidencing Their Attendance. In Case Videoconferencing, Webcasting Or Other Similar Technologies Will Be Used, Attendance Of Participants Shall Likewise Be Recorded By The Bac Secretariat. In Case The Bids Cannot Be Opened As Scheduled Due To Justifiable Reasons, The Rescheduling Requirements Under Section 29 Of The 2016 Revised Irr Of Ra No. 9184 Shall Prevail. 18.2. The Preliminary Examination Of Bids Shall Be Governed By Section 30 Of The 2016 Revised Irr Of Ra No. 9184. 19. Detailed Evaluation And Comparison Of Bids 19.1. The Procuring Entity’s Bac Shall Immediately Conduct A Detailed Evaluation Of All Bids Rated “passed” Using Non-discretionary Pass/fail Criteria. The Bac Shall Consider The Conditions In The Evaluation Of Bids Under Section 32.2 Of 2016 Revised Irr Of Ra No. 9184. 19.2. If The Project Allows Partial Bids, All Bids And Combinations Of Bids As Indicated In The Bds Shall Be Received By The Same Deadline And Opened And Evaluated Simultaneously So As To Determine The Bid Or Combination Of Bids Offering The Lowest Calculated Cost To The Procuring Entity. Bid Security As Required By Itb Clause 16 Shall Be Submitted For Each Contract (lot) Separately. 19.3. In All Cases, The Nfcc Computation Pursuant To Section 23.4.2.6 Of The 2016 Revised Irr Of Ra No. 9184 Must Be Sufficient For The Total Of The Abcs For All The Lots Participated In By The Prospective Bidder. 20. Post Qualification Within A Non-extendible Period Of Five (5) Calendar Days From Receipt By The Bidder Of The Notice From The Bac That It Submitted The Lowest Calculated Bid, The Bidder Shall Submit Its Latest Income And Business Tax Returns Filed And Paid Through The Bir Electronic Filing And Payment System (efps), And Other Appropriate Licenses And Permits Required By Law And Stated In The Bds. 21. Signing Of The Contract The Documents Required In Section 37.2 Of The 2016 Revised Irr Of Ra No. 9184 Shall Form Part Of The Contract. Additional Contract Documents Are Indicated In The Bds. Section Iii. Bid Data Sheet Notes On The Bid Data Sheet (bds) The Bid Data Sheet (bds) Consists Of Provisions That Supplement, Amend, Or Specify In Detail, Information, Or Requirements Included In The Itb Found In Section Ii, Which Are Specific To Each Procurement. This Section Is Intended To Assist The Procuring Entity In Providing The Specific Information In Relation To Corresponding Clauses In The Itb And Has To Be Prepared For Each Specific Procurement. The Procuring Entity Should Specify In The Bds Information And Requirements Specific To The Circumstances Of The Procuring Entity, The Processing Of The Procurement, And The Bid Evaluation Criteria That Will Apply To The Bids. In Preparing The Bds, The Following Aspects Should Be Checked: A. Information That Specifies And Complements Provisions Of The Itb Must Be Incorporated. B. Amendments And/or Supplements, If Any, To Provisions Of The Itb As Necessitated By The Circumstances Of The Specific Procurement, Must Also Be Incorporated. Bid Data Sheet Itb Clause 5.2 For This Purpose, Contracts Similar To The Project Refer To Contracts Which Have The Same Major Categories Of Work, Which Shall Be: Construction, Renovation, Rehabilitation, Repair Of School, Laboratory And Office Buildings. 7.1 Subcontracting Is Not Allowed. 10.3 Appropriate Pcab License Commensurate To The Project. 10.4 The Key Personnel Must Meet The Required Minimum Years Of Experience Set Below: Key Personnel General Experience Relevant Experience Civil Engineer/ Architect At Least 5 Years At Least 5 Years Materials Engineer At Least 5 Years At Least 5 Years Foreman At Least 5 Years At Least 5 Years Safety Officer At Least 5 Years At Least 5 Years Skilled Laborer At Least 3 Years At Least 3 Years Laborer - - 10.5 The Minimum Major Equipment Requirements Are The Following: Equipment Capacity Number Of Units Mini Dump Truck Or Elf Truck 1 Concrete Mixer One Bagger 2 Cut Off/ Bar Cutter - 2 Bar Bender - 2 Concrete Vibrator - 2 Welding Machine Heavy Duty 2 12 Alternative Bids Are Not Allowed. 15.1 The Bid Security Shall Be In The Form Of A Bid Securing Declaration Or Any Of The Following Forms And Amounts: A. The Amount Of Not Less Than Php500,000.0 [two Percent (2%) Of Abc], If Bid Security Is In Cash, Cashier’s/manager’s Check, Bank Draft/guarantee Or Irrevocable Letter Of Credit; B. The Amount Of Not Less Than P1,250,000.00 [ Five Percent (5%) Of Abc] If Bid Security Is In Surety Bond. 19.2 Partial Bids Are Not Allowed. 20 Building Permit, Occupancy Permit, Locational Clearance, Environmental Compliance Certificate, Certification That The Project Site Is Not Within A Geohazard Zone.etc. 21 Additional Contract Documents Relevant To The Project That May Be Required By Existing Laws And/or The Procuring Entity, Such As Construction Schedule And S-curve, Manpower Schedule, Construction Methods, Equipment Utilization Schedule, Construction Safety And Health Program Approved By The Dole, And (pert/cpm) Or Other Acceptable Tools Of Project Scheduling. Section Iv. General Conditions Of Contract Notes On The General Conditions Of Contract The General Conditions Of Contract (gcc) In This Section, Read In Conjunction With The Special Conditions Of Contract In Section V And Other Documents Listed Therein, Should Be A Complete Document Expressing All The Rights And Obligations Of The Parties. Matters Governing Performance Of The Contractor, Payments Under The Contract, Or Matters Affecting The Risks, Rights, And Obligations Of The Parties Under The Contract Are Included In The Gcc And Special Conditions Of Contract. Any Complementary Information, Which May Be Needed, Shall Be Introduced Only Through The Special Conditions Of Contract. 1. Scope Of Contract This Contract Shall Include All Such Items, Although Not Specifically Mentioned, That Can Be Reasonably Inferred As Being Required For Its Completion As If Such Items Were Expressly Mentioned Herein. All The Provisions Of Ra No. 9184 And Its 2016 Revised Irr, Including The Generic Procurement Manual, And Associated Issuances, Constitute The Primary Source For The Terms And Conditions Of The Contract, And Thus, Applicable In Contract Implementation. Herein Clauses Shall Serve As The Secondary Source For The Terms And Conditions Of The Contract. This Is Without Prejudice To Sections 74.1 And 74.2 Of The 2016 Revised Irr Of Ra No. 9184 Allowing The Gppb To Amend The Irr, Which Shall Be Applied To All Procurement Activities, The Advertisement, Posting, Or Invitation Of Which Were Issued After The Effectivity Of The Said Amendment. 2. Sectional Completion Of Works If Sectional Completion Is Specified In The Special Conditions Of Contract (scc), References In The Conditions Of Contract To The Works, The Completion Date, And The Intended Completion Date Shall Apply To Any Section Of The Works (other Than References To The Completion Date And Intended Completion Date For The Whole Of The Works). 3. Possession Of Site 4.1. The Procuring Entity Shall Give Possession Of All Or Parts Of The Site To The Contractor Based On The Schedule Of Delivery Indicated In The Scc, Which Corresponds To The Execution Of The Works. If The Contractor Suffers Delay Or Incurs Cost From Failure On The Part Of The Procuring Entity To Give Possession In Accordance With The Terms Of This Clause, The Procuring Entity’s Representative Shall Give The Contractor A Contract Time Extension And Certify Such Sum As Fair To Cover The Cost Incurred, Which Sum Shall Be Paid By Procuring Entity. 4.2. If Possession Of A Portion Is Not Given By The Above Date, The Procuring Entity Will Be Deemed To Have Delayed The Start Of The Relevant Activities. The Resulting Adjustments In Contract Time To Address Such Delay May Be Addressed Through Contract Extension Provided Under Annex “e” Of The 2016 Revised Irr Of Ra No. 9184. 4. The Contractor’s Obligations The Contractor Shall Employ The Key Personnel Named In The Schedule Of Key Personnel Indicating Their Designation, In Accordance With Itb Clause 10.3 And Specified In The Bds, To Carry Out The Supervision Of The Works. The Procuring Entity Will Approve Any Proposed Replacement Of Key Personnel Only If Their Relevant Qualifications And Abilities Are Equal To Or Better Than Those Of The Personnel Listed In The Schedule. 5. Performance Security 5.1. Within Ten (10) Calendar Days From Receipt Of The Notice Of Award From The Procuring Entity But In No Case Later Than The Signing Of The Contract By Both Parties, The Successful Bidder Shall Furnish The Performance Security In Any Of The Forms Prescribed In Section 39 Of The 2016 Revised Irr. 5.2. The Contractor, By Entering Into The Contract With The Procuring Entity, Acknowledges The Right Of The Procuring Entity To Institute Action Pursuant To Ra No. 3688 Against Any Subcontractor Be They An Individual, Firm, Partnership, Corporation, Or Association Supplying The Contractor With Labor, Materials And/or Equipment For The Performance Of This Contract. 6. Site Investigation Reports The Contractor, In Preparing The Bid, Shall Rely On Any Site Investigation Reports Referred To In The Scc Supplemented By Any Information Obtained By The Contractor. 7. Warranty 7.1. In Case The Contractor Fails To Undertake The Repair Works Under Section 62.2.2 Of The 2016 Revised Irr, The Procuring Entity Shall Forfeit Its Performance Security, Subject Its Property(ies) To Attachment Or Garnishment Proceedings, And Perpetually Disqualify It From Participating In Any Public Bidding. All Payables Of The Gop In His Favor Shall Be Offset To Recover The Costs. 7.2. The Warranty Against Structural Defects/failures, Except That Occasioned-on Force Majeure, Shall Cover The Period From The Date Of Issuance Of The Certificate Of Final Acceptance By The Procuring Entity. Specific Duration Of The Warranty Is Found In The Scc. 8. Liability Of The Contractor Subject To Additional Provisions, If Any, Set Forth In The Scc, The Contractor’s Liability Under This Contract Shall Be As Provided By The Laws Of The Republic Of The Philippines. If The Contractor Is A Joint Venture, All Partners To The Joint Venture Shall Be Jointly And Severally Liable To The Procuring Entity. 9. Termination For Other Causes Contract Termination Shall Be Initiated In Case It Is Determined Prima Facie By The Procuring Entity That The Contractor Has Engaged, Before, Or During The Implementation Of The Contract, In Unlawful Deeds And Behaviors Relative To Contract Acquisition And Implementation, Such As, But Not Limited To Corrupt, Fraudulent, Collusive, Coercive, And Obstructive Practices As Stated In Itb Clause 4. 10. Dayworks Subject To The Guidelines On Variation Order In Annex “e” Of The 2016 Revised Irr Of Ra No. 9184, And If Applicable As Indicated In The Scc, The Dayworks Rates In The Contractor’s Bid Shall Be Used For Small Additional Amounts Of Work Only When The Procuring Entity’s Representative Has Given Written Instructions In Advance For Additional Work To Be Paid For In That Way. 11. Program Of Work 11.1. The Contractor Shall Submit To The Procuring Entity’s Representative For Approval The Said Program Of Work Showing The General Methods, Arrangements, Order, And Timing For All The Activities In The Works. The Submissions Of The Program Of Work Are Indicated In The Scc. 11.2. The Contractor Shall Submit To The Procuring Entity’s Representative For Approval An Updated Program Of Work At Intervals No Longer Than The Period Stated In The Scc. If The Contractor Does Not Submit An Updated Program Of Work Within This Period, The Procuring Entity’s Representative May Withhold The Amount Stated In The Scc From The Next Payment Certificate And Continue To Withhold This Amount Until The Next Payment After The Date On Which The Overdue Program Of Work Has Been Submitted. 12. Instructions, Inspections And Audits The Contractor Shall Permit The Gop Or The Procuring Entity To Inspect The Contractor’s Accounts And Records Relating To The Performance Of The Contractor And To Have Them Audited By Auditors Of The Gop Or The Procuring Entity, As May Be Required. 13. Advance Payment The Procuring Entity Shall, Upon A Written Request Of The Contractor Which Shall Be Submitted As A Contract Document, Make An Advance Payment To The Contractor In An Amount Not Exceeding Fifteen Percent (15%) Of The Total Contract Price, To Be Made In Lump Sum, Or At The Most Two Installments According To A Schedule Specified In The Scc, Subject To The Requirements In Annex “e” Of The 2016 Revised Irr Of Ra No. 9184. 14. Progress Payments The Contractor May Submit A Request For Payment For Work Accomplished. Such Requests For Payment Shall Be Verified And Certified By The Procuring Entity’s Representative/project Engineer. Except As Otherwise Stipulated In The Scc, Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Not Be Included For Payment. 15. Operating And Maintenance Manuals 15.1. If Required, The Contractor Will Provide “as Built” Drawings And/or Operating And Maintenance Manuals As Specified In The Scc. 15.2. If The Contractor Does Not Provide The Drawings And/or Manuals By The Dates Stated Above, Or They Do Not Receive The Procuring Entity’s Representative’s Approval, The Procuring Entity’s Representative May Withhold The Amount Stated In The Scc From Payments Due To The Contractor. Section V. Special Conditions Of Contract Notes On The Special Conditions Of Contract Similar To The Bds, The Clauses In This Section Are Intended To Assist The Procuring Entity In Providing Contract-specific Information In Relation To Corresponding Clauses In The Gcc Found In Section Iv. The Special Conditions Of Contract (scc) Complement The Gcc, Specifying Contractual Requirements Linked To The Special Circumstances Of The Procuring Entity, The Procuring Entity’s Country, The Sector, And The Works Procured. In Preparing This Section, The Following Aspects Should Be Checked: A. Information That Complements Provisions Of The Gcc Must Be Incorporated. B. Amendments And/or Supplements To Provisions Of The Gcc As Necessitated By The Circumstances Of The Specific Purchase, Must Also Be Incorporated. However, No Special Condition Which Defeats Or Negates The General Intent And Purpose Of The Provisions Of The Gcc Should Be Incorporated Herein. Special Conditions Of Contract Gcc Clause 2 The Intended Completion Date Of Construction Of 2-storey Agroforestry Building With Rainwater Catchment Facility Is Two Hundred Seventy (270) Calendar Days From The Date Of The Receipt Of Notice To Proceed. 4.1 The Schedule Of Delivery Of The Possession Of The Site To The Contractor Is Upon The Receipt Of The Notice To Proceed. 6 The Site Investigation Reports Are: 7.2 In Case Of Permanent Structures, Such As Buildings Of Types 4 And 5 As Classified Under The National Building Code Of The Philippines And Other Structures Made Of Steel, Iron, Or Concrete Which Comply With Relevant Structural Codes (e.g., Dpwh Standard Specifications), Such As, But Not Limited To, Steel/concrete Bridges, Flyovers, Aircraft Movement Areas, Ports, Dams, Tunnels, Filtration And Treatment Plants, Sewerage Systems, Power Plants, Transmission And Communication Towers, Railway System, And Other Similar Permanent Structures:] Fifteen (15) Years. 10 A. Dayworks Are Applicable At The Rate Shown In The Contractor’s Original Bid. 11.1 The Contractor Shall Submit The Program Of Work To The Procuring Entity’s Representative Within 7 Calendar Days Of Delivery Of The Notice Of Award. 11.2 The Amount To Be Withheld For Late Submission Of An Updated Program Of Work Is 1% Of The Progress Billing. 13 The Amount Of The Advance Payment Is Fifteen Percent (15%) Of The Contract Price To Be Paid Upon Written Request Of The Contractor Reconciling On The Date Of The Notice To Proceed And Upon Submission Of An Irrevocable Standby Letter Of Credit Of Equivalent Value From A Commercial Bank, And Bank Guarantee Or A Surety Bond Callable Upon Demand, Issued By A Surety Or Insurance Company Duly Licensed By The Insurance Commission. 14 Materials And Equipment Delivered On The Site But Not Completely Put In Place Shall Not Be Included For Payment. 15.1 The Date By Which “as Built” Drawings Are Required Is Fifteen (15) Calendar Days From Completion Of Project. 15.2 The Amount To Be Withheld For Failing To Produce “as Built” Drawings And/or Operating And Maintenance Manuals By The Date Required Is 0.1% Of The Final Contract Amount. Section Vi. Specifications Notes On Specifications A Set Of Precise And Clear Specifications Is A Prerequisite For Bidders To Respond Realistically And Competitively To The Requirements Of The Procuring Entity Without Qualifying Or Conditioning Their Bids. In The Context Of International Competitive Bidding, The Specifications Must Be Drafted To Permit The Widest Possible Competition And, At The Same Time, Present A Clear Statement Of The Required Standards Of Workmanship, Materials, And Performance Of The Goods And Services To Be Procured. Only If This Is Done Will The Objectives Of Economy, Efficiency, And Fairness In Procurement Be Realized, Responsiveness Of Bids Be Ensured, And The Subsequent Task Of Bid Evaluation Facilitated. The Specifications Should Require That All Goods And Materials To Be Incorporated In The Works Be New, Unused, Of The Most Recent Or Current Models, And Incorporate All Recent Improvements In Design And Materials Unless Provided Otherwise In The Contract. Samples Of Specifications From Previous Similar Projects Are Useful In This Respect. The Use Of Metric Units Is Mandatory. Most Specifications Are Normally Written Specially By The Procuring Entity Or Its Representative To Suit The Works At Hand. There Is No Standard Set Of Specifications For Universal Application In All Sectors In All Regions, But There Are Established Principles And Practices, Which Are Reflected In These Pbds. There Are Considerable Advantages In Standardizing General Specifications For Repetitive Works In Recognized Public Sectors, Such As Highways, Ports, Railways, Urban Housing, Irrigation, And Water Supply, In The Same Country Or Region Where Similar Conditions Prevail. The General Specifications Should Cover All Classes Of Workmanship, Materials, And Equipment Commonly Involved In Construction, Although Not Necessarily To Be Used In A Particular Works Contract. Deletions Or Addenda Should Then Adapt The General Specifications To The Particular Works. Care Must Be Taken In Drafting Specifications To Ensure That They Are Not Restrictive. In The Specification Of Standards For Goods, Materials, And Workmanship, Recognized International Standards Should Be Used As Much As Possible. Where Other Particular Standards Are Used, Whether National Standards Or Other Standards, The Specifications Should State That Goods, Materials, And Workmanship That Meet Other Authoritative Standards, And Which Ensure Substantially Equal Or Higher Quality Than The Standards Mentioned, Will Also Be Acceptable. The Following Clause May Be Inserted In The Scc. Sample Clause: Equivalency Of Standards And Codes Wherever Reference Is Made In The Contract To Specific Standards And Codes To Be Met By The Goods And Materials To Be Furnished, And Work Performed Or Tested, The Provisions Of The Latest Current Edition Or Revision Of The Relevant Standards And Codes In Effect Shall Apply, Unless Otherwise Expressly Stated In The Contract. Where Such Standards And Codes Are National, Or Relate To A Particular Country Or Region, Other Authoritative Standards That Ensure A Substantially Equal Or Higher Quality Than The Standards And Codes Specified Will Be Accepted Subject To The Procuring Entity’s Representative’s Prior Review And Written Consent. Differences Between The Standards Specified And The Proposed Alternative Standards Shall Be Fully Described In Writing By The Contractor And Submitted To The Procuring Entity’s Representative At Least Twenty-eight (28) Days Prior To The Date When The Contractor Desires The Procuring Entity’s Representative’s Consent. In The Event The Procuring Entity’s Representative Determines That Such Proposed Deviations Do Not Ensure Substantially Equal Or Higher Quality, The Contractor Shall Comply With The Standards Specified In The Documents. These Notes Are Intended Only As Information For The Procuring Entity Or The Person Drafting The Bidding Documents. They Should Not Be Included In The Final Bidding Documents. Proposed Construction Of 2-storey Agroforestry Building With Rainwater Catchment Facility Basc Drt Campus Technical Specifications Bulacan Agricultural State College Pinaod, San Ildefonso, Bulacan November 2024 Specifications 1. General Requirements 1.1 These Specifications Are Intended To Cover All Labor And Materials Required For The Complete Construction Of The Proposed Projects As Shown In The Working Drawings As Described Herein. 1.2 Materials And/ Or Work Not Specifically Mentioned In The Specifications, Working Drawings, And Other Contract Documents But Is Implied And Deemed Necessary To Complete The Work Shall Be Supplied By The Contractor And Executed In A Workman-like Manner, Of Appropriate Number, Location, And Size Of The Highest Quality Available Without Extra Cost To The Owner. 1.3 The Owner Reserves The Right To Alter And/or Omit Any Part Of The Plans With The Approval Of The Architect Or Engineer As The Case May Be. Any Extra Charge Must Be Situated To The Architect And/or Project Manager For Approval Before Final Acceptance. 1.4 The Contractor Shall Secure All Permits And Licenses As Required And Also Shall Be Responsable For All The Liabilities, Under Workmen’s Compensation, Sss, Insurance, Etc. 1.5 The Contractor Shall Furnish For Approval Of The Architect/engineer, With Promptness, Samples As Specified Or Required. Works Shall Be In Accordance With The Approved Samples. 1.6 The Contractor Shall Guarantee The Words, Except For Those With Specific Guarantee For A Period Of One (1) Year After Final Acceptance By The Owner. He Shall Repair,replace And Make Good At His Expenses Any And All Defects, Which May Arise During That Term Of Guarantee And Warranty Due To Defective Workmanship And/or Interior Quality Of Materials. 2. Methods Of Construction 2.1 The Construction Shall Be Done In The Manner That Would Cause Least Disturbance To Neighborhood And Occupant Of The Area. The Contractor Will Be Allowed To Work 24 Hours If Necessary To Complete The Work On Time Subject To Approval Of The Owner. 2.2 All Works To Be Done Shall Be Of The Best Quality And Workmanship. 3. Masonry 3.1 Exterior Wall Should Be Chb 5 Inches Wall Bearing With 10 Mm Diameter Reinforcement Bars Spaced @ 0.80 Meter For Vertical And For Every 3 Layers Of Chb For Horizontal Bars. 3.2 Partition Wall Should Be Chb 4 Inches With 10 Mm Diameter Reinforcement Bars Spaced @ 0.80 Meter For Vertical And For Every 3 Layers Of Chb For Horizontal Bars In Rooms,hallway,and Toilet. 3.3 Low Partition Should Be Chb 4 Inches 1.80 Meters High With 10 Mm Diameter Reinforcement Bars Spaced @ 0.80 Meters For Vertical And For Every 3 Layer Of Chb For Horizontal Bars In Toilet Partition/cubicles. 4. Wall Finishes 4.1. Interior Walls Finishes Should Be Smooth Plain Cement Plaster; Concrete Neutralizer Treatment; Patching; Paint Finish (boysen Paint Or Approved Equal) W/ 4” Base Board. Note: Patchwork Should Be Followed With One Coat Of Concrete Primer As Primer-surfacer To Reduce Unsightly Uneven Appearance After Topcoat Application. 4.2. Exterior Wall Finishes Should Be Smooth Plain Cement Plaster; Concrete Neutralizer Treatment; Patching; 2 Coat Paint Finish (boysen Paint Or Approved Equal). 4.3. Provide 40 Cm X 40 Cm Glazed Wall Tiles (eurotiles Or Approved Equal) From Finish Floor Line To 1.80 Meter High, For All Toilet And Cubicles 4.4. Provide 40 Cm X 40 Cm Glazed Wall Tiles (eurotiles Or Approved Equal) For Splashboards For Lavatories In Laboratory/ Kitchen. 4.5. Provide 2” Thick Simulated Stone Cladding (asi, Stone Age Or Approved Equal), See Plans And Drawings. 5. Ceiling Finishes 5.1. All Interior Ceiling - 6 Mm Thick Fiber Cement Hardiflex Ceiling Board Riveted On Metal Furring Channels Providing A V-cut In Every Joint; Prevent Rivet Head To Exposed In Ceiling Surface; Patching All Rivets And Joints W/ Skim Coat; 2 Coat Paint Finish Flat Latex Paint (boysen Or Approved Equal). 5.2. Outside Ceiling – 8” X L X 0.4 Mm Thick Spandrel (union Brand Or Approved Equal). 5.3. Provide Eaves Hole For Ventilation (see Plans And Drawings) 5.4. Provide 4” Ceiling Drop If Necessary (see Plans And Drawings). 6. Carpentry Works 6.1. Cabinets Beneath The Lavatory/ Kitchen Counters In 2” X 3” Kd Treated Wood Frame; ¾” Mdf Membrane Press Doors W/ Liston; Paint Finish. 6.2. Provide Concealed Hinges And Handle For Cabinet Doors. 6.3. All Door Jamb Should Be 2’ X 6” Steel, Paint Finish. 7. Doors/hardwares 7.1. 1.0 M X 2.1 M X 41 Mm Thick Kiln Dry Solid Panel-type Door W/ Simulated Wood Grain Including 50 Mm X 150 Mm Solid Door Jamb W/ Simulated Wood Grain; Varnish Finish. For Classrooms (see Plans And Drawings). 7.2. 0.9 M X 1.2 M Flush Door W/ Jamb, For Common And Pwd Cr; Varnish Finish 7.3. 0.6 M X 1.60 M Aluminum (analok) Door W/ Handle, Hinges And Locksets For Cubicle In Toilets. 7.4. 0.8m X 2.1 M X 41 Mm Thick Kiln Dry Solid Panel-type Door W/ Simulated Wood Grain Including 50 Mm X 150 Mm Solid Door Jamb W/ Simulated Wood Grain; For Stockroom/electrical Room/beneath The Stairs; Varnish Finish. 7.5. Provide 1 Set Of Door Knob (yale Or Approved Equal) And 4 Pcs Of 3-1/2” Hinges (loose Pin Stanley Or Approved Equal) Each Panel-type Door. 8. Windows 8.1. 2.4 M X 1.2 M And 1.2 M X 1.2m Sliding Window 0.90m From Finísh Floor Line For Classrooms (see Plans And Drawings) 8.2. 0.5 M X 0.5 M And 0.6 M X 1.2 M Aluminum And Glass Awning Window Elevated 1.80m & 1.55m From Finísh Floor Line For Toilets. (see Plans And Drawings) 8.2. 1.2 M X 1.8 M Aluminum And Glass Awning & Fixed Type Window Elevated 0.35m From Finísh Floor Line For Ramps. (see Plans And Drawings) 8.3. All Windows Shall Have Grills Made Of 1” X 1” X 1.2 Mm Thick Galvanize Iron Square Tube Welded Except For Ramp Windows (see Plans And Drawings); Quick Drying Enamel Paint Finish. 8.4. All Aluminum Frames Shall Be Of The Best Quality, Analok Finish Free From Internal Defects. 8.5. All Glass Shall Be ¼” Thick Brown In Color, Unless Specify On Plan. 9. Tile Works 9.1. 60 Cm X 60 Cm Non-skid Tiles, Eurotiles Or Approved Equal, For Flooring At All Floors And 60 Cm X 60 Cm Unglazed For Hallways (submit Sample For Approval). 9.2. 30 Cm X 30 Cm Unglazed Tiles, Eurotiles Or Approved Equal For Landing,thread,and Riser In All Stairs. (submit Sample For Approval). 9.3. 30 Cm X 30 Cm Unglazed Tiles, Eurotiles Or Approved Equal, For Walls Of Toilets And Cubicles. (submit Sample For Approval). 9.4. 60 Cm X 60 Cm Doublé Polish Glazed Tiles, Eurotiles Or Approved Equal For Countertops For Sink And Lavatories. (submit Sample For Approval). 9.5. Provide Tile Grout For Tile Joints. 9.6. Provide 2 Coats Of Wáter Proofing Before Laying Of Floor Tiles In All Toilets In The Second Floor-fourth Floor. 10. Sanitary Work/ Fittings & Fixtures 10.1. Fittings & Fixtures 10.1.1. Wáter Closet - Closed-coupled Wáter Closet Dual Flush By Pozzi Or Approved Equal W/ Complete Fittings And Accessories. (submit Sample For Approval). 10.1.2. Lavatory - Basin-type Counter Lavatory By Pozzi Or Approved Equal W/ Complete Fittings And Accessories. (submit Sample For Approval). 10.1.3. Lavatory Faucet - Basin Mixer W/ Complete Accessories By Hcg Or Approved Equal And Hose Bibb For Every Wáter Closet. (submit Sample For Approval). 10.1.4. Urinal - Wash Down/ Gravity-flushing By Hcg Or Approved Equal W/ Complete Fittings And Accessories. (submit Sample For Approval) 10.1.5. Soap Holder – By Pozzi Or Approved Equal. 10.1.6. Tissue Holder – By Pozzi Or Approved Equal. 10.1.7. Floor Drain – 4” X 4” Stainless Steel Floor Drain. 10.2. 25 Mm And 20 Mm Polypropylene Random (ppr) Pipes And Ppr Fittings For Wáter Supply Lines/ Cold Wáter Lines. (as Per Plan). 10.3. 100mm (4”) And 50 Mm (2”) Diameter Unplasticized Polyvinyl Chloride (upvc) Sanitary Pipes And Fittings (neltex Orange Series 1000). (as Per Plan). 10.4. One (1) Septic Tank (as Per Plan) 10.5. Drainage System And Catch Basins (as Per Plan) 10.6. Provide P-trap To All Floor Drains And Sink. 11. Painting Works Materials Brand – Boysen Or Approved Equal. 11.1. For Interior/exterior Concrete Plaster: Pre-treatment : Concrete Neutralizer. Test With Litmus Or Ph Paper First Coat : Water-based Epoxy Primer (for Badly Weathered Concrete Or When Long Lasting Durability Is Desired) Patchwork : Patch-eeze Patching Compound. Note: Patchwork Should Be Followed With One Coat Of Concrete Primer As Primer-surfacer To Reduce Unsightly Uneven Appearance After Topcoat Application. Second Coat : Two (2) Coats Of Semi-gloss Latex. 12.2. For Interior Ceilings: First Coat : Interior Primer And Sealer Patchwork : Skim Coat Second Coat : Two (2) Coats Of Flat Latex 12.3. For Interior Woodworks And Doors: First Coat : Wood Putty Second Coat : Two (2) Coats Of Quick Drying Enamel. 12. Electrical Works 12.1. Wires / Conductors 12.1.1. Power Line - Insulated Copper Wire For 600v Level, Thw For Main Feeder And Tw For Load Side, Sycwin, Philflex Or Approved Equal. 12.2. Conduits 12.2.1. Service Entrance – Rigid Steel Consduit (rsc), Galvanized Iron Schedule 40. 12.2.2. Internal & Embedded – Pvc Pipes By Powerguard Or Approved Equal 12.3. Fixtures & Devices 12.3.1. Utility Box – 2” X 4” Poly Or Approved Equal. 12.3.2. Junction Box – 4” X 4” W/ Cover Poly Or Approved Equal. 12.3.3. Switches – 2” X 4” Switch Set By Panasonic Or Approved Equal (1 Gang/2 Gang/3 Gang) See Plans And Drawings. 12.3.4. Outlets – 2” X 4” Dúplex Convenience Outlet Set By Panasonic Or Approved Equal. 12.3.5. Panel Board – Ga. # 16 Metal Enclosure With Copper Bus Bar, Dead Front, Flush Mounted, Nema Brand Or Approved Equal. 12.3.6. Circuit Breaker – Molded Case Polyester Resin, Bolt Ton Type Thermal Magnetic Type, Common Internal Trip, 250v Ac, 10kaic Mínimum, General Electric Or Approved Equal (ampere Rating As Specified On Plans). 12.3.7. Grounding System – 16 Mm Dia. X 3000mm Hot Dipped Galvanized Steel Ground Rod. 12.4. Lighting Fixtures 12.4.1. Louver 4x20 With 20 Watts Luminaire Led T8 Light W/ Aluminum Reflector (surface Type). 15.4.2. 6” Dia. Receptacle W/ 16 Watts Led Bulb Firefly Or Approved Equal. 13. Concrete Works 14.1. Class A Mixture (1 Part Portland Cement, 2 Part Sand, And 4 Part Gravel) For Slabs In 2nd Floor And Landings, Stairs, Columns, Beams, Lintel Beams, Tie Beams, Column Footings, Wall Footings, Canopy And Septic Tank. 14.2. Class B Mixture (1 Part Portland Cement, 2-1/2 Part Sand, And 5 Part Gravel) For Slabs In Ground Floor And All Other Concrete Not Mention In 14.1. 14.3. Cement Plaster Must Be 1 Part Portland Cement, And 3 Part Sand. 14. Miscellaneous 14.1. Provide ¼” Thick X 4 Ft. High Mirror Glass For Wall Of All Toilets Covering The Entire Length Of Countertops Of Lavatory. 14.2. Provide Peebles Stone Or Waffle Tiles For All Ramp-up And Exterior Steps/stairs Covering The Thread And Riser. 14.3. Stairs And Pwd Ramp-up - Provide 2” Ø X 1.5 Mm Thick Stainless Tube (mirror Type Sus 304) For Stairs Handrail And Main Post; 1-1/2” Ø X 1.5 Mm Thick Stainless Tube For Vertical Members; 1” Ø X 1.5 Mm Thick Stainless Tube For Horizontal Members. Buffing Finish. 14.4. Corridor Railing – Provide 2” Ø Pipe For Handrail; All Joints Must Be Welded Together. Paint Finish. 14.5. Provide 4 Ceiling Fan 16” (asahi Or Approved Equal) Each Classroom. 14.6. Provide 2 Sets Of 4’ X 8’ White Board W/ Aluminum Frame Each Classroom. 14.7. Provide 35 Sets Of Arm Chair (monoblock) Each Classroom. 14.8. Provide Teacher’s Table & Chair Each Classroom. 14.9. Provide Fire Extinguisher 10lbs For Each Classroom. 14.10. Provide Emergency Light For Each Classroom. 14.11. Provide Emergency Fire Alarm For Every Floor. 14.12. Provide Exhaust Fan 12” At Each Toilet. Provide Also Manhole Cover At Each Toilet And Storage Room On Both Floors. 14.13. Provide 4-ibc (intermediate Bulk Container) Tanks For Rainwater Catchment (1000 L Capacity Each), 2- Elevated Wáter Tank (1000 L Capacity Each) (install Horizontal) With Booster Pump 1.5hp. 14.14. Provide Also Pvc Accordion Type Partition At 2ndfloor. 14.15. Provide 10mm Roof Insulation Double-sided At Roofing. 14.16. Provide (2) Sets Of Split Type Airconditioning Unit 2hp – Supply And Install Section Vii. Drawings Section Viii. Bill Of Quantities Notes On The Bill Of Quantities Objectives The Objectives Of The Bill Of Quantities Are: A. To Provide Sufficient Information On The Quantities Of Works To Be Performed To Enable Bids To Be Prepared Efficiently And Accurately; And B. When A Contract Has Been Entered Into, To Provide A Priced Bill Of Quantities For Use In The Periodic Valuation Of Works Executed. In Order To Attain These Objectives, Works Should Be Itemized In The Bill Of Quantities In Sufficient Detail To Distinguish Between The Different Classes Of Works, Or Between Works Of The Same Nature Carried Out In Different Locations Or In Other Circumstances Which May Give Rise To Different Considerations Of Cost. Consistent With These Requirements, The Layout And Content Of The Bill Of Quantities Should Be As Simple And Brief As Possible. Daywork Schedule A Daywork Schedule Should Be Included Only If The Probability Of Unforeseen Work, Outside The Items Included In The Bill Of Quantities, Is High. To Facilitate Checking By The Entity Of The Realism Of Rates Quoted By The Bidders, The Daywork Schedule Should Normally Comprise The Following: A. A List Of The Various Classes Of Labor, Materials, And Constructional Plant For Which Basic Daywork Rates Or Prices Are To Be Inserted By The Bidder, Together With A Statement Of The Conditions Under Which The Contractor Will Be Paid For Work Executed On A Daywork Basis. B. Nominal Quantities For Each Item Of Daywork, To Be Priced By Each Bidder At Daywork Rates As Bid. The Rate To Be Entered By The Bidder Against Each Basic Daywork Item Should Include The Contractor’s Profit, Overheads, Supervision, And Other Charges. Provisional Sums A General Provision For Physical Contingencies (quantity Overruns) May Be Made By Including A Provisional Sum In The Summary Bill Of Quantities. Similarly, A Contingency Allowance For Possible Price Increases Should Be Provided As A Provisional Sum In The Summary Bill Of Quantities. The Inclusion Of Such Provisional Sums Often Facilitates Budgetary Approval By Avoiding The Need To Request Periodic Supplementary Approvals As The Future Need Arises. Where Such Provisional Sums Or Contingency Allowances Are Used, The Scc Should State The Manner In Which They Will Be Used, And Under Whose Authority (usually The Procuring Entity’s Representative’s). The Estimated Cost Of Specialized Work To Be Carried Out, Or Of Special Goods To Be Supplied, By Other Contractors Should Be Indicated In The Relevant Part Of The Bill Of Quantities As A Particular Provisional Sum With An Appropriate Brief Description. A Separate Procurement Procedure Is Normally Carried Out By The Procuring Entity To Select Such Specialized Contractors. To Provide An Element Of Competition Among The Bidders In Respect Of Any Facilities, Amenities, Attendance, Etc., To Be Provided By The Successful Bidder As Prime Contractor For The Use And Convenience Of The Specialist Contractors, Each Related Provisional Sum Should Be Followed By An Item In The Bill Of Quantities Inviting The Bidder To Quote A Sum For Such Amenities, Facilities, Attendance, Etc. Signature Box A Signature Box Shall Be Added At The Bottom Of Each Page Of The Bill Of Quantities Where The Authorized Representative Of The Bidder Shall Affix His Signature. Failure Of The Authorized Representative To Sign Each And Every Page Of The Bill Of Quantities Shall Be A Cause For Rejection Of His Bid. These Notes For Preparing A Bill Of Quantities Are Intended Only As Information For The Procuring Entity Or The Person Drafting The Bidding Documents. They Should Not Be Included In The Final Documents. Bill Of Quantities Item Description Unit Qty Unit Cost Amount I. Design And Permit A. Detailed Engineering And Architectural Design Lot 1.00 250,000.00 250,000.00 B. Permits, Insurance And Bonds Lot 1.00 Ii. General Requirements A. Mobilization/demobilization Lot 1.00 B. Temporary Facilities Lot 1.00 C. Safety And Health Requirements Lot 1.00 Ii. Earth Works A. Staking And Layout Lot 1.00 B. Excavation Works Cu.m 242.43 C. Backfilling Works Cu.m 170.90 D. Gravel Bedding Cu.m 35.75 E. Soil Poisoning Lot 1.00 F. Disposal And Hauling Of Materials Lot 1.00 Iii. Structural/civil Works A. Concrete Works Structural Concrete Cu.m 369.38 Reinforcing Steel Including Ties Kgs 38,213.68 Formworks And Scaffoldings Sq.m 2,755.79 B. Roof Framing Works Lot 1.00 Iv. Architectural Works A. Masonry Works Sq.m 1,820.07 B. Ceiling Works Sq.m 650.00 C. Floor Finishes Sq.m 1,073.16 D. Wall Finishes Sq.m 1,820.07 E. Doors And Windows 1000x2100 Solid Wood (tanguile) Panel Door With 50x150mm Steel Jamb; Complete With Hardware And Accessories Keyed Entry Door Knob; Varnish Finish Sets 16.00 900x2100 Solid Wood (tanguile) Panel Door With Stainless Steel Kick Plate On 50x150mm Steel Jamb; Complete With Hardware And Accessories Keyed Entry Door Knob; Varnish Finish Sets 2.00 900x2100 Solid Wood (tanguile) Panel Door With 50x150mm Steel Jamb; Complete With Hardware And Accessories Keyed Entry Door Knob; Varnish Finish Sets 4.00 800x1200 Aluminum Panel Door On 50x150mm Steel Jamb; Complete With Hardware And Accessories Latch Lock Sets 14.00 800x2100 Solid Wood (tanguile) Panel Door 50x150mm Steel Jamb; Complete With Hardware And Accessories Keyed Entry Door Knob; Varnish Finish Sets 6.00 2400x1200 6mm Clear Ordinary Glasss On Powder Coated Aluminum Framed Sliding Type Window With 1"x1" Tubular Spaced @4in Window Grills Steel; Provide With Complete Hardware Accessories Sets 16.00 1150x1200 6mm Clear Ordinary Glasss On Powder Coated Aluminum Framed Sliding Type Window With 1"x1" Tubular Spaced @4in Window Grills Steel; Provide With Complete Hardware Accessories Sets 16.00 1200x1800 6mm Thk Tempered Glass On Powder Coated Aluminum Frame Fixed & Awning Type Window; Provide With Complete Hardware Accessories Sets 3.00 600x1600 6mm Clear Ordinary Glasss On Powder Coated Aluminum Framed Awning Type Window With 1"x1" Tubular Spaced @4in Window Grills Steel; Provide With Complete Hardware Accessories Sets 4.00 500x500 6mm Clear Ordinary Glasss On Powder Coated Aluminum Framed Awning Type Window With 1"x1" Tubular Spaced @4in Window Grills Steel; Provide With Complete Hardware Accessories Sets 2.00 F. Thermal & Moisture Protection Lot 1.00 G. Railings Lot 1.00 H. Tinsmithry Works Lot 1.00 Including Pe Insulation 10mm X Double Sided I. Miscellaneous Emergency Light. Twinhead Sets 12.00 White Board, 4'x8' With Eraser Sets 16.00 Teacher's Tables, Wooden With Cabinet Sets 8.00 Teacher's Chair Sets 8.00 Student Arm Chair, Plastic Sets 280.00 V. Electrical Works A. Roughing Ins Lot 1.00 B. Wires And Cables Lot 1.00 C. Lighting Fixtures Lot 1.00 D. Wiring Devices Lot 1.00 Vi. Mechanical Works Fire Extinguisher 10lbs Set 8.00 Fire Alarm Set 2.00 Exhaust Fan Set 6.00 Split-type Aircon, 2hp Set 2.00 Ceiling Fan Set 32.00 Consumables Lot 1.00 Folding Partition (pvc Accordion) Lot 1.00 Lavatory Counter Cabinets Lot 1.00 Viii. Plumbing Works A. Plumbing Fixtures Water Closet With Accessories (tank Type) Set 16.00 Urinal (with Privacy Partition) Set 8.00 Bidet Spray Set 16.00 Counter Lavatory With Granite And Accessories Set 18.00 Mirror Set 4.00 Lavatory Faucet Pcs 18.00 Hose Bibb Faucet Pcs 16.00 Tissue Paper Holder Pcs 16.00 Floor Drain Pcs 20.00 B. Sewer Line And Vent System Lot 1.00 C. Waterline System Lot 1.00 D. Storm Drainage System Lot 1.00 E. Others (tank) Ibc Tanks (1000l) - Rainwater Catchment Set 4.00 Water Tank - 1000l Set 2.00 Booster Pump, 1.5hp Set 1.00 Septic Tank Lot 1.00 Grand Total Cost (inclusive Of Ocm, Profit And Vat) I Hereby Certify To Comply With All The Above Technical Specifications As Per Prices Quoted In The Bill Of Quantities. Name Of Company/bidder Signature Over Printed Name Of Date Representatives Section Ix. Checklist Of Technical And Financial Documents Notes On The Checklist Of Technical And Financial Documents The Prescribed Documents In The Checklist Are Mandatory To Be Submitted In The Bid, But Shall Be Subject To The Following: A. Gppb Resolution No. 09-2020 On The Efficient Procurement Measures During A State Of Calamity Or Other Similar Issuances That Shall Allow The Use Of Alternate Documents In Lieu Of The Mandated Requirements; Or B. Any Subsequent Gppb Issuances Adjusting The Documentary Requirements After The Effectivity Of The Adoption Of The Pbds. The Bac Shall Be Checking The Submitted Documents Of Each Bidder Against This Checklist To Ascertain If They Are All Present, Using A Non-discretionary “pass/fail” Criterion Pursuant To Section 30 Of The 2016 Revised Irr Of Ra No. 9184. Checklist Of Technical And Financial Documents I. Technical Component Envelope Class “a” Documents Legal Documents ⬜ (a) Valid Philgeps Registration Certificate (platinum Membership) (all Pages); Or ⬜ (b) Registration Certificate From Securities And Exchange Commission (sec), Department Of Trade And Industry (dti) For Sole Proprietorship, Or Cooperative Development Authority (cda) For Cooperatives Or Its Equivalent Document; And ⬜ (c) Mayor’s Or Business Permit Issued By The City Or Municipality Where The Principal Place Of Business Of The Prospective Bidder Is Located, Or The Equivalent Document For Exclusive Economic Zones Or Areas; And ⬜ (e) Tax Clearance Per E.o. No. 398, S. 2005, As Finally Reviewed And Approved By The Bureau Of Internal Revenue (bir). Technical Documents ⬜ (f) Statement Of The Prospective Bidder Of All Its Ongoing Government And Private Contracts, Including Contracts Awarded But Not Yet Started, If Any, Whether Similar Or Not Similar In Nature And Complexity To The Contract To Be Bid; And ⬜ (g) Statement Of The Bidder’s Single Largest Completed Contract (slcc) Similar To The Contract To Be Bid, Except Under Conditions Provided Under The Rules; And ⬜ (h) Philippine Contractors Accreditation Board (pcab) License; Or Special Pcab License In Case Of Joint Ventures; And Registration For The Type And Cost Of The Contract To Be Bid; And ⬜ (i) Original Copy Of Bid Security. If In The Form Of A Surety Bond, Submit Also A Certification Issued By The Insurance Commission; Or Original Copy Of Notarized Bid Securing Declaration; And (j) Project Requirements, Which Shall Include The Following: ⬜ A. Organizational Chart For The Contract To Be Bid; ⬜ B. List Of Contractor’s Key Personnel (e.g., Project Manager, Project Engineers, Materials Engineers, And Foremen), To Be Assigned To The Contract To Be Bid, With Their Complete Qualification And Experience Data; ⬜ C. List Of Contractor’s Major Equipment Units, Which Are Owned, Leased, And/or Under Purchase Agreements, Supported By Proof Of Ownership Or Certification Of Availability Of Equipment From The Equipment Lessor/vendor For The Duration Of The Project, As The Case May Be; And ⬜ (k) Original Duly Signed Omnibus Sworn Statement (oss); And If Applicable, Original Notarized Secretary’s Certificate In Case Of A Corporation, Partnership, Or Cooperative; Or Original Special Power Of Attorney Of All Members Of The Joint Venture Giving Full Power And Authority To Its Officer To Sign The Oss And Do Acts To Represent The Bidder. Financial Documents ⬜ (l) The Prospective Bidder’s Audited Financial Statements, Showing, Among Others, The Prospective Bidder’s Total And Current Assets And Liabilities, Stamped “received” By The Bir Or Its Duly Accredited And Authorized Institutions, For The Preceding Calendar Year Which Should Not Be Earlier Than Two (2) Years From The Date Of Bid Submission; And ⬜ (m) The Prospective Bidder’s Computation Of Net Financial Contracting Capacity (nfcc). Class “b” Documents ⬜ (n) If Applicable, Duly Signed Joint Venture Agreement (jva) In Accordance With Ra No. 4566 And Its Irr In Case The Joint Venture Is Already In Existence; Or Duly Notarized Statements From All The Potential Joint Venture Partners Stating That They Will Enter Into And Abide By The Provisions Of The Jva In The Instance That The Bid Is Successful. Ii. Financial Component Envelope ⬜ (o) Original Of Duly Signed And Accomplished Financial Bid Form; And Other Documentary Requirements Under Ra No. 9184 ⬜ (p) Original Of Duly Signed Bid Prices In The Bill Of Quantities; And ⬜ (q) Duly Accomplished Detailed Estimates Form, Including A Summary Sheet Indicating The Unit Prices Of Construction Materials, Labor Rates, And Equipment Rentals Used In Coming Up With The Bid; And ⬜ (r) Cash Flow By Quarter. Bid Form For The Procurement Of Infrastructure Projects [shall Be Submitted With The Bid] _________________________________________________________________________ Bid Form Date : _________________ Project Identification No. : _________________ To: [name And Address Of Procuring Entity] Having Examined The Philippine Bidding Documents (pbds) Including The Supplemental Or Bid Bulletin Numbers [insert Numbers], The Receipt Of Which Is Hereby Duly Acknowledged, We, The Undersigned, Declare That: A. We Have No Reservation To The Pbds, Including The Supplemental Or Bid Bulletins, For The Procurement Project: [insert Name Of Contract]; B. We Offer To Execute The Works For This Contract In Accordance With The Pbds; C. The Total Price Of Our Bid In Words And Figures, Excluding Any Discounts Offered Below Is: [insert Information]; D. The Discounts Offered And The Methodology For Their Application Are: [insert Information]; E. The Total Bid Price Includes The Cost Of All Taxes, Such As, But Not Limited To: [specify The Applicable Taxes, E.g. (i) Value Added Tax (vat), (ii) Income Tax, (iii) Local Taxes, And (iv) Other Fiscal Levies And Duties], Which Are Itemized Herein And Reflected In The Detailed Estimates, F. Our Bid Shall Be Valid Within The A Period Stated In The Pbds, And It Shall Remain Binding Upon Us At Any Time Before The Expiration Of That Period; G. If Our Bid Is Accepted, We Commit To Obtain A Performance Security In The Amount Of [insert Percentage Amount] Percent Of The Contract Price For The Due Performance Of The Contract, Or A Performance Securing Declaration In Lieu Of The The Allowable Forms Of Performance Security, Subject To The Terms And Conditions Of Issued Gppb Guidelines For This Purpose; H. We Are Not Participating, As Bidders, In More Than One Bid In This Bidding Process, Other Than Alternative Offers In Accordance With The Bidding Documents; I. We Understand That This Bid, Together With Your Written Acceptance Thereof Included In Your Notification Of Award, Shall Constitute A Binding Contract Between Us, Until A Formal Contract Is Prepared And Executed; And J. We Understand That You Are Not Bound To Accept The Lowest Calculated Bid Or Any Other Bid That You May Receive. K. We Likewise Certify/confirm That The Undersigned, Is The Duly Authorized Representative Of The Bidder, And Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary To Participate, Submit The Bid, And To Sign And Execute The Ensuing Contract For The [name Of Project] Of The [name Of The Procuring Entity]. L. We Acknowledge That Failure To Sign Each And Every Page Of This Bid Form, Including The Bill Of Quantities, Shall Be A Ground For The Rejection Of Our Bid. Name: ___________________________________________________________________ Legal Capacity: ____________________________________________________________ Signature: ________________________________________________________________ Duly Authorized To Sign The Bid For And Behalf Of: __________________________________ Date: ___________________ [bidder’s Letterhead] Name Of The Procuring Entity : Bulacan Agricultural State College Project: 2024-01-infra: Construction Of 2-storey Agroforestry Building With Rainwater Catchment Facility Location Of The Project : Doña Remedios Trinidad, Bulacan List Of All Ongoing Government & Private Contracts Including Contracts Awarded But Not Yet Started Business Name : Business Address :______________________________________________________________________ Name Of Contract/ Project Cost A. Owner’s Name B. Address C. Telephone Nos. Nature Of Work Bidder’s Role A. Date Awarded B. Date Started C. Date Of Completion % Of Accomplishment Value Of Outstanding Works / Undelivered Portion Description % Planned Actual Government Private Note: This Statement Shall Be Supported With: Total Cost 1 Notice Of Award (for Government Projects) 2 Notice To Proceed (for Government Projects) 3 Contract Submitted By : (printed Name & Signature) Designation : Date : [bidder’s Letterhead] Name Of The Procuring Entity : Bulacan Agricultural State College Project: 2024-01-infra: Construction Of 2-storey Agroforestry Building With Rainwater Catchment Facility Location Of The Project : Doña Remedios Trinidad, Bulacan Statement Of Single Largest Completed Contracts (slcc) In The Last Five (5) Years Business Name : Business Address : Name Of Contract A. Owner Name B. Address C. Telephone Nos. Nature Of Work Contractor’s Role A. Amount At Award B. Amount At Completion C. Duration A. Date Awarded B. Contract Effectivity C. Date Completed Description % Government Private Attached Herewith Are The Following Documents: Contract Agreement, Notice Of Award, Notice To Proceed, Official Receipt/invoice, Certificate Of Final Inspection, And Certificate Of Acceptance, As Evidences In Support Of The Foregoing Information, Certificate Of Good Performance Submitted By : (printed Name & Signature) Designation : ____________________________________________ Contract Agreement Form This Agreement Made The _____ Day Of __________ 20_____ Between [name Of Procuring Entity] Of The Philippines (hereinafter Called “the Entity”) Of The One Part And [name Of Supplier] Of [city And Country Of Supplier] (hereinafter Called “the Supplier”) Of The Other Part: Whereas The Entity Invited Bids For Certain Goods And Ancillary Services, Viz., [brief Description Of Goods And Services] And Has Accepted A Bid By The Supplier For The Supply Of Those Goods And Services In The Sum Of [contract Price In Words And Figures] (hereinafter Called “the Contract Price”). Now This Agreement Witnesseth As Follows: 1. In This Agreement Words And Expressions Shall Have The Same Meanings As Are Respectively Assigned To Them In The Conditions Of Contract Referred To. 2. The Following Documents Shall Be Deemed To Form And Be Read And Construed As Part Of This Agreement, Viz.: (a) The Supplier’s Bid, Including The Technical And Financial Proposals, And All Other Documents/statements Submitted (e.g. Bidder’s Response To Clarifications On The Bid), Including Corrections To The Bid Resulting From The Procuring Entity’s Bid Evaluation; (b) The Schedule Of Requirements; (c) The Technical Specifications; (d) The General Conditions Of Contract; (e) The Special Conditions Of Contract; (f) The Performance Security; And (g) The Entity’s Notice Of Award. 3. In Consideration Of The Payments To Be Made By The Entity To The Supplier As Hereinafter Mentioned, The Supplier Hereby Covenants With The Entity To Provide The Goods And Services And To Remedy Defects Therein In Conformity In All Respects With The Provisions Of The Contract 4. The Entity Hereby Covenants To Pay The Supplier In Consideration Of The Provision Of The Goods And Services And The Remedying Of Defects Therein, The Contract Price Or Such Other Sum As May Become Payable Under The Provisions Of The Contract At The Time And In The Manner Prescribed By The Contract. In Witness Whereof The Parties Hereto Have Caused This Agreement To Be Executed In Accordance With The Laws Of The Republic Of The Philippines On The Day And Year First Above Written. Signed, Sealed, Delivered By The (for The Entity) Signed, Sealed, Delivered By The (for The Supplier) Omnibus Sworn Statement (revised) [shall Be Submitted With The Bid] _________________________________________________________________________ Republic Of The Philippines ) City/municipality Of ______ ) S.s. Affidavit I, [name Of Affiant], Of Legal Age, [civil Status], [nationality], And Residing At [address Of Affiant], After Having Been Duly Sworn In Accordance With Law, Do Hereby Depose And State That: 1. [select One, Delete The Other:] [if A Sole Proprietorship:] I Am The Sole Proprietor Or Authorized Representative Of [name Of Bidder] With Office Address At [address Of Bidder]; [if A Partnership, Corporation, Cooperative, Or Joint Venture:] I Am The Duly Authorized And Designated Representative Of [name Of Bidder] With Office Address At [address Of Bidder]; 2. [select One, Delete The Other:] [if A Sole Proprietorship:] As The Owner And Sole Proprietor, Or Authorized Representative Of [name Of Bidder], I Have Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary To Participate, Submit The Bid, And To Sign And Execute The Ensuing Contract For [name Of The Project] Of The [name Of The Procuring Entity], As Shown In The Attached Duly Notarized Special Power Of Attorney; [if A Partnership, Corporation, Cooperative, Or Joint Venture:] I Am Granted Full Power And Authority To Do, Execute And Perform Any And All Acts Necessary To Participate, Submit The Bid, And To Sign And Execute The Ensuing Contract For [name Of The Project] Of The [name Of The Procuring Entity], As Shown In The Attached [state Title Of Attached Document Showing Proof Of Authorization (e.g., Duly Notarized Secretary’s Certificate, Board/partnership Resolution, Or Special Power Of Attorney, Whichever Is Applicable;)]; 3. [name Of Bidder] Is Not “blacklisted” Or Barred From Bidding By The Government Of The Philippines Or Any Of Its Agencies, Offices, Corporations, Or Local Government Units, Foreign Government/foreign Or International Financing Institution Whose Blacklisting Rules Have Been Recognized By The Government Procurement Policy Board, By Itself Or By Relation, Membership, Association, Affiliation, Or Controlling Interest With Another Blacklisted Person Or Entity As Defined And Provided For In The Uniform Guidelines On Blacklisting; 4. Each Of The Documents Submitted In Satisfaction Of The Bidding Requirements Is An Authentic Copy Of The Original, Complete, And All Statements And Information Provided Therein Are True And Correct; 5. [name Of Bidder] Is Authorizing The Head Of The Procuring Entity Or Its Duly Authorized Representative(s) To Verify All The Documents Submitted; 6. [select One, Delete The Rest:] [if A Sole Proprietorship:] The Owner Or Sole Proprietor Is Not Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; [if A Partnership Or Cooperative:] None Of The Officers And Members Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; [if A Corporation Or Joint Venture:] None Of The Officers, Directors, And Controlling Stockholders Of [name Of Bidder] Is Related To The Head Of The Procuring Entity, Members Of The Bids And Awards Committee (bac), The Technical Working Group, And The Bac Secretariat, The Head Of The Project Management Office Or The End-user Unit, And The Project Consultants By Consanguinity Or Affinity Up To The Third Civil Degree; 7. [name Of Bidder] Complies With Existing Labor Laws And Standards; And 8. [name Of Bidder] Is Aware Of And Has Undertaken The Responsibilities As A Bidder In Compliance With The Philippine Bidding Documents, Which Includes: A. Carefully Examining All Of The Bidding Documents; B. Acknowledging All Conditions, Local Or Otherwise, Affecting The Implementation Of The Contract; C. Making An Estimate Of The Facilities Available And Needed For The Contract To Be Bid, If Any; And D. Inquiring Or Securing Supplemental/bid Bulletin(s) Issued For The [name Of The Project]. 9. [name Of Bidder] Did Not Give Or Pay Directly Or Indirectly, Any Commission, Amount, Fee, Or Any Form Of Consideration, Pecuniary Or Otherwise, To Any Person Or Official, Personnel Or Representative Of The Government In Relation To Any Procurement Project Or Activity. 10. In Case Advance Payment Was Made Or Given, Failure To Perform Or Deliver Any Of The Obligations And Undertakings In The Contract Shall Be Sufficient Grounds To Constitute Criminal Liability For Swindling (estafa) Or The Commission Of Fraud With Unfaithfulness Or Abuse Of Confidence Through Misappropriating Or Converting Any Payment Received By A Person Or Entity Under An Obligation Involving The Duty To Deliver Certain Goods Or Services, To The Prejudice Of The Public And The Government Of The Philippines Pursuant To Article 315 Of Act No. 3815 S. 1930, As Amended, Or The Revised Penal Code. In Witness Whereof, I Have Hereunto Set My Hand This __ Day Of ___, 20__ At ____________, Philippines. [insert Name Of Bidder Or Its Authorized Representative] [insert Signatory’s Legal Capacity] Affiant [jurat] [format Shall Be Based On The Latest Rules On Notarial Practice] Bid Securing Declaration Form [shall Be Submitted With The Bid If Bidder Opts To Provide This Form Of Bid Security] Republic Of The Philippines) City Of _______________________) S.s. Bid Securing Declaration Project Identification No.: [insert Number] To: [insert Name And Address Of The Procuring Entity] I/we, The Undersigned, Declare That: 1. I/we Understand That, According To Your Conditions, Bids Must Be Supported By A Bid Security, Which May Be In The Form Of A Bid Securing Declaration. 2. I/we Accept That: (a) I/we Will Be Automatically Disqualified From Bidding For Any Procurement Contract With Any Procuring Entity For A Period Of Two (2) Years Upon Receipt Of Your Blacklisting Order; And, (b) I/we Will Pay The Applicable Fine Provided Under Section 6 Of The Guidelines On The Use Of Bid Securing Declaration, Within Fifteen (15) Days From Receipt Of The Written Demand By The Procuring Entity For The Commission Of Acts Resulting To The Enforcement Of The Bid Securing Declaration Under Sections 23.1(b), 34.2, 40.1 And 69.1, Except 69.1(f),of The Irr Of Ra No. 9184; Without Prejudice To Other Legal Action The Government May Undertake. 3. I/we Understand That This Bid Securing Declaration Shall Cease To Be Valid On The Following Circumstances: A. Upon Expiration Of The Bid Validity Period, Or Any Extension Thereof Pursuant To Your Request; B. I Am/we Are Declared Ineligible Or Post-disqualified Upon Receipt Of Your Notice To Such Effect, And (i) I/we Failed To Timely File A Request For Reconsideration Or (ii) I/we Filed A Waiver To Avail Of Said Right; And C. I Am/we Are Declared The Bidder With The Lowest Calculated Responsive Bid, And I/we Have Furnished The Performance Security And Signed The Contract. In Witness Whereof, I/we Have Hereunto Set My/our Hand/s This ____ Day Of [month] [year] At [place Of Execution]. [[insert Name Of Bidder Or Its Authorized Representative] [insert Signatory’s Legal Capacity] Affiant [jurat] [format Shall Be Based On The Latest Rules On Notarial Practice] Net Financial Contracting Capacity Year 20 1 Total Assets 2 Current Assets 3 Total Liabilities 4 Current Liabilities 5 Net Worth (1-3) 6 Net Working Capital (2-4) The Net Financial Contracting Capacity (nfcc) Based On The Above Data Is Computed As Follows: Nfcc = [(current Assets – Current Liabilities) (15)] Minus Value Of All Outstanding Or Uncompleted Portions Of The Projects Under Ongoing Contracts Including Awarded Contracts Yet To Be Started Coinciding With The Contract To Be Bid. The Values Of The Domestic Bidder’s Current Assets And Current Liabilities Shall Be Based On The Latest Audited Financial Statements Submitted To The Bir. Nfcc = Php Submitted By: Name Of Bidder Signature Of Authorized Representative Over Printed Name Date: _______________________________________
Closing Soon2 Dec 2024
Tender AmountPHP 25 Million (USD 423.2 K)
4591-4600 of 4597 active Tenders